Construction Fundamentals Study Guide

Download as pdf or txt
Download as pdf or txt
You are on page 1of 68

Level 1 Construction Fundamentals Study Guide

CONSTRUCTION MATERIALS, METHODS AND PLAN READING


CSI MasterFormat Document Organization
In the early 1960s the need for a uniform system for organizing specifications was identified and
resulted in the publishing of the CSI MasterFormat, named after its author, the Construction
Specifications Institute (CSI). The CSI MasterFormat introduced the seventeen division format
associated with the ability to organize an infinite number of subject sections. In 1978,
Construction Specifications Canada (CSC) joined with CSI to produce the first edition of
MasterFormat.
The MasterFormat incorporates a complete organizational format for project manuals by
including bidding requirements, contract forms, conditions of the contract and the General
Requirements, in addition to the Technical Specifications Divisions 02 through 16. This
document has been the construction industrys consensus standard for the organization of
technical information. It is accepted by the U.S. federal agencies and most state and local
governments. It was subsequently adopted by the McGraw-Hill Sweets Catalogs, the R.S. Means
cost estimating books, and other organizations.
MasterFormat is intended to classify detailed construction information into a standard order or
sequence by materials and methods. This is done by establishing a detailed master list of
divisions, sections and parts. The MasterFormat facilitates construction communication,
promotes standardization in the industry, and facilitates the retrieval of information. It is
primarily used for the organization of project manuals, detailed construction cost estimates, and
product data filing.
CSI MasterFormat Structure
The MasterFormat groups information into these areas:
C
C
C
C
C

Bidding Requirements and Forms


Contract Forms (Agreement)
Conditions of the Contract (General and Supplementary)
General Requirements (Division 01)
Technical Specifications Division (02 through 16)

173

Level 1 Construction Fundamentals Study Guide


MasterFormat Numbering System
The MasterFormat number system categorizes the Bidding Requirements and Forms, Contract
Forms and Conditions of the Contract into Division 0 - Bidding Requirements. Second, the
MasterFormat uses a series of numbers associated with the sixteen divisions which address
detailed construction specifications associated with products and systems. Division 1 - General
Requirements outlines the specific administrative and procedural requirements that apply to all of
the Technical Specification sections. Divisions 02 through 16 - Technical Specifications contain a
written description of the specific requirements relating to a specific product or system. The
Construction Specifications Institute (CSI) has developed the following Standard MasterFormat
numbering system consisting of the following Documents and Divisions.
CSI MasterFormat Divisions
DIVISION
DIVISION
DIVISION
DIVISION
DIVISION
DIVISION
DIVISION
DIVISION
DIVISION
DIVISION
DIVISION
DIVISION
DIVISION
DIVISION
DIVISION
DIVISION
DIVISION

00 - BIDDING REQUIREMENTS
01 - GENERAL REQUIREMENTS
02 - SITE WORK
03 - CONCRETE
04 - MASONRY
05 - METALS
06 - WOOD AND PLASTICS
07 - THERMAL AND MOISTURE PROTECTION
08 - DOORS AND WINDOWS
09 - FINISHES
10 - SPECIALTIES
11 - EQUIPMENT
12 - FURNISHINGS
13 - SPECIAL CONSTRUCTION
14 - CONVEYING SYSTEMS
15 - MECHANICAL
16 - ELECTRICAL

CSI Masterformat Sections


The CSI Masterformat breaks down Divisions 02 - 16 into Sections using a three-digit
numbering system. For example, in Division 02 - Sitework the Earthwork is under section
number 200. Therefore, the complete Division and Section number is 02200.

174

Level 1 Construction Fundamentals Study Guide


Masterformat- Broadscope Section Titles
00010
00100
00200
00300
00400
00500
00600
00700
00800
00900

PRE-BID INFORMATION
INSTRUCTIONS TO BIDDERS
INFORMATION AVAILABLE TO BIDDERS
BID FORMS
SUPPLEMENTS TO BID FORMS
AGREEMENT FORMS
BONDS AND CERTIFICATES
GENERAL CONDITIONS
DRAWINGS AND SCHEDULES
ADDENDA AND MODIFICATIONS

DIVISION 4 - MASONRY
04100
04150
04200
04400
04500
04550
04600

Note: Since the items listed above are not specification sections, they are referred to as
"Documents" in lieu of "Divisions or Sections" in the Master List of Section Titles,
Numbers, and Broadscope Explanations.

DIVISION 5 - METALS

DIVISION 1 - GENERAL REQUIREMENTS


01010
01020
01025
01030
01040
01050
01060
01070
01080
01090
01100
01200
01300
01400
01500
01600
01700
01800

05010
05030
05050
05100
05200
05300
05400
05500
05580
05700
05800
05900

SUMMARY OF WORK
ALLOWANCES
MEASUREMENT AND PAYMENT
ALTERNATES/ALTERNATIVES
COORDINATION
FIELD ENGINEERING
REGULATORY REQUIREMENTS
ABBREVIATIONS AND SYMBOLS
IDENTIFICATION SYSTEMS
REFERENCE STANDARDS
SPECIAL PROJECT PROCEDURES
PROJECT MEETINGS
SUBMITTALS
QUALITY CONTROL
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
MATERIALS AND EQUIPMENT
CONTRACT CLOSEOUT
MAINTENANCE

06050
06100
06130
06150
06170
06200
06300
06400
06500
06600

DIVISION 2 - SITEWORK
SUBSURFACE INVESTIGATION
DEMOLITION
SITE PREPARATION
DEWATERING
SHORING AND UNDERPINNING
EXCAVATION AND SUPPORT SYSTEMS
COFFERDAMS
EARTHWORK
TUNNELING
PILES AND CAISSONS
RAILROAD WORK
MARINE WORK
PAVING AND SURFACING
PIPED UTILITY MATERIALS
WATER DISTRIBUTION
FUEL DISTRIBUTION
SEWERAGE AND DRAINAGE
RESTORATION AND UNDERGROUND PIPELINES
PONDS AND RESERVOIRS
POWER AND COMMUNICATIONS
SITE IMPROVEMENTS
LANDSCAPING

FASTENERS AND ADHESIVES


ROUGH CARPENTRY
HEAVY TIMBER CONSTRUCTION
WOOD-METAL SYSTEMS
PREFABRICATED STRUCTURAL WOOD
FINISH CARPENTRY
WOOD TREATMENT
ARCHITECTURAL WOODWORK
PREFABRICATED STRUCTURAL PLASTICS
PLASTICS FABRICATIONS

