THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Contract
Title
Aprons, Taxiways, Roads, Tunnels, Bridges, Load Centers, and Infrastructure, Transportation Center (422)
Method Statement
For
Fire Protection Piping Installation And Testing
(Package 421)
Submitted By:
Prepared By
(Contractor/Sub-Con)
Name:
Reviewed By
(QA/QC
Manager)
Eng. Oussama Abbas
Reviewed By
(Safety Manager)
Approved By
(Project Manager)
Signature:
Date:
Page 1 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
List of Contents
Section
Title
Page
1.0
SCOPE OF WORKS
06
2.0
PURPOSE
06
3.0
ACRONYMS
06
4.0
CLASSES OF FIRE
07
5.0
CLASSIFICATION OF OCCUPANCY
07
6.0
AREA OF APPLICATION
7.0
RESPONSIBILITIES
7.1
7.2
7.3
7.4
7.4
8.0
8.1
8.2
08-09
9
9-10
10
10
10-11
TECHNICAL SUBMISSIONS
Shop Drawing
Material Submittals for Fire Fighting System & Accessories
9.0
CONFORMANCE CRITERIA
9.1
9.2
9.3
10.0
10.1
11
12-13
13
13-14
14
14-15
15-16
Page 2 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
List of Contents
Section
11.0
11.1
11.2
11.3
11.3.1
11.3.2
11.3.2.1
11.3.2.2
11.3.2.3
11.4
11.4.1
11.4.2
11.4.3
11.4.4
11.4.5
11.4.6
11.4.7
11.4.8
11.4.9
11.4.10
11.4.10.1
11.4.10.2
11.4.10.3
11.4.10.4
11.4.11
11.4.11.1
11.4.11.2
11.4.11.3
11.4.11.4
Title
Page
GENERAL PROCEDURES
Material delivery, handling & storage
Tools and Equipment
Pre-Installation Procedures
Painting Procedure
Grooving Procedure
Setting Grooving Machine
Pipe Grooving Procedure
Pipes Threading Procedure
Installation Procedures
Sleeves
Fire Sealant
Groove Coupling Installation
Lubrication of Gasket
Tightening Nuts of Grooved Coupling
Mechanical Tee - Installation
Installation Hanger & Support
Installation Beam Clamp Hanger & Support
Installation Flexible Coupling as per NFPA 13 - Chapter 9
Pipe Identification, Tagging and Labeling
Pipe Identification Installation
Valve - Tag Installation
Warning - Tag Installation
Metal Label for Equipment Installation
Automatic Wet Sprinkler System
Intallation Wet Sprinkler System
Hydrostatic Pressure Leak Test
Flushing Procedure
Interface
16
17-18
18
19
19
20-24
24-29
29-31
31-34
34
35-36
36
36-38
39-41
41-42
42
42-43
44
44
44-45
45-46
46
47-48
48-51
51-53
53-54
54-55
Page 3 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
List of Contents
Section
Title
Page
11.4.12
55-56
11.4.12.1
11.4.12.2
11.4.12.3
11.4.12.4
11.4.12.5
11.4.12.6
11.4.12.7
11.4.12.8
11.4.12.9
11.4.12.10
11.4.13
11.4.13.1
11.4.13.2
11.4.13.3
11.4.13.4
11.4.13.5
11.4.13.6
11.4.13.7
11.4.13.8
11.4.13.9
11.4.13.10
11.4.13.11
11.4.14
11.4.14.1
11.4.14.2
11.4.14.3
11.4.14.4
11.4.14.5
11.4.14.6
11.4.14.7
56-57
57-58
58
59-60
61
61
62
62-63
63-70
71-72
72
72-73
73
73-74
75
75-77
77-78
79
79
80
81-82
82-83
84-85
85-87
87
87-88
88
88-90
91
92
Page 4 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
List of Contents
Section
Title
Page
11.4.15
11.4.15.1
11.4.16
11.4.16.1
11.4.17
11.4.17.1
11.4.17.2
11.4.18
11.4.19
11.4.20
11.4.21
11.4.21.1
11.4.21.2
92-93
94
95
96-97
97-98
98-100
100-102
102-103
103-104
104
104
11.4.21.3
11.4.21.4
11.4.21.5
Page 5 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
ACRONYMS
NFPA
QA/QC
WPSS
KAIA
K.S.A.
