Introduction To Project Planning & Management: CEM Solutions
Introduction To Project Planning & Management: CEM Solutions
CEM Solutions
Objectives of Today
1.
2.
3.
4.
5.
Henry Gantt
Gantt Charts
Henry Fayol
A Gantt chart created using Microsoft Project (MSP). Note (1) the critical path is in red, (2) the
slack is the black lines connected to non-critical activities
Resources
A
Labor (Skilled)
Labor (Unskilled)
Machinery
Materials
Project Management
Initiation
Planning and design
Execution and construction
Monitoring and controlling systems
Completion & closing
Planning
Resources
Cost
House # 2
Architectural Works
Up to Ground Floor
Main Project
House # 3
Electrical & Plumbing
WBS Level 1
WBS Level 2
WBS Level 3
Architectural Works
Up to Ground Floor
House # 2
House # 3
WBS Level 1
WBS Level 2
Earth Compaction
Main Project
WBS Level 3
Activities
Architectural Works
Up to Ground Floor
House # 2
House # 3
WBS Level 1
WBS Level 2
Earth Compaction
Main Project
WBS Level 3
Activities
Relationships