TO-HQ-02-013 Rev 00 Philosophy For Emergency Generator and S PDF
TO-HQ-02-013 Rev 00 Philosophy For Emergency Generator and S PDF
TO-HQ-02-013 Rev 00 Philosophy For Emergency Generator and S PDF
Philosophy
for
Emergency Generator and Switchboard
Onshore
Document Number
TO-HQ-02-013-00
00
Final Issue
JS
31/5/05
JEA
31/5/05
A2
JS
28/5/05
A1
RH
22/12/04
JS
31/12/04
Issue
Rev
Origin
By
Date
Chkd
By
Date
PZ
03/6/05
MF
03/6/05
Appd By
Date
Appd
By
Date
Revision
Description of revision
A1
For Comment/Approval
A2
00
Final Issue
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
2 of 22
Contents
1.0 PREFACE .......................................................................................................................4
2.0 DEFINITIONS .................................................................................................................4
3.0 ABBREVIATIONS...........................................................................................................4
4.0 INTRODUCTION.............................................................................................................4
5.0 APPLICABLE CODES, STANDARDS AND REGULATIONS........................................5
5.1
5.2
General ....................................................................................................................................... 9
Prime Mover ............................................................................................................................. 10
Starting Methods ..................................................................................................................... 11
Generator.................................................................................................................................. 12
Generator control panel .......................................................................................................... 14
Emergency Switchboard......................................................................................................... 16
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
3 of 22
1.0
PREFACE
This Philosophy defines the OMV Exploration & Production GmbH corporate
policy on the design of Emergency Generators and Switchboards for
onshore hydrocarbon production and processing facilities. The document
specifies basic requirements and criteria, defines the appropriate codes and
standards, and assists in the standardisation of facilities design across all
onshore operations.
The design process needs to consider project specific factors such as the
location, production composition, production rates and pressures, the
process selected and the size of the plant. This philosophy aims to address
a wide range of the above variables, however it is recognised that not all
circumstances can be covered. In situations where project specific
considerations may justify deviation from this philosophy, a document
supporting the request for deviation shall be submitted to OMV E&P for
approval.
Reference should be made to the parent of this philosophy, document
number TO-HQ-02-001 for information on deviation procedures and
Technical Authorities, general requirements and definitions and
abbreviations not specific to this document
2.0
DEFINITIONS
There are no definitions with particular relevance to this document.
3.0
ABBREVIATIONS
The following abbreviations are relevant to this document:
4.0
AVR
UL
Underwriters Laboratory
INTRODUCTION
The tenets of this philosophy are enshrined in the belief that upon loss of
mains supply the following requirements must be secured by the transfer from
mains supply to emergency supply.
Safety of Personnel.
Security of the surrounding environment.
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
4 of 22
Local Regulations,
National standards.
Design of the emergency generator system shall comply with the standards listed
within this philosophy, however, for instances where local standards are more
onerous local standards shall apply.
5.1
API RP 540
NEMA MG1
NEMA MG2
IEC 60034-1
IEC 60204-1
IEC 60439-1
Low-voltage switchgear and control gear assemblies Part 1: Type-tested and partially type-tested assemblies
IEC 60947-1
IEC 60947-4-1
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
5 of 22
5.2
6.0
IEEE C37.20.1
UL 891
Dead-Front Switchboards
UL 1558
ISO 3046-1
Reciprocating
internal
combustion
engines
-Performance -- Part 1: Declarations of power, fuel and
lubricating oil consumptions, and test methods -Additional requirements for engines for general use
BS 5514-3
Reciprocating
internal
combustion
engines:
performance. Specification for test measurements
ISO 3046-4
Reciprocating
internal
combustion
Performance -- Part 4: Speed governing
engines
--
ISO 3046-5
Reciprocating
internal
combustion
engines
Performance -- Part 5: Torsional vibrations
--
BS 5000-11
BS 5000-3
References
TO-HQ-02-011
TO-HQ-02-012
TO-HQ-02-039
SYSTEM GOAL
The emergency generator and switchboard are intended to provide a secure
electrical supply, independent of any external supply and the main generation
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
6 of 22
system for the installation, for vital services for which a short break in supply is
tolerable.
Typically, the services will be those that present a load of a magnitude such that
a no-break battery UPS would not be practicable, or economically justified by the
risk mitigated by the provision of such a system, such as emergency lighting or
HVAC for buildings housing equipment essential for the restoration of normal
conditions following a power failure.