BMS
PPE
MEP
HSE
SBG
CRS
DCS
DN
NPS
SH
F
DAR
ITP
AFFF
ID
ASME
FDC
AWWA
SS
Meaning
National Fire Protection Association
Quality Assurance/Quality Control
Wet Pipe Sprinkler System
King abdulaziz International Airport
Kingdom of Saudi Arabia
Building Management System
Personal Protective Equipment
Mechanical, Electrical and Plumbing
Health and Safety Engineer
Saudi Binladin Group
CMs Reply to Submittals
Document Submittal
Nominal Diameter
Nominal Pipe Size
Shop Drawing
Fire Protection
Dar al handasah
Inspection and Testing Plan
Aqueous Film Forming Foam
Inside Diameter
American Society of Mechanical Engineer
Fire Department Connection
American Water Works Association
Stainless Steel
Page 6 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Light Hazard: Low quantity of combustibles with low heat release (e.g.,
churches, hospitals, museums)
Extra Hazard 1: High quantity of combustibles with high heat release and
no flammable or combustible liquids (e.g., aircraft hangers, saw mills)
Extra Hazard 2:High quantity of combustibles with high heat release and
flammable and combustible liquids (e.g., plastics processing, flammable
liquids spraying)
Page 7 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
S.N.
1
2
3
4
5
6
7
8
9
10
Building/Zone(421)
Flans Glazing
Zone A-Terminal
Processor
Zone B-West
Domestic Pier
Zone C-East Doestic
Pier
Zone D-Central Pier
Zone E-International
Hub
Zone F-West
International Pier
Zone G-East
International Pier
Zone H-Garden
F155-APM
Maintenance Station
11
12
J600-Crisis
Management Centre
G100-ATC Tower
G200-West Supporting
Tower
13
14
15
G300-Meteorological
Observation Building
16
17
18
19
20
WPSS
FM200
IG-55
DELUGE
FOAM
FIRE
HOSE
CABINET
PreAction
Page 8 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
S.N.
21
22
23
Building/Zone(421)
WPSS
FM200
B360-Saudi Airlines
MCC
H110 Data Center
H120 Data Center
IG-55
DELUGE
FOAM
FIRE
HOSE
CABINET
PreAction
7.0 RESPONSIBILITIES
7.1 The Construction Manager
To ensure that all preparation and application works are carried out
according to the contract specifications, shop drawings and
manufacturer data sheet.
Coordinate all the site activities required for the installation of the
fire fighting system, whether external or internal, according to the
project specification, manufacturer data sheet and approved shop
drawings.
Page 9 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
To ensure that the foreman is fully aware of the work sequence and
related testing before proceeding with installation.
To coordinate with safety officer and to ensure that the works are
carried out in safe practicing method.
Page 10 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 11 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Reference Number
421-422-MTS-F-00772-00
421-422-MTS-F-00624-02
Status
CODE 2
CODE 2
421-422-MTS-F-00266-01
CODE 2
421-422-MTS-F-00267-01
CODE 2
421-422-MTS-F-00539-00
421-422-MTS-F-00552-00
421-MTS-M-00107-01
CODE 2
CODE 2
CODE 1
421-422-MTS-F-00548-00
CODE 2
421-422-MTS-F-00523-00
CODE 2
421-422-MTS-F-01109-01
CODE 2
421-422-MTS-F-00454-00
CODE 2
421-422-MTS-F-00428-00
421-422-MTS-F-01221-00
421-422-MTS-F-01226-00
CODE 2
CODE 2
CODE 2
421-422-MTS-F-00317-00
421-MTS-M-00049-00
CODE 2
CODE 2
421-422-MTS-F-01421-00
CODE 2
421-422-MTS-F-00609-00
421-422-MTS-M-00186-01
421-MTS-F-01371-00
421-422-MTS-M-249-00
421-422-MTS-F-00575-00
CODE 2
CODE 2
CODE 2
CODE 2
CODE 2
421-422-MTS-F-00522-00
CODE 2
Page 12 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
S.N.
Submittal Description
24.0 Pressure Reducing Valves Fire
Fighting Application
25.0 Sprinklers
26.0 Pressure Gauge for Use in Fire
Fighting System
27.0 Sprinklers
28.0 Sprinklers
29.0 Sprinklers
30.0 Zone Control - Valves
31.0 Foam-Water System for B120 Radio
Sire All VHF/UHF Station Buildings
32.0 Fire Hose Reel Cabinets
33.0 IG-55 Fire Suppression System
Reference Number
Status
421-422-MTS-F-00514-00
421-MTS-F-00437-01
CODE 2
CODE 2
421-422-MTS-F-00391-00
421-422-MTS-F-00457-01
421-422-MTS-F-00549-00
421-422-MTS-F-00478-00
421-422-MTS-F-00487-00
CODE 2
CODE 2
CODE 2
CODE 2
CODE 2
421-MTS-F-00460-04
421-422-MTS-F-00744-01
421-MTS-F-01400-00
CODE 2
CODE 3
CODE 3
Page 13 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
10.0
Page 14 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
10.1
Environmental Requirements:
The building should ideally been closed and weather-tight.
