Soil-Cement Inspector Manual PCA

Download as pdf or txt
Download as pdf or txt
You are on page 1of 34

f]~j

I~ORTLAND

CEMENT

ASSOCIATION

SOIL-CEMENT
INSPECTORS
MANUAL

PAO5O.O 3

SOIL-CEMENT
INSPECTORS

MAN UAL

PORTLAND

CEMENT

ASSOCIATION

5420 Old Orchard Road, Skokie, Illinois 60077-1083


Phone: 847.966.6200; Fax: 847.966-9781
Web site: www.portcement.org
2001 Portland Cement Association
All rights reserved

Foreword

Contents
Foreword

An introduction to Soil-Cement

Chapter 1 Checklist

Chapter 2 Inspection of Site Preparation


Identification of Soil Materials
Site Preparation
Equipment Check
Pulverization

8
8
8
11
13

Chapter 3 Inspection of Processing Operations


Cement Application
Water Application
Uniformity of Mix: Depth and Width of Treatment
Compaction
Finishing
Joint Construction
Degree of Compaction and Final Depth Check
Curing
Opening to Traffic
Maintenance

15
15
31
44
46
47
48
49
57
57
57

Appendix
Equipment for Field Tests
Form Sheets

. . .

59
59
60

This second edition of Soil-Cement Inspectors Manual out


lines and illustrates procedures for inspection of soil-cement
construction. Each step of proper inspection and control is
explained; sample problems are given to show how to com
pute material quantities and perform field tests. Tables and
charts to simplify these calculations are also included.
Other PCA publications of interest to the soil-cement in
spector are listed at the back of this manual.

An Introduction
to Soil-Cement
Soil-cement is a mixture of pulverized soil material and meas
ured amounts of portland cement and water, compacted to
high density. As the cement hydrates, the mixture becomes a
hard, durable paving material. A bituminous wearing course
is placed on the soil-cement base to complete the pavement.
Only three basic ingredients are needed for soil-cement:
soil material, portland cement, and water. The soil in soilcement can be a wide variety of materials. Either in-place or
borrow material can be used. Old granular-base roads, with
or without their bituminous surfaces, can be recycled to make
soil-cement.
Soil-cement is sometimes called cement-treated base or
cement-stabilized-aggregate base. Regardless of what it is
called, the principles governing its composition and construc
tion are the same.
Before construction with soil-cement starts, the soil mate
rials that will be treated with cement should have been identi
fied and representative samples of each type tested. These
tests determine the minimum cement content required to
harden each material adequately and the approximate opti
mum moisture content and density values for use in construc
tion.
Soil-cement road construction involves two stepsprepa
ration and processing. Variations in these steps are dictated
by the type of mixing equipment used. Regardless of the
equipment and methods used, it is essential to have an ade
quately compacted, thorough mixture of soil material with the
proper amounts of cement and moisture. The completed soilcement must be adequately cured.
Soil, cement, and water can be (1) mixed in place using trav
eling mixing machines, or (2) mixed in a central mixing plant.
The types of mixing equipment are
1. Traveling mixing machines
a. Flat-transverse-shaft type
Single-shaft mixer
Multiple-shaft mixer
b. Windrow-type pugmill
4

2. Central mixing plants


a. Continuous-flow-type pugmill
b. Batch-type pugmill
c. Rotary-drum mixers
Steps for construction with traveling mixing machines are
1. Preparation
a. With in-place soil material
Shape roadway to crown and grade.
Scarify roadway soil material.
Pulverize if necessary.
Prewet as needed.
Shape prepared soil material.
b. With borrow material
Shape subgrade to crown and grade.
Compact subgrade.
Place borrow material.
Shape borrow material.
2. Soil-cement processing
Spread portland cement and mix.
Apply water and mix.
Compact.
Finish.
Cure.
Construction steps for central-mixing-plant construction
are
1. Preparation
Shape subgrade to crown and grade.
Compact subgrade.
2. Soil-cement processing
Mix soil material, cement, and water in plant.
Haul mixed soil-cement to roadway and spread.
Compact.
Finish.
Cure.
Compacted and finished soil-cement contains sufficient
moisture for adequate cement hydration. A moisture-retaining
cover is placed over the soil-cement soon after completion to
retain this moisture and permit the cement to hydrate. Most
soil-cement is cured with bituminous material, but other mate
rials (see page 57) are satisfactory.
5

Chapter 1

Ch ec

IS

Field inspection of soil-cement construction involves the con


trol of five factors:
Cement content
Moisture content
Mixing
Compaction
Curing
The inspector can easily control these factors by organiz
ing the inspection steps into a routine that fits in with the se
quence of construction operations.
The following checklist covers the inspection steps required
to assure quality soil-cement:
1. Have soil surveys, laboratory reports, plans, and specifi
cations been reviewed and correlated with job condi
tions?
2. Have all soft subgrade areas been corrected? Has the
roadway been shaped to crown and grade? Have man
hole covers and other obstacles been removed or low
ered?
3. Is all of the construction equipment properly adjusted and
in good working condition?
4. Have the soil materials been pulverized sufficiently, and
will their moisture contents allow them to mix readily with
cement?
5. Has the proper quantity of cement been spread uniform
ly? Has the central mixing plant been properly calibrated?
6. Is the soil-cement mixture between optimum moisture
and 2% above optimum moisture?
7. Is the mixture uniform and thoroughly mixed? Are the
width and depth of treatment according to the plans?
8. Is the finished surface moist, dense, and free of compac
tion planes?
9. Is the soil-cement mixture at the transverse construction
joint well mixed and compacted?
10. Are the specified density and depth of treatment being
achieved?
11. Is sufficient curing material for complete coverage being
applied? Where subjected to traffic, has the bituminous
material been sanded sufficiently to prevent pickup?
8

12. Have any defects been repaired for full depth of


The treatment?
proper methods of controlling each of these 12 items are
described in following chapters.

Chapter 2

Inspection of Site Preparation


Before processing begins, laboratory reports, soil surveys,
plans, and specifications are reviewed by the inspector. The
inspector should be thoroughly familiar with the specifications
and must insist upon compliance with them. The construction
site is inspected to make sure that the soil materials are at
proper grade and adequately pulverized, and that the subgrade is stable throughout the project.

Identification of Soil Materials


Cement requirements are determined in the laboratory before
construction and are tabulated in the laboratory reports along
with identification information for the soil. (See Fig. 1.)
The soil materials to be processed in the field are compared
with the identification data given in the laboratory report and
with information given in the plans and specifications. This will
assure the use of the proper amount of cement. If there is an
obvious difference between the materials tested and the soil
materials on the site, further testing may be necessary.

Co

w
C

x
I
ICC

ICC
C.)

Co

Co
ICo

w
I

IC.

~ I
D
Co

~h

Site Preparation
Areas of unstable subgrade must be corrected before proc
essing starts, since proper compaction of soil-cement will not
be possible if the subgrade cannot support the compaction
equipment.
Unstable subgrade soils, which usually contain excess
moisture, can generally be detected by observing their stabil
ity under the wheels of the motor grader as it shapes the area
prior to soil-cement processing. Shallow wet spots can be im
proved by aerating and drying. When deep unstable areas are
encountered, it is usually necessary to remove the underlying
soil and replace it with better material. An alternate method of
correction is to treat the subgrade with cement.
When in-place soil materials are used, the grade at the start
of construction will influence the final cross section. There
fore, before processing is started, the roadway should be
shaped to approximate crown and grade. Maintenance of
8

~ ~
~ 11111111 ~ll
~

r~ ~ ii ~

-~ill~ll ~

Fig. 1. Summary of soil and soil-cement tests on Soil No. C.


9

essed. This permits processing over manholes without diffi


culty or delay. Manhole locations should be accurately refer
enced with offset stakes. After final finishing but before the
soil-cement has hardened, manhole frames and covers are
replaced. Soil-cement is then tamped (to maximum density)
around the structures, or ready mixed concrete is placed and
finished to grade.

Equipment Check
All equipment necessary for construction must be at the jobsite and in good operating condition before processing begins.
A short trial run is valuable in assuring proper operation and
adjustment of equipment.
Listed below are items that should be checked prior to proc
essing.

Fig. 2. Unstable subgrade areas can usually be detected by


observing their stability under the motor-grader wheels. Soft
areas must be corrected before processing starts.

crown and grade prior to soil-cement construction will permit


rapid runoff of water during heavy rains and is good insurance
against wet spots developing.
Prewetting of dry, in-place soil materials is common prac
tice. Applying water during preparation saves time during
actual processing operations because most of the required
water will already have been added to the soil material. In very
granular materials, prewetting prevents cement from sifting to
the bottom of the mix by causing it to adhere more readily to
the sand and gravel particles.
Guide stakes should be set 1 ft (0.3 m) beyond the proposed
pavement edges to control the width of treatment and to guide
the equipment operators during construction.
Soil-cement street processing is facilitated by removing
manhole covers and frames and covering the holes with
heavy sheet metal or planks just below the depth to be proc
10

Central Mixing
1. Cement feed, Is the cement meter on the central plant in
good condition and in an exposed location where it can
conveniently be calibrated? Does the plant include a surge
tank between the cement silo and the feeder to maintain a
constant head of cement for the feeder? Have air jets been
installed in the hoppers to produce a loose, uniform, accu
rate flow of cement? Is there a positive connection between
the soil feed and cement feed apparatus so that if the ce
ment feed stops, the soil supply will stop?
2. MIxer. Are the paddles all in place and in good condition?
Does the spraybar give a uniform, constant spray of water?
Can the required quantity of water be delivered through the
plant under maximum production?
3. Transporting equIpment. Is the equipment of sufficient
capacity to meet the production requirements? Are protec
tive covers provided for use during bad weather?
4. Spreader. Is it in good operating condition and adjusted to
spread the mixed soil-r.ement to the proper loose depth and
width?
Mixed in Place
1. Cement spreader. Is the conveyor belt or chain on the
cement spreader in good condition? Does the spreader run
11

smoothly? Are the proper gears and plates installed? Is the


truck hitch operating properly?
2. Cement trucks. Are the cement trucks equipped with spe
cial hitches for attaching the cement spreader? Are the
truck beds tight enough to prevent loss of cement? Are the
trucks equipped with tarpaulins for protection against rain?
3. Mixing machines. Are the tines or paddles all in place and
in good condition? Does the spraybar on each mixer give a
uniform, constant spray? Be sure that it does not leak water
when turned off.

