Completion Design
Completion Design
Completion Design
INTRODUCTION
In simple terms, the term 'well completion' refers to the methods
by which a newly drilled well can be finalized so that reservoir
fluids can be produced to surface production facilities efficiently
and safely.
In general, the process of completing a well includes the following:
A method of providing satisfactory communication between the
reservoir and the borehole.
The design of the tubular (casing and tubing) which will be installed
in the well.
An appropriate method of raising reservoir fluids to the surface.
DESIGN CONSIDERATIONS
Before a production well is drilled, a great deal of planning must be
undertaken to ensure that the design of the completion is the best
possible. A number of factors must be taken into consideration
during this planning stage, which can broadly be split into
reservoir considerations and mechanical considerations.
RESERVOIR CONSIDERATIONS:
Producing Rate
Multiple Reservoirs
Reservoir Drive Mechanism
Secondary Recovery Requirements
Stimulation
Sand Control
Artificial Lift
Workover Requirements.
MECHANICAL CONSIDERATIONS:
Functional Requirements
Operating Conditions
Component Design
Component Reliability
Safety.
PERFORATING
History Of Perforation
In Brief
The major disadvantage with this method were that :1. the bullet remained in the perforation tunnel,
2. penetration was not very good,
3. some casings could not be perforated effectively.
up,
perforating orientation.
Charge Detonates
Liner Begins To
Collapse
3- semi-expendable guns
the charges are secured on a retrievable wire carrier or metal
bar., This reduces the debris left in the well and generally
increases the ruggedness of the gun.
Perforation Methods
There are four main types of perforating
guns:
1.
2.
3.
4.
Operations
When the decision is made to perforate, several questions
need to be answered to ensure maximum flow efficiency
from the perforated zone. Some of those questions are;
shot density,
phase angle,
penetration length,
penetration diameter.
Shot Density
Computer programs are used to determine the number of
shots per foot (spf) or shots per meter (spm) required for the
reservoir (using the anticipated production rate of the well).
Regardless of the number of shots, the clean up efficiency
mustdensity
be keptininhomogeneous,
mind.
Shot
isotropic formations should be a
minimum of 8 spf but must exceed the frequency of shale
laminations.
If perforating with through-tubing guns, this will require multiple
runs.
A shot density greater than this is required where:
Phase Angle
The phase angle or phasing "is the direction in which the
shaped charges are fired relative to the other shots in the
gun.
Common phase angles are 45o, 60o, 90o and 120o. This
phasing becomes very important when perforating horizontal
boreholes where you want to perforate only the low side of
the hole or where there are other tubing strings in the well
and the perforations have to be performed around the other
completion strings.
Penetration Length
The actual depth of penetration has a great effect on
production
performance, therefore it is usually necessary to obtain the
greatest penetration possible. The length of the perforation
is difficult to determine, and tunnel length is generally
provided by the manufactures, based on gum size, test
material (i.e. concrete or sandstone, etc.) and shot type (i.e.
Gravel Pack Charge or Deep Penetrating Charge).
Generally, the deep penetration charge will give a tunnel
between 1 and 2 feet in length, while the gravel pack shot
will only be about 8 inches in length.
Penetration Diameter
Gravel pack charges produce large diameter holes (around 1inch), while the deep penetrating charges will produce an
opening between 0.5 and 0.75 inches in diameter.
Underbalanced
Overbalanced Perforating
Casing
Cement
Perforating
gun
Completion fluid
in wellbore
Perforations can
be plugged with
debris in wellbore
Pressure
controls well
during
completion
Oil or gas
reservoir
Underbalanced Perforating
Casing
Cement
Perforating
gun
Well will be
live and need
control after
perforating
Completion fluid
in wellbore
Perforations will
be clean from
surge in wellbore
Oil or gas
reservoir
CLASSIFICATION OF
COMPLETIONS
Mode of Production
This relates to the manner that well fluid is transferred from the
wellbore at the formation depth to the surface, i.e.:
Flowing
Artificial lift.
CLASSIFICATION-BY
RESERVOIR/WELLBORE INTERFACE
1- Open Hole Completions
In this type of completion the
casing is set in place and
cemented above the productive
formation(s). Further drilling
extends the wellbore into the
reservoir(s) and the extended
hole is not cased;
Slotted Liner
Pre-packed Screen
A pre-packed screen is constructed
of an outer and inner wrapped
screens with resin coated gravel
placed between the screens. This
gives a performance better than a
wire wrapped screen but less that
an open hole gravel pack,
CLASSIFICATION-BY MODE OF
PRODUCTION
Tubing less Completions
Casing flow completions
are a particularly low-cost
completion method used
in marginal flow
conditions such as low
rate gas wells,
NOTE:
Most operators do not normally use casing Dow completions,
primarily because the production casing is exposed to well
pressure and/or corrosive fluids. Tubingless completions are
potentially hazardous especially in offshore installations as
there is an increased risk of collision damage with no facility to
install down hole safety valve systems. The use of casing flow
production methods are discouraged both offshore and
onshore.
