Document Control Procedure
Document Control Procedure
REVISION LIST
Rev. 0
GENERAL PROCEDURE
DOCUMENT CONTROL PROCEDURE
SECTION
REV.
DATE
DESRCIPTION
Page 2 of 17
Rev. 0
Date: 11/07/2012
DESCRIPTION OF AMENDMENT
TABLE OF CONTENT
SECTION
GENERAL PROCEDURE
DOCUMENT CONTROL PROCEDURE
1.0
PURPOSE
2.0
SCOPE
3.0
REFERENCES
4.0
DEFINITION
5.0
PROCEDURE
Rev. 0
Date: 11/07/2012
5.1
RESPONSIBILITY
5.2
5.3
DISTRIBUTION OF PROCEDURES
5.4
5.5
5.6
5.7
CHARGE (SC)
5.8
5.9
5.10
6.0
SPECIAL REQUIREMENTS
7.0
RECORDS
APPENDICES
APPENDIX I INTERNAL TRANSMITTAL SHEET
APPENDIX II INTERNAL CONTROL DISTRIBUTION LIST OF RECORD
APPENDIX III DOCUMENT CHANGE NOTICE
APPENDIX IV REVISION NOTICE
APPENDIX V SITE TECHNICAL QUERY / SITE CHANGE
1.0
PURPOSE
This provides guidelines and proper control for approval, issuance,
changes, receipt and withdrawal of all documents in Engineering &
Construction.
GENERAL PROCEDURE
DOCUMENT CONTROL PROCEDURE
2.0
Rev. 0
Date: 11/07/2012
SCOPE
Shall cover the preparation, submission, distribution and control of the
following documents;
a.
b.
c.
d.
3.0
REFERENCES
CSBs QGP-5-01 : Document Control Procedure
FSP-CSB-12
: Design Control Procedure
Contract Document EXHIBIT IV
4.0
DEFINITIONS
Controlled Copy A document which is given a serial number and shall
allocated to a specific person.
The recipient acknowledges receipt and be kept current for all
amendments and revisions to that documents.
Uncontrolled Copy A document that is issued for information only and
recipient as not kept current with the latest amendment and revision to
that particular document.
Documents Shall include procedures, specification, drawings and work
instruction either individually or collectively.
CLIENT PCSB
MTO Material Take Of
STQ Site Technical Query
SC Site Charge
PMT Project Management Team
5.0
PROCEDURE
5.1
Responsibility
5.1.1 Each Department Manager whose department prepares and
issues the original and revision there to shall be responsible
GENERAL PROCEDURE
DOCUMENT CONTROL PROCEDURE
Rev. 0
Date: 11/07/2012
General Requirement
5.2.1 All procedures submission for the project shall be controlled
and coordinate by the Project Manager.
5.3
5.2.2
5.2.3
5.2.4
Distribution of Procedures
5.3.1 Distribution of procedures shall be controlled and
uncontrolled copy and to be indicated on the cover page.
Controlled Copy shall be distributed to relevant personnel on
need to know basis.
5.4
5.3.2
5.3.3
5.4.3
GENERAL PROCEDURE
DOCUMENT CONTROL PROCEDURE
5.4.4
5.5
Rev. 0
Date: 11/07/2012
5.6
5.7
5.8
GENERAL PROCEDURE
DOCUMENT CONTROL PROCEDURE
Rev. 0
Date: 11/07/2012
5.10
GENERAL PROCEDURE
DOCUMENT CONTROL PROCEDURE
Rev. 0
Date: 11/07/2012
d. Accept-as-is
c) The corrective action as proposed bu discipline
engineer shall be agreed by PCSB QA Inspector and the
responsible Discipline Engineer. PCSB shall review the
non-conformance and approved / agree to CSBs
proposed deposition.
d) Where a correct disposition of a non-conformance will
require engineering evaluation such as taking actual
test sample, recalculation and redesign before
disposition is made the responsible Discipline Engineer
shall refer the matter to the Project Manager for further
action. Such change shall be approve by client prior to
any work commence.
e) Rework or repair shall be carried out in accordance to
approved applicable documented procedures and
monitored by Discipline Engineer to ensure the
required quality is achieved.