Page 15 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.0
GENERAL PROCEDURES
11.1
Deliver pipes and tubes with factory end cap. Maintain the end
cap thru shipping, storage and handling to prevent damage to the
pipe end to prevent deposit of dirt, debris and moisture inside it.
Check Portable fire extinguisher for any damage in the body, the
availability of the hose and proper pressure by looking at the
sight glass.
Keep the extinguisher in the original pack and store it in a dry and
shaded location.
Page 16 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.2
Leve Bar
Pipe Stand use to level the pipe during threading & grooving.
Hack and Saw use to cut full threaded rod prior to install pipe
support.
Chalk Line
Page 17 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
End Caps use to plug all end pipes opening prior for leak
testing.
11.3
Page 18 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 19 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
and
1. Make sure the proper roll set is installed on the tool for
the pipe size and material to be grooved. Rolls are
marked with the pipe size, part number and the color
coded according to the pipe material.
2. Loosen the wing nuts and move the adjustable guards
to the full up position. Tighten the wing nuts.
Page 20 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 21 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 22 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
10. Remove the guard setting pad. Store the pad on the
hook provided under the hydraulic hand pump
support.
Page 23 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
and
Page 24 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
4.
5.
Page 25 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
6.
Connect
electrical
source.
the
tool
to
an
internally-grounded
7.
8.
Page 26 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
9.
Page 27 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 28 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 29 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 30 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
15. Reverse the ratchet mechanism and turn the die head in
the opposite direction. Be care full to maintain control of
the threader as the dies are removed. Threads can be
damaged when the die head is being removed if you
dont maintain control and move the piece smoothly.
16. Stand the pipe on end and gently tap it to remove
any particles that may be lodges within.
17. Clean the pipe with cloth, removing any oil. Be careful,
the threads will be very sharp.
18. Seal the threading with a pipe thread compound when
attaching the pipe to the connector.
19. Clean the pipe threader machine thoroughly after use so
the oils and metal pieces do not damage the machine,
which could cause sub-standard threading during your
next project.
11.4
Installation Procedure
11.4.1 Sleeves
o Size of Sleeves against pipe diameter shall be installed as
per the approved shop drawing.
o Establish the exact location and/or elevation of the pipes to
be provided with pipe sleeve, referring on the approved shop
drawings.
o Install following pipe sleeves as per its application: passing
through penetration in floors, partition, roofs and walls.
Page 31 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Area of Application
Fire Protection
Piping Sleeves.
Material
Specification
Pipe Size
Galvanized Steel
Pipe Sleeve
As per approved
materials
Concrete slabs
above grade
Galvanized Steel
Pipe Sleeve
As per approved
materials
Interior partitions
Galvanized Steel
Pipe Sleeve
As per approved
materials
Page 32 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 33 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 34 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 35 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 36 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 37 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
o Visually inspect the bolt pads at each joint to ensure metalto-metal contact is achieved.
o Negative bolt pad offsets can occur when the nuts are not
tightened evenly, which produces over-tightening of one side
and under-tightening of the other side. In addition, negative
offsets can occur if both nuts are under-tightened.
Page 38 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 39 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
3a. Make sure the locating collar engages the outer hole
properly. Check this engagement by rocking the upper
outlet housing in the hole.
Page 40 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
4.
5.
Page 41 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 42 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 43 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.10
Page 44 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 45 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Valve Schedule for each piping system on 8-1/2-by11-inch (A4) bond paper. Tabulate valve number,
piping system, system abbreviation (as shown on
valve tag), location of valve (room or space),
normal-operating position (open, closed, or
modulating), and variations for identification. Mark
valves for emergency shutoff and similar special
uses.
Page 46 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.11
Page 47 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 48 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
2.
3.
Page 49 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 50 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 51 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 52 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 53 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 54 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
S.N.
100
38
135-170
57-77
Temperature
Classification
Ordinary
150
66
175-225
79-107
Intermediate
Color
Code
Uncolored/
Black
White
3
4
5
6
7
225
300
375
475
625
107
149
191
246
329
250-300
325-375
400-475
500-575
650
121-149
163-191
204-246
260-302
343
High
Extra High
Very High
Ultra High
Ultra High
Blue
Red
Green
Orange
Orange
Glass
Bulb
Orange /
Red
Yellow /
Green
Blue
Purple
Black
Black
Black
Page 55 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.12
Page 56 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Agent
Fire
Page 57 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
4. Select the hanger based on size of the pipe and install the
hanger rod to the drop in anchor.
