Sewerage
Sewerage
Sewerage
Year II:
Semester Two:
DAR ES SALAAM
ii
ACKNOWLEDGEMENT
Special thanks are firstly due to our project supervisor Dr. Kasseva in
collaboration with Mr. Zakayo for their through guidance supervision during our
project preparation.
Secondly we do thank Kijitonyama Ward Executive Officer (WEO) and DAWASA
officers who contributed much in compilation of this project.
Lastly we would like to thank our fellow students for their strong operation which
simplified our task.
ABSTRACT
The project deals with the identification of problems associated with sewerage
and drainage systems at Kijitonyama (Mpakani A and B). The project also covers
proposed solution of the problems identified, which include modification of the
existing systems and the cost estimation of the project. The total cost of the
project is estimated to T.shs.66,346,266/=
ii
TABLE OF CONTENTS
ACKNOWLEDGEMENT.......................................................................................i
ABSTRACT..........................................................................................................ii
TABLE OF CONTENTS......................................................................................iii
CHAPTER ONE......................................................................................................1
1.0 INTRODUCTION..............................................................................................1
1.1 OBJECTIVE..................................................................................................1
1.2 SCOPE..........................................................................................................1
1.3 METHODOLOGY..........................................................................................2
CHAPTER TWO.....................................................................................................3
2.0
LITERATURE REVIEW...............................................................................3
2.1
2.1.1
2.1.2
2.1.3
Ventilation of sewer...........................................................................5
2.1.4
2.1.5
Design slopes....................................................................................6
2.1
2.2.1
PIPE LAYING........................................................................................7
2.2.3
MANHOLES..........................................................................................8
2.2.4
2.2.5
2.3
2.3.1
STORM RUNOFF...............................................................................13
2.3.2
CHAPTER THREE...............................................................................................17
3.0
3.1
LOCATION............................................................................................17
3.1.1
CLIMATIC CONDITIONS....................................................................17
3.1.2
POPULATION.....................................................................................17
3.1.3
SOCIAL SERVICES............................................................................19
3.1.4
3.1.5
Accessibility.....................................................................................20
3.4
3.6
3.6.1
Problems Identified.........................................................................23
3.6.2
Proposed solutions.........................................................................26
CHAPTER FOUR.................................................................................................27
4.0
4.2
Basic Considerations..............................................................................27
4.2
Hydraulic design.....................................................................................28
CHAPTER FIVE....................................................................................................30
5.0
5.1
5.2
5.2.1
5.3
DESIGN OF CULVERTS........................................................................33
CHAPTER SIX......................................................................................................36
6.0
COST ESTIMATION..................................................................................36
6.1
6.2
6.3
6.4
6.4.1
iv
CHAPTER SEVEN...............................................................................................41
7.0
7.1
CONCLUSION.......................................................................................41
7.2
RECOMMENDATIONS..........................................................................41
LIST OF TABLES
Table-1 : Available Sizes Ranges Commonly Used Pipe For Gravity Flow
Sewers.........................................................................................................4
Table 2:
CHAPTER ONE
1.0 INTRODUCTION
The major problem associated with sanitary sewage and storm water in many
developing communities is lack of proper drainage and sewerage system, and
this is due to poor planning of residential areas, lack of technical and engineering
construction.
As we know this sanitary sewage and storm water imposes great danger for our
health and environment, so we need to collect, treat and safely dispose.
Therefore lack of these systems for collection, treatment and disposal is a
problem because overflow may occur to the ground surface and cause
contamination of the environment.
Generally proper designing of sewerage and drainage system is required in order
to reduce these problems to extent that will not cause public disaster.
1.1 OBJECTIVE
The general objective of this project is to enable the students to practice the
knowledge obtained from the subject taught in the semester, especially sewerage
and drainage engineering fluid mechanics.
1.2 SCOPE
1.3 METHODOLOGY
Different methods were set to collect various information and data, so that
methods used were
literature review
questionnaire interview
site visit and physical observation of the case study
CHAPTER TWO
2.0
LITERATURE REVIEW
Currently the manning equation is used most commonly for the design of
sanitary sewers. The manning equation is
Where,
1 2 3 12
R S
n
v
velocity, (m/s)
friction factor
hydraulic radius
The recommended n value for the design of new and existing well
-constructed sewers is 0.0013. An n value of 0.015 is recommended for
the analysis of older sewers.
Table-1 : Available Sizes Ranges Commonly Used Pipe For Gravity Flow Sewers
Type of Pipe
Asbestos cement AC
Minimum sewer sizes are usually specified in local building codes. The
smallest sewer used should be larger than the building sewer connection
so that objects passed through the building sewer will not clog the
municipal sewer.
(ii)
(iii)
fts) when the sewer is flowing full or half full. To prevent the deposition of
sand and gravel a velocity of 0.75 m/s (2.5 ft/s) is recommended. To avoid
damaging sewers it is recommended that the maximum flow velocities be
limited to values equal to or less than 3.0m/s (10 fts).