DIVISION 7 - THERMAL AND MOISTURE PROTECTION


07100
07150
07190
07200
07250
07300
07400
07500
07570
07600
07700
07800
07900

WATERPROOFING
DAMPROOFING
VAPOR AND AIR RETARDERS
INSULATION
FIREPROOFING
SHINGLES AND ROOFING TILES
PREFORMED ROOFING AND CLADDING/ SIDING
MEMBRANE ROOFING
TRAFFIC TOPPING
FLASHING AND SHEET METAL
ROOF SPECIALTIES AND ACCESSORIES
SKYLIGHTS
JOINT SEALERS

DIVISION 8 - DOOR AND WINDOWS


08100
08200
08250
08300
08400
08500
08600
08650
08700
08800
08900

DIVISION 3 - CONCRETE
03100
03200
03250
03300
03370
03400
03500
03600
03700
03800

METAL MATERIALS
METAL FINISHES
METAL FASTENING
STRUCTURAL METAL FRAMING
METAL JOISTS
METAL DECKING
COLD-FORMED METAL FRAMING
METAL FABRICATIONS
SHEET METAL FABRICATIONS
ORNAMENTAL METAL
EXPANSION CONTROL
HYDRAULIC STRUCTURES

DIVISION 6 - WOOD AND PLASTICS

TECHNICAL SPECIFICATIONS
02010
02050
02100
02140
02150
02160
02170
02200
02300
02350
02450
02480
02500
02600
02660
02680
02700
02760
02770
02780
02800
02900

MORTAR
MASONRY ACCESSORIES
UNIT MASONRY
STONE
MASONRY RESTORATION AND CLEANING
REFRACTORIES
CORROSION RESISTANT MASONRY

CONCRETE FORMWORK
CONCRETE REINFORCEMENT
CONCRETE ACCESSORIES
CAST-IN-PLACE CONCRETE
CONCRETE CURING
PRECAST CONCRETE
CEMENTITIOUS DECKS
GROUT
CONCRETE RESTORATION AND CLEANING
MASS CONCRETE

175

METAL DOORS AND FRAMES


WOOD AND PLASTIC DOORS
DOOR OPENING ASSEMBLIES
SPECIAL DOORS
ENTRANCES AND STOREFRONTS
METAL WINDOWS
WOOD AND PLASTIC WINDOWS
SPECIAL WINDOWS
HARDWARE
GLAZING
GLAZED CURTAIN WALLS

Level 1 Construction Fundamentals Study Guide


DIVISION 9 - FINISHES
09100
09200
09230
09250
09300
09400
09500
09540
09550
09600
09630
09650
09680
09700
09780
09800
09900
09950

11700 MEDICAL EQUIPMENT


11780 MORTUARY EQUIPMENT

METAL SUPPORT SYSTEMS


LATH AND PLASTER
AGGREGATE COATINGS
GYPSUM BOARD
TILE
TERRAZZO
ACOUSTICAL TREATMENT
SPECIAL SURFACES
WOOD FLOORING
STONE FLOORING
UNIT MASONRY FLOORING
RESILIENT FLOORING
CARPET
SPECIAL FLOORING
FLOOR TREATMENT
SPECIAL COATINGS
PAINTING
WALL COVERING

11850 NAVIGATION EQUIPMENT


DIVISION 12 - FURNISHINGS
12050 FABRICS
12100 ARTWORK
12300 MANUFACTURED CASEWORK
12500 WINDOW TREATMENT
12600 FURNITURE AND ACCESSORIES
12670 RUGS AND MATS
12700 MULTIPLE SEATING
12800 INTERIOR PLANTS AND PLANTERS
DIVISION 13 - SPECIAL CONSTRUCTION
13010 AIR SUPPORTED STRUCTURES
13020 INTEGRATED ASSEMBLIES
13030 SPECIAL PURPOSE ROOMS
13080 SOUND, VIBRATION, AND SEISMIC CONTROL
13090 RADIATION PROTECTION
13100 NUCLEAR REACTORS
13120 PRE-ENGINEERED STRUCTURES
13150 POOLS
13160 ICE RINKS
13170 KENNELS AND ANIMAL SHELTERS
13180 SITE CONSTRUCTED INCINERATORS
13200 LIQUID AND GAS STORAGE TANKS
13220 FILTER UNDERDRAINS AND MEDIA
13230 DIGESTION TANK COVERS AND APPURTENANCES
13240 OXYGENATION SYSTEMS
13260 SLUDGE CONDITIONING SYSTEMS
13300 UTILITY CONTROL SYSTEMS
13400 INDUSTRIAL AND PROCESS CONTROL SYSTEMS
13500 RECORDING INSTRUMENTATION
13550 TRANSPORTATION CONTROL INSTRUMENTATION
13600 SOLAR ENERGY SYSTEMS
13700 WIND ENERGY SYSTEMS
13800 BUILDING AUTOMATION SYSTEMS
13900 FIRE SUPPRESSION AND SUPERVISORY SYSTEMS

DIVISION 10 - SPECIALTIES
10100 CHALKBOARDS AND TACKBOARDS
10150 COMPARTMENTS AND CUBICLES
10200 LOUVERS AND VENTS
10240 GRILLES AND SCREENS
10250 SERVICE WALL SYSTEMS
10260 WALL AND CORNER GUARDS
10270 ACCESS FLOORING
10280 SPECIALTY MODULES
10290 PEST CONTROL
10300 FIREPLACES AND STOVES
10340 PREFABRICATED EXTERIOR SPECIALTIES
10350 FLAGPOLES
10400 IDENTIFYING DEVICES
10450 PEDESTRIAN CONTROL DEVICES
10500 LOCKERS
10520 FIRE PROTECTION SPECIALTIES
10530 PROTECTIVE COVERS
10550 POSTAL SPECIALTIES
10690 PARTITIONS
10650 OPERABLE PARTITIONS
10670 STORAGE SHELVING
10700 EXTERIOR SUN CONTROL DEVICES
10750 TELEPHONE SPECIALTIES
10800 TOILET AND BATH ACCESSORIES
10880 SCALES
10900 WARDROBE AND CLOSET SPECIALTIES

DIVISION 14 - CONVEYING SYSTEMS


14100 DUMBWAITERS
14200 ELEVATORS
14300 MOVING STAIRS AND WALKS
14400 LIFTS
14500 MATERIAL HANDLING SYSTEMS
14600 HOISTS AND CRANES
14700 TURNTABLES
14800 SCAFFOLDING
14900 TRANSPORTATION SYSTEMS