5. Check the pipe length as per the approved shop drawing and
cut it by using speed metal cutting machine ensuring it
perpendicular to the pipe.
6. Place the pipe to the threading machine and thread it
accordingly.
7. Make sure that the thread of the pipe is in good condition.
8. Remove the oil from the pipe end after the threading wrap with
abaca fiber with joint compound.
9. Install the pipe to the threaded fittings.
10. After the completing the pipe installation, clean out the
internal surface of pipe work by purging air.
11.4.12.2 Maximum Horizontal Spacing of FM200 System
Pipe
Distance
Rod
Size
Between
Diameter
(in.)
Support
(in.)
NOTE:
s (feet)
3/8
3/8
3/8
3/8
3/8
3/8
3/8
Page 58 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
10
3/8
11
1/2
12
1/2
Pipe S ize Change W hen the change in pipe s ize is done at a tee, this is accom plished by
using either a reducing tee or a standard tee and reduc ing f ittings. All
at a Tee
reducers m ust be concentric bell reducers or concentric reducing
couplings.
Pipe S ize Change W hen the change in pipe s ize is done at an elbow, this is accomplished b y
using either reducing elbows or a standard elbo w with concentric bell
at an Elbow
reducers or concentric reducing couplings
Pipe S ize Change W hen the change in pipe s ize accomplished at a coupling, only concentric
bell reducers or concentric reducing c ouplings can be used.
at a Coupling
Page 59 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
lbs. ( kg. )
12
70.263
(8)
35
(15)
60
(27)
70.264
215
(88)
375
(153)
650
(267)
1000
(423)
70.268
70.269
70.27
Fill Range
in. (mm)
lbs. (kg)
in. (mm)
in. (mm)
21
21
22.375
(568.3)
32.5
(825.5)
(5.5)
22
(9.5)
38
(25)
1
(9.5)
31
(10)
(17)
(25)
(14.5)
(178)
39
68
52
10.75
28
(18)
(30.5)
(25)
(23.6)
(273)
(711.2)
63
108
77
10.75
38.75
(28.5)
87
(49)
150
(25)
3
(34.9)
150
(273)
20
(984.3
) 23.63
(39.5)
124
(68)
216
(80)
3
(68)
155
(508)
20
(600.1)
28.87
(56.5)
217
(98)
378
(80)
3
(70.3)
225
(508)
20
(733.3
) 42.5
(98.5)
378
(171.5
) 660
(80)
3
(102.1
) 385
(508)
24
(1079.5
) 50.625
(171.5
(299)
(80)
(174.6
(610)
598
1045
(271.5
(474)
(80)
)
70.271
Dimension (approximate)
Diameter
Height
(178)
7
70.265
100
70.266
(44)
150/150 70.267
i
Tare
Weight
Fill Range
Valve Size
Minimum Maximum
Fill Increments
Container Super - Pressurization
Container
Storage Temperture
Level
Limitation
Container Rating
550
(249.5
40 to 70 lbs / ft
24
(610)
Mounting
Position
Upright
Upright
Horizont
- al
Horizon
Upright
tal
Horizont
Upright
al ( Valve
Upright /
Up) )
Inverted
Upright
(Upright
Valve
Up)
- )
( Valve
Upright
Up)
- )
(1286)
( Valve
Up)
Upright
70
(1778)
( Valve
Up)
630 to 1121 Kg / m
1.0 lbs
0.5
kg filling with dry
360 psig @ 70:F ( 24.8 bar @ 21:C ) after
nitrogen
32:F (0:C) - Minimum
Dot 4BW500
Page 60 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
FACTOR
MOUNTING
SURFACE
ENVIRONMENTAL
EFFECTS
TEMPERATURE
Factor to be considered.
CONSIDERATON
Container brackets must be mounted securely to solid load-bearing surfaces that will
support the container load.
Some installations may require additional mounting support not supplied by supplier
Container(s) should be located in clean, dry, and relatively vibration-free areas. Avoid
aisle ways and other high traffic areas where physical damage or tampering is more
likely.Container(s) should never be mounted where the container could potentially
be splashed with, or submerg ed in any liquid.Do not locate containers where they
would be subject to physical damage, exposure to corrosive chemicals, or harsh
weather conditions.
