Schedule Level of Details
Schedule Level of Details
37R-06
2 of 7
(PUBLIC REVIEW DRAFT) Schedule Levels of DetailAs Applied in Engineering, Procurement, and
Construction
3 of 7
(PUBLIC REVIEW DRAFT) Schedule Levels of DetailAs Applied in Engineering, Procurement, and
Construction
Description
End Usage
(PUBLIC REVIEW DRAFT) Schedule Levels of DetailAs Applied in Engineering, Procurement, and
Construction
4 of 7
June 23, 2009
Level 2
Level 3
Level 4
Level 5
(PUBLIC REVIEW DRAFT) Schedule Levels of DetailAs Applied in Engineering, Procurement, and
Construction
5 of 7
June 23, 2009
As the project moves into subsequent phases and more scope information becomes available, the
schedule is revised to reflect this additional detail (which is sometimes referred to as a rolling-wave
method of scheduling). For example, an EPC schedule early in the project could be developed to Level 3
in terms of the detailed engineering/design phase, but the procurement and construction phases might
only be detailed to Level 1 or 2. This would be generally true at conceptual design, or at the basic
(preliminary) design stage (or phase).
The EPC Level 1 schedule summarizes the overall project for client and management. EPC Level 1
schedules show start and finish dates for the major project phases and key milestones (such as design,
procurement, construction, and commissioning and start-up). Significant contract milestones and projectspecific milestones or activities are included in EPC Level 1 schedules as required by the project
execution plan.
EPC Level 2 schedules contain more detailed activities for each of the summary phases previously
identified in the Level 1 schedule. This often includes a breakout of the various trades or disciplines
responsible for the activities in each phase, the critical procurement activities, the major elements of
construction, and general commissioning and start-up requirements. Generally in the EPC Level 2, this is
the first level of scheduled detail where logical links or task relationships may be shown.
EPC Level 3 is the first level where the full use of critical path method (CPM) techniques could be shown
effectively. In addition to start and finish dates for each grouping of deliverables or activities within each
phase of the project, EPC Level 3 schedules include major review and approval dates as well. Most EPC
schedule models are not developed below Level 3 in terms of CPM activity detail, with the intent to keep
the schedule broad enough to be described for any specific project.
Since EPC schedule levels are normally limited to Levels 1 through 3, sometimes an external schedule
or set of schedules would be included for a project. These external schedules are called Level 4.
EPC Level 4 are detailed work schedules and would be prepared outside of the CPM software, The
theory is, that if there is too much detail within the CPM network, the schedule would not only lose its
flexibility as a value-added tool to manage the job, but schedule maintenance would become difficult, due
to the greater effort needed to maintain the CPM logic after each progress update. A variety of software
tools can be employed to develop work schedules at Level 4 and below: spreadsheets, databases, and
word processing are all utilized.
Descriptive Methodology
The descriptive levels methodology that has been utilized by the construction industry simply uses
descriptive words in place of numerical levels to identify the desired level of a schedule detail. Because of
the varied background and confusion of the previously described mutually-exclusive schedule levels, this
often results in misunderstandings due to the inconsistent numbering systems or confusion regarding the
descriptive terms. For example, a Summary schedule and a Master schedule are not the same thing. A
Master schedule is a consolidated schedule that incorporates multiple, related projects or parts of a
project so that they can be monitored and controlled as a unit. Therefore this has stimulated the need to
clarify the similarities and the distinctive characteristics of these schedule levels descriptions as follows:
Program/ Project Summary Schedule
The Summary schedule contains the least amount of detail and is a summary the overall program or
project timeline for client and upper management. Typically the summary schedule includes the status of
major functions and milestone objectives. The program or project owner provides the basic guidance of
the project's scope to establish this schedule. The program summary schedule is a timeline of the various
related projects.
Milestone Schedule
(PUBLIC REVIEW DRAFT) Schedule Levels of DetailAs Applied in Engineering, Procurement, and
Construction
6 of 7
June 23, 2009
Project milestone objective (target) dates are determined during the development of the project
conceptual basis and are presented in this schedule. The milestone schedule can be either in a tabular
or time scaled graphic format.
Project Level Schedule
The project level schedule is an activity and deliverable-centered schedule. Typically consisting of the
major project phases and features of work, the project level schedule integrates the projects engineering,
procurement and construction activities in time scaled network logic or bar charts. The CPM scheduling
technique is used to develop the project level schedule and the project critical path can be identified.