DIVISION 11 - EQUIPMENT
11010 MAINTENANCE EQUIPMENT
11020 SECURITY AND VAULT EQUIPMENT
11030 TELLER AND SERVICE EQUIPMENT
11040 ECCLESIASTICAL EQUIPMENT
11050 LIBRARY EQUIPMENT
11060 THEATER AND STAGE EQUIPMENT
11070 INSTRUMENTAL EQUIPMENT
11080 REGISTRATION EQUIPMENT
11090 CHECKROOM EQUIPMENT
11100 MERCANTILE EQUIPMENT
11110 COMMERCIAL LAUNDRY AND DRY CLEANING EQUIPMENT
11120 VENDING EQUIPMENT
11130 AUDIO-VISUAL EQUIPMENT
11140 SERVICE STATION EQUIPMENT
11150 PARKING CONTROL EQUIPMENT
11160 LOADING DOCK EQUIPMENT
11170 SOLID WASTE HANDLING EQUIPMENT
11190 DETENTION EQUIPMENT
11200 WATER SUPPLY AND TREATMENT EQUIPMENT
11280 HYDRAULIC GATES AND VALVES
11300 FLUID WASTE TREATMENT AND DISPOSAL EQUIPMENT
11400 FOOD SERVICE EQUIPMENT
11450 RESIDENTIAL EQUIPMENT
11460 UNIT KITCHENS
11470 DARKROOM EQUIPMENT
11480 ATHLETIC, RECREATIONAL AND THERAPEUTIC EQUIPMENT
11500 INDUSTRIAL AND PROCESS EQUIPMENT
11600 LABORATORY EQUIPMENT
11650 PLANETARIUM EQUIPMENT
11660 OBSERVATORY EQUIPMENT

DIVISION 15 - MECHANICAL
15050 BASIC MECHANICAL MATERIALS AND METHODS
15250 MECHANICAL INSULATION
15300 FIRE PROTECTION
15400 PLUMBING
15500 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
15550 HEAT GENERATION
15650 REFRIGERATION
15750 HEAT TRANSFER
15850 AIR HANDLING
15880 AIR DISTRIBUTION
15950 CONTROLS
15990 TESTING, ADJUSTING, AND BALANCING
DIVISION 16 - ELECTRICAL
16050 BASIC ELECTRICAL MATERIALS AND METHODS
16200 POWER GENERATION
16300 HIGH VOLTAGE DISTRIBUTION (ABOVE 600-VOLT)
16400 SERVICE AND DISTRIBUTION (600-VOLT AND BELOW)
16500 LIGHTING
16600 SPECIAL SYSTEMS
16700 COMMUNICATIONS
16850 ELECTRIC RESISTANCE HEATING
16900 CONTROLS
16950 TESTING

176

Level 1 Construction Fundamentals Study Guide


CSI MaterFormat Parts
Each technical Specification Section within a Division is further broken down into Parts. Part 1
is titled General. Part 2 is titled Products, and Part 3 is titled Execution. Part 1 contains these
titles: Work Included, References, Quality Assurance, Submittals, Storage, and Environmental
Requirements. Part 2 contains these titles: Acceptable Manufacturers, Types of Materials and
Product Standards. Part 3 contains these titles: Preparation, Installation, Tolerances, Cleaning
and Protection of the finished work. The discussion and example below will primarily focus on
Part 1 titled General and the subsection titled Reference standards because it utilizes the law
principle called Incorporated by Reference.
Part 1 generally contains a list of additional reference standards with complete designations and
titles. It also identifies specific requirements for the submittal of shop drawings and product data
sheets for each section. Reference standards are documents that are not physically attached with
the Documents, but are referenced to in the documents may be part of the contract. The most
common clause used to incorporate an item by reference is to state in the documents that the
Reference Standards are "herewith made a part of the Specifications." This normally requires the
Contractor to have these available at the job site. The specific Reference Standards that the
Contractor must refer to are stated at the beginning of each Section of the Technical
Specifications under Part 1. For example, Division 3 is Concrete and Section 200 is Concrete
Reinforcement, PART 1.03 is Reference Standards and the A - J refers to the specific reference
Standards required. Numerous CSI Division numbers, Section numbers with Part 1 Reference
Standards and their abbreviations are shown below.
03100 Concrete Formwork
PART 1
GENERAL
1.03
Reference Standards
B.
ACI SP-4 Formwork for Concrete
American Concrete Institute. Special Publication -4.
03200 Concrete Reinforcement
1.03
Reference Standards
I.
CRSI 65 Recommended Practice for Placing Bar Supports, Specifications
and Nomenclature. Concrete Reinforcing Steel Institute.
03300 Cast-in-Place Concrete
1.03
Reference Standards
N.
ASTM C-94 Specifications for Ready-mixed concrete.
American Society for Testing Materials
02200 Excavation
1.06
Reference Standards
AASHTO - MI47-65 - Materials for Aggregate and Soil - Aggregate.
Am. Association of State Highway/Transportation Officials.
177

Level 1 Construction Fundamentals Study Guide


05120 Structural Steel
1.03
Reference Standards
AISC - Specification for the Design, Fabrication and Erection
American Institute of Steel Construction
AWS - D1.1 - Structural Welding Code
American Welding Society
SJI - Standard Specifications for Open Web Steel Joists
Steel Joist Institute
09250 Gypsum Board Systems
1.04
Reference Standards
ANSI/ASTM C36 - Gypsum Wallboard.
American National Standards Institute.
American Society for Testing Materials.
15050 Basic Mechanical Materials and Methods
1.06
Reference Standards
ASME B16 - Boiler and Pressure Vessel Code
American Society of Mechanical Engineers
ASHRAE 15 - Safety Code for Mechanical Refrigeration
American Society for Heating, Refrigerating, and Air
Conditioning Engineers.
AWWA C601 - Standard Methods for the Examination of Water & Waste
American Water Works Association
UL 378 - Standard for Draft Equipment.
Underwriter Laboratories, Inc.
AMCA 99 - Standards Handbook.
Air Movement and Controls Association
15300 Fire Protection Piping
1.03
Quality Assurance
NFPA 13 - Sprinkler Systems
National Fire Protection Association.
15880 - Air Distribution
1.03
Reference Standards
SMACNA Symbols for Ventilation and Air Conditioning.
Sheet Metal and Air Conditioning Contractors National
Association.
16700 - Communications
1.03
Reference Standards
NEC - National Electrical Code
TIA - Telecommunication Industry Association.
178

Level 1 Construction Fundamentals Study Guide


CSI Master Format Exercise
1.