Container locations must be between 32oF (0 Deg C) to 130oF (54.4 Deg C)
Temperatures outside of this range may result in the system not supplying the
desired quantity of agent or accide ntal discharge.
RANGE
In general, the larger the container, the more difficult it will be to remove it from the
system for maintenance and service.
SERVICEABILITY
FLOOR SPACE
However, smaller containers that are located in a sub -floor space, under a
computer bank,or above the ceiling over the same computer bank can be difficult
as well.
Consideration should be gi ven to the space available to install the container(s).
Page 61 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 62 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 63 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 64 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 65 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 66 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 67 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 68 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 69 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 70 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 71 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.12.10
Interface
Page 72 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
The design concentration for the gas shall comply with the
requirements of NFPA 2001 and will have to be approved by
the Consultant. The discharge duration of the gas shall be
within 60 seconds and pipes have been sized accordingly.
Page 73 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 74 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 75 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 76 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Procedure:
Page 77 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 78 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 79 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 80 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 81 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.13.10
Page 82 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.13.11
Interface
Page 83 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 84 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.14
Description engineered, fixed, automatically actuated, lowexpansion, AFFF fire extinguishing system for flammableliquid fires. System includes diaghragm proportioning tank
and devices as per NFPA 16.
Water for the foam system is drawn from the bladder type
foam tank and extinguishing panel are located within the
generator room.
Page 85 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
All the components use for the system including but not
limited to bladder tank, foam concentrate, pre action valves,
isolation valves, sprinklers, foam proportioner, etc. shall be
UL listed / FM approved and shall be approved by
Consultant.
Install piping and other components level and plumb. Install pipe
and fittings, valves, and discharge devices according to
requirement listed in NFPA 16.
Page 86 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 87 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 88 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 89 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 90 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 91 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 92 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.14.7 Interface
11.4.15
Page 93 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
The size of the deluge valve, its flow rate, the system water
supply pressure and type of detection system are all
determined by the size and type of fire risk involved.
Page 94 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.15.1 Interface
Interfacing with other services is required for Fire
Protection Systems in order to make the system
effective.
Interfacing can be achieved by connecting any dry cont
act (potential free) outputs from the system to the
service where we have to get the system interfaced.
Elevators should be captured to ground floor or any
other safe floor in case of fire.
Double-knock system shall be with:
o Sensing of heat (bulb fuses) by the sprinkler.
o Detection of Smoke / fire through fire alarm
system (FAS) detectors.
Page 95 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.16
Page 96 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.16.1 Interface
Deluge system are used for fast, total application
of water in Extra-Hazardous areas and in waterspray systems. Deluge valves are essentially
check valves with a clapper latched in the closed
position (see picture below). The actuating
system unlatches the valve, allowing the water to
enter the piping system and flow out the heads.
Page 97 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.17
Page 98 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Page 99 of 104
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Installation:
1. Install double door fire hose cabinets in
locations and at mounting heights indicated
as per approved shop drawing.
2. Fasten cabinets to structure, square and
plumb.
3. Provide inside latch and lock for break-glass
panels.
4. Fasten mounting brackets to inside surface
of fire hose cabinet square and plumb.
5. Install hose rack assembly at the upper
compartment. Include hose valve, hose rack,
water-retention device, hose pins and hose.
Operation semiautomatic. Hose with swivel
inlet, coupling, gaskets and nozzle.
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
Installation:
1. Install double door fire hose cabinets in
locations and at mounting heights indicated
as per approved shop drawing.
2. Fasten cabinets to structure, square and
plumb.
3. Provide recessed fire hose cabinet.
4. Provide inside latch and lock for break-glass
panels.
5. Fasten mounting brackets to inside surface
of fire hose cabinet square and plumb.
6. Install hose rack assembly at the upper
compartment. Include hose valve, hose rack,
water-retention device, hose pins and hose.
Operation semiautomatic. Hose with swivel
inlet, coupling, gaskets and nozzle.
7. Hose NPS 1-1/2 (DN40). Length 100 feet
(30 meter). Jacket is made high tenacity
polyster yarn. Lining material is Poly
Urethane. Cover made of synthetic material.
8. Nozzle: spray nozzle. Made of chromeplated brass. Adjustable from shutoff to fog
spray or straight stream.
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.19
THE ENGINEER:
THE CONTRACTOR:
Jeddah, KSA
Contractor: Saudi Binladin Group
Contract No.: J-10-421/422-PF-0
Method Statement For Fire Protection Installation & Testing (Packaged 421)
11.4.20
References:
Manufacturers Recommendation.
Materials Submittals.
11.4.21
Attachment