Tubing Retrievable
Safety Valve
Circulating Device
Artificial Lift
When a reservoir's natural pressure is insufficient to
deliver liquids to surface production facilities, artificial lift
methods are necessary to enhance recovery.
Plunger Lift
The plunger lift system, is a low rate lift system in which
annulus gas energy is used to drive a plunger carrying a
small slug of liquid up the tubing when the well is opened at
surface. Subsequent closing of the well allows the plunger
to fall back to bottom.
Plunger lift is useful for de-watering low rate gas wells.
Key considerations are:
The tubing must be drifted prior to installation
The annulus is open to store lift gas
A nipple/ collar stop must be installed to support a catcher
and shock absorber.
Gas Lift
Gas lift supplements the flow process by the addition of compressed gas
which lightens the liquid head, reduces the liquid viscosity, reduces
friction and supplies potential energy in the form of gas expansion,
Continuous gas lift is used to lift liquid from reservoirs that have a high
productivity index (PI) and a high bottom hole pressure BHP.
Intermittent lift is used in reservoirs that exhibit low PI/low BHP, low PI/high
BHP, or high PI/low BHP.
Liquid production can range from 300 - 4,000 bbls/ day (48 - 636 m3/ day)
through normal size tubing strings. Casing flow can lift up to 25,000 bbls/
day (3,975m3/ day).
Key considerations for gas lift are:
Tubing size
The need for a packer
Setting depths for gas-lift valves.
CLASSIFICATION BY
NUMBER OF ZONES
COMPLETED
Single Zone Completions
Produce only one zone from that well and drill additional wells
to produce from the other pay zones.
HORIZONTAL COMPLETIONS
'Multi-zonal' wells are prime candidates for horizontal
completions as are formations that have naturally fractured
networks from which large production increases can be
expected,
COMPLETION
COMPONENTS
COMPLETION COMPONENTS
1. RE-ENTRY GUIDE
2. LANDING NIPPLE
3. TUBING PROTECTION JOINT
4. PERFORATED JOINT
5. SLIDING SIDE DOOR
6. FLOW COUPLINGS
7. SIDE POCKET MANDRELS
8. SUB-SURFACE SAFETY VALVES (SSSVS)
9. ANNULUS SAFETY VALVES (ASVS)
10.DOWNHOLE CHOKE ASSEMBLIES
11.TUBING HANGER
12.XMAS TREE
13.EXPANSION JOINTS
14. Production Packer
1- RE-ENTRY GUIDE
A re-entry guide generally takes one of two forms:
A. Bell Guide
The Bell Guide; Figure 1, has a 45
lead in taper to allow easy re-entry
into the tubing of well intervention
tool strings (i.e., wire line or coiled
tubing). This guide is commonly
used in completions where the end
of the tubing string does not need to
bypass the top of a liner hanger.
B. Mule Shoe
The Mule Shoe Guide; Figure 1,
is essentially the same as the Bell
Guide with the exception of a
large 45 shoulder. Should the
tubing land on a liner lip while
running the completion in the well,
the large 45 shoulder should
orientate onto the liner lip and
kick the tubing into the liner.
2- LANDING NIPPLE
NOTE:
In highly deviated wells, it may not be possible to use Landing
Nipples at inclinations greater than 70. Wireline operators
commonly use Landing Nipples for depth references. Although
Their Primary Function is as locating devices.
Applications
1- Single and dual completions
Bottom No Go :
4- PERFORATED JOINT
A Perforated Joint, may be incorporated in the
completion string for the purpose of providing bypass
flow if bottom hole pressure and temperature gauges
are used for reservoir monitoring. The design criteria
for a Perforated Joint is that the total cross-sectional
area of the holes should be at least equivalent to the
cross sectional area corresponding to internal
diameter of the tubing.
NOTE:
As with all communication devices, the
differential pressure across SSDs should be
known prior to opening.
NOTE:
6- FLOW COUPLINGS
Flow Couplings are used in many
completions above and/ or below a
completion component where
turbulence may exist to prevent loss
of tubing string integrity and
mechanical strength due to internal
erosion directly above and/or below
the component. Turbulence may be
caused by the profiles internal to a
component.
NOTE:
Circulation Valves
NOTE:
An SPM may be used as a circulation device in preference to an SSD as
side pocket valves may be retrieved for repair and/or seal replacement.
Disadvantages
The cost of a downhole choke is greater than an equivalent surface
choke.