Alternatively, the emergency system will act as a back-up for systems which
have a no-break supply, but for which it would not be practicable to install
batteries having a capacity sufficient to maintain power autonomously for the
duration of all foreseeable power outages, such as fire fighting systems, plant
control systems, aircraft warning systems, etc.
The analysis of which services which will require an emergency supply, and for
what duration, is dealt with in more depth in Document No TO-HQ-02-011 Philosophy for Electrical Design Onshore.
7.0
SYSTEM BOUNDARIES
The boundaries of the emergency generator and switchboard system are the:
8.0
DESIGN PHILOSOPHY
The emergency generator set and switchboard shall be of types accepted as
providing a high degree of reliability, within the capabilities of normal industrial
equipment: It is not envisaged that any system requiring a higher level of integrity
should be reliant solely upon an emergency generator.
The emergency switchboard shall be supplied, by an interconnector circuit, from
the main power distribution system, to reduce the running hours required of the
emergency generator. Nevertheless, the arrangements should facilitate regular
on-load testing.
In normal operation, the emergency generator shall start automatically, then be
connected automatically to the emergency switchboard, on detection of loss of
voltage at the main switchboard from which the emergency switchboard is
normally fed.
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
7 of 22
The starting and control arrangements shall be totally independent of the main
power system, as should be the fuel supply. The capacity of the emergency fuel
supply shall be determined following consideration of the duration for which the
emergency supply is required to be available.
The emergency generator and switchboard shall be located outside any
hazardous area or high fire risk location. Consideration should also be given to
locating the equipment so as to enhance the likelihood of it remaining operational
in the event of a major incident, where the normal hazardous area classification
boundaries no longer apply.
Consideration should also be given to the benefits of configuring the emergency
power distribution network as a non-earthed (IT) system, so that a single earth
fault does not result in loss of services on the faulted circuit.
The Philosophy is structured on the basis of the elements shown below, each of
which shall be allocated to a specific sub-section. Within each sub-section, the
reader shall be directed to the associated clause within the NEC for core
philosophy information and be provided with detail on specific issues.
9.0
Prime Mover
Starting Method
Generator
Emergency Switchboard
Busbars
Circuit Breakers
Generator incomer
Interconnector Circuit
Feeder Circuits
DESIGN CONSIDERATIONS
The ratings of the generator set and switchboard depend upon the loads
determined by the risk analyses and system design studies, and the applicable
regulations, as requiring an emergency supply. It is expected that these would
not fall into a band where High Voltage generation would be appropriate: the
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
8 of 22
General
For core Philosophy guidance, refer NEC, Articles 700 and 705.
Specific Issues:
This philosophy considers that:
The generator set shall consist of a diesel reciprocating engine prime mover,
mounted on a bedplate with, and directly coupled to, an a.c. generator.
The maximum voltage delivered by the generator shall be below 1000V at
50/60Hz and is, subject to compliance with regulatory requirements, regulatory
requirements and in accordance with the system design philosophy (see
Document No TQ-HQ-01-011 Philosophy for General Electrical Design
Onshore), ungrounded or grounded (earthed).
The Interconnector feeder shall be protected against short-circuit and overload at
the point of connection to the main system, and as a minimum, short-circuit at the
emergency board.
The Interconnector feeder shall be disconnected automatically at the emergency
switch board upon loss of mains power.
Upon loss of mains supply the emergency Generator shall start and shall be
connected to emergency switch board when its output voltage has reached
between 85% and 95% of its nominal value: this operation shall be completed
within 10 to 45 seconds.
All non-emergency loads shall have been automatically disconnected from the
emergency switch board.
The rating of the emergency generator shall be based on continuous operation
with no diversity factor assumed.
The Emergency Generator and Switchboard shall be housed in a building or
Enclosure having passive fire protection to a level determined by a previously
conducted risk assessment. The design of the building or enclosure shall take
into account blast overpressure, so that the risk of loss of the emergency supply,
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
9 of 22
Prime Mover
For core Philosophy guidance, refer NEC Article 700-12. Account is also to be
taken of the relevant requirements of Document No TO-HQ-02-039 Philosophy for Rotating and Reciprocating Equipment Onshore
Specific Issues:
This philosophy considers that:
The engine should be selected from the Manufacturers standard range, and
should be of a type, rating and method of manufacture for which satisfactory
service experience can be confirmed.
The engine should generally be of the water cooled type, with a water to air heat
exchanger (radiator), although consideration could be given to the use of direct
air cooled engines for small installations. For either type of engine, an electric
sump heater shall be provided where necessary to ensure reliable starting under
the coldest conditions encountered at the site. Water cooled engines shall also
be provided with a jacket heater in order to ensure rapid starting and acceptance
of load under these conditions.