What CSI Division contains technical information on Soil Compaction requirements?


A.
B.
C.
D.

2.

What CSI Division contains technical information on Structural Steel?


A.
B.
C.
D.

3.

06
09
10
14

What CSI Division contains technical information on Plumbing?


A.
B.
C.
D.

5.

01
03
05
15

What CSI Division contains technical information on Drywall?


A.
B.
C.
D.

4.

01
02
04
16

03
05
11
15

What CSI Division contains technical information on the Air Handling system?
A.
B.
C.
D.

11
13
14
15

179

Level 1 Construction Fundamentals Study Guide


CSI Master Format Exercise
6.

What CSI Division contains technical information on the Conveyor System?


A.
B.
C.
D.

7.

What CSI Division contains technical information on the Boiler System?


A.
B.
C.
D.

8.

02
06
09
16

What CSI Division contains technical information on Roofing?


A.
B.
C.
D.

10.

11
13
14
15

What CSI Division contains technical information on Painting?


A.
B.
C.
D.

9.

11
13
14
15

04
06
07
10

What CSI Division contains technical information on Food Service Equipment?


A.
B.
C.
D.

10
11
13
15

180

Level 1 Construction Fundamentals Study Guide


CSI Master Format Exercise
11.

According to CSI, What Division (s) are considered the Technical Specifications?
A.
B.
C.
D.

12.

What CSI Division applies to all contractors and subcontractors?


A.
B.
C.
D.

13.

00
01
04
16

What is the name of the legal principle for referring the contractor to other documents
that are not contained in the documents provided?
A.
B.
C.
D.

15.

01
02
09
15

What CSI Division contains the Bid Requirements for a project?


A.
B.
C.
D.

14.

00 - 01.
01
01 - 16.
02 - 16.

Reference Standards.
Incorporated by Reference.
Standard General Conditions
General Conditions of the Contract.

What is the official name of the technical reference source that is mentioned in the
documents to Design the Formwork and it is published by ACI?
A.
B.
C.
D.

Formwork Handbook.
Formwork for Concrete.
Formwork Design Manual.
Concrete Formwork Design Manual.

181

Level 1 Construction Fundamentals Study Guide


CSI Master Format Exercise
16.

What is the official name of the technical reference source that is mentioned in the
documents to Place the Slab Bolsters and it is published by CRSI?
A.
B.
C.
D.

17.

Your specifications reference this construction organization Acronym of ACI that


publishes numerous Technical Reference Sources. What is the correct name of ACI?
A.
B.
C.
D.

18.

Cost System Information.


Construction Standards Institute.
Construction Standards Information.
Construction Specifications Institute.

Your specifications reference this construction organization Acronym of CRSI that


publishes numerous Technical Reference Sources. What is the correct name of CRSI?
A.
B.
C.
D.

20.

American Concrete Institute.


Associated Contractors Institute.
American Construction Institute.
Associated Constructors Institute.

Your specifications reference this construction organization Acronym of CSI that


publishes numerous Technical Reference Sources. What is the correct name of CSI?
A.
B.
C.
D.

19.

Steel Riggers Handbook.


Steel Reinforcement Guide.
Recommended Practice for Placing Bar Supports, Specifications & Nomenclature.
Manual of Steel Erection Practices.

Concrete Reinforcing Steel Institute.


Crane and Riggers Specification Institute.
Concrete Reinforcement Standards Institute
Concrete Reinforcement Specifications Institute.

Your specifications reference this construction organization Acronym of AISC that


publishes numerous Technical Reference Sources. What is the correct name of AISC?
A.
B.
C.
D.

American Institute of Steel Contractors.


American Institute of Steel Constructors.
American Institute of Steel Construction.
American Institute of Structural Concrete.
182

Level 1 Construction Fundamentals Study Guide


CSI Master Format Exercise
21.

Which CSI part number contains information on Reference Standards the contractor or
subcontractor must consult?
A.
B.
C.
D.

22.

Which CSI part number contains information on the installation procedures the contractor
or subcontractors must consult?
A.
B.
C.
D.

23.

02660
02700
15300
15400

Which Division and Section number contains technical information on the exterior
sewerage and drainage system?
A.
B.
C.
D.

25.

1
2
3
4

Which Division and Section number contains technical information on the interior
plumbing?
A.
B.
C.
D.

24.

1
2
3
4

02660
02700
15300
15400

Which Division and Section number contains technical information on the interior
Electrical Service and Distribution system?
A.
B.
C.
D.

02600
02780
15950
16400
183

Level 1 Construction Fundamentals Study Guide


CSI Master Format Exercise
26.

Which Division and Section number contains technical information on the


communications systems?
A.
B.
C.
D.

27.

Your specifications reference this construction organization Acronym of ASHRAE that


publishes numerous Technical Reference Sources. What is the correct name of
ASHRAE?
A.
B.
C.
D.

28.

American Steel Housing Rating Association of Engineers.


Associated Structural Hoists Rating Association of Engineers.
American Society for Heating, Refrigerating and Air Conditioning Engineers.
Associated Society for Heating, Refrigerating and Air Conditioning Engineers.

Your specifications reference this construction organization Acronym of TIA that


publishes numerous Technical Reference Sources. What is the correct name of TIA?
A.
B.
C.
D.

29.

02780
15950
16500
16700

Trade Industry Association.


Testing Industry Association.
Transportation Industry of America.
Telecommunication Industry Association.

Your specifications reference this construction organization Acronym of UL that


publishes numerous Technical Reference Sources. What is the correct name of UL?
A.
B.
C.
D.

Union Laboratories.
United Laboratories.
Utility Laboratories.
Underwriter Laboratories.