Project Control Schedule
The project control schedule is the detailed CPM schedule indicating the planned sequence to perform
the work. The project control schedule clearly shows work by responsibility and is usually presented in bar
chart or tabular format. The construction phase schedule indicates the planned sequence to perform the
work, requirements for manpower and equipment, access and work space limitations, and reflect activities
of subcontractors, equipment vendors and suppliers. Project control schedules include activities for key
design documents to/from design consultants, subcontractors and key vendors, preparation of design
calculations, construction and pre-commissioning documents, drawings, materials, and commissioning
interface (by others) activities. Each of the responsible project participants is responsible to maintain and
status the performance of their work activities. The project control schedule must include the entire project
scope of work, identify interfaces and potential impacts to other contractors, operations and maintenance
shutdowns, delays and disruptions, and is to be used for progress and performance measurement.
Look ahead Schedule
The project master CPM schedule can produce a detailed look-ahead schedule in bar chart format
showing activities for a period of time less than the total project duration. The look-ahead schedule
highlights the near term priorities for each of the project team participants and is periodically reviewed at
site meetings so responsibilities can be confirmed, actual dates and progress assigned, and potential
conflicts and interferences prevented.
The look-ahead schedule would be developed with the relevant superintendent and field engineers for
each trade or craft discipline and ultimately would integrate all of the crafts work schedules. A combined
look-ahead schedule includes the past period actual or as-built performance as the first of a four-period
schedule with the three-period look-ahead period. Routinely, look-ahead time periods are three-weeks to
90-days. Turn-around schedule activities used for refineries and process production plants are usually
much more detailed and, thus, cover a shorter look-ahead calendar time period. Turn-around schedule
activities are measured in minutes or hours instead of rather than days.
Task Lists
To manage daily work activities and provide the craft or crews with the proper tools and equipment when
needed, individual or crew task checklists are often developed. These are non-CPM task or work lists
that allow a project team to plan and document their work on a more detailed basis.
Supporting Data
An additional level of non-CPM detail would be project-supporting data that is usually compiled in
spreadsheets or databases. These would be schedule narratives, project submittal registers, requests for
information, punch lists and similar collections of data that contain time-sensitive components.
REFERENCES
1. AACE International Recommended Practice 10S-90, Cost Engineering Terminology, AACE
International, Morgantown, WV, (latest revision).
2. Hollmann, John K., PE CCE, Editor, Total Cost Management Framework: An Integrated Approach to
Portfolio, Program and Project Management, AACE International, Morgantown, WV, 2006.
(PUBLIC REVIEW DRAFT) Schedule Levels of DetailAs Applied in Engineering, Procurement, and
Construction
7 of 7
June 23, 2009
th
3. Amos, Dr. Scott J., PE, Editor, Skills & Knowledge of Cost Engineering, 5 Edition, AACE
International, Morgantown, WV, 2004.
4. Construction Industry Institute (CII) Publication 6-5 (September 1987), Project Control for
Construction, Reviewed by CII June 23, 2004, Construction Industry Institute, Austin, TX, 2004
5. Humphreys, Kenneth K., PE CCE, Editor, Jelens Cost and Optimization Engineering, 3rd Edition,
McGraw-Hill, New York, NY, 1991
6. Lewis, James P., Project Planning, Scheduling and Control, 3rd Edition, McGraw-Hill, New York, NY,
2006.
7. OBrien, James J., Plotnick, Fredric L., CPM in Construction Management, 6th Edition, McGraw-Hill,
New York, NY, 2006
8. AACE International Planning & Scheduling Committee Forum message exchange, November 2007,
www.aacei.org/forums.
9. Stephenson, H. Lance, CCC, Schedule Management: Schedule Classifications vs. Levels, AACE
International Transactions, AACE International, Morgantown, WV, 2007.
10. Woolf, Murray B., FASTER Construction Projects with CPM Scheduling, McGraw-Hill, New York, NY,
2007.
CONTRIBUTORS
Edward E. Douglas III, CCC, PSP (Author)
Christopher W. Carson, PSP
Paul E. Harris, CCE
John K. Hollmann, PE CCE CEP
Donald F. McDonald, Jr. PE CCE PSP
Stephen E. Mueller, CCC EVP
Michael R. Nosbisch, CCC PSP
Anthonius Pramudhito
Arash Ranjbaran, PSP
Dr. Randy R. Rapp, PE CCE
H. Lance Stephenson, CCC
Ronald M. Winter, PSP