Water Source and Equipment


Is there any chance that the water source is contaminated?
If so, has the water been tested in the laboratory? Is the water
pump in good working order? Are all of the nozzles on the
spraybars unclogged? Have all leaks been eliminated?

Motor Grader
Is the motor grader blade in good condition and not worn excessively?

Fig. 4. Screening soil-cement mixture through No. 4 (4.75-mm)


sieve to determine percent pulverization.

Compaction Equipment
Fig. 3. Checking for water truck spraybar leakage.

Is the tamping roller filled with water or sand? Are the tamping
feet the proper size, shape, and length for the type and thick
ness of soil to be processed? Are the rubber-tire and steelwheel rollers of the proper weight?

Pulverization
Most soil materials require little if any pulverization before
processing starts. However, the heavier clayey soils do re
quire some preliminary work. The keys to pulverization of
clayey soils are proper moisture control and proper equip
ment.
Most specifications require that, at the completion of moist
mixing, 80% of the soil-cement mixture pass the No. 4 (4.75mm) sieve and 100% pass the 1-in. (25-mm) sieve, exclusive
of gravel or stone retained on these sieves. This is checked
by making a pulverization test. The test consists of screening
a representative sample of soil-cement through a No. 4(4.75mm) sieve. Any gravel or stone retained on the sieve is picked
13

out and discarded. The clay lumps retained and the pulverized
soil passing the No.4(4.75-mm) sieve are weighed separately
and their dry weights determined. The degree of pulverization
is calculated as follows:
dry weight of soil-cement mixture
passing No. 4 (4.75-mm) sieve
% pulverization dry weight of total sample exclusive 100
of gravel retained on No.4(4.75-mm)
sieve
.

For practical purposes, wet weights of materials are often


used instead of the corrected dry weights. The wet-weight
measurements are reasonably accurate and permit immedi
ate adjustments in pulverization and mixing procedures if
necessary.
Pulverization can be improved by
1. Slower forward speed of the mixing machine
2. Additional passes, if using a multiple-pass mixing
machine
3. Replacing worn mixer teeth
4. Prewetting and premixing the soil before processing
begins
Soil material that contains excessive moisture will not mix
readily with cement; therefore, the moisture content of the
material should be checked visually before cement is applied.
The percentage of moisture in the material at the time of ce
ment application should not exceed the optimum moisture
content.

Chapter 3

Inspection of Processing Operations


Soil-cement construction operations are well suited to an
orderly procedure of inspection and field control. This pro
cedure is aimed at controlling the amount of cement and
water, and the degree of mixing and compaction.
Daily processing is best carried out in several sections rath
er than one long section. This permits more efficient use of
equipment and thus speeds up operations. It also permits
compliance with time limits for moist-mixing, compacting, and
finishing, as given in the specifications.

Cement Application
Since cement hydration practically ceases when tempera
tures approach freezing, cement should not be applied when
air temperature is 40F (4 C) or lower. Cement must not be
applied when the soil material or subgrade is frozen.
The amount of cement required is specified either as a per
centage of cement by weight of oven-dry soil material, or in
pounds of cement per cubic foot (kilograms per cubic meter)
of compacted soil~cement.* Fig. 5can be used to convert from
one to the other if the maximum dry density of the compacted
soil-cement is known.
EXAMPLE 1.

Calculate the quantity of cement per cubic foot of compacted


soil-cement.
GIVEN: Maximum dry density of compacted soil-cement
121.2 lb per cubic foot (1941 kg/m3)
Specified cement content by dry weight of soil material... 6%
PROCEDURE: Calculate the weight of soil material by dividing
the weight of soil-cement by the quantity 1 plus the cement
content expressed as a decimal:
(1.00.06)

114.3 lb per cubic foot (1831 kg/m3)

The quantity of cement in each cubic foot is


121.2 114.3 = 6.9 lb per cubic foot (110 kg/m3)
-

*Previous editions of this handbook used percentage of cement by


volume as an alternate method of expressing cement content This
was based on a 94-lb (43-kg) U.S. bag of cement.

15

TABLE 1. Normal Range of Cement Require


ments for B- and C-Horizon Soils*

AASHTO
Soil Group

Cement,
pounds per
cubic foot of
compacted
soil-cement

Cement
percentage
by weight of
soil

Cement,
kilograms per
cubic meter of
compacted
soil-cement

1600-

iOO

IS

15-

i7
is

14

230
220
210

15
14

A-i-a
A-i-b
A-2-4

3-5
5-8

5-7
7-8

80-110
110-130

5-9

7-9

110-140

A-2-7 ~
A-3
A-4
A-S
A-6
A-7

7-il
7-12
8-13
9-15
10-16

8-11
8-il
8-11
9-13
9-13

130-180
130-180
130-180
140-210
140-210

los

iz

190

i2

180

iio

170
iO

iSoo-

percentage

Material
Caliche
Chat
Chert
Cinders
Limestone screenings

Marl
Red dog
Scoria containing plus
No 4 material
Scoria (minus No 4
material only)
Shale or disintegrated
shale
Shell soils
Slag (air-cooledl
Slag (water-cooled)

by weight of
soil

Cement,
pounds per
cubic foot of
compacted
soil-cement

s
~8-

Cement,
kilograms per
cubic meter of
compacted
soil-cement

7
7
8
8
5
11
8

8
8
8
8
7
10
8

130
130
130
130
110
160
130

11

ii

180

130

10
7
7
12

10
8
8
9

160
130
130
140

2000-

125

2100-

30

~6

-s

___~

35
2200-

-1306
-20~

TABLE 2. Average Cement Requirements


of Miscellaneous Materials
Cement,

-iso~

A-horizon soils (topsol s may Contain organic or other material det


rimental to cement reaction and thus require highercement factors
For dark grey to grey A-horizon soils, increase the above Cement
contents 4 percentage po nts 4 b Cu ft 60 kg m j of compacted
soii-cement(; for black A-hor zon soi a 6 percentage points 6 b Cu
ft [100 kg m I of compacted s cement

i60

25

1900-

16

200

i3

i700-

240

-ioo

-90

-140

-80

2300-i45

Fig. 5. Cement factor conversion chart.

Cement Application for


Mixed-in-Place Construction
Bulk Cement spreaders should be operated at a constant slow
rate of speed and a relatively constant level of cement kept in
the hopper to obtain a uniform cement spread. A true line at
the edge of the pavement should be maintained by using a
stringline. There should be no skips between spreading lanes.
Fig. 6 and Table 3 can be used to determine quantities of
17

TABLE 3. Cement Spread Requirement, Pounds


per Square Yard per Inch of Compacted
Thickness (kg/rn2 per 10 mm)

5.~I,Iy of cqll~OM 2[ 101,1 logIn no, gb.,,


34

120

us

bOoth

0,10 .10111

im

Fig. 6. Quantity of cement per unit length for given depth and
width of treatment for specified cement contents.

cement per square yard (square meter) of pavement or per


linear foot (meter). If the soil-cement is mixed in windrows, Fig.
7 can be used to determine cement quantities per linear foot
(meter) of windrow.

Check on Cement Spread


A check on the accuracy of the cement spread is necessary
to ensure that the proper quantity is actually being applied.
When bulk cement is being used, the check is made in two
ways:
1. Spot check. Place a canvas, usually 1 sq yd (1 m2)in area,
18

Cement content.
pounds per
cubic foot of
compacted
soil-cement

cement spread,
pounds per square
yard per inch of
thickness of
compacted
soil-cement

Cement content.
kilograms per
cubic meter of
compacted
soil-cement

Cement spread,
kilograms per square
meter per 10mm
of thickness of
compacted
soil-cement

4.5
5.0
5.5
6.0
6.5
7.0
7.5
80
8.5
9.0
9.5
10.0
105
11.0
11.5
12.0
12.5
13.0
13.5
14.0
14.5
15.0
15.5
160

3.38
3.75
4.13
4.50
4.88
5.25
5.63
6.0
6.38
6.75
7.13
7.50
7.88
8.25
8.63
9.0
9.38
9.75
10.13
10.50
1088
11 25
1163
12.0

72
80
88
96
104
112
120
128
136
144
152
160
168
176
184
192
200
208
216
224
232
240
248
256

0.72
0.80
0.88
0.96
1.04
1.12
1 20
128
1.36
1.44
1.52
1.60
168
1 76
184
1 92
2.00
2.08
2.16
2.24
2.32
2.40
248
256

on the roadway ahead of the cement spreader. After the


spreader has passed, carefully pick up the canvas and
weigh the cement collected on it.
2. Overall check. Check the distance of area over which a
truckload of cement of known weight is spread.
EXAMPLE 2.