Check Answers

184

Level 1 Construction Fundamentals Study Guide


Construction Methods. Materials and Equipment
The contractor is responsible for the temporary shoring system selected and the design of the
shoring system. These are not shown on the plans or described in any detail within the
construction documents. The estimator is responsible for determining the number, size and cost
for all temporary structures. These structures are normally utilized to restrain water, soil, existing
structures, etc. Some of the more common temporary systems are described below.
Temporary Shoring Systems
The Cofferdam is a water tight rectangular structure built to restrain water and soil. It is utilized
around the foundations of bridge piers or to have working space to place an item below grade. A
cofferdam contains driven sheet piling (Uprights), wales(Walers) and Cross braces (Struts). To
ensure structural soundness of the cofferdam, the sheet piles are driven beyond the bottom of the
excavation at least two feet. This extension is called the Toe. The most common materials for
construction of a cofferdam are wood timber and structural steel. If moderate ground water is
encountered, Tongue & Groove sheeting is normally utilized to keep out the water. If
considerable water is present, steel sheet piling is used.
Cribbing and Tie Backs shoring is a method of restraining a vertical wall of soil where it is
impractical to slope the soil such as in a downtown area where the excavation and new
substructure are below the street level. This system requires timbers called cribbing to be placed
horizontally with rods (tiebacks) drilled through the cribbing at an angle back into the soil. This
shoring system allows the contractor to maximize the open space.
Underpinning is the process of supporting an existing structure when the new excavation will be
below the existing structures foundation. This requires temporary supports to support the
structure while an extension to the existing foundation is being placed.
Dewatering is the process of removing water or in some cases lowering the water table to install
an item below the existing water table. There are two dewatering methods. The first method is by
utilizing a pump with a suction hose and discharge hose. The second method is to utilize wells
points placed at specified intervals to lower the water table temporarily.
Equipment Mobilization is the process of loading off- road equipment, transporting it to the job
site and assembling at the site. The assembly of a large lifting crane can require 7 -9 workers
approximately three days if the crane requires the boom to be assembled and the cables to be run
through the cranes jib. Equipment Demobilization is the process of disassembling equipment.

185

Level 1 Construction Fundamentals Study Guide


Excavation Shoring Systems
A Support or Shoring System is a structure such as a timber shoring system or hydraulic shoring
system that supports the sides of an excavation and protects employees against cave-ins.
According to the OSHA Excavation Safety Standards, anytime a worker enters a trench at least
five (5) feet deep you must provide protection from cave-ins. After a qualified person has
determined the type of soil, they have a few options. First, they can design a shoring system using
the Shoring Designs provided in the Standards. The Second option is to design a support system
using a Manufacturer's system. Finally, they can use a trench box. Below we will define the
shoring options outlined in the excavation safety standards for shoring systems less than twenty
feet deep. According to the OSHA Construction Standards, for excavations more than twenty
(20) feet deep you must contact a Registered Professional Engineer (RPE) to design the
protection system.
The OSHA Standards for the Construction Industry 29 CFR Part 1926.650(b) titled, Definitions
applicable to subpart P - Excavations defines the following shoring terms.
The Sheeting means the individual members of a shoring system that are closely spaced together
to retain the earth. Sheeting is also called Uprights or Sheet Piling. OSHA defines the term
Uprightsas the vertical members of a trench shoring system placed in contact with the earth
and usually positioned so that individual members do not contact each other (p 253).
The Wales means the horizontal members of a shoring system placed parallel to the excavation
face whose sides bear against the vertical members of the shoring system. They are set
perpendicular to the sheeting. The Crossbraces or Struts are the horizontal members of the
shoring system that span across the width of an excavation. They are installed perpendicular to
the sides of the excavation and the ends are connected to either uprights or wales.
OSHA also defines Tight Sheeting as the use of specially-edged timber planks (e.g. Tongue and
Groove) at least three inches thick. These are used when conditions are saturated or submerged in
water as defined in the OSHA 1926.652(g). Also, Close Sheeting refers to the space between the
timber planks not to exceed inch when placed edge to edge according to OSHA 1926.652(g),
titled Notes for all Tables in paragraph 2.
The Shield or Trench Box is a structure that normally does not prevent a cave-in but protects
employees within the structure. Shields may be permanent structures or may be designed to be
portable and moved along the trench. Shields used in trenches are usually referred to as "trench
boxes" or "trench shields.

186

Level 1 Construction Fundamentals Study Guide


Concrete Support Systems
Concrete Formwork is a temporary support system for restraining the compressive force from the
concrete. The OSHA Standards for the Construction Industry 29 CFR Part 1926.700(b) titled,
Definitions applicable to subpart Q - Concrete and Masonry Construction defines the following
formwork terms. Formwork is the total system of support for freshly placed or partially cured
concrete, including the sheeting that is in contact with the concrete as well as all supporting
members including shores, reshores, hardware, braces, and related hardware. Shoring means a
supporting member that resists a compressive force imposed by a load. Reshoring means the
construction operation in which shoring equipment called reshores is placed, as the original
forms and shores are removed, in order to support partially cured concrete and construction loads
for elevated slab and beams. The slip form system is used to make a continuous vertical concrete
pour which moves up on the freshly poured concrete at a constant speed.
Another temporary operation is called a Lift-Slab or a jacking operation which takes cured
concrete slabs and lifts them vertically into placed using hydraulic jacks. An additional
temporary system is called tilt-up construction. This system has the concrete poured on the
ground into panels and after they are cured they are lifted or tilted up into place vertically.
Finally, there is a formwork system called a flying deck form system which is a complete
formwork support system that is repositioned using a crane for the next pour.
There are various methods for pouring the concrete such as direct chute, crane and bucket,
concrete buggies, concrete pumping, tremie, shotcrete and sometimes by conveyor. The Concrete
bucket is attached to the crane and a person pulls on a handle which opens the bottom of the
bucket and pours concrete. This method is called the crane and bucket operation. There are two
types of concrete buggies: Hand or Georgia buggies and the motorized buggies. The hand
Georgia buggy has a very limited capacity of about 1.5 cubic feet, therefore, it is used to move
small amounts of concrete. The Motorized Concrete Buggy is a small rubber tired vehicle with a
dump box that carries up to 14 cubic feet. A Concrete pump is a truck mounted equipped with a
placement boom or hose which pressurizes the hose system to pump the concrete to elevated
locations or an inaccessible location. Tremie is the process of pouring concrete under water using
a tube that is submerged into the fresh concrete at all times.
The Structural Engineering Institute (SEI) of the American Society of Civil Engineers (ASCE)
insists that more failures occur during construction than after completion, therefore, they have
developed a standard titled, SEI/ASCE 37-02, Design Loads on Structures During Construction.
Another temporary area that fails during construction is the masonry wall bracing. Under the
Construction OSHA Standards Part 1926.700 titled Masonry Construction it states that
temporary bracing should be provided for walls more than 8 feet high and the bracing shall not
exceed 20 feet horizontally. Recently, the Masonry Institute has developed a temporary masonry
bracing standard for construction.