(ii)
(iii)
2.1 SEWER
CONSTRUCTION
AND
MAINTENANCE
Leakage from sewers as the result of the failure or blockage of a pipe can
lead to sewers health hazards and costly repairs. Care is essential
In the handling, bedding and backfilling of pipes and fittings
Jointing to minimize leakage and infiltration
Horizontal and vertical alignment, to minimize the risk of clogging and
2.2.1
PIPE LAYING
Type
Range
of
(mm)
cement 100 - 900
Asbestos
pipe
diameter Remarks
Gravity and pressure
types (autoclave
Clay (Vitrified)
100 - 900
covered)
Glazed and unglazed
gravity type
Circular, elliptical
pipe
Concrete
cast
in -
place
Iron (cast) pipe
Plastic
(solid
100 - 1200
treatment works
wall) For service lines and For service lines and
pipe
2.2.3
laterals
laterals
MANHOLES
The manholes help in joining sewer length, and also help in their
inspection, cleaning and maintenance. If the manhole covers are
perforated, they may also assist in ventilating the sewers.
2.2.4
LOCATION
AND
SPACING
OF
MANHOLES
The manholes are generally provided at every bend junction, change of
gradient, or line between two manholes is laid straight with even gradient.
Even when the sewer line runs straight, the manholes are provided at
regular intervals. The spacing of the manholes depends mainly upon the
size of sewer line. The large is the diameter of sewer, the greater will be
spacing between the manholes. The manhole spacing, generally adopted,
on straight sewer reaches, are given below:-
Diameter up to 0.3m
Diameter up to 0.6m
Diameter up to 0.9m
Diameter up to 1.2m
Diameter up to 1.5m
Diameter greater than 1.5m
Depth
0.8m or less
0.8m and 2.1m
>2.1m
chambers
1.2m x 0.9m
Circular chambers with
thickness up
to
rectangular
(a) 1.5m
depth
chambers
(b) >1.5m
30cm
depth
2.2.5
Access Shaft
The upper portion of a deep manhole is called access shaft,. Its
minimum size for a rectangular manhole is about 0.75 x 0.6m and
for a circular manhole, the minimum diameter is about 0.6 to 0.75m.
Its depth depends upon the depth of the manhole and the height
required for the working diameter.
10
Working Chamber
The lower portion of the manhole is known as the working chamber,
as it provides a working space for inspecting and cleaning
operations. Its minimum size for rectangular manhole is about 1.2m
x 0.9m and for a circular manhole, the minimum diameter is about
1.2m The height of this chamber should generally be not less than
1.8m or so.
(iii)
The Benching
I.e. the bottom or invest portion of manhole
the button portion of the manhole is constructed in cement
concrete.
channel is generally
constructed, and the sides are made to slope towards it, as shown
in section A-A. The concreting is know as benching, and facilitates
the entry of sewage into the main sewer. If the branch as well as
the sewer meets at the same level at the bottom of the manhole,
channels connected with each other will have to be constructed.
Such constructions are made with easy causes.
(iv)
11
Steps or Ladders
Steps are generally provided for descending into the manhole. The
steps are made of cast iron, and are placed staggered at a
horizontal distance of about 20cm and at a vertical centre to centre
distance of about 30cm. If the steps are made of double width,
staggering is not required. The steps should be fully in bedded in
walls.
(vi)
12
slipping of the persons working over it. The top of the cover carriers
an arrow marks that shows the direction of sewerage flow.
The weight of the cover and the frame varies between 90 to 270kg.
The lighter cover is adopted to carry lighter traffic, and heavier one
is adopted to carry heavier traffic.
water
drainage
include
street
gutters,
formed
channels,
2.3.1
STORM RUNOFF
13
14
2.3.2
ESTIMATION
OF
QUANTITY
OF
STORWATER
When rain falls over the ground surface, a part of it percolates into ground, a part
if evaporated and the remaining part overflows as storm water or floodwater. The
quality of storm water is determined by using empirical formula. Rational method
is mostly used now days in small area. This method is recommended to a
maximum of 3 square kilometres.
CiA
Where Q
storm water
A
tB
time of concentration
16
CHAPTER THREE
3.0
EXISTING SITUATION OF
THE STUDY AREA
3.1 LOCATION
Kijitonyama is one of the words in Kinondoni District , which is one among
the three Municipality of Dar es Salaam City.
To the north, it is bordered by Mikocheni ward, to the East it is bordered by
Mwananyamala ward. To the South there is Sinza and Mwenge is on the
western side. The place has no any industries.
3.1.1
CLIMATIC CONDITIONS
17
3.1.2
POPULATION
18
3.1.3
Males
3,312
2,872
2,733
2,383
11,200
Females
3502
3207
2889
2608
12206
Total
6714
5940
5761
4991
23,406
Percentage
28.7%
25.4%
24.6%
21.3%
100%
SOCIAL SERVICES
3.1.4
In our study area there is a total of 1903 residential plots in which some
of them include shops (as commercial buildings). The majority of residents
in our study area are employed 70% while the rest 30% are not. The
income distribution for the households in the study area is as shown in the
table below.
19
% of householders
10%
13%
41%
36/=
100/=
3.1.5 Accessibility
Since the area is well planned, access roads are available making the
area readily accessible from the old Bagamoyo road and other minor
roads present in the area.