Coolant radiators mounted externally or in the wall of the generator building shall
be provided with suitable louvres or shutters for weather protection. Where the
generator building is required to provide a given level of passive fire protection,
this should be maintained by the provision of fire dampers and suitable insulation
for the radiators. Externally mounted radiators shall also be protected similarly.
The rated power of the engine, for continuous operation and overload conditions,
determined in accordance with ISO 3046-1, shall be sufficient to meet the duty
required of the emergency generator set as determined by the system design
studies. Any likely deterioration under the proposed maintenance regime for the
installation should be taken into account in determining the rating.
The prime mover ratings shall be adjusted for the highest expected ambient
temperatures and derated, where necessary, for total system inlet and exhaust
pressure losses.
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
10 of 22
Special consideration should be given, when sizing the prime mover, for service
where large motors are to be started across the line.
Drive belts for auxiliary equipment shall be guarded appropriately, with full
allowance being made for adjustment throughout the life of the belt.
Combustion air filtration shall be provided as required by local conditions and the
point from which air is drawn. Provision shall be made, by means of a blow-in
door or similar, for the engine to be able to continue running if the intake filter
should become blocked. Where the generator building is required to provide a
given level of passive fire protection, this should be maintained by the provision
of fire dampers and suitable insulation for the ventilation air intakes for the
building and the combustion air intake for the engine, if ducted through the wall of
the building.
The engine should be provided with an aspiration air intake valve, activated
under emergency shutdown conditions, to ensure safe shutdown in the event of
a major release of flammable gas.
Means should be provided, if the engine is turbo-charged, for automatically
draining, or preventing the formation of, condensate within the inlet manifold.
9.3
Starting Methods
For core Philosophy guidance, refer NEC Article 700.
Specific Issues:
This philosophy considers that:
Compressed air, hydraulic, or electric start methods are acceptable, provided
that the engine manufacturer can confirm satisfactory field experience for the
arrangement offered.
Where justified by the economic or safety consequences of failure to start,
consideration should be given to the provision of redundant starting
arrangements, preferably of different types.
Whichever system or combination of systems is employed, two independent
sources of stored energy, each sufficient for at least three consecutive start
attempts, shall be provided. The electrical supplies for the necessary pumps,
compressors and battery chargers shall be taken from the emergency
switchboard.
The pumps, compressors or battery chargers should be rated so as to be
capable of recharging one of the sources of stored energy to a level sufficient to
provide a further three start attempts within an acceptable period. 15 minutes
would be appropriate for hydraulic and compressed air systems, and one hour,
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
11 of 22
Generator
For core Philosophy guidance, refer NEC Articles:- 445, 700.
Specific Issues:
This philosophy considers that:
The generator shall be designed to perform in accordance with NEMA Standards
Publication MG1 or an equivalent IEC or national standard.
The generator should be of the revolving field, brushless, type, so as to eliminate
all arcing contacts and to reduce maintenance requirements. The use of a
permanent magnet exciter is the preferred method, to avoid risk of failure, to
achieve excitation after a lengthy period out of service.
The generator should have a design temperature rise of 80C, by resistance,
(NEMA Class B), but be constructed with a minimum of NEMA Class F insulation
to provide optimum balance between initial cost and long-life operations. The
generator shall be derated in accordance with manufacturers recommendations
if operated in a higher ambient temperature than for which its rating has been
determined (normally 40C).
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
12 of 22
The generator shall be capable of an overload power of not less than 10 per cent
at its rated power factor for a period of 15 minutes without injurious heating. It
shall also be capable of withstanding on test, without injury, the following
momentary overload: an excess current of 50 per cent for 15 seconds after
attaining the temperature rise corresponding to rated load, the terminal voltage
being maintained as near the rated value as possible. This does not apply to the
overload torque capacity of the prime mover.
The Enclosure of the generator may be of the open, drip-proof, type, provided
that the generator set is housed in a building, as recommended. However, if the
building has a water spray or water mist fire extinguishing system, an enhanced
degree of protection, sufficient to allow the generator to continue to function in
the event of spurious operation of the fire extinguishing system, shall be
specified. For optimum protection of the windings of a generator installed
outdoors, a totally enclosed type of construction would be required.
Anti-condensation heaters should be provided to keep windings dry when the
generator is not operating.
The lubrication arrangements for bearings shall include effective means to
ensure that lubricant does not reach the machine windings or other conductors
and insulators.