187

Level 1 Construction Fundamentals Study Guide


Lifting Systems
The Jin Pole is a lifting system which utilizes a single pole or double pole above grade vertical
lifting system with the intended purpose of lifting an unusually long horizontal piece of
equipment into its permanent vertical position. The Jin poles are attached to a temporary
foundation and the guy lines are attached to the top of each Jin pole and tied to deadmen buried
in the ground.
Cranes are used to hoist and move loads from one location to another and it is necessary to know
the lifting capacity and working range of a crane selected to perform a given service.
Manufacturers and suppliers furnish this information in literature describing their products.
When a crane lifts a load there is a tendency to tip the machine over. This introduces what is
defined as the tipping condition. A machine is considered to be at the point of tipping when a
balance is reached between the overturning moment of the load and the stabilizing moment of the
machine when the crane is on a firm level supporting surface. A track mounted or a crawler
mounted crane sets on a track base which rotates 360 degrees and the boom is attached at the
base of the crane. A rubber tired crane is extremely mobile and it can be easily transported from
one job site to another over the road. The crane mat is normally made of large square timbers tied
together using cables threaded through the center of the timbers at specified spacings. It is best to
place the crane on a mat to ensure that the load is distributed evenly.
Tower Cranes are available as rail mounted units, stationary units, climbing units and mobile
units. The rail mounted units can be equipped with fixed or slewing towers. Tower cranes
generally have a larger area of coverage than climbing and stationary tower cranes. Tower cranes
have their boom above the structure and it lifts the load vertically until it is above the structure,
then it can move the load horizontally. A tower crane looks like an offset Tee.
A Crane Load Capacity Chart is provided with each crane by the crane manufacturer which
indicates its safe lifting capacity under differing conditions. The major factor for safely lifting a
load by a crane is its operating radius which is the horizontal distance from the center of the
rotation to the hook. Some other factors which affect lifting capacity are the position of the crane
in relationship to its base, the placement or use of outriggers and the soil conditions. Also, the
boom angle for a crawler mounted lifting crane is normally between 55 degrees and 80 degrees.
Working Range of a Crane Chart
This crane table shows lifting ranges for a dragline, a clamshell and a lifting crane. From the crane
table, the working range of a dragline is from 25 degrees to 39 degrees, the clamshell range is
between 40 degrees and 54 degrees and the crane lifting range is between 55 degrees and 80
degrees. The crane chart also contains the distance from the center line rotation in feet along the
horizontal axis and the height of a structure in feet such as a wall along the vertical structure. To
utilize the chart, lets assume that you are lifting an item over a vertical wall that is 45 feet above
the ground and the horizontal distance from the centerline of the rotation is 60 feet.
188

Level 1 Construction Fundamentals Study Guide


The fist step is to find the working range for a lifting crane which is between 55 degrees and 80
degrees. Next, find the length of boom in feet required by determining if the rotation distance or
the height above the ground is the controlling factor. In this example, using the height in feet
above the ground of 45 feet and in the lifting crane range of 55 - 80 degrees the length of boom,
the curved lines, needed is 50 feet. Now, using the center line rotation in feet of 60 feet and in the
lifting crane range of 55 - 80 degrees the length of boom needed is 100 feet. This is found by
entering the table along the horizontal axis at 60 feet and following the vertical line until it in
within the lifting crane range and finding the intersection of the length of boom in feet curved line
and the vertical (60 feet) line. The Crane Chart below indicates the working range of a crane.

Adapted from Peurifoy (1985). Construction Planning, Equipment, and Methods. Upper Saddle
River, NJ: Prentice-Hall. (p 224).

189

Level 1 Construction Fundamentals Study Guide


Sling Angles are formed by the legs of the sling and the horizontal plane and the rated capacity of
any sling depends on its size, its configuration and the angles. A sling with two legs that is used to
lift a 1000 pound object will have a 500 pound load in each leg when the sling angle is 90
degrees. The load in each leg will increase as the angle is decreased and at 30 degrees the load
will be 1000 pounds in each leg. Therefore, it is extremely important to keep the sling angles
greater than 45 degrees. Hence, sling angles approaching 30 degrees should be considered
extremely hazardous and avoided at all costs. Some load tables list sling angles as low as 15
degrees but the use of any sling at an angle less than 30 degrees is extremely dangerous. This is
not only because of the high loads associated with them but because of the effect on the load of an
error in sling angle measurement of as little as 5 degrees. It has been shown that an assumed sling
angle of 15 degrees has an assumed load of 1,932 pounds per Leg but, if the actual angle is
actually 10 degrees then the actual load is 2,880 pounds per leg. This illustrates how cautious you
must be in ensuring that the angle is greater than 45 degrees and the importance of measuring the
angle accurately.
The major types of crane attachments are the lift hook, the lifting beam and hook, the concrete
bucket, the clamshell bucket, orange peel bucket, the pile driver, the auger or drilled attachment,
and the dragline. Each attachment is described below. The Lift Hook has a sling or a configuration
of slings connected to the hook on the crane. The Lifting Beam is utilized to lift long items such as
beams for a bridge. The Beam has two lifting at each end with the crane hook connected to the
center of the lifting beam. The Clamshell bucket opens and is dropped straight down into the soil
being excavated and the jaws close toward each other. The Clamshell bucket is utilized to
excavate inside the cofferdam after the sheet piles are driven. The Orange Peel bucket is similar
to the Clamshell bucket but it opens and has straighter sides and it is dropped straight down into
the soil being excavated and the jaws close toward each other. The Pile Driver can replace the
boom or it can be attached to the boom via the hook and suspended from the crane. The Auger or
Drilled pile is an attachment to the crane for drilling Caissons. These drill attachments have a
mechanical device at the bottom of the caisson to form the bell.
Finally, the Dragline is used to excavate earth and load it into hauling units, such as trucks or
tractor-pulled wagons, or to deposit it in levees, dams, and spoil banks near the pits from which it
is excavated. A dragline usually does not have to go into a pit or hole in order to excavate. It may
operate on natural ground while excavating material from a pit with its bucket. This will be very
advantageous when earth is removed from a ditch, canal, or pit containing water. If the earth is
hauled with trucks, they do not have to go into the pit and contend with mud. If the earth can be
deposited along a canal or ditch or near a pit, it frequently is possible to use a dragline with a
boom long enough to dispose of the earth in one operation, eliminating the need for hauling units,
which will reduce the cost of handling the soil. A Dragline is an excellent unit for excavating
trenches when an angle of repose can be utilized without shoring.

