Purpose:
The purpose of this procedure is to provide a system to ensure that
materials and key consumables are properly identified and traceable at all
stages starting from receipt, storage, issue and assembly into the final
product during execution of M1 project.
2.0
Scope:
This procedure shall apply to the project material and consumables that
become part of the final/permanent facilities used for Infrastructure M1OL2K project.
3.0
4.0
References:
03IN03-066/GS/PQP/003 :
G8S-6500-01
G8S-6500-02
G8S-6500-03
Abbreviations/Definitions:
Owner
GS
Contract
LE (QC)
QCI
MRR
5.0
:
:
Procedure:
Material that form part of final/permanent installations shall be identified,
and monitored for meeting traceability requirements from the receipt
stage to final assembly.
5.1
Page 3 of 5
Date: 31-May-06
of
5.1.3 While delivered items are awaiting receipt inspection under inspection
tags/boards are placed to clearly identify the status of the materials.
Inspected materials are accepted/cleared for use, are stacked in the
designated storage areas. Identified/tagged with delivery order number as
applicable.
5.1.4 The products that are found not complying with the requirements of
project specifications and material requisition, material receipt report will
be forwarded to the Owner material control for further action. Until the
product is confirmed acceptance for use, it is placed in designated
quarantine location and listed in the quarantined item list for monitoring
its status.
5.1.5 The material controller will organize of non-conforming products to the
designated quarantine area and where there is a mixture of materials to
be quarantined, they shall be suitable type with respect to the materials to
be stored, and controlled storage areas shall be provided where necessary.
Only upon completion of satisfactory disposition and after acceptance of
the disposition by the QA/QC team the material can if accepted, be moved
to the designated storage areas.
5.1.6 Material status in terms of under inspection accepted stock and
quarantined is monitored by the Material Controller on regular basis.
All MRRs pending inspection are filed separately and the file handed over
to QA/QC team for clearance. MRRs on approval are removed from this file
and transferred to the accepted MRRs file. These files lively updated, and
the status of items pending inspection can be obtained from this file at
any time: a list for pending MRRs is prepared and communicated
internally.
Accepted Stock status can be obtained from computerized stock status.
5.1.7 All accepted materials shall be stored in container, covered or open (as
appropriate) warehouse and under stores direct control to prevent
unauthorized use. Requirement for material storage and issue are coved
in the procedure number: 03IN03-066/GS/QP/016.
5.2
GS Doc.No. 03IN03-066/GS/QP/019
M1 Project Rev.No.0
Al-Shuaiba, Kuwait
Page 4 of 5
Date: 31-May-06
The QA/QC team complies test packs, welding history sheets, which
includes all materials, location, testing and inspection data and results
required to meet traceability requirements.
Surplus materials at the end of the Project are listed with identification
details and forwarded to the Owner.
Documentation:
The following is the documentation required to comply with the
requirement of this procedure:
Delivery Notes
Tally sheets
Packing Lists
Material Receipt Report
Identification Tags
Bin Cards
Quarantined item list
Issue Slips
Inspection Reports
Test packs
Welding History Sheets
Material / Test Certificates
Welding Reports
Attachments:
1. Product Identification for critical Raw materials
2. Colour coding for Piping materials
3. Colour coding for Gasket materials
GS Doc.No. 03IN03-066/GS/QP/019
M1 Project Rev.No.0
Al-Shuaiba, Kuwait
Page 5 of 5
Date: 31-May-06