Progress Report - TT14259-PGB-611 & 644 - 05.01.15 PDF
Progress Report - TT14259-PGB-611 & 644 - 05.01.15 PDF
Progress Report - TT14259-PGB-611 & 644 - 05.01.15 PDF
REPORT
PROJECT
FABRICATION SCHEDULE FOR 6 UNITS OF TUBE BUNDLE T2-661 & T2-644, T3-661 &
T3-644, T4-661 & T4-644 AND SUPPLY OF 1000 PIECES OF LOW FINNED TUBES FOR
PGB, KERTEH.
CLIENT
ITEM
PROJECT NO
TT14259
DOCUMENT No.
DOCUMENT TITLE
15.01.2014
FOR INFORMATION
Wan
Zai
JL
Issued
Date
Description
Prep'd
Chk'd
App'd
Client
Page 1 of 3
TT12131
CLIENT :
TITLE :
REPORT DATE :
01/01/2015 - 15/01/2015
Date Start :
REPORT NO :
Date Finish :
26.02.2015
Report Date : 15.01.2015
Week Duration : 8-9 Week
23.01.2015
Description
Weightage
Engineering
Procurement
Fabrication
Inspection & Testing
Packing & Shipping
Overall
Plan %
Actual %
Variance
11.00%
29.00%
43.00%
11.00%
6.00%
5.00%
8.60%
0.00%
0.00%
0.00%
4.30%
7.20%
0.00%
0.00%
0.00%
-0.70%
-1.40%
0.00%
0.00%
0.00%
100.00%
13.60%
11.50%
-2.10%
Remarks
Description
Engineering & VDRL Design and drawing - in progress, visit PGB to get clear copy DOSH Submission, 3rd Party, Client approval
of drawing
Procurement
Expediting tube delivery status, forge material procurement air freight option
Fabrication
Baffle fabrication
5
6
Area of Concern
Remedial Measures
DOSH HQ Approval
Status
Pending submission
% completion
100.0%
80.0%
60.0%
40.0%
20.0%
0.0%
10
12/24
12/31
1/7
1/14
1/21
1/28
2/4
2/11
2/18
2/25
3/4
Progress Plan
0.0%
0.7%
6.5%
13.7%
22.3%
30.9%
38.1%
49.6%
65.5%
81.3%
100.0%
Actual Plan
0.0%
1.4%
5.8%
11.5%
Page 2 of 3
TT12131
CLIENT :
TITLE :
REPORT DATE :
01/01/2015 - 15/01/2015
REPORT NO :
Date Start :
23.01.2015
Date Finish :
Report Date :
26.02.2015
15.01.2015
NIL
Page 3 of 3
FABRICATION SCHEDULE FOR 6 UNITS OF TUBE BUNDLE T2-661 & T2-644, T3-661 & T3-644, T4-661 & T4-644 AND SUPPLY OF 1000 PIECES OF LOW FINNED TUBES FOR PGB, KERTEH.
ID
Task Name
Duration
Start
Finish
%
January 2015
February 2015
March 2015
Complete W1
W2
W3
W4
W5
W6
W7
W8
W9
W10
W11
W12
W13
W1
21 2325272931 2 4 6 8 10 12141618202224 262830 1 3 5 7 9 1113 151719 21232527 1 3 5 7 9 11 13151719 21232
Sun 22/2/15
14%
56 days
Tue 23/12/14
0 days
Tue 23/12/14
Tue 23/12/14
100%
1 day
Mon 5/1/15
Mon 5/1/15
100%
4 days
Tue 6/1/15
Fri 9/1/15
100%
3 days
Sat 10/1/15
Mon 12/1/15
50%
3 days
Tue 13/1/15
Thu 15/1/15
0%
35 days
Thu 15/1/15
Sun 22/2/15
0%
38 days
Tue 6/1/15
Mon 16/2/15
36%
Confimation of order
Materials procurement
10
11
12
13
5 days
Tue 6/1/15
Sat 10/1/15
100%
30 days
Wed 14/1/15
Mon 16/2/15
25%
12 days
Tue 6/1/15
Sat 17/1/15
25%
12 days
Tue 6/1/15
Sat 17/1/15
25%
35 days
Sun 18/1/15
Wed 25/2/15
0%
1 day
Sun 18/1/15
Sun 18/1/15
0%
23/12
Kick Off Meeting
Design and drawings
Submit to Third Party for verification
Submit to PGB for review
Submit & Approval to DOSH for app
Tube materials - Stock
Tube sheets. Body flanges etc.
Baffle plates, tie rods, spacers etc.
Materials inspection (Plates and tubes)
14
15
12 days
Mon 2/2/15
Sun 15/2/15
0%
16
1 day
Tue 17/2/15
Tue 17/2/15
0%
17
5 days
Wed 11/2/15
Sun 15/2/15
0%
18
1 day
Wed 18/2/15
Wed 18/2/15
0%
19
1 day
Thu 19/2/15
Thu 19/2/15
0%
20
2 days
Tue 17/2/15
Wed 18/2/15
0%
21
0.5 days
Fri 20/2/15
Fri 20/2/15
0%
22
1 day
Mon 23/2/15
Mon 23/2/15
0%
23
1 day
Tue 24/2/15
Tue 24/2/15
0%
24
1 day
Wed 25/2/15
Wed 25/2/15
0%
58 days
Thu 25/12/14
Thu 26/2/15
39%
Sun 25/1/15
75%
25
26
30 days
Thu 25/12/14
27
15 days
Mon 26/1/15
Fri 13/2/15
0%
28
Finning works
12 days
Sat 14/2/15
Wed 25/2/15
0%
29
Delivery to site
1 day
Thu 26/2/15
Thu 26/2/15
0%
Task
Milestone
External Tasks
Split
Summary
External Milestone
Progress
Project Summary
Deadline
Page 1