Acosta, Timothy John S. 2007-16445 CE 112: Elevation Nod eID FT

This document contains the results of a hydraulic analysis of a proposed water transmission system for a subdivision. It includes tables showing node elevations, demand over time, pump operating hours, and flow and pressure results. Graphs show the demand pattern, flow during pumping and non-pumping periods. The analysis found that demand requirements were met over 24 hours without excessive pressures when a high storage tank was included to reduce pump run time.

Uploaded by

Tim Acosta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
38 views10 pages

Acosta, Timothy John S. 2007-16445 CE 112: Elevation Nod eID FT

This document contains the results of a hydraulic analysis of a proposed water transmission system for a subdivision. It includes tables showing node elevations, demand over time, pump operating hours, and flow and pressure results. Graphs show the demand pattern, flow during pumping and non-pumping periods. The analysis found that demand requirements were met over 24 hours without excessive pressures when a high storage tank was included to reduce pump run time.

Uploaded by

Tim Acosta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 10

Acosta, Timothy John S.

2007-16445
CE 112

Figure 1. Proposed Transmission System for Subdivision


Network Table Nodes at 0:00 Hrs
Elevation
Nod
e ID
ft
Junc
3
30
Junc
4
28
Junc
5
27
Junc
6
27
Junc
7
26
Junc
8
28
Junc
9
27
Junc
10
27

Junc
11
26
Junc
12
26
Junc
13
26
Junc
14
27
Network Table Nodes at 0:00 Hrs
Eleva
tion
Node ID
ft
Junc 15
28
Junc 16
27
Junc 17
26
Junc 18
24
Junc 19
25
Junc 20
25
Junc 21
23
Junc 22
30
Junc 1
0
Tank Ext
31
Tank
HighTank
25

Figure 2. Operating Hours for Pump during 24 Hour Analysis

8
7
6
5
4
3
2
1
0
1 2 3 4 5 6 7 8 9 101112131415161718192021222324

Figure 3. Demand for a 24 Hour Period

CE 112 Project
Time Series Table
17
Dema
Time
nd
Hours
GPM
0:00
0.05
1:00
0.16
2:00
0.26
3:00
0.42
4:00
3.64
5:00
0.73
6:00
0.57
7:00
0.42
8:00
0.31
9:00
0.21
10:00
0.57
11:00
1.09
12:00
0.47

- Node
Head
ft
31
31.66
32.29
32.9
33.46
33.44
33.94
34.47
35.01
35.57
36.14
36.47
36.28

13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
24:00:
00

0.16
0.1
0.16
0.47
1.25
0.62
0.36
0.16
0.1
0.1
0.05

36.19
36.16
36.14
36.11
36.03
35.8
35.69
35.62
35.6
35.58
35.56

0.05

35.55

Table of
Sample
Junction at
Phase 1 of
Subdivision

CE 112 Project
Time Series Table
12
Dema
Time
nd
Hours
GPM
0:00
0.05
1:00
0.16
2:00
0.26
3:00
0.42
4:00
3.64
5:00
0.73
6:00
0.57
7:00
0.42
8:00
0.31
9:00
0.21
10:00
0.57

- Node
Head
ft
31
31.66
32.29
32.9
33.46
33.44
33.94
34.47
35.01
35.57
36.14

11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
24:00:
00

1.09
0.47
0.16
0.1
0.16
0.47
1.25
0.62
0.36
0.16
0.1
0.1
0.05

36.47
36.28
36.19
36.16
36.14
36.11
36.03
35.8
35.69
35.62
35.6
35.58
35.56

0.05

35.55

Table of Sample Junction at Phase 2 of Subdivision

CE 112 Project
Time Series Table - Node
HighTank
Dema
Pressu
Time
nd
Head
re
Hours GPM
ft
psi
0:00 58.03
31
2.6
1:00
55.6 31.66
2.89
2:00
53.2 32.29
3.16
3:00 49.99 32.89
3.42
4:00
-2.27 33.46
3.67
5:00 44.35 33.43
3.65
6:00 46.24 33.94
3.87
7:00 48.09 34.46
4.1
8:00 49.08 35.01
4.34
9:00 50.04 35.56
4.58
10:00 43.49 36.13
4.82

11:00
12:00
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
24:00:
00

-17.47
-7.49
-2.5
-1.66
-2.5
-7.49
-19.97
-9.98
-5.82
-2.5
-1.66
-1.66
-0.83

36.47
36.28
36.19
36.16
36.14
36.11
36.03
35.8
35.69
35.62
35.6
35.58
35.56

4.97
4.89
4.85
4.84
4.83
4.82
4.78
4.68
4.63
4.6
4.59
4.58
4.57

-0.83

35.55

4.57

Assumed Values for


Analysis
Tank
Diameter
Tank
Height
Pipe
Pipe
Roughness

30
12
8
130

Figure 4. Flow For Pipeline from Phase 2 Going to the High Tank

Figure 5. Flow During Pumping Period of A Day

Figure 6. Flow During Off Period of Pump


Summary and Assumptions of Analysis:
Demand Requirements were met for a 24 Hour Period Analysis with no
disconnection of links due to excessive pressure. Ext Tank was a dummy tank to
simulate an inflow from another transmission system. The High Tank was proposed
to keep a storage system as to not make the pump work all the time for a 24 hour
period.