The document is a 10-page checklist in Chinese for validating site survey information against existing site conditions for a wireless network project. It includes checks for basic site information, antenna and equipment details, available space, power infrastructure, photos, proposed design solutions and bills of materials. Sections cover validating the location, equipment, power sources, solutions, drawings and layouts according to the survey data and design requirements.

Uploaded by

Jily Rain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
268 views10 pages

Check List

The document is a 10-page checklist in Chinese for validating site survey information against existing site conditions for a wireless network project. It includes checks for basic site information, antenna and equipment details, available space, power infrastructure, photos, proposed design solutions and bills of materials. Sections cover validating the location, equipment, power sources, solutions, drawings and layouts according to the survey data and design requirements.

Uploaded by

Jily Rain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 10

Proprietary Confidential

ZTE

Check Point
Site Location
Basic Information

Site/Tower Owner
Site Type

Ant amount

Ant Type
Ant on the tower Vakidation
(RF&MW)
Ant Height

Ant Size

Space Validation

Ground Available
Space

Tower Available
Space
AC Power
Power Info. Validation

DC Power

<>

10 , 1

Proprietary Confidential

ZTE

Power Info. Validation


Battery

<>

10 , 2

ZTE

Proprietary Confidential

Check List
1.Site Address of survey site is correct or not;
2.Site coordinate is correct or not;
3.Site ID match the coordinate and address or not;
1.Site/Tower Ower is correct or not;
2.Site/Tower Ower ID correct or note;
1.The site type is same with the survey or not;
2.Tower type is same with the survey or not;
3.Tower height is same with the survey or not;

Score
3
3
3
3
3
3
3
4

1.The RF Ant amount is same with the survey data or not;


2.The quantity of RF Ant for each tower leg is same with the survey data or
not;

3.The MW Ant amount is same with the survey data or not;


4.The quantity of MW Ant for each tower leg is same with the survey data
or not;
1.RF Ant type is same with the survey data or not;
2.MW Ant type is same with the survey data or not;

1.The actually RF Ant height is same with the survey data or not

2.The actually MW Ant height is same with the survey data or not

3.The actually RF Ant azimuth is same with the survey data or not

4.The actually MW Ant azimuth is same with the survey data or not

1.Actually RF Ant size is same with the survey data or not

2.Actually MW Ant size is same with the survey data or not


1.The pad/ground/shelter/room available space is same with the survey
data or not;
1.The pad/ground/shelter/room available space is same with the survey
data or not;
2.The sizt of existing Pad/ground/shelter/room is same with the survey
data or not;
3.The existing equipment on the existing pad / in the shelter/room is same
with the survey latout or not;

1.Tower available space is same with the survey data or not;

1.Existing AC Power information is same with the survey data or not;

1.Existing AC Power information is same with the survey data or not;

<>

4
3
3

4
4
4
4

10 , 3

ZTE

Proprietary Confidential

1.Existing battery information is same with the survey data or not;

<>

10 , 4

Check point
Tower Provier

Site ID

Basic Information
Checking

Vertical Space On Tower

Site Type(GF/RT, tower


type)
Information Filling

Ant Amount

RF&MW Information
Checking

Ant Type

Ant Size

RRU Quantity

Smartfren Equipment
Room
Smartfren Tower/Pole
Layout Checking
Ground Available Space
Cable Tray & Rounting
Power Info. Validation

Power Info. Validation

Check List

Score

1.Tower provider is correct or not

1.Tower provider ID is correct or not

2.SF ID is correct or not


3.ZTE ID is correct or not

5
5

1.Vertical Space On Tower is match with the


existing RF&MW information or not

1.Site type must match with the survey pictures


and the layout

2.The tower type must match with the pictures

1.Other information need filling

1.The existing RF Ant amount match with the


survey pictures or not

2.The existing MW Ant amount match with the


database or not
3.The new RF Ant amount match the database or
not
4.The new MW Ant amount match the database
or not
1.The new RF Ant type match the
solutionTDD/FDD/TDD-FDD

5
5
5
4

1.The RF Ant size match the the type;

2.The MW size match the MW planning


database;

1.RRU quantity match the


solutonTDD/FDD/TDD-FDDor not

2.The solution need the filter or not;

1.The layout of the site need show the Smartfren


equipment room/pad clearly

1.The layout of the site need show the Smartfren


tower/pole clearly
1.The layout of the site need show the Smartfren
available clearly

4
4

1.The layout of the site need show the Smartfren


equipment rounting clearly

1.Power information match the Power database


or not;

Check Point
Site
Location(Address/Coordinate)

Site Type(GF/RT, tower type)

Current Information Checking


Ant on tower checking(RF&MW)

Civil work

Existing GPS systeam

Wireless Solution
Preliminary Solution

TX solution
Photo Remark Checking

Photo list

Check List
1.compare with the database,checking the site address and
the coordinate correct or not

1.The site type match with the survey picture or not;


2.Tower type is same with the survey pictureor not;
3.Tower height is same with the survey or not;
1.The existing RF&MW Ant amount is same with the survey
pictures and CAF or not;
2.The existing RF&MW Ant height is same with CAF ornot
3.The existing RF&MW Ant azimuth is same with CAF or
not
4.The existing feeder/Jumper information have been filled or
not
1.The Dimension of the existing pad/shelter match with the
drawing or not
2.The Space available for new equipment is match the
survey picture and the drawing or not
1.The information of GPS have been filled or not
1.The solution model is correct or not;
2.Site configuration information match the survey pictures or
not;
3.Power configuration information
(preliminary stage) match the survey pictures or not;
4.Battery solution match the Power Database or not
Antenna suggestion (preliminary stage) is correct or not
The Proposed GPS System solution and the materials are
correct or not
The Cables are correct or not

Score

4
4
4
4
5
5
5
5
5
5
5
5
5
5
5
5
5

1.The TX solution match the TX solution database or not

1.The photos are complete or not

2.The photh have been marked as SF requirement or not

Check Point

Site Model validation(RAN & Power


solution)
Proposed Solution

TX solution validation
Mini CME solution validation
RAN BOM
Main Equipment BOM

Power BOM
TX BOM if any
Materials Type

Installation Auxiliary Materials

Materials Qty
Material Length

Bill of Quantity of Mini CME

Bill of Quantity of Mini CME


Drawings list validation

Layout validation
Site Design Drawings

Cabling validation(Power &


Grounding)
CME design (if any )validation

Check List

Score

1.The solution model is correct or not;

2.Proposed RAN Solution is correct or not;

3.Proposed LTE Antenna&Feeder System


information is correct or not;

4.Power Equipment Information is correct or


not;
1.The TX solution match with the TX planning
database or not;
1.The CME solution match the actual case or
not;

5
5
5

1.RAN BOM match the solution or not;

1.Power BOM match the solution or not;

1.TX BOM if have is correct or not

2.TX BOM if not need fill some words

1.The material type match the proposed


solution or not;

1.The material Qty is correct or not;

1.The material length match the actually


routing or not;

The bill of quantity of Mini CME match the


solution and the actually case or not

1.The drawings are complete as the drawing


list or not;

1.The existing layout need clearly show the


existing equipment and the routing;

2.The Proposed layout need match the


solution;

3.The equipment need match the actual case;

1.The cabling validation match the equipments;

CME design must conform the standard.