20
Pipe Layout
The network of water supply pipes in the area is of looped. Network type.
This is facilitated by the fact that the area is well planned allowing for
proper pipe network to be laid.
3.3.1
Percentage
70%
25%
5%
100%
21
22
23
24
The solid wastes in the study area are not properly managed. Crude
dumping is practiced leading to clusters of solid wastes at various places
not specifically designated for solid waste disposal.
(ii)
(iii)
(iv)
(v)
25
CHAPTER FOUR
4.0
DESIGN OF SEWERAGE
SYSTEM
26
120
Where,
Po
Present population
growth rate
4 .3
P 23406 1
100
future population
192106
Peak factor =
Where P
5
p
0.008m/m.
-Invert level
Lower invert level =
x
elevation
lower
sewer
Chamber depth
Upper and =
Chamber depth
Upper and =
Chamber depth
28
CHAPTER FIVE
5.0
The aim of storm water drainage system is to collect surface runoff and
discharge it in a sanitary manner, which cannot lead to health as well as
environmental hazards. In urban areas, this is particularly important since
most areas are paved leading to accumulation of storm water due to
reduced ground infiltration.
Rainfall intensity
The amount of storm water in an area depends upon the rainfall
intensity, the higher the amount of rainfall the larger the amount of
storm water discharge. This in turn affects the size of drainage
channel required for a given area.
(b)
(c)
Catchments area
The storm drainage system required will depend on the area
served. Larger area will require large drainages system where as
smaller area will need a smaller drainage system.
(e)
Ground obstruction
Obstruction to the ground prevent water from reacting the ground
so that ground infiltration will be low leading to accumulation of
storm drainage.
(f)
Atmospheric condition
The rate of storm water production can also be affected by
atmospheric conditions. Areas with higher temperature will have
higher evaporation rates and therefore considerably reduce the
amount of storm discharge.
30
to estimate the ground slope and therefore design the channel, which can
allow gravity flow of storm water.
The Mannings formula was used to determine the size and velocity of flow
for each estimated discharge.
From Q
But
AV
Wetted perimeter
1 2 3 12
R S
n
Where
A
P
CiA
where;
31
(2)
where
N
ti
Te
The empirical formula (3) above varies depending on the allocation the
return period used and the rainfall duration used in designing. In our case
we used
76.2
for smaller channesl and
tc 10
101.6
te 20
32
Ax(2gh)
Cd
Where Q
Cd
entrance)
D
2
1.25
D
2
0.75D
Cd
33
2 gh
D 2
4
Cd
but
Cd= 0.62
D 2
4
0.62
2 g .0.75 D
2 g .0.75 D
4Q
x0.62 x 14.715
D (Qx .53535)
1
.
87
or D
A
P
D 2
4 x 0.81 D
1 2 3 12
R S
n
(1)
34
CHAPTER SIX
6.0
6.1
COST ESTIMATION.
TRENCHES
Excavation cost estimation is based on the actual volume of soil from one
manhole to another for each like.
The following formula is used for volume of earth, V,
V
(h1+h2)LW
h1
h2
Width
Where,
Table 5 : shows calculations involved in cost estimation and the total cost.
35
Unit
(T.shs)
5,500.00
6,500.00
7,500.00
8,500.00
9,500.00
10,000.00
11,000.00
11,500.00
12,000.00
15,702,500
767,000
4,500,000
977,500
570,000
800,000
2,585,000
1,725,000
480,000
100 x 1000mm
500/=
250,000/=
10,000/=
260500/=
36
DEPTH
<1m
1<h<1.5m
>1.5m
UNIT COST
T.SHS.
260,000
350,000
450,000
TOTAL
COST
3,126,000
1,190,000
450,000
19,526,000
Cost estimation for this type of channel is based on the following formula
Cross sectional area of the channel, A is
A
1 d (b+b+nd+nd)
2
1 d (2b+2nd)
2
d(b+nd)
d=
depth of channel
Where,
B=
A=d(b+d)
Where n=1 for =45
But the volume of earth to be excavated is give by
37
38
RATES M3 TOTAL
(T.SHS)
AMOUNT
1000
1000
1000
1000
625800
81180
1009220
1494000
Unit Cost
Total
Cost
10000
10000
10000
10000
Total
322,700
1,272,800
2,418,800
1,505,950
55202250
CHAPTER SEVEN
7.0
CONCLUSION AND
RECOMMENDATIONS
7.1 CONCLUSION
The proper sewerage system and storm water drainage system is an
important parameter for hygienic environment and is one of the basic need
for improving human health.
The provision of the system ensures a reliable hygienic Environment to
the Area to which the system have been designed.
Kijitonyama Mpakani A and B has been facing some problems of floods
during rain seasons and streets and roads are let open draining to the
streets during this period by some people to avoid the desludging costs.
7.2 RECOMMENDATIONS
In order that the designed system function at efficient level the following
are our recommendations.
To minimize the problem of people throwing solid wastes into the open
channels, people should be made aware the blockage which would result into
difficult of the system.
For long run operation and maintenance organization should be
encouraged in the neighbourhood in order to provide some funds, equipment
39
40