190

Level 1 Construction Fundamentals Study Guide


Excavation Equipment
Power Shovels are normally utilized in an area where the excavation is above the location of the
machine. The shovels bucket opens at the bottom to place the soil into trucks. They are capable
of excavating all classes of earth, except solid rock, without prior loosening. They may be
mounted on crawler tracks, in which case they are referred to as crawler-mounted. They may also
be mounted on rubber-tired wheels. The non-self-propelled units mounted on the rear of trucks,
which are refereed to as truck-mounted, have separate engines for operating them. The Hydraulic
Backhoe is normally utilized in an area where the excavation is below the location of the
machine. The bucket action of a Backhoe is to pull the excavated material toward the machine.
Front End Loaders are used extensively to excavate earth, gravel or rock materials from a pile and
place the material into a truck to be transported over a road and deposited at another location.
There are basically two types of front-end-loaders, the crawler-tractor-mounted and the wheeltractor-mounted. They may be further classified by the capacities of the buckets or the weights
that the buckets can lift.
Scrapers are used to move large quantities of earth economically for relatively short haul
distances. There are a number of different types of scrapers such as the crawler-type tractor,
pulling a rubber-tired self-loading scraper. The high draw-bar pulls in loading a scraper, combined
with good traction, even on poor haul roads, gives the crawler tractor an advantage for short hauls.
However, as the haul distance is increased, the low speed of a crawler tractor is a disadvantage
compared with a wheel tractor. Unless the loading operation is difficult, a crawler tractor can load
a scraper without the aid of a bulldozer. However, if there are several scraper units on a job, the
increased output resulting from using a bulldozer to help load the scrapers usually will justify the
use of a bulldozer. Te wheel-tractor scrapers are for longer haul distances because of their higher
speed. Also, a wheel type tractor-pulled self-loading scraper will permit it to move earth more
economically than a crawler-type tractor. Although, the wheel-type tractor scraper lacks loading
ability, the higher travel speed, which may exceed 30 mph for some models, will offset the
disadvantage in loading when the haul distance is sufficiently long. The size of a scraper may be
specified as the struck, or heaped, capacity of the bowl, expressed in cubic yards. The struck
capacity is the volume of the material that a scraper will hold when the top of the material is
struck off even with the top of the bowl. In specifying the heaped capacity of a scraper, some
manufacturers specify the slope of the material above the sides of the bowl with the designation
SAE which means the Society of Automotive Engineers. The SAE specifies a slope of 2:1,
measured horizontally and vertically, respectively. Since, the slope will vary with the class of
material being hauled, the heaped capacity is only an approximate value.
The Bottom-dump Wagons are to be used to haul materials, such as sand, gravel, reasonably dry
earth, coal, etc., which flow easily, the use of bottom-dump wagons will reduce the time required
to unload the units. Such units are particularly suitable for use where the materials are distributed
in layers on a fill or are discharged through grizzlies into hoppers. The rapid rate of discharging
the load gives these wagons a time advantage over rear-dump trucks.
191

Level 1 Construction Fundamentals Study Guide


Compaction Equipment
The Technical Specifications normally state the compaction method and the optimum moisture
content range. The measurement testing method for determining if the desired compaction has be
attained is the Modified Proctor Test or the Standard Proctor Test. For a contractor to attain the
prescribed compaction, it must determine the number of passes for a roller with a specified unit
pressure under the roller areas and the depth of each layer of soil to produce the desired
compaction. Compaction is attained by applying energy to a soil by one or more of the following
methods. The different methods to apply the energy is by a kneading or tamping action, a static
weight, a vibrating action, or an impacting force. The common pieces of compaction methods are
described below.
A kneading roller is the sheep's-foot type. This roller, which may be towed by a tractor or selfpropelled, consists of a hollow steel drum on whose outer surface there are welded a number of
projecting steel feet, which on different pieces of equipment may be of varying lengths and cross
sections. A unit may consist of one or several drums mounted on one or more horizontal axles.
The weight of a drum may be varied by adding water or sand to produce unit pressures under the
feet up to 750 psi or more. As a sheeps foot roller moves over the surface, the feet penetrate the
soil to produce a kneading action and a pressure to mix and compact the soil from the bottom to
the top of the layer. With repeated passages of the roller over the surface, the penetration of the
feet decreases until the roller is said to walk out of the fill. The Sheep's-foot rollers are quite
effective in compacting clays and clay mixtures. However, they cannot compact granular soils
such as sand and gravel. Also, the depth of a layer of soil to be compacted is limited too
approximately the length of the feet.
Smooth-wheel Rollers may be classified by weight, which is usually stated in tons. A three-wheel
two-axle roller. The front wheel is used for steering, while the two rear wheels are used for
driving the unit. A two-wheel tandem roller of varying size is available. A three-wheel tandem
roller differs from the two-wheel tandem unit in that it has three drums and three axles. This unit
can be more effective than the two-wheel tandem or the three-wheel two-axle units in eliminating
or reducing transverse surface roughness because of the concentration of pressure on the middle
wheel when the unit passes over high spots in the surface being compacted. The rolls are steel
drums, which may be ballasted with water or sand to increase the weights. If a roller is designated
as 14-20 tons, it means that the minimum weight of the machine only is 14 tons and that it can be
ballasted to give a maximum weight of 20 tons. These rollers are effective in compacting granular
soils, such as sand, gravel, and crushed stone, and they are also effective in smoothing surfaces of
soils that have been compacted by tamping rollers. Another type designates the weight per linear
inch of roller, such as 300 lb. per inch of roller width. Specifying the minimum weight per linear
inch of width is a more definitive method.
Pneumatic-tired Rollers are surface rollers which apply the principle of kneading action to affect
compaction below the surface. They may be self-propelled or towed and they may be small or
192

Level 1 Construction Fundamentals Study Guide


large-tired units. The small-tired units usually have two tandem axles with four to nine tires on
each axle. The rear wheels are spaced to travel over the surfaces between the front wheels, which
produces a complete coverage of the surface. The wheels may be mounted in a manner that will
give them a wobbly-wheel effect to increase the kneading action on the soil. The Large-tired rollers
are available in sizes varying from 15 to 200 tons gross weight. These units are frequently used to
compact subgrade and base material on airfields and earth-fill dams.
The Manually Operated Vibratory Tamping Compactor is used in locations where larger units are
not practical. These are self-propelled and they are called a vibrating plate for compacting sand or a
vibrating sheepsfoot compactor for compacting clay.
The Manually Operated Rammer Compactor is normally gasoline-engine-driven rammer used for
compacting cohesive or mixed soils in confined areas. these units range in impact from about 300
to 900 or more ft-lb per sec at an impact rate up to 850 per minute, depending on the specific
model. Performance criteria include pounds per blow, area covered per hour, and depth of
compaction (lift) in inches. Rammers are self-propelled in that each blow moves them ahead
slightly to contact new soil.
Types of Equipment Suited for Compacting Different Types of Soils
Type compactor

Soil best suited for

Max. effect in
loose, lift, in.