The flowing pressure immediately downstream of the downhole choke
must be calculated to ensure critical flowing conditions.
If any change in the flow rates are required, the choke must be removed
from the well using wireline, and a replacement installed.
An adjustable choke must be installed at surface to control the well
when bringing the well back into production. The well would be brought
on gradually with the adjustable choke until the well is being controlled
by the downhole choke. The adjustable surface choke would then be
opened fully.
12- XMASTREE
An Xmas Tree is an assembly of valves, all with specific
functions, used to control flow from the well and to provide well
intervention access for well maintenance or reservoir
monitoring.
A Xmas Tree may be a composite collection of valves or,
more commonly nowadays, constructed from a single block.
The solid block enables the unit to be smaller and
eliminates the danger of leakage from
Swab Valve
COMPLETION AND
WORKOVER FLUID
4. Fluid Loss
Fluid loss characteristics may have to be tailored to prevent loss of
excessive quantities of fluid to the formation, or to permit
application of "hydraulic stress" to an unconsolidated sand
formation.
5. Viscosity-Related Characteristics
Viscosity-Related Characteristics, such as yield point, plastic viscosity,
and gel strength. May have to be tailored to provide fluid lifting
capacity required to bring sand or cuttings to the surface at
reasonable circulating rates.
Lab tests show that many viscosity builders cause permanent reduction
in permeability. This can be minimized by careful polymer selection
along with adequate fluid Joss control to limit invasion.
6. Corrosion Products
The fluid should be chemically stable so that reaction of
free oxygen with tubular steels is minimized, and that iron
in solution is sequestered and not permitted to precipitate
in the formation.
A reasonable upper limit on corrosivity for a completion or
workover fluid is 0.05 Ib/ft2. (About 1 mil) per workover. For a
packer fluid, the corrosivity target should be about 1 mil per
year, but 5 mils per year are considered to be an acceptable
upper limit.
7. Mechanical Considerations
Rig equipment available for mixing, storage, solids removal, and
circulating is often a factor in fluid selection
8. Economics
The most economical fluid commensurate with the well's susceptibili
to damage should
Prepared Salt WaterFresh water is often desirable a basic fluid due to the difficulty of
obtaining clean sea or formation water
Desired type and amount of salt is then added. Where clean
brine is available at low cost, it may be preferable to purchase
brine rather than mix it on location.
Practicalities
From the standpoint of preventing formation damage in sandstones
due to disturbance of montmorillonite or mixed-layer clays, the
prepared salt water should, theoretically, match the formation water in
cation type and concentration.
PERFORATION FLUIDS
Perforating fluids are not necessarily-a distinct type of fluid, but are
distinguished here to emphasize the importance of perforating in a nosolids fluid .
Salt Water or Oil
When clean, these do not cause, mud plugging of perforations, but
if the pressure differential is into the formation, fine particles of
charge debris will be carried into the perforation.
Acetic Acid
Nitrogen
This has advantages as a perforating fluid in low pressure
formations, or where rig time or swabbing costs are very
high, or where special test programs make it imperative that
formation contamination be avoided.
Gas Wells
These can be completed economically in clean fluid by
perforating one or two holes, bringing the well in and cleaning to
remove as much well bore fluid as possible, then perforating the
remaining zones as desired.
PACKER FLUIDS
Criteria Water-base drilling mud as used today are generally not good packer mud.
Recommendation:
1. Use diesel oil or sweet crude treated with an inhibitor where density
requirements permit.
2. Use clear water or brine with an inhibitor and a biocide. Inhibitor and
biocide must be compatible.
Condition B
No high strength pipe involved in completion. Fluid density greater
than 11.5 ppg required. Bottom-hole temperature does not exceed
300F.
Recommendation:
Condition C
A.No high strength pipe involved in completion. Density of more
than 11.5 ppg required. Bottom-hole temperature exceeds 300F.
Recommendation:
1. Use properly formulated oil mud.
Condition D
High strength pipe to be used. Under any condition of fluid density or
bottom-hole temperature.
Recommendation:
1. Where fluid density requirements permit, use oil treated with both an
oil-soluble and a brine-dispersible corrosion inhibitor.
2. Use oil mud formulated to meet density and temperature
requirements.
Well KIWNG
'Circulation rather than bull heading is the preferable, way to kill conventional
completions.
An adjustable choke should be used to hold casing back pressure on the
formation when killing a well by circulation. For a high pressure well, a Swaco
well. Control choke may be desirable.
STIMULATION
Stimulation Methods
Well stimulation was mentioned as a means of increasing well
productivity. Several methods may be applied, depending on
the individual situation.
