Precast Technology With The Case Study of BWSL
Precast Technology With The Case Study of BWSL
Precast Technology With The Case Study of BWSL
Particulars
Pg no.
3
Types and procedure of precast concrete construction
12
Precast technology in residential building
21
Case study on the precast technology in Bandra worli
68
sea link (BWSL)
Research paper study on the future of precast
94
technology in law rise building
Precast technology
Subject:
Topic:
Precast technology
Date:
Precast Concrete
Introduction to precast concrete
Types and procedure of precast concrete construction
Precast technology in residential building
Case study on the precast technology in Bandra worli
sea link (BWSL)
Research paper study on the future of precast
technology in law rise building
Video on manufacturing of precast wall
Video on installation of precast modular pavement
Precast Concrete
Precast concrete is a construction
product produced by casting concrete in
a reusable mould or "form" which is then
cured in a controlled environment,
transported to the construction site and
lifted into place. In contrast, standard
concrete is poured into site-specific
forms and cured on site.
4
History
precast paneled buildings were pioneered
in Liverpool England, in 1905
A process was invented by city engineer John
Alexander Brodie.
Between 1917 and 1932, they erected 145
such buildings
Why Precast???
Speed to market
Strong image
High quality
Low maintenance
Effective pricing
Safety
Early input
Why precast ?? As a
Project Manager
Raw Materials
Portland cement
water
Sand
Gravel
admixtures
For light weight
clay, shale, or slate
pumice and scoria blast furnace
Design
The shapes and sizes of most common concrete blocks have been
standardized to ensure uniform building construction.
block design, called a split-faced block, includes a rough, stone-like
texture on one face of the block instead of a smooth face
we must consider not only the desired shape, but also the
manufacturing process required to make that shape
We must consider the utility facility requirements in building during
design
10
Procedure for
precast
manufacturing
11
12
13
Assembly of moulds
14
15
16
17
18
Transport to site
19
Erection at site
20
21
Large-Panel Systems
The designation large-panel system refers to multistory structures
composed of large wall and floor concrete panels connected in the
vertical and horizontal directions so that the wall panels enclose
appropriate spaces for the rooms within a building. These panels
form a box-like structure
22
Large panel
23
24
Frame Systems
Precast frames can be constructed using either linear
Elements or spatial beam-column sub assemblages.
Precast beam-column sub assemblages have the advantage that the
connecting faces between the sub assemblages can be placed away from
the critical frame regions; however, linear elements are generally
preferred because of the difficulties associated with forming, handling,
and erecting spatial elements.
The use of linear elements generally means placing the connecting faces at
the beam-column junctions.
25
Installation CONSIDERATIONS
26
Crane Position
27
28
Setting Out
1. Surveyor to set cross reference.
2. Transfer grid and mark wall position on slab.
3. Mark 100mm offset line from rear building
edge.
4. Offset wall position by 200 mm.
5. Secure 2x2 timber to the floor at wall edge to guide wall.
29
Setting Out
30
31
Wall Positioning
1. The first wall in place has to be the partition wall
at the rear.
2. Mark a line parallel to and 100mm from the
external edge of the wall.
3. Place shim plate @~500 c/c on the floor and
level to wall soffit. Shim plate may also be
placed on Non-shrink mortar bed and allow to
set.
4. Adjust position of the dowel bar.
32
Setting Out
33
34
Wall Adjustment
1. Position adjacent walls and plumb wall corners
at 200 mm offset
2. Adjust verticality until within +2 or 2 mm
3. Ensure the four faces of every walls are
adjusted
4. Position string 250 mm from face of walls
5. Walls within the same line are to be adjusted
within same tolerance
6. Ensure air-pocket is fully grouted
35
Wall Adjustment
36
37
39
40
41
42
Staircase
1. Position landing or slab and verify soffit
level at four corners.
2. Adjust level to within tolerance.
3. Position shim plates at staircase support
location to correct level.
4. Verify level difference between pegs on
top and below.
