Low Voltage Circuit Breaker Testing

Why Test? Series

unit operation without using primary current. The test set will pass
enough current to check any desired calibration point. The breaker
must be de-energized before checking the operation of the solidstate trip units. If the test set shows that the solid-state trip unit is
not functioning properly, the trip unit should be replaced.

Defective circuit breakers can allow extensive damage, personnel


injury, or make an outage more widespread when a fault occurs.
They can also trip when they shouldnt causing expensive downtime.

The primary current injection method is usually preferred because it


is expected that this method verifies that the sensors and wiring, as
well as the conduction path in the breaker. It is recommended that
the primary injection test be performed simultaneously on all three
phases when testing breakers with solid state-trip units. If three phase
primary injection testing is not practical, then it is recommended
that the sensors and wiring should be tested separately. This testing
should be performed per NETA and NEMA procedures in accordance
with manufacturers recommendations.

They fail. A survey by Hartford Insurance Company found that air


circuit breakers represent 19.5% of electrical power system failures.
Test results on circuit breakers by NETA (InterNational Electrical
Testing Association) firms show over a 15% failure rate.

There is no way to know if a circuit breaker will operate properly


under fault or overload conditions unless it is tested, preferably by
a primary injection test. (Refer to NEMA Standard AB 4 Guidelines
of Inspection and Preventive Maintenance of Molded Case Circuit
Breakers Used in Commercial and Industrial Applications.)

How Do They Sense Overcurrent?

Solid State Trips: Current transformers send signals to a solid-state


logic box or microcomputer which determines the tripping time.
This technology is very precise, flexible, and reliable.
Thermal Magnetic: A bimetallic release or solder pot is heated by
load current for overload tripping. Instantaneous or short circuit
tripping uses a core with a restraint spring. These methods are found
in motor overloads and molded case circuit breakers.
Electromechanical Trips: Magnetic cores pull against oil dashpots or
air diaphragms or mechanical flywheels to create time delay tripping
on overloads. Core and spring units are found on instantaneous
trips for low voltage air circuit breakers.

Why Do They Fail Or Fail?

Current sensors fail because they are mis-wired or broken, or solid


state components have failed or are incorrectly programmed. Trip
linkages fail because dust, hardened grease, corrosion, misalignment
or frozen or broken parts prevent operation (even though the
breaker may be operated manually and therefore appear to operate
properly). The current-carrying parts and main contacts fail because
they have been damaged by fault interruption or operating springs
have fatigued such that they no longer provide adequate opening
or closing force or because internal connection have become loose.
The case or insulation fails because it has cracked or been damaged.
Common failures include: dashpots leaking, spurious tripping,
linkage not adjusted, no tripping at all, broken cases exposing live
parts, loose internal connections, defective or broken parts, metal
fatigue, age, overuse or misapplication.

Measure contact voltage drop at rated current, (finds


loose connections, improper contact pressure, or
damaged main contacts).
Test instantaneous trip function with pulse or higher
currents until trip occurs, (tests short circuit protection
capability).
Measure overload tripping time at 300% rated current.
Check mechanical operation. Inspect for broken parts.
Test operation of ground fault, short time pickup and
delay, shunt trips, undervoltage releases, alarm
functions, electrical spring charging mechanism, etc.
Check insulation resistance phase-to-phase and phase-
to-ground, closed and across open contacts.

W H Y T EST?

Why Test Circuit Breakers?

Special Considerations

Testing is recommended at start-up and every three


years there after
Circuit breaker must be de-energized to perform test
For primary current injection testing, a power source
capable of supplying 100 amps at 208 or 480 volts is
required to power the test set

How Should They Be Tested?

Electrical Reliability Services


1 (877) 468-6384
www.electricalreliability.com

2010 Emerson Network Power


02-YT-01

Solid-state units can be tested by either secondary or primary


current injection. The secondary injection test is performed using
a specially designed power supply unit. It should be noted that the
secondary injection method only tests the solid-state trip unit logic
and does not test the current sensors, wiring, or the breaker current
handling components. Most solid-state trip units have terminal
blocks that are equipped with test plug terminals for making the
calibration test. The test set allows checking of the solid-state trip