The three principal stimulation methods in their chronological
order of development are:
1. Nitro-shooting.
2. Acidizing .
3. Hydraulic Fracturing.
Nitro-shooting
The use of explosives to improve productivity is practically as old as the oil
industry
Benefits:
1.
2.
3.
4.
Limitations:
1. Clean out problems and expense.
2. Hazard to personnel, well, equipment.
3. Limited to open-hole completions.
Acidizing:
Goal of Acidizing
0 _______________ 1 m
Benefits:
1. Moderate bore-hole enlargement.
2. Primarily adapted to formations of appreciable calcareous content
(not generally adaptable to sandstone).
3. Cleans out, enlarges, and interconnects fractures, vugs, other
channels.
4. Stimulant relatively inexpensive.
5. Adaptable to both open-hole and set-through completions.
Limitations:
1. May require residue cleanout.
2. Somewhat hazardous and corrosive.
Hydraulic Fracturing
The basic procedure involves
the injection of a fracturing fluid and propping agent into the pay
zone under sufficient pressure to open existing Fractures and/or
create new ones.
These are extended some distance around the well by continued High
pressure injection after the initial breakdown or rock rupture has
occurred. Upon cessation of pumping (as pressure is reduced) the
fractures remain open, being held in place by the propping agent, a
carefully sized, silica sand. This process is applicable to virtually all
reservoir rocks and may be combined with acid treatments in
limestone areas.
Fracture fluid:
Early fracture techniques generally utilized thickened gels made from
kerosene and diesel oil. Currently, lease crude oil is the principal
Fracture fluid; it may be thickened by additives if necessary for sand
suspension.
Fluids native to the formation are less prone to damage permeability
and should be used if available.
Gas wells have been treated with water-base fracture fluids, however,
fresh water should not be used if the sand is susceptible to clay swelling.
Combined acid-fracture treatments using gelled acid or acid-oil
emulsions have been successfully applied in various carbonate areas.
Sand-fluid ratio:
Sand concentrations of 1/2 to1/4 lb/gal have been frequently used
in fracturing. It is difficult to define any universally applicable
optimum concentration and quite possibly such a figure may vary
with the area. From field experience, it appears that 1 to 2 lb /gal is
the most commonly applied range of concentration.
Size of treatment
In moderate to high permeability zones which have been badly
damaged during completion, small treatments may be completely
adequate.
In tight zones, the large volume treatment may give optimum
results.
The economics of treatment size requires careful analysis; it is
certain that considerable
Benefits:
1. No bore-hole enlargement.
2. Highly flexible procedure:
a. Permits multiple or single fracture.
b. Can combine advantages of fracturing and acidizing.
c. Wide latitude of sand-carrier agent.
3.
4.
5.
6.
Limitations:
1.
2.
3.
4.
5.
SQUEEZE CEMNTING
Squeeze Cementing
The technical literature contains a
number of papers on squeezing
wells. Still, many unanswered
questions are frequently asked.
Where does the cement go on a
squeeze job?
What is formation breakdown
and is it necessary?
Should water or mud be used for
breakdown?
Will squeezed cement completely
surround a wellbore?
Can perforations be plugged with
cement?
Can the quantity of cement be
controlled during placement?
Mud-Plugged Perforations
Perforations will usually have some degree of mud fill-up,
depending on the completion fluid or primary cementing
technique and the breakdown process.
Mud filter cake is capable of withstanding high pressure
differentials, especially in the direction from the wellbore to the
formation and the high pressures may create a fracture before
accepting cement filtrate.
Selective breakdown and cleanup of single perforations prior to a
stimulation treatment have revealed the presence of as much as
1000 psi higher pressure on an adjacent perforation.
Many squeeze failures may be attributed to subsequent cleanup
of a previously plugged perforation which did not accept the
cement slurry during the squeeze job.
Hole Conditions
It is absolutely necessary for the hole to be in good condition
before starting a remedial squeeze job; otherwise, the problems
may become multiplied because of some condition that would be
adverse to the operation .
The casing should be in gauge, clear of debris, and clear of any
residual cement sheath from a previous operation.
A packer miss run may result because the packer seat could not
be reached or attained.
A scraper and bit should be run to check this condition and total
depth tagged up to be sure fill up is not excessive.
The hole should be circulated until clean and balanced.
. Gas "bullheaded" into the formation ahead of the cement could
percolate through the cement and leave the cement
honeycombed.
Packer Seat
A squeeze packer should be set as closely as practical to
the squeeze target .
This leaves the least completion fluid in the rathole to
be forced ahead of the cement into the formation.
Any appropriate connection that will seat the packer
between 30 to 60 feet above the squeeze target will
allow an error of one joint of tubing.
Special cases such as a low pressure zone which will
require a hesitation-type squeeze may require setting
the packer much higher so that the hesitation process
may begin with cement below the packer.