5.10.4Corrective action
a) Where applicable, decide if the BC requires Corrective
Action.
b) Any changes from PCSB standard or codes shall be
approve by senior discipline engineer from the site
team.
5.10.5NCR Close out
a) NCR shall be closed when the repair or rework is done
is satisfactory or when the deviation proposal has been
agreed and approved by the client, QC Inspector shall
sign on the close-out column after verification and final
acceptance/inspection have been carried out at site.
Note : Any deviation proposal shall be in-line with
change control procedure
b) Ensure that after the NCR has been close-out any
marking or tagging is removed from the nonconforming item.
c) Prepare and update NCR Register.
5.10.6Analysis of NCR
a. Submit a copy of completed NCR to QA Engineer
b. Review the non-conformity and the disposition taken.
Forward any reviews of NCR that require QMRs
attention.
c. NCR reviews shall be evaluated and discussed during
Management Review.
All NCR & proposed corrective action shall be properly
documented for PCSBs appraisal / approval CSB shall also
perform trending analysis on recurring items in the NCR
Register.
GENERAL PROCEDURE
DOCUMENT CONTROL PROCEDURE
Rev. 0
Date: 11/07/2012
6.0
SPECIAL REQUIREMENTS
7.0
RECORDS
GENERAL PROCEDURE
DOCUMENT CONTROL PROCEDURE
APPENDICES
Rev. 0
GENERAL PROCEDURE
DOCUMENT CONTROL PROCEDURE
Rev. 0
Date: 11/07/2012
ITS NO :
PROJECT TITLE :
FROM :
JOB NO.:
NO
.
REFERENCE NO.
DESCRIPTION/
TITLE
SHT NO.
REV
NO.
ISSUE
NO.
QT
Y
REMARK :
FOR THE FOLLOWING ACTION :
REVIEWED
COMMENT
APPROVAL
&
RETENTION
DISTRIBUTION
INFORMATION
OTHER
S:
RECEIVED BY:
DATE:
GENERAL PROCEDURE
Page 12 of 17
Rev. 0
Date: 11/07/2012
RECORD NO. :
REV NO. :
PAGE NO. :
OF
DOC.TITLE :
DOC.NO :
CNTROLL
ED
NO.
REVISION
DATE ISSUE
TO
GENERAL PROCEDURE
Page 13 of 17
Rev. 0
Date: 11/07/2012
ORIGINATING DEPT. :
PROPOSED CHANGE :
PROPOSASL
DATE :
INITIATED
BY
REVIEWED BY :
DATE :
COMMENT / REMARKS :
APPROVE
D
NOT
APPROVED
GENERAL PROCEDURE
DOCUMENT CONTROL PROCEDURE
Rev. 0
GENERAL PROCEDURE
DOCUMENT CONTROL PROCEDURE
Rev. 0
Date: 11/07/2012
CLIENT
PROJECT
REV
BY
DATE
DRAWN / PREPARED
DESCRIPTION
JOB NO. :
REF.DWG :
SHT. :
REV. :
BY
DATE
CHECKED
TITLE
GENERAL PROCEDURE
Page 16 of 17
Originator Ref :
Discipline :
Dept. :
Drawing Nos.
CONTRACT REF :
PROJECT NO/TITLE :
STQ/SC NO. :
Sht.
No.
Rev. No.
System/Line
referred to
Rev. 0
Date: 11/07/2012
Clarification
Cost Impact
Design
Approval
No./Item Other
Discipline
affected
STQ/SC TITLE :
REPLIED BY
APPROVED BY
NAME/SIGNATU
RE
Approved
DATE
GENERAL PROCEDURE
DOCUMENT CONTROL PROCEDURE
Rev. 0