Determine the linear distance a truckload of cement should


travel to spread the required amount of cement.
GIVEN: Required cement content
6.9 lb per cubic foot
(110kg m)
Depth of compacted soil-cement
6 in. (150 mm)
Width of spread
8 ft (2.4 m)
Weight of truckload of cement
15,400 lb (6990 kg)
19

:::~

4 ~:~jj~::

Fig. 8. weighing cement collected on a square yard (m2) of


canvas is a check on the quantity of cement spread.
a

vertically to the bottom edge and read the quantity of cement


per unit length required: 27.6 lb per foot (41.1 kg/rn).
The required distance of travel for the 15,400-lb (6990-kg)
truckload of cement to obtain the specified cement spread
equals the total weight of cement on the truck divided by the
pounds (kilograms) per linear foot (meter) required:
15A00

IouaIou

IfS

Lip _uaAo

JO

LJ&IaM

Lq ~uawa, lu;ond

Fig. 7. Quantity of cement per unit length of windrow for specified


cement content.

PROCEDURE: Enter Fig. 6 on the top edge at 6.9 lb of cement


per cubic foot (110 kg/rn3) and proceed vertically to the 6-in.
(150-mm) depth line; proceed horizontally to intersection with
line representing 8-ft (2.4-rn) width of spread; then proceed
20

558ft(170m)

If the truck traveled only 530ft (1 61 m), morethan the required


quantity of cement was applied and the spreader should be
adjusted to spread slightly less cement. The quantity of ce
ment actually spread in this case is:
15,400 lb 530 ft = 29.1 lb/foot (43.3 kg/rn)
or
291 lb ft 4 cu ft ft* 73 lb per cubic foot (117 kg m
This is compared to 6.9 lb percubic foot (110kg m ) required.
*Spread is for 1-ft (03-rn) length 8-ft (24-rn) width, and 6-in (150mm) depth: 1 x 8 x 6 12 4 cu ft ft (037 m m
21

Bagged-Cement Spread for


Mixed-in-Place Construction

I.

When bags of cement are used on small jobs, a simple but


exact method for properly placing the bags is necessary. The
bags should be spaced at approximately equal transverse and
longitudinal intervals that will ensure the proper percentage
of cement. Positions can be spotted by flags or markers fas
tened to chains at proper intervals to mark the transverse and
longitudinal rows.

Calibrating Central Mixing Plants


When borrow materials are specified, central plants with pugmill-type mixers or rotary-drum mixers are often used to mix
soil-cement. Use of such equipment makes it necessary to
proportion the cement and the soil aggregate before they
enter the mixing chamber. Central mixing plants can be cali
brated as explained below.

Fig. 9. The distance over which a truckload of cement of known


weight spreads is a check on the quantity of cement spread.
Bulk cement that is spread mechanically on the top of a
wndrow of soil may be checked by forming a trough in the top
of the windrow and placing a piece of canvas in the trough.
Cement spread is checked by pushing two metal plates into
the top of the windrow exactly 1 ft or 1 m apart. All cement be
tween the plates is carefully collected and weighed. This is a
direct method of finding the quantity of cement spread per unit
length.
Generally, the spreader is first adjusted at the start of con
struction by checking the cement spread per unit length of
windrow or per square yard (m2). Then, when the proper ad
justments have been made, a continuous check of the spread
is easily made by determining the distance over which each
truckload is spread. Bag cement is checked by counting the
number of bags placed per 100-ft (30-m) station. It is impor
tant to keep a continuous check on cement-spreading opera
tions.
22

Continuous-Flow Mixing Plant


The soil material alone is run through the plant for a given
period of time and collected in a truck. This should be done for
specific periods of time, such as 1, 2, and 3 minutes, to deter
mine the uniformity of flow and the quantity of soil material go
ing through the plant. The amount of moist soil per hourdivided
by the quantity 1 plus the moisture content (expressed as a
decimal) will give the quantity of dry soil per hour.
EXAMPLE 3.

Find the hourly delivery rate of dry soil material.


GIVEN: Moist soil material going through the plant per hour
500 tons (454 f)*
Moisture content of material
5.5%
PROCEDURE: Delivery rate of dry soil material is
(1.0 0055)

474 tons per hour (430 t/h)

Cement is calibrated in a similar manner by diverting it di*1 t

1 tonne

1000 kg

1 Mg
23

Cit

Fig. 10. Soil material is collected in a truck to determine rate of


feed.
Fig. 12. Collecting soil material from main feeder belt to
determine dry weight and rate of feed.
EXAMPLE 4.

I
-/

Fig. 11. Rate of cement feed is calibrated to revolutions of the ce


ment feeder.

rectly from the cement feeder into a truck or suitable container


while soil material is going through the plant. A diversion chute
directs the cement from the cement meter to the container.
The plant is run at full capacity during calibration so that oper
ations will be comparable to those of actual running conditions
and power drawdown will not affect calibration results during
cement trials. Generally, periods of 15, 30, and sometimes 45
seconds are used to determine the uniformity of feed and the
quantity of cement delivered.
24

Determine the amount of cement required per minute.


GIVEN: Specified cement content by weight of dry soil mate
rial
6%
PROCEDURE: 474 tons per hour (430 t/h) (from Example 3)
of dry soil material requires 474 x 0.06 = 28.4 tons of cement
per hour (25.8 t/h), or
28.4x 2000
60

948 lb of cementperminute (430kg mm)

Rather than arbitrarily adjusting the cement feeder until the


correct amount of cement is being discharged, first determine
the relationship between various feeder gate openings or
revolutions per minute (depending on type of feeder) and
amount of cement discharged. Plot this relationship to find the
gate opening or revolutions per minute (RPM) for the required
amount of cement.
A second method is to operate the plant with only soil aggre
gate material feeding onto the main conveyor belt. The mate
rial on a selected length of conveyor belt is collected and its
dry weight determined. The plant is then operated with only
cement feeding onto the main conveyor belt. If a variable
speed screw or vane cement feeder is being used, several
trials are made at different revolutions-per-minute (RPM) set25

tings on the cement feeder. If a belt cement feeder is being


used, trials are made at different cement feeder gate open
ings. The cement on the selected length of conveyor belt is
collected and weighed for each trial run. A calibration graph
can then be drawn by plotting the RPM setting or gate open
ing on the cement feeder on the horizontal scale and the com
puted percent of cement by dry weight of soil material on the
vertical scale. Thus, for a constant supply of soil material, the
setting on the cement feeder for the required quantity of ce
ment can be determined from the graph.
EXAMPLE 5.

Determine cement meter setting.


GIVEN: Specified cement content by weight of dry soil mate
rial
6%
Moisture content of material
5.5%
PROCEDURE: Determine the weight of soil material on the
main conveyor belt at various feeder gate openings.
Gate opening
Moist soil material on belt
in.
(mm)
lb on 5ft
(kg on 1.5 m)
225
(100.4)
8
(200)
191
( 85.3)
7
(175)
156
( 69.6)
6
(150)
121
( 54.0)
5
(125)
Calculate the weight of dry soil material by dividing the quan
tity of moist soil material by the quantity 1 plus the moisture
content expressed as a decimal:
Moist soil material
(1.0 + 0.055)
Dry soil material
per unit length
Gate opening
Dry soil material on belt
of belt
in.
(mm)
lb on 5ft (kg on 1.5 m) lb/ft
(kg/m)
8
(200)
213
(95.2)
42.6
(63.5)
7
(175)
181
(80.8)
36.2
(53.9)
6
(150)
148
(66.0)
29.6
(44.0)
5
(125)
115
(51.2)
23.0
(34.1)
26

Determine weight of cement on main conveyor belt at various


RPM settings of feeder:
Cement per unit
Cement on belt
____________________________
length of belt
RPM
setting
lb on lOft
(kg on 3.Om)
lb/ft
(kg m)
14
28.7
(12.8)
2.87
(4.27)
12
25.5
(11.4)
2.55
(3.80)
10
22.2
( 9.9)
2.22
(3.30)
8
19.0
( 8.5)
1.90
(2.83)
For production, the main feeder belt is set at 8 in. (200 mm).
Calculate the cement content by weight of dry soil material at
8-in. (200-mm) soil-aggregate feeder belt setting for each
cement feeder setting.
Example for RPM setting of 14:
2.87 lb cement
42.6 lb dry soil material

100= 6.7% cement

RPM
setting

Cement content by weight


of dry soil material, %
6.7
14
6.0
12
5.2
10
4.5
8
An RPM setting of 12 will give the required cement content
of 6% by weight of dry soil material.

EXAMPLE 6.

Find the production of the plantwith the 8-in. (200-mm)feeder


gate opening and 1 2-RPM cement feeder setting.
GIVEN: Total length of main feeder belt
165.0 ft
(50.29 m)
Average time for one revolution of belt
26.7 seconds
PROCEDURE: Calculate average belt speed:
165.0/26.7 = 6.18 ft/second (1.88 m/s)
Dry soil material plus cement going through plant:
27

Add for evaporation loss


2%
Moisture in soil material
5.5%
From previous example, dry soil material used
474
tons per hour (430 t/h)
From previous example, cement used.... 28.4 tons per hour
(25.8 t/h)
PROCEDURE: Water in soil material: 474 x 0.055 = 26.1 tons
per hour (23.7 t/h)
Soil material and cement: 474 + 28.4 = 502.4 tons per hour
(455.8 t/h)
Water required: 502.4 x 0.135* = 67.8 tons per hour (61.5 t/h)
Water to add: 67.8- 26.1 = 41.7 tons per hour (37.8 t/h)

0
0

---~

or
~~= 167 U.S. gal per minute (632 L/min)
or 139 imperial gallons per minute
8

Cement feeder setting, RPM


Fig. 13. Example of calibration curve for a central-mixing-plant
cement feeder.

Soil:
Cement:

42.6 lb x 6.18 ft/sec x 3600 sec 2000 lb = 474.0


2.55 lb x 6.18 ft/sec x 3600 sec 2000 lb = 28.4
502.4
tons per hour (455.8 t/h)

Once the plant is properly calibrated, only one check a day


is usually necessary. A cement batch weigher between the silo
and holding hopper will keep track of cement used. Occasion
ally, the silo should be emptied completelyto checkthe amount
of cement used against bulk transport weights.
Water is calibrated by weighing the amount discharged for
one minute and comparing it with the water meter that meas
ures rate of flow on the mixer.
To determine the quantity of water needed for the mixture,
the moisture content in the soil material and the percent of
moisture required must be known.
EXAMPLE 7.

Determine the amount of water needed per minute.


GIVEN: Optimum moisture content
28

11.5%

Batch-Type Mixing Plant


When soil-cement is mixed in a batch-type pugmill or rotarydrum mixing plant, the proper quantities of soil material, ce
ment, and water for each batch are weighed before being
transferred to the mixer.
EXAMPLE 8.

Calculate the correct proportionsfora 2000-lb (907-kg) batch


of soil-cement to be mixed in a batch-type pugmill or rotarydrum mixing plant.
GIVEN: Cement content by weight of soil material
6%
Optimum moisture content by weight of soil material plus
cement
11 .5%
Moisture content of raw soil material
5.5%
PROCEDURE:
1. Weight of dry soil material plus cement per batch
2000
(1.0 + 0.135*) 1762 lb (800 kg)
Percentage of moisture required equals the optimum moisture
content (11 .5%) plus 2% for evaporation.
1 U.S. gal weighs 8.33 lb
1 imperial gallon (imp gal) weighs 10.0 lb.
29

8. Batch-weights corrected for moisture in soil material:


Cement
lOOlb (45kg)
Water
147 lb (67kg)
Moist soil material 1753 lb (795 kg)
2000 lb (907 kg)

1111

~1

Fig. 14. Each load of soil-cement from a central mixing plant is


weighed for a continuous record of the quantity processed.
Note tarp being placed over the soil-cement to minimize evap
orative moisture lost during transport. Covering soil-cement
also protects it from rain.
2. Weight of dry soil material:
1762
= 1662 lb (754kg)
(1.0 + 0.06)
3. Weight of cement:
1762- 1662= 100 lb (45 kg)
4. Weight of moist soil material:
1662 x (1.0 + 0.055) = 1753 lb (795 kg)

Water Application
One of the five control factors for soil-cement is proper mois
ture content. The optimum moisture content determined in the
laboratory is used as a guide when starting construction. At
the conclusion of moist-mixing, a moisture-density test,
AASHTO T134 or ASTM D558, is made on a representative
sample of the mixture taken from the roadway. This test deter
mines the optimum moisture and maximum density to be used
for field control of the section under construction. These re
sults may differ from laboratory values due to minor variations
in the soil material or due to the effects of partial hydration of
the cement during the mixing period.
In the moisture-density test, the soil-cement mixture is
compacted in three layers of approximately equal thickness
in a 1 30-cu-ft (943-cm ) mold with collar attachment, some
times called a Proctor mold. The mold should be on a rigid, uni
form foundation.
Each layer is compacted by 25 uniformly distributed vertical
blows of a 5 -lb (2.5-kg) rammer with a free fall of 12 in. (305
mm). The thickness of the layers is controlled so that the third
layer extends above the top of the mold about 2 in. (13 mm)
into the collar extension. After the collar is removed, the soilcement is trimmed to the exact height of the mold: then the
assembly is weighed. The net wet weight of the compacted
Fig. 15. Running a field moisture-density test.

5. Weight of water in soil material:


1753_1662=91 lb(41 kg)

..,

6. Weight of water needed:


2000- 1762 = 238 lb (108 kg)
7. Weight of water to add:
238-91 147 lb (67 kg)
or 17.6 U.S. gal (67 L) (14.7 imp gal)
30

ii

MOISTURE-DENSITY RELATIONS

MOISTURE-DENSITY RELATIONS
STATE

DATE

cou~nv

ROUTE

LOCATION:

PROJECT N

PROJECT

PROJECT NO

REMARKS

TEST NUMBER
iii Wetweightspecimen + mold

lb

i2i Weight St mold

lb

i3i Net wetweight specimen (1) (2)


(4i Wlume St mold
(5) Wet density (3) i4i
i61 Wet weight sample + Container
(7) Dry weight sample + cOntainer
(8) Weight of moisture iEi

lb

I + (lv)

~
i29_0_ 131i

~ ~
~
~

5~_.
~
Ib/Cuft

~ .974.

kg

.3_Sos

kg

(5) Wet density (31

(4)

2058.

ZL40.

.2J.45..

._SL..

(7) Dry mass sample + container

18) Mass of moisture 16) (7)

..._$L .........Z8....

........

g
g

L~..
.554..

-i-

(1 +

(to)) 100

._~..o..

(11))

kgb5

I 883

Euxe.se~iasadecmai

Maximum Density

ISO

120.0

Muximum Density
lb/cu ft

1922
~ 19

Optimum Moisture
11.8

ite

Inspector

10
MOISTURE CONTENT,ft.

10
MOISTURE CONTENT.%

material at different moisture contents is determined in this


manner.
For each trial, the moisture content is determined and the

19CC

Inspector

Fig. 16. Typical field moisture-density data and curve in U.S.


customary units.

kg/m5

Optimum Moisture

z
a

32

kgb5

(it) Moisturn Content ((8)

E0r.SS.dflad.o,,,&

181 Wet mass sample + Container

)t2) Dry density (5)

9.815.

Cm

19) Mass 01 Container


(10) Net muss dry sample (7) (9)

.52.4.... ....584....
~

.uL~... 1.LS..

kg

(2) MaSs xl mold


(4) Volume 01 mOld

.105....

~~~__

TEST NUMBER
(1) Wet mass specimen + mold
(3) Net wet muss specimen )t) (2)

.SL

ilSi Netweightdrysample~7( )9i


(It) Moisturecontent (8) (10) 100
(12) Dry density (5)

12.95.. .12.96.

cx ft
lb/Cu ft

i7i

(9) Weight of Container

L2..40

Ii

15

Fig. 17. Typical field moisture-density data and curve in SI units.

dry weight calculated and plotted against ittoform a moisturedensity curve(Figs.16 and 1 7).The optimum mo sture content
is that at which the greatest dry density is obtained. This den-

33

sity is referred to as the maximum density, and represents


approximately the density to be attained in soil-cement con
struction.
Many engineers have devised shortcuts in making field
moisture-density tests. For instance, the field sample, which
is near optimum moisture, is split in three parts and one portion
is used to establish a point near the peak of the moisture-den
sity curve (Fig. 18). A second portion of material with the addi
tion of a small increment of water is then used to establish a
point on the wet side of the curve. The third part of the original
field sample. which has dried slightly in the interim, is used to
establish a dry point on the curve.
With a little experience, an inspector can accurately judge
when a soil-cement mixture is at optimum moisture by its feel
and by the way it packs into the mold. Such shortcuts de
crease the time required to make a moisture-density test and

produce reliable results when tests are performed by an ex


perienced operator.
Field moisture-density tests are important and should be
conducted regularly to control construction variables and
assure satisfactory results. Figs. A-i and A-2 in the Appendix
are typical form sheets used for moisture-density determina
tions in the field.

Moisture Test
In order to estimate mixing-water requirements, representa
tive moisture samples are obtained from the raw soil prior to
mixing and water application.
The moist samples are weighed, then dried and reweighed.
The moisture content is computed as follows:
wet weight dry weight
Percent moisture =
x 100
dry weight
For field testing, samples containing gravel retained on the
No. 4 (4.75-mm) sieve should weigh at least 750 g. Samples
containing no gravel should weigh at least 400g. Tables 4 and
5 can be used to determine moisture contents for moist sam
ples weighing either 750 or 400 g when their dry weights are
known.
-

20-

~I950

1900
850

(I)

110-

10

15

MOISTURE CONTENT. %

Fig. 18. Field moisture-density curve for soil-cement mixture at


or near optimum moisture can be established by running the test
in the order indicated.
34

Fig. 19. Soils are dried on a portable stove to determine moisture


content.

Dry weight,
g
649.0
648.0
647.0
646.0
645.0
644.0
643.0
642.0
641.0
640.0
639.0
638.0
637.0
636.0
635.0

0.8
0.9
1.1
1.2
1.4
1.5
1.6
1.8
1.9
2.0
2.2
2.3
2.5
2.6
2.7

% moisture
12.1
12.3
12.4
12.6
12.8
13.0
13.1
13.3
13.5
13.6
13.8
14.0
14.2
14.3
14.5
14.7
14.9
15.0
15.2
15.4

744.0
743.0
742.0
741.0
740.0
739.0
738.0
737.0
736.0
735.0
734.0
733.0
732.0
731.0
730.0

Dry weight,
g
669.0
668.0
667.0
666.0
665.0
664.0
663.0
662.0
661.0
660.0
659.0
658.0
657.0
656.0
655.0
654.0
653.0
652.0
651.0
650.0

634.0
633.0
632.0
631.0
630.0

714.0
713.0
712.0
711.0
710.0

719.0
718.0
717.0
716.0
715.0

724.0
723.0
722.0
721.0
720.0

729.0
728.0
727.0
726.0
725.0

0.1
0.3
0.4
0.5
0.7

749.0
748.0
747.0
746.0
745.0

Dry weight,
g

% moisture

Dry weight,
g

18.3
18.5
18.7
18.9
19.0

17.4
17.6
17.7
17.9
18.1

16.5
16.6
16.8
17.0
17.2

15.6
15.7
15.9
16.1
16.3

% moisture

5.0
5.2
5.3
5.5
5.6

4.3
4.5
4.6
4.7
4.9

3.6
3.7
3.9
4.0
4.2

2.9
3.0
3.2
3.3
3.4

% moisture

614.0
613.0
612.0
611.0
610.0

619.0
618.0
617.0
616.0
615.0

624.0
623.0
622.0
621.0
620.0

629.0
628.0
627.0
626.0
625.0

Dry weight,
g

694.0
693.0
692.0
691.0
690.0

699.0
698.0
697.0
696.0
695.0

704.0
703.0
702.0
701.0
700.0

709.0
708.0
707.0
706.0
705.0

Dry weight,
g

22.1
22.3
22.5
22.7
23.0

21.2
21.4
21.6
21.8
22.0

20.2
20.4
20.6
20.8
21.0

19.2
19.4
19.6
19.8
20.0

% moisture

8.1
8.2
8.4
8.5
8.7

7.3
7.5
7.6
7.8
7.9

6.5
6.7
6.8
7.0
7.1

5.8
5.9
6.1
6.2
6.4

% moisture

594.0
593.0
592.0
591.0
590.0

599.0
598.0
597.0
596.0
595.0

604.0
603.0
602.0
601.0
600.0

609.0
608.0
607.0
606.0
605.0

Dry weight,
g

674.0
673.0
672.0
671.0
670.0

679.0
678.0
677.0
676.0
675.0

684.0
683.0
682.0
681.0
680.0

689.0
688.0
687.0
686.0
685.0

Dry weight,

TABLE 4. Moisture Contents of Samples Weighing 750 g Wet and Having


Final Dry Weight Shown

26.3
26.5
26.7
26.9
27.1

25.2
25.4
25.6
25.8
26.0

24.2
24.4
24.6
24.8
25.0

23.2
23.4
23.6
23.8
24.0

% moisture

11.3
11.4
11.6
11.8
11.9

10.5
10.6
10.8
10.9
11.1

9.6
9.8
10.0
10.1
10.3

8.9
9.0
9.2
9.3
9.5

k moisture

~,,

Dry weight,
g
349.5
349.0
348.5
348.0
347.5

0.8
0.9
1.0
1.1
1.3
1.4
1.5
1.7
1.8
1.9
2.0
2.2
2.3
2.4
2.6

% moisture
11.3
11.4
11.6
11.7
11.9
12.0
12.2
12.4
12.5
12.7
12.8
13.0
13.2
13.3
13.5
13.6
13.8
14.0
14.1
14.3

397.0
396.5
396.0
395.5
395.0
394.5
394.0
393.5
393.0
392.5
392.0
391.5
391.0
390.5
390.0

Dry weight,
g
359.5
359.0
358.5
358.0
357.5
357.0
356.5
356.0
355.5
355.0
354.5
354.0
353.5
353.0
352.5
352.0
351.5
351.0
350.5
350.0

342.0
341.5
341.0
340.5
340.0

344.5
344.0
343.5
343.0
342.5

347.0
346.5
346.0
345.5
345.0

382.0
381.5
381.0
380.5
380.0

384.5
384.0
383.5
383.0
382.5

387.0
386.5
386.0
385.5
385.0

389.5
389.0
388.5
388.0
387.5

0.1
0.3
0.4
0.5
0.6

399.5
399.0
398.5
398.0
397.5

Dry weight,
g

% moisture

Dry weight,
g

17.0
17.1
17.3
17.5
17.6

16.1
16.3
16.4
16.6
16.8

15.3
15.4
15.6
15.8
15.9

14.4
14.6
14.8
14.9
15.1

% moisture

4.7
4.8
5.0
5.1
5.3

4.0
4.2
4.3
4.4
4.6

3.4
3.5
3.6
3.8
3.9

2.7
2.8
3.0
3.1
3.2

% moisture

332.0
331.5
331.0
330.5
330.0

334.5
334.0
333.5
333.0
332.5

337.0
336.5
336.0
335.5
335.0

339.5
339.0
338.5
338.0
337.5

Dry weight,
g

372.0
371.5
371.0
370.5
370.0

374.5
374.0
373.5
373.0
372.5

377.0
376.5
376.0
375.5
375.0

379.5
379.0
378.5
378.0
377.5

Dry weight,
g

20.5
20.7
20.8
21.0
21.2

19.6
19.8
19.9
20.1
20.3

18.7
18.9
19.0
19.2
19.4

17.8
18.0
18.2
18.3
18.5

% moisture

7.5
7.7
7.8
8.0
8.1

6.8
7.0
7.1
7.2
7.4

6.1
6.2
6.4
6.5
6.7

5.4
5.5
5.7
5.8
6.0

% moisture

322.0
321.5
321.0
320.5
320.0

324.5
324.0
323.5
323.0
322.5

327.0
326.5
326.0
325.5
325.0

329.5
329.0
328.5
328.0
327.5

Dry weight,
g

362.0
361.5
361.0
360.5
360.0

364.5
364.0
363.5
363.0
362.5

367.0
366.5
366.0
365.5
365.0

369.5
369.0
368.5
368.0
367.5

Dry weight,
g

TABLE 5. Moisture Contents of Samples Weighing 400 g Wet and Having


Final Dry Weight Shown

24.2
24.4
24.6
24.8
25.0

23.3
23.5
23.6
23.8
24.0

22.3
22.5
22.7
22.9
23.1

21.4
21.6
21.8
22.0
22.1

% moisture

10.5
10.7
10.8
11.0
11.1

9.7
9.9
10.0
10.2
10.3

9.0
9.1
9.3
9.4
9.6

8.3
8.4
8.5
8.7
8.8

% moisture

Some agencies use the large calcium carbide/acetylene


gas pressure moisture tester for determining moisture con
tent. It can be used only for materials that pass the No.4(4.75mm) sieve, and the sample size is very limited.

Mixing-Water Requirements for


Mixed-in-Place Construction

The approximate percentage of mixing water required is equal


to the difference between the optimum moisture content and
the moisture content of the soil material as determined above.
About 2% additional moisture must be added to account for
the dry cement added to the soil and for evaporation that nor
mally occurs during processing. The quantity of water re
quired per unit length or per minute for 1% moisture can be
determined by using Fig. 20.
EXAMPLE 9.
Determine water required.
GIVEN:
In-place moisture content of raw soil material
5.5%
Optimum moisture content
11.5%
Maximum density.... 121.2 lb per cubic foot (1941 kg/m3)
Compacted depth
6 in. (150 mm)
Mixing width
8 ft (2.4 m)
Mixing rate
30 ft per minute (9.1 m/min)
PROCEDURE:
1. The approximate percentage of moisture required equals
the difference between the optimum moisture content
and the moisture content of the raw soil material, plus
2% of the total mixture (forevaporation): 11.5- 5.5 + 2 = 8%.
2. Enter Fig. 20 at the left edge at 8-ft (2.4-m) width of proc
essing and proceed horizontally to the 6-in. (150-mm)
depth line; then proceed downward until the 121 .2-lb/
Cu ft (1941-kg/m3) density line is intersected. Proceed
horizontally to the right and read gallons per foot (L/m)
for 1% moisture: approximately 0.58 U.S. gal per foot, or
0.48 imp gal per foot (7.2 L/m).
3. Multiply gallons per foot (L/m) by the 8% moisture re
quired: 8 x 0.58 = 4.6 U.S. gal per foot, or 3.8 imp gal per
foot (8 x 7.2 = 58 L/m).
40

cJ

S
*
~n

I
0

I.,

I
g~

cJ

I
0
c~i

I
~

I
0

-~

Suissa~ojd ~0 LBPIM

Fig. 20. Quantity of water required to raise the moisture content


of soil-cement mixture one percentage point.
4. Continue on Fig. 20 horizontally from gallons per foot
(L/m) for 1% moisture until the travel-speed line of 30 ft
per minute (9.1 m/min) is intersected. Then proceed
41

downward and read gallons per minute (LImin) for 1%


moisture change: 17.4 u.s. gal or 14.5 imp gal (65.9 L).
5. Multiply gallons per minute (L/min) for 1% moisture
change by the 8% moisture required: 17.4 x 8 = 139 u.s.
gal per minute or 116 imp gal per minute (526 L/min).
If the soil-cement is being processed in windrows, the ap
proximate mixing water requirements are based on the quan
tity of soil material and cement per unit length of windrow.
EXAMPLE 10.

62.4 24 38.4 lb per foot (57.1 kg/m)


38.4/8.33 = 4.6 U.S. gal per foot or 3.8 imp gal per foot
(57 L/m)
This is the quantity of water to be added per unit length of
windrow.
7. Quantity of water to be added per unit of time:
4.6 x 12 ft per minute (forward speed of mixer) = 55.2 u.s.
gal per minute or 46.0 imp gal per minute (209 L/min)
-

Calculate quantity of water required.

Mixing-Water Requirements for


Central Mixing Construction

GIVEN: Weight of soil material at field moisture content per


unit length of windrow
460 lb per foot (685 kg/m)
Moisture content of in-place raw soil material
5.5%
Optimum moisture content of soil-cement mixture
11.5%
Forward speed of mixing machine, approximately 12 ft per
minute (3.7 rn/mm)

The quantity of water required in central mixing plants to bring


the soil-cement mixture to optimum moisture is based on the
quantity of soil material and cement entering the plant. The
calculations for the quantity of water required are included in
the examples in the section Calibrating Central Mixing
Plants.

...

PROCEDURE:
1. Convert weight of soil material per unit length of windrow
at its in-place moisture content to weight of the ovendry
soil material:
460
= 436 lb ovendry soil material
(1.0 + 0.055)
per linear foot (649 kg/rn)
2. Quantity of cement required per unit length of windrow:
436 x 0.06 = 26.2 lb per foot (39 kg/rn)
3. Quantity of dry soil material plus cement per unit length
of windrow:
436 + 26.2 = 462.2 lb per foot (688 kg/rn)
4. Quantity of water in soil material per unit length of windrow:
460 436 = 24 lb per foot (35.7 kg/rn)
-

5. Estimate quantity of water required per unit length of


windrow to bring mixture to required moisture (optimum
moisture content, 11 .5%, plus 2% for evaporation):
462.2

0.135

62.4 lb per foot (92.9 kg/rn)

6. Subtract water in the soil material:


42

Hand-Squeeze Test for Moisture Content


With a little experience, an inspector can estimate the mois
ture content of a soil-cement mixture by observation and feel.
A mixture near or at optimum moisture content is just moist
enough to dampen the hands when it is squeezed in a tight
cast. Mixtures above optimum will leave excess water on the
Fig. 21. Soil-cement at optimum moisture casts readily when
squeezed in the hand and can be broken into two pieces without
crumbling.
I

_.

hands, while mixtures below optimum will tend to crumble


easily. If the mixture is near optimum moisture content, the
cast can be broken into two pieces with little or no crumbling.
The hand-squeeze test is not a replacement for the stand
ard moisture-content test, but it does reduce the number of
these tests required during construction. The moisture-deter
mination test validates what has been determined by visual
inspection and the hand-squeeze test.

Moisture for Compaction and Finishing


At the start of compaction, the moisture content of the soilcement mixture must be at slightly above optimum. A final
check of moisture is made at this time. Proper moisture is nec
essary for proper compaction and for hydration of the cement.
Because of evaporation, it is better to have a slight excess of
moisture than a deficiency when compaction begins.
During compaction and finishing, the surface of the soilcement mixture may become dry, as evidenced by greying of
the surface. When this occurs, very light applications of water
are made to bring the moisture content back to optimum. A
pressure distributor is used to make these fog applications
of water. Proper moisture in the compacted soil-cement is evi
denced by a smooth, moist, tightly knit surface free of checks,
cracks, or ridges.

Fig. 22. Uniform color indicates thorough mixing.


tionship varies slightly with the type of soil being processed.
Routine depth checks should be made during mixing opera
tions to assure that the specified thickness is attained.
Line stakes set 1 ft (0.3 m) outside the desired roadway
edge are used to control width of processing. It is important
that a uniform mix be obtained at the edges.
Fig. 23. A stick with marks on it can be used to check the depth
of the loose soil-cement. Frequent depth checks of the loose
mixture should be made.

Uniformity of Mix: Depth


and Width of Treatment
A thorough mixture of pulverized soil, cement, and water is
necessary to make quality soil-cement. The uniformity of mix
is checked by digging trenches or a series of holes at regular
intervals for the full depth of treatment and then inspecting the
color of the exposed material. The area between mixing lanes
should also be checked. When the mixture is of uniform color
and texture from top to bottom, the mix is satisfactory. A mix
ture that has a streaked appearance has not been mixed suf
ficiently.
Depth of mixing is usually checked at the same time as uni
formity. Usually 8to gin. (200 to 230 mm)of loose mixwill pro
duce about a 6-in. (150-mm) compacted thickness. This rela
44

45

In street construction, special attention should be given to


the mixing of soil-cement adjacent to curbs and gutters. All
soil and cement should be moved away from the gutter sec
tion for the full depth of processing using the point of the
motor-grader blade, a plow, or other devices. After mixing is
performed, the material is bladed back and compacted.

Compaction
The principles governing compaction of soil-cement are the
same as those for compacting the same soil materials without
cement treatment. The soil-cement mixture at optimum mois
ture should be compacted and finished immediately. Moisture
loss by evaporation during compaction and finishing, indica
ted by a greying of the surface, should be replaced with light
applications of water.
Tamping (sheepsfoot) rollers are generally used for initial
compaction except for the more granular soils. To obtain ade
quate compaction, it is sometimes necessary to operate the
rollers with ballast to give greater unit pressure. The general
rule is to use the greatest contact pressure that will not exceed
the bearing capacity of the soil-cement mixture and that will
still walk out in a reasonable number of passes.
When tamping rollers are used for initial compaction, the
mixed material must be loose so that the feet will pack the bot
tom material and gradually walk out on each succeeding pass.
If penetration is not being obtained, the scarifier on a motor
grader or a traveling mixer can be used to loosen the mix dur
ing start of compaction, thus allowing the feet to penetrate.
Vibratory-steel-wheel rollers, grid rollers, and segmented
rollers can be used satisfactorily to compact soil-cement
made of granular soil materials. Vibratory-plate compactors
are used on nonpiastic granular materials.
Pneumatic-tire rollers can be used to compact coarse sand
and gravel soil-cement mixtures with very little plasticity and
very sandy mixtures such as dune, beach, or blow sand, which
have little or no binder material. Some rollers permit rapid infla
tion and deflation of the tires while compacting.
Pneumatic-tire rollers pulled by track-type tractors equip
ped with street plates can be used to compact cohesionless
sand mixtures. The weight and vibration of the tractor aid in
compaction.

46

Fig. 24. Compacting the soil-cement with a vibratory steel


wheel roller.

Heavy three-wheel steel rollers can be used to compact


coarse granular materials containing little or no binder. Grav
elly soils that have low plasticity are best suited for compac
tion with these rollers.
For best results, compaction should start immediately after
the soil material, cement, and water have been mixed. Re
quired densities are then obtained more readily, there is less
water evaporation, and daily production is increased.

Finishing
There are several acceptable methods for finishing soilcement. The exact procedure depends on equipment, job
conditions, and soil characteristics. Regardless of method,
the fundamental requirements of adequate compaction
and optimum moisture must be met to produce a high-quality
surface. The surface should be smooth, dense, and free of
ruts, ridges, or cracks.

material next to the joint must be thoroughly compacted. The


joint should be left slightly high; then during final blading it is
trimmed to grade with the motor grader and rerolled.

When shaping is done during finishing, all smooth surfaces,


such as tire imprints and blade marks, should be lightly
scratched with a weeder, nail drag, coil spring, or spiketooth
harrow to remove cleavage or compaction planes from the
surface. The reason for this is that a thin layer of soil-cement
placed on top of these compaction planes may not adhere
properly and in time may fracture, loosen, and spall. For good
bond, the area must be rough and damp. Scratching should be
done on all soil-cement mixtures except those containing
appreciable quantities of gravel.
The surface should be kept damp during finishing opera
tions. Steel-wheel rollers can be used to smooth out ridges left
by the initial pneumatic-tire rolling. Steel-wheel rollers are
particularly advantageous when rock is present in the surface.
A broom drag can sometimes be used advantageously to pull
binder material in and around pieces of gravel that have been
set by the steel-wheel roller. Instead of using a steel-wheel
roller, surfaces can be shaved with the motor grader and then
rerolled with a pneumatic-tire roller to seal the surface. Shav
ing consists of lightly cutting off any small ridges left by the fin
ishing equipment. Only a very thin depth is cut and all material
removed is bladed to the edge of the road and should not be
used. The final operation usually consists of a light application
of water and rolling with a pneumatic-tire roller to seal the sur
face. The finished soil-cement is then cured.
Regardless of the method used, the surface should be main
tained at not less than optimum moisture content during finish
ing and the compacted surface should be smooth, dense, and
free of compaction planes and cracks.
A complete discussion of finishing of soil-cement, including
a suggested step-by-step procedure to be used for various
soil types, can be found in the PCA publication Soil-Cement
Construction Handbook, EBOO3.

The most common density test methods are


1. Nuclear method
2. Sand-cone method
3. Balloon method
If the test is performed with care, these and other methods
can be used to determine the degree of compaction obtained.
Various types of apparatus are available for all these methods.
A comparison of dry densities is used to determine the degree
of compaction obtained; however, a rough check on the
degree of compaction can be made quickly by comparing wet
densities.
Densities should be determined at several locations on the
first few sections completed; the tests are made immediately
after final rolling. Comparison of these densities with the re
sults of the field moisture-density test indicates any adjust
ments in compaction procedures that may be required to en
sure compliance with job specifications. Specifications gen
erally require that the density obtained not be less than 96%
as determined by the field moisture-density test. After com
paction procedures have been adjusted, only routine daily
density checks are required.
In street construction, special attention to compaction ad
jacent to the curb, gutter, and utility structures is necessary.
The wheels of a motor grader can be used to obtain additional
compaction along the gutter line.

Joint Construction

Nuclear Method

At the end of each days construction, a transverse construc


tion joint is formed by cutting back into the completed soilcement, using the toe of the motor-grader blade or axes. The
resulting joint should be vertical and firm.
During processing of the abutting section, it is important that
the material next to the joint be mixed well. The joint is cleaned
of all dry and unmixed material and retrimmed if necessary.
Then the mixed moist material is bladed back to the joint. The

Many agencies that are engaged in compaction control on a


fairly regular basis use the nuclear method in the direct trans
mission mode of operation (ASTM D2922 and D3017,
AASHTO T238 and T239). Many of these nondestructive tests
can be run in a short time. Proper calibration, operation, and
maintenance of the equipment are essential. A license is re
quired and operator instructions and safety precautions must
be adhered to.

48

Degree of Compaction
and Final Depth Check

49

.,,-.
~

~
.,..

~r~

~
;.

,.

j51

..,

1
t

Fig. 25. Density of compacted soil-cement being determined by


the nuclear method in the directtransmisSiOfl modeof operation.

Fig. 26. Density of compacted soil-cement being determined by

the sand-cone method. A hole is dug in the base, and the dry

weight of the material removed and the volume of the hole are
computed.

Sand-Cone Method
The sand-cone method, AASHTO Ti 91 or ASTM Dl 556, is

one of the most common for determining in-place densities.


Fig. 26 shows the apparatus used.
The sand should be clean, dry, uniform, uncemented, dur
able, and free-flowing. The sand should be comprised of
natural subrounded or rounded particles. The maximum-size
particle should pass the No. 10 (2.0-mm) sieve with less than
3% passing the No. 60 (0.25-mm) sieve. The sand must be airdry both at the time its bulk density is determined and when it
is used for in-place density determinations.
The procedure for calibrating the sand and funnel and for
making the test follows.
Calibration of Sand and Apparatus
1. Determine the weight of the density apparatus.
2. Pour the air-dry sand into the inverted apparatus through
the open valve until the jug and the pycnometer top are
full. During this operation the funnel shall be approximate
ly half-full of sand at all times. Avoid jarring or vibrating
the density apparatus while the sand is flowing. When the
sand stops flowing, close the valve and remove the ex
50

cess sand in the funnel. Weigh the apparatus and sand


and determine the net weight of sand. Remove the sand
from the density apparatus.
3. Determine the volume of the jug and pycnometer top with
water. Pour water into the inverted density apparatus
through the open valve until water appears in the funnel.
Close the valve, remove excess water, and dry the funnel
and outside surfaces of the apparatus. Weigh the appa
ratus and the water and determine the net weight of water.
Remove the water and dry the apparatus.
EXAMPLE 11.

Determine unit weight of sand and calibrate funnel.


PROCEDURE:
1. Weight of apparatus filled with sand

1 7.91 lb
(8.124 kg)
2. Weight of apparatus
4.20 lb (1 .905 kg)
3. Weight of sand, (1) -(2)
13.71 lb (6.219 kg)
4. Weight of apparatus filled with water
12.75 lb
(5.783 kg)
51

5. Weight of water, (4) (2). 8.55 lb (3.878 kg)


6. Volume of apparatus, (5) / 62.4*
0.137 Cu ft
(0.00388 m3)**
7. Unit weight of sand, (3) / (6)
100.1 lb/cu ft
(1603 kg/m3)
-

Calibration of Funnel
To determine the weight of sand required to fill the funnel, in
vert the density apparatus full of sand on the metal base plate
on a smooth, flat surface; then open the valve until the sand
stops flowing. Close the valve and remove the apparatus and
unused sand.
EXAMPLE 12.
Calculate the amount of sand needed to fill the funnel and
base plate.
PROCEDURE:
1. Weight of apparatus and sand at start
17.91 lb
(8.124 kg)
2. Weight of apparatus and unused sand
13.98 lb
(6.341 kg)
3. Weight of sand to fill funnel and base plate, (1) (2)..
3.93 lb (1 .783 kg)
-

Density Test
1. Level the surface of the test area. Using the base plate as
a guide, dig a hole approximately 5 in. (125 mm) in diam
eter almost through the depth of treatment, using a ham
mer and chisel or soil auger. To avoid enlargement of the
hole by pressure of the excavating tools, material should
be loosened in the test hole by cutting. Carefully remove
all loosened material in the test hole and place itin a tight
ly covered container. Clean the hole with a brush and re
move all loose particles. Use care during the test to avoid
losing any material removed from the test hole.
2. Determine the volume of the test hole by the use of the
density apparatus and calibrated sand. Fill the jug with
the sand and weigh the apparatus and sand. Invert the
*1 cu ft of water weighs 62.4 lb.
~1 m3 of water has a mass of 1000 kg

52

apparatus and place the funnel rim over the hole and in
the groove provided in the base plate. Open the valve and
allow the sand to fill the test hole and funnel. Avoid jarring
or vibrating the density apparatus during the test. After
the sand has stopped flowing, close the valve and weigh
the apparatus and remaining sand. The sand used to fill
the test hole is the weight of sand released in the test
minus the weight of sand in the upper cone.
3. Determine the moist weight of all material removed from
the test hole. Mix the material thoroughly, then take a rep
resentative sample and determine its moisture content.
Using this moisture content, calculate the dry weight of
material removed from the test hole.
4. For gravelly soils, determine the percentage of gravel re
tained on the No. 4 (4.75-mm) sieve of the material re
moved from the test hole.
Calculations
1 The moisture content and the ovendry weight of material
removed from the test hole are calculated as follows:
% moisture of representative sample
= wet weight-dryweight ~ 100
dry weight
Dry weight of material from test hole
wet weiqht
1.0 + (% moisture/100)
% retained on No. 4 (4.75-mm) sieve
= weight retained on No.4(4.75-mm) sieve
100
total dry weight of sample
2. The volume of the test hole, in cubic feet (m3), is calcu
lated as follows:
weight of sand used minus sand in upper cone, lb (kg)
unit weight of the sand, lb/cu ft (kg/rn3)
.

3. The in-place, ovendry density, in pounds per cubic foot


(kg/rn3) of the soil-cement equals
dry weight of material removed from hole, lb (kg)
volume of hole, Cu ft (m3)
53

Rubber-Balloon Method
As with the sand-cone method, the density hole is dug and all
the material removed is placed in a container and its dry
weight determined. The volume of the hole is then determined
directly using a calibrated apparatus containing water. A pres
sure bulb exerts pressure on the water and a rubber balloon
containing water is forced into the confines of the density hole
(ASTM D21 67, AASHTO T205). The difference between the
initial and final water volume readings is the volume of the
hole. Like other methods, the rubber-balloon method has limi
tations and care must be taken in running the test.

aAoJb ~o
~N

Q
N

~()
N

~
N

j~

ds

~iI~8

n~I

~
U,

Record of Field Density Tests

.a_ ~

+0

55
~LX

~
U

~
U~

5~Z

~
& ~
U,

A record of density and depth data should be kept. The proce


dure for keeping records is illustrated on the form sheet (Fig.
A-3) in the Appendix.

Correcting for Differences in Gravel Content

Occasionally, field densities of soil-cement containing large


percentages of gravel do not agree with the moisture-density
test results. The percentage of gravel in the material taken
from the density hole may be different from that in the sample
used in the field moisture-density test. This difference in den
sity can be corrected by using Fig. 28. A similar chart is given
in AASHTO T224.
Fig. 27. Measuring depth of
treatment through the density
hole. A phenolphthalein solution
can be squirted down the side
of a freshly cut face of newly
compacted soil-cement. The
soil-cement will turn pinkish-red
while the untreated subgrade
material
will
retain
its
/
natural color.

0+

S
E

B ro/q~ ~ ~G

Fig. 28. Density correction chart for differences in gravel content.

54

55

EXAMPLE 13.

Find density corrected for gravel content.


GIVEN:
Percentage of gravel larger than No.4(4.75-mm) sieve in field
moisture-density test sample
18%
Percentage of gravel larger than No. 4 (4.75-mm) sieve in
sample from field density hole
11%
Bulk specific gravity of gravel
2.50*
Maximum density from field moisture-density curve deter
mined on sample containing 18% gravel
120.0 lb per
cubic foot (1922 kg/m3)
PROCEDURE:
On the grid (Fig. 28) locate the intersection of 120.0 lb per
cubic foot (1922 kg/m3) dry density and 18% gravel. With a
straightedge, intersect this point and the specific gravity of
2.50, then extend this line until it intersects the vertical line on
the grid representing 11 % gravel. Project this point horizontal
ly to the dry density scale on the left edge: 118.2 lb per cubic
foot (1893 kg/m3)
ANSWER:
The density of 118.2 lb per cubic foot (1893 kg! m3) is the cor
rected theoretical maximum dry density of the field moisturedensity testforasample containing 11% gravel instead of 18%
gravel. The in-place dry density of the material tested should
be compared to this corrected density.
After the density determination is made, the compacted
depth is measured. The depth of treatment is usually quite
apparent because of the difference in color between the subgrade and the soil-cement mixture. However, it is sometimes
difficult to distinguish the bottom of treatment by color, in
which case water is poured into the density hole and allowed
to stand. The subgrade will be softened while the full depth of
treatment will remain firm. The bottom of treatment can then
*Bulk specific gravity of gravel (pycnometer method)
A
B
Y
Z

56

=
=
=
=

B +~

be determined by probing with a pointed instrument.


A phenolphthalein solution can be squirted down the side of
a freshly cut face of newly compacted soil-cement. The soilcement will turn pinkish-red while the untreated subgrade
material will retain its natural color.

Curing
Soil-cement at optimum moisture contains sufficient moisture
for adequate cement hydration. After final compaction, a
moisture-retaining cover is placed over the soil-cement to
permit the cement to hydrate. Moist soil-cement is cured with
bituminous material, but other materials such as waterproof
paper or plastic sheets, wet straw or sand, fog-type water
spray, and wet burlap or cotton mats are entirely satisfactory.
The bituminous materials most commonly used are emulsified
asphalt SS-1, RC-250, MC-250, and RT-5.
The rate of application varies from 0.15 to 0.30 gal per
square yard (0.7 to 1 .4 L!m2). Before the bituminous material
is applied, the surface of the soil-cement should be moist and
free of dry, loose material. In most cases a light application of
water precedes the bituminous cure.
When the air temperature is expected to reach the freezing
point, the soil-cement should be protected from freezing for 7
days after its construction and until it has hardened.
(

.7..

ovendry weight of gravel, grams


saturated surface-dry weight of gravel, grams
weight of pycnometer filled with water, grams
weight of pycnometer and saturated surface-dry gravel, filled
with water, grams

Fig. 28.Water truck applies light water spray to soil-cement sur


face to maintain moisture throughout compaction, finishing, and
curing operations.
57

Opening to Traffic
Completed portions of soil-cement can be opened immedi
ately to local traffic and to construction equipment providing
the soil-cement has hardened sufficiently to prevent marring
or distorting of the surface, and providing the curing material
is not impaired. If the bituminous moisture-retaining cover
has not dried sufficiently to prevent pick-up, sufficient sand or
grandular cover should be applied.

Maintenance
Specifications require that the contractor maintain the soilcement in good condition until all work has been completed and
accepted. Any defects that occur should be repaired immedi
ately by replacing the soil-cement for the full depth of treatment.
Areas deficient in thickness should also be remedied by replac
ing the material for full depth of treatment rather than by adding
a thin layer of soil-cement to the completed work.

58

Appendix
Equipment for Field Tests
1. Field laboratory.
2. Two-burner field stove.
3. Split moisture-density mold and rammer(1 /30-cu-ft [943cm3] mold; sleeved 5Y2-lb [2.5-kg] rammer).
4. Balance with weights, 750-g capacity.
5. Scale with weights, 20-lb (9-kg) capacity.
6. Three 3x3-ft (lxi -m) pieces of canvas.
7. Spring scale, 100-lb (45-kg) capacity.
8. Set of 8-in-diameter (200-mm) sieves: 2 in. (50 mm), 34 in.
(19 mm), and No. 4 (4.75 mm).
9. Sand-cone density apparatus with supply of dry sand of
known unit weight.
10. A 5-in.-diameter (125-mm) soil auger and No. 2 shorthandled square-pointed shovel.
11. Hammer and two 1-in. (25-mm) masons chisels.
12. Six tin pie plates and six h-gal (2-L) containers with lids.
13. Two 1 0-in-diameter (250-mm) frying pans.
14. A 100-mI glass graduated cylinder.
*-5..A 10-in. (250-mm) butcher knife, 12-in. (300-mm) steel
straightedge, and 10-in. (250-mm) trowel.
16. Two 1 2-qt (11 -L) pails, two large spoons, and a 2-in. (50mm) paint brush.
17. A 5x5-ft (1 .5x1 .5-rn) canvas sample cloth.
18. Ruler and 50-ft (15-rn) tape.

59

Moisture-Density Relations

Moisture-Density Relations

(U.S. Customary Units)

(SI Units)
flflATIflN

DATE

STATE
ROUTE

PROJECT:

PROJECT NO

COUNTY

STATION:_________________________ REMARKS:

TESTNUMBER
(1) Wet weight specimen

1
+

(2) Weight 01 mOld

lb

(3) Net wet weight specimen (I)


(4) Volume of mold
(5) Wet density (3)

(2)

(4)

(8) Weight of moisture (6)

[I

(5) Wet densdy (3) (4)

)1t))

g
5

g
g

(10) Net mass dry sample (7()9)

(it) Moisture content ((8)

lb/cu It

(8) Mass of moisture (6) (7)


(9) Mass of container

(12) Dry density (5)

(1

(10)] 100

(11()

kg/rn

Mammum Density

Maoimum Density

kyIm

lb/cu If

kg
kg
kg
cm
kg/mu

(6) Wet mats sample + container


(7) Dry mass sample + container

(7)

(9) We:ghtotcontainer
(IS) NetweightdrysarnPle(7( (9)
(it) Moisturecofltenti)8) (iO))iOO
(12) Drydensity)5)

lb
Cu It
lb/cu It

(6) Wet weight sample + contamer


(7) Dryweight sample + container

REMARKS:____________________________

TEST NUMBER
(I) Wet mass specimen + mold
(2) Mass of mold
(3) Net wet mass spec:men (1) (2)
(4) Volume of mold

lb

mold

PROJECT NO.:

STATION:

Optimum Moislure

Optimum Mc,sture

0)
C
0

~
MOISTURE CONTENT.%

Fig. A-i. Form sheet for recording field moisture-density data


(U.S. customary units).

60

Inspector

Inspector

MOISTURE CONTENT. %

Fig. A-2. Form sheet for recording field moisture-density data


(SI units).

61

Field Density

Field Density

LOCATION
PROJECT

DATE

LOCATION

DATE

PROJECT NO

PROJECT

PROJECT NO

REMARKS
REMARKS
WeaWeIglitot Sample trese Test Hole

Wee WeIght of Sereplefrom Test Hole


(I)

Wet WeightotSamPle+Pe1

lb

121

Weightof Pen

(31

Wet Weight 01 Sample From Test Hole (1)

(2)

lb

kg

lb

kg

Holame Detemileetlen of Test Hole


4

lnSalWeightOtApParatuO~ Sand

Final Weightof Apparatus

lb

(El

Weight 01 Sand Used (4)

(SI

lb

(7)

Less Weight at Sand in Furerel

lb

1W
(5)

Weightot Sand Uead to FilITest Hole (6)


UnitWeightotSand(asCalibrated(

(IS)

i~urneotTestHnle(g(

Sand

(7)

(9)

kg
kg
kg

lb
lb/cuR

kg
............kglmi

cuR

.______.cm

(I)

Wet Weightol Sample

(2)

WeightolPan

(3)

WetWeightxlSampleFmmTestHole(1)

Pan
(2)

1203

lb

5.965

kg

3.10

lb

1406

kg

603

lb

4459

kg

1791

lb

6124

kg

646

lb

2 030

kg

6194

kg

*tume Determleag(ae of Tees Hole


Id)

lnibalWeightofApparatuo.Sand

b)

Final Weight at Apparatus

(61

WeighrxlbondUsad(4()b(

1149

lb

)7(

LessWeigktotgandinpunnral

3.93

lb

1.763

kg

(6)

WeighrotSandUsedroFieTeothtole)6((7)

792

lb

9411

kg

(51
(IS)

Unit Weight xl Sand (at catbraled)


SalumeofTeetHole(9) (9)

Sand

100 I
00791

lb/ca g
cuR

1603
213

kg/mr
cmi

Molotare Coolest Determln.gloe


Meletere Contest Detenolsetlon
(111

WetWeightotbalnPle+Cmttorrem

(12)

Dry Weight of Sample

)t3(

WeighlolCorrtainer

(14)

WeigbtotMoloture(l1(

Container
g
(12)

tb)

DryWeIghlotSaInPta(t2(

(16)

MmstureCOntentStd(

(131

(ml)

Wet WeightotSample

Container

1210

(12)

Dry Weightof Sample

Container

1106

(13)

Weight of Coritoner

(ld)

Weight of Moisture )tt)

113)

DryWeightotSemple)t2)

(16)

MoistumCorrrenr (ld(

376
(12)

04

113)

750

(151) 150

II 2

(tb((ISO
Denety

Dermeftp
(Ill

DryWaightotbanrplehOrrrTestHxle(3(

hg)

Dry Density(17)

(19)

Maximum Dry Density


Itrom Rest M-D relebmis)

(25)

DegreeOfCompactixflSlo)

(IS)

It

(16)9

(17)

DryWeighrolSamplehmnTesrHole(3) .-(t

lb

kg

)16(

Dry Density (17)

lblcutt

kg/me

1101

Manimam Dry Deosby


(fromlehtM-Drelatixss)

(20)

DegreeotCompactionplt8)

Ibicu 9

kglm

(IS)

)rgr(

004

lb

010

kg

1177

lb/caR

1003

kglm

20.0

Ib/oult

1925

kg/m3

(t9)(rSS

90

(15)1120
Depth

Depth
(Sm)

)Sr)
Depth at Treabnent

DepthntTmabnent

6-114

109

mm

eon

emseede,.dec?d

Irapector

Fig. A-3. Form sheet for in-place density testsand-Cone


method.
62

Fig. A-4. Example of in-place density test datasand-cone


method.
63

Related Publications
The following publications are available for purchase
from the Portland Cement Association.

Cement-Treated Aggregate Base, SR221


PCA Soil Primer, EBOO7
Properties and Uses of Cement-Modified Soil, 1411
Soil-Cement Construction Handbook, EBOO3
Soil-Cement Laboratoiy Handbook, EB052
Suggested Specifications for Soil-Cement Base
Course, lSOO8
Thickness Design for Soil-Cement Pavements, EB068
The publications listed above can be obtained by writing,
calling, or faxing Customer Service, Portland Cement
Association, 5420 Old Orchard Road, Skokie, Illinois
60077-1083, Phone: 847.966.6200, Fax: 847.966.9666 or
for a complete listing of all our products visit our Web site
at: www.portcement.org.

This publication is intended SOLELY for use by PROFESSIONAL PER


SONNEL who are competent to evaluate the significance and limitations
of the information provided herein, and who will accept total responsi
bility for the application of this information. The portland Cement
Association DISCLAIMS any and all RESPONSIBILITY and LIABILITY for
the accuracy of and the application of the information contained in this
publication to the full extent permitted by law.
Warning: Contact with wet (unhardened) concrete, mortar, cement, or
cement mixtures can cause SKIN IRRITATION, SEVERE CHEMICAL
BURNS (THIRD-DEGREE), or SERIOUS EYE DAMAGE. Frequent expo
sure may be associated with irritant and/or allergic contact dermatitis.
Wear waterproof gloves, a long-sleeved shirt, full-length trousers, and
proper eye protection when working with these materials. If you have to
stand in wet concrete, use waterproof boots that are high enough to keep
concrete from flowing into them. Wash wet concrete, mortar, cement, or
cement mixtures from your skin immediately. Flush eyes with clean water
immediately after contact. Indirect contact through clothing can be as
serious as direct contact, so promptly rinse out wet concrete, mortar,
cement, or cement mixtures from clothing. Seek immediate medical
attention if you have persistent or severe discomfort.

]
KEYWORDS: calibration, cement application, compaction, curing,
density, equipment, finishing, inspection, maintenance, mixing
plants, moisture, moisture density, pulvenzation, site preparation,
soil-cement processing, soil identification, soil materials, uniformity,
water application.
ABSTRACT: Describes procedures for inspecting soil-cement construction. Sample problems are given that show typical calculations
required for computing material quantities, and for field test. Tables
and charts to simplify these calculations are included.
REFERENCE: Soil-Cement Inspectors Manual
Portland Cement Association, 2001.

64

(PAO5O.03),

You might also like