Where the shaft voltage of the generator, measured between shaft ends, may
exceed a value acceptable for the type of bearing employed (250 mV for rolling
element bearings), suitable bearing insulation arrangements shall be provided,
with a single, disconnectable, earth connection for equipotential bonding
purposes.
The generator shall be constructed such that, under any operating conditions, it
is capable of withstanding the effects of a sudden short-circuit at its terminals
without damage.
The generator shall be provided with automatic means of voltage regulation;
voltage build-up is not to require an external source of power. Provision shall be
made to safeguard the distribution system should there be a failure of the voltage
regulating system resulting in a High Voltage. Solid state voltage regulators are
preferred for high reliability, long life, fast response and stable regulation. The
voltage regulators for machines rated in excess of 200kVA should be protected
by the provision of under-frequency and overvoltage sensors.
The voltage regulator should have an adjustable droop characteristic, or be
otherwise arranged, to allow parallel operation with the main power system.
Consideration may also be given to automatic power factor control, if extended
periods of parallel operation are anticipated.
Philosophy for Emergency Generator and Switchboard
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
13 of 22
control logic (preferably utilising hard wired relay logic, for ease of fault
finding and rectification, and predictable operation under all conditions);
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
14 of 22
metering;
synchronising equipment;
engine tachometer;
current);
hours-run meter;
The ingress protection of the panel shall be suitable for its location. Drip
proof/NEMA type 2/IP22 shall be suitable if located within the generator room
and not subject to water spray from fire extinguishing system; NEMA Type 3 or
4/IP55 or better, otherwise.
Philosophy for Emergency Generator and Switchboard
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
15 of 22
The power supply for the panel shall have a battery backup, which should be
separate from the engine start batteries.
9.6
Underspeed;
Vibration;
Undervoltage;
Underfrequency;
Loss of excitation;
Generator differential;
Overfrequency;
Emergency Switchboard
For core Philosophy guidance, refer NEC Articles:- 110, 480, 700 and 705.
Specific issues are addressed below.
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
16 of 22
General requirements
The switchboard should be arranged to provide convenient and safe access to
qualified personnel to operate and perform maintenance on the equipment. An
unobstructed space not less than 1 m wide shall be provided in front of the
switchboard.
Where the switchboard contains withdrawable equipment, the unobstructed
space shall not be less than 0,4 m wide with this equipment in its fully withdrawn
position.
Where necessary, the space at the rear of the switchboard is to be ample to
permit maintenance and in general not less than 0,7 m. In any event, the
arrangements are to comply with the relevant statutory requirements, e.g.
those of the NEC, Art.110.
The spaces required for access shall have non-slip surfaces, electrically
insulated, or provided with insulating mats.
The switchboard should, preferably, meet the requirements of ANSI C37.20.1 or
UL 1558 for Low Voltage metal enclosed power circuit breaker switchgear.
Consideration may also be given to the use of a switchboard compliant with UL
Std 891 for dead-front switchboards or international standards such as IEC
60439, Low Voltage switchgear and control gear assemblies.
The ingress protection (IP) of the switchboard shall be suitable for its location.
Drip proof/NEMA type 2/IP22 shall be suitable if located within the generator
room and not subject to water spray from fire extinguishing system; NEMA Type
3 or 4/IP55 or better, otherwise.
The short-circuit ratings of the switchboard busbar system shall be adequate for
the prospective fault level at the switchboard. The rated short-circuit making and
breaking capacity of every protective device shall be adequate for the
prospective fault level at its point of installation.
The construction of the switchboard should be of a type that confines an internal
fault in a busbar dropper, feeder or starter compartment to the affected unit, so
that other parts of the switchboard remain fit for service.
Consideration should be given to the provision of windows or removable panels
to allow safe on-load thermographic examination of the internal load current
carrying parts of the switchboard.
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
17 of 22
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
18 of 22
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
19 of 22
DESIGN CRITERIA
The essential design criteria are referenced in Sections 8 and 9. It is
recommended, however, that the ratings of emergency generator and
switchboard and the design of the switchboard should allow for the expansion of
the plant and additional or enhanced loads.
11.0
DOCUMENTATION REQUIREMENTS
Technical manuals including the following information shall be provided:
12.0
Operating particulars, such that operators not having familiarity with the
equipment can operate it safely.
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
20 of 22
ratings of
converters;
machines,
transformers,
batteries
and
semiconductor
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
21 of 22
Document Number
Rev
Page
Onshore
TO-HQ-02-013
00
22 of 22