Sheep's foot

Clay, silty clay, gravel with


clay binder

Steel tandem two-axle

Sandy silts, most granular


material with some clay
binder

Steel tandem three-axle

Max.
Tons.

Nearly uniform

20

4 to 8

Average*

16

Same as above

4 to 8

Average*

20

Steel three-wheel

Granular or granular-plastic
material

4 to 8

Average* to uniform

20

Pneumatic, small-tire

Sandy silts, sandy clays,


gravelly sand and clays with
few fines

4 to 8

Average* to uniform

12

Pneumatic large-tire

All types

? to 24

Uniform

50

Vibratory

Sand, silty sands, silty


gravels

3 to 6

Uniform

30

Combinations

All

3 to 6

Uniform

20

* The density may decrease with depth

193

7 to 12

Density gained in lift

Level 1 Construction Fundamentals Study Guide


Temporary Material and Equipment Exercise
1.

Which party is normally responsible for estimating and pricing the temporary structures?
A.
B.
C.
D.

2.

Which party is normally responsible for designing the temporary structures?


A.
B.
C.
D.

3.

Steel Piling.
Sheet Piling.
Wood Piling.
Concrete Piling.

Which of the following systems is designed to carry the vertical load of the structure?
A.
B.
C.
D.

5.

Owner.
Vendor.
Contractor.
Architect/Engineer.

Which of the following systems is designed to restrain horizontal temporary loads such as
soil and water?
A.
B.
C.
D.

4.

Owner.
Vendor.
Contractor.
Architect/Engineer.

Piling.
Cofferdam.
Timber Shoring.
Cribbing and Tie-backs.

Which of the following systems is utilized for supporting an existing structure when the
new excavation will be below the existing structures foundation while the extension to the
existing foundation is being placed?
A.
B.
C.
D.

Piling.
Cofferdam.
Underpinning.
Cribbing and Tie-backs.

194

Level 1 Construction Fundamentals Study Guide


Temporary Material and Equipment Exercise
6.

Which of the following systems is utilized for restraining a vertical wall of soil and other
loads where it is impractical to slope the soil such as in a downtown area where the
excavation and new substructure are below the street level?
A.
B.
C.
D.

7.

Which of the following systems is designed as an enclosed structure to restrain soil and
water, therefore, allowing workers to work inside safely?
A.
B.
C.
D.

8.

Caisson.
Jin Poles.
Cofferdam.
Underpinning.

In construction, what is the proper terminology for transporting the off road equipment to
the job site?
A.
B.
C.
D.

9.

Piling.
Cofferdam.
Underpinning.
Cribbing and Tie-backs.

Hauling.
Mobilization.
Militarization.
Transportation.

What is the lifting system called which consists of two vertical towers with a cross beam on
top with the intended purpose of lifting an unusually long piece of equipment which was
transported horizontally and it is lifted into its permanent vertical position?
A.
B.
C.
D.

Caisson.
Jin Pole.
Cofferdam.
Tower Crane.

195

Level 1 Construction Fundamentals Study Guide


Temporary Material and Equipment Exercise
10.

What are the components of a cofferdam or a support system?


A.
B.
C.
D.

11.

What is a toe in relationship to a Cofferdam?


A.
B.
C.
D.

12.

The Architect shall design the protection system.


The Project Engineer shall design the protection system.
The designated Competent Person shall design the protection system.
The Registered Professional Engineer shall design the protection system.

What is another name for Sheeting?


A.
B.
C.
D.

14.

The Tie Back extension beyond the Cribbing at least 2 feet.


The horizontal Wales which extends beyond the wall at least 2 feet.
The braces set at a 45-degree angle and extended into the ground at least 2 feet.
The vertical sheeting extended below the bottom of the excavation at least 2 feet.

According to the OSHA Construction Safety Standards, what is required for shoring
systems more than 20 feet deep?
A.
B.
C.
D.

13.

Sheeting, Wales, and Cross braces.


Posts, Stringers, Joists and Pans.
Posts, Stringers, Joists and Plyform.
Wall forms, Wall Ties, Wales, Hairpins and Braces.

Piles.
Struts.
Uprights.
Caissons.

What does close sheeting mean in relationship to a shoring system?


A.
B.
C.
D.

The span across the width of an excavation.


The spacing between timber planks not to exceed inch.
Tongue and groove timber planks at least 3 inches thick.
The use of a trench box or trench shield while working in the excavation.

196

Level 1 Construction Fundamentals Study Guide


Temporary Material and Equipment Exercise
15.

Which piece of equipment and attachment would be the most efficient method to excavate
inside a cofferdam?
A.
B.
C.
D.

16.

Which piece of equipment sets below the excavation and the bucket pushes up?
A.
B.
C.
D.

17.

Shovel.
Backhoe.
Dragline.
Wheel-tractor Scraper.

Which piece of equipment has its boom above the structure and it lifts the load vertically
until it is above the structure, then it can move the load horizontally?
A.
B.
C.
D.

19.

Power Shovel.
Hydraulic Backhoe.
Dragline.
Wheel-tractor Scraper.

Which piece of equipment is used to excavate ponds or soil under water?


A.
B.
C.
D.

18.

Shovel with a 3-CY bucket.


Backhoe with a 3-CY bucket.
Crane with an Auger Attachment.
Crane with a Clamshell attachment.

Shovel.
Backhoe.
Tower Crane.
Track-mounted Crane.

Which piece of equipment is most efficient for compacting granular soils such as sand,
gravel, and crushed stone?
A.
B.
C.
D.

Backhoe.
Sheepsfoot.
Smooth-Wheel Roller.
Wheel-tractor scraper.

197

Level 1 Construction Fundamentals Study Guide


Temporary Material and Equipment Exercise
20.

Which of the following temporary systems is utilized to support freshly placed concