METHOD
WTP & WWTP
Date: 01/02/2010
Rev. : 00
Page: 1 of 11
I.
GENERAL
The main work of this project is Construction Works for Water Treatment Plant and Waste
Water Treatment Plant which is Scope of Works, as follow :
I.1
EARTH WORKS
The works will be executed after the sub structure work for embankment have been finished.
Meanwhile, the excavation for bored pile, pile cap and tee beam will be axecution after the
bored pile works have been finished.
I.2
STRUCTURAL WORKS
The Structural works will be started after the sub structure works have been finished. It will be
started from Main building. By the underground level up to the top level.
I.3
ARCHITECTURAL WORKS
The Architectural Works will be started after a part of structure works have been finished.
I.4
I.5
EXTERNAL WORKS
The extenal works will the executed with a part of structure works and another part shall be
wait the construction works of structure have been finished especially for lanscaping and
parking area. Monthly working of time to be needed is 25 days, where is the effective daily
working time is 7 hours. Productivity of each equipment to be used, depends on the effective
working hour respect to rainy season.
Date: 01/02/2010
Rev. : 00
Page: 2 of 11
II.
Autolevel = 1 unit
Theodolith = 1 unit
Concrete mixer
Concrete vibrator
Bar Cutter
Bar Bender
Tamping Rammer
Back Hoe
Pipe Support
Beaty Scaffolding
Generator set.
Cranes
Engineer Office
Contractor Office
Date: 01/02/2010
Rev. : 00
Page: 3 of 11
Fencing
Temporary Acces Road
Comunication and Transformation System
Engineer Office
Ware house, Work shop and Guard house
Water and Power Supply
We will provide 1 ( one ) unit of generator set 20 KVA for daily lighting of temporary
buildings and site.
Water for construction works will be provided to used by bore well and the other one for
drinking will be provided by water mineral agent.
Parking area for the Engineer and Contractor will be provide around the office.
Fence
Fencing works will be made around of construction works site
Temporary Acces Road
Temporary Acces Road will be made as an instruction by the engineer and will be
coverage to the all of the construction works. ( as attached )
Communication System
We will be provided the communication facilities like telephone and handy talkie to
operate on site.
Date: 01/02/2010
Rev. : 00
Page: 4 of 11
Date: 01/02/2010
Rev. : 00
Page: 5 of 11
Date: 01/02/2010
Rev. : 00
Page: 6 of 11
IV.2 STANDARDS
American Society for Testing and Material ( ASTM, 1973 ) ASTM D. 3441 79 Test
Method for Dutch Code Parameter
Reinforcement
Reinforcement works will be executed by the iron mongery and to used the Bar Bender
and Bar Cuter Equipment. The Reinforcement electricity will be made on workshop by
Tower Crane.
Formwork
The material formwork to be used for pile cap work are plywood 12mm, wood 5/7 and
and separator and form tie.
The execution of works will be done by skilled labour and unskilled labour, as to
achieved the high works productivity.
Concreting
Concreting works will be execution by truck mixer staright on the concreting location
and used the concreting gutter and loader. The characteristic of the concrete to be used
k-300 and will be supplied from Ready Mixed Supplier.
Date: 01/02/2010
Rev. : 00
Page: 7 of 11
IV.5 EQUIPMENT
IV.5.1 Bored pile works
Crans = 1 unit
Tremie = 1 unit
Water Pump = 2 units
Gutter = 2 units
IV.5.2 Pile Cap and Tie Biem
The Electricity Bar Cutter = 1 unit
Bar Bender = 1 unit
Concrete Vibrator = 4 units
Generator Set = 1 unit
Concrete Pump = 1 unit
Date: 01/02/2010
Rev. : 00
Page: 8 of 11
V.
Soil excavation (bored pile), soil inspection, soil removal, bored pile fabrication
Splices instalation
Fondation reinforcement installation
Static loading test
V.2 STANDARDS
American Society for Testing and Material (ASTM, 1973), ASTM D 3441 79 Test Method for
Dutch Cone Penetrometer.
V.3 EQUIPMENT
Crawler Crane
Drill machine incuding welly grass
Bits (Auger Bucket Auger, Cleaning Bucket)
Rumer
Casing pipe
Submersible pump
Tremie
Chisel
Transportaion
Truck Mixer
Preparation :
The preparation of the marking points for drilling area
Drilling planed for bored pile
Planning for the embankment system
Planning for the accesss road for bored pile and truck mixer.
V.5.2 Mobilization and Assembling
V.5.3 Site Surveying and Setting Out
V.5.4 The shalow drilling for auger driling machine with diameter have been planed.
V.5.5 The installation for the casing on drilling hole and pressing with hammer.
V.5.6 To used the bucket auger for drilling
V.5.7 To cleaning for the based hole of drilling by cleaning bucket machine
V.5.8 The installation of the fabricated rebar by crane on drilling the drilling hole
V.5.9 The installation for poured concrete by used the pvc tremie pipe in such way by DT
V.5.10 PVC Tremie pipe and steel casing pulled out after concreting completion.
Date: 01/02/2010
Rev. : 00
Page: 9 of 11
VI.2 STANDARDS
VI.2.1
VI.2.2
VI.2.3
VI.2.4
VI.3 EQUIPMENT
Universal Lift
Concrete Mixer
Concrete Pump
Vibrator
Compressor
Bar Bender
Bar Cutter
Genset
Theodolith
Water pass
Welded Machine
Beaty Scaffolding
Support pipe
Site Surveying/Unizet
Installation and erection of rebar
Date: 01/02/2010
Rev. : 00
Page: 10 of 11
Fabricating of formwork
Site Surveying/Unized
Installs fabricating formwork and controlling the elevation
Installs and take up a position of rebar
Installation/preparation of concreting
Concreting
Maintenance
Removal of the formwork and installation of pipe support
The removal of pipe support
Plywood 9 mm
Nails
Form oil
The equipment to be used :
Bar Cutter
Bar Binder
Beaty Scaffolding
Support Pipe
The Technical Analysis of structure works for each floor.
Date: 01/02/2010
Rev. : 00
Page: 11 of 11