5. Hoist staircase in place.
6. 10mm gap between precast plank andstaircase
43
Staircase
44
45
Installation Requirements
Elements of control
Alignment, Verticality and Levels
Tolerance level
1. For Wall
Vertical deviation +2 mm, -2 mm
Horizontal deviation 0 mm
46
Connection types
47
48
Columns Connection
49
50
Beam-column connection
51
52
Slab-Beam Connection
53
54
CONSTRAINTS
SOLUTIONS
and
components.
! Study the locality and look for at
available space
for turning. Have one worker direct traffic while crane
and trailer is turning.
The
consultants must write
Board for approval much earlier
begins.
in to National Parks
before
construction
55
56
57
Cost saving
58
59
Time saving
60
61
Time comparision
62
Material saving
63
Limitations
Each panel variation (especially openings, bracing inserts and lifting inserts) calls for complex, specialized
engineering design.
It is often more expensive than alternatives (can be offset by reduced construction times, earlier access by following
trades, and simplified finishing and services installation).
Building services (power, water and gas outlets; conduits and pipes) must be accurately cast in and are difficult to add or
alter later. This requires detailed planning and layout at design stage when plumbing and electrical trades are not usually
involved.
Panel connection and layout for lateral bracing requires detailed design.
Temporary bracing requires floor and wall inserts that have to be repaired
later.
64
Dr Jacqueline Glass is the British Cement Association Senior Lecturer in the School of Architecture at
Oxford Brookes University where she has been carrying out research in concrete construction since 1994.
Dr Glass is currently Project Manager of an EPSRC funded research project in innovation in reinforced
concrete and has previously contributed to Partners in Technology projects on
tilt-up and hybrid concrete construction. Dr Glass is Architectural Consultant to the British Cement
Association and the Reinforced Concrete Council and is an active participant on several concrete industry
trade associations. She has published widely in both trade journals and scholarly publications and has
lectured in the UK and USA on a broad range of concrete related topics.
65
This report is about the future use of precast concrete in low-rise housing in the UK. It has been
produced in response to a growing level of interest in prefabrication.
focuses on the use of precast concrete, and considers the history of precast concrete in housing
examines the key features of concrete in general, and precast concrete specifically. Fire resistance,
thermal mass, acoustic insulation and durability are included together with a discussion of cost and value
issues
considerations such as services integration and adaptability are related to the future needs of
occupants, and procurement strategies are noted.
66
67
Case study on
Precast deck of
BWSL
68
: 5.6 kilometres
Width
Height
69
70
SAGMENT PARAMETERS
Length:1.5m to 3.1m.
post tensioned
72
60
73
75
1)
2)
Turn Buckles
3)
4)
Tower Crain
5)
Concrete Pumps
6)
of
segments.
76
77
78
79
80
65
Casting Yard
81
82
83
Erection of segment
84
Launching Truss: Weighing 1250 tonnes and measuring 112 m in length, it was used for lifting segments
each weighing 130 tonnes. This has been fabricated in India.
Flat barge: Size 30x12x2m. Like motor boats, they are driven inside the sea for material transportation.
Crawler crane: Capacity ranges from 75-150 tons. It is used for material and heavy lifting activities.
13 barges for concrete
eight steel boats
three tug boats
six smaller passenger boats.
85
86
71
87
Erection of segment
88
72
89
90
91
Solution
Excavation of the ground to a depth of ~
2.5Mtrs.
Strengthening the ground using rubble soling
and filling the voids with sand.
The soling thus done was compacted layer by
layer using vibratory rollers.
Total area of the Pre-cast Yard was covered with
a layer of PCC.
RCC Footing done to facilitate storing of
segments.
92
The superstructure of the approach bridges was the heaviest spans in the country
to be built with span-by-span method using overhead gantry through a series of
vertical and horizontal curves.
Erection of 20000 MT Bandra cable-stayed deck supported on stay cables within a
very close tolerance of deviations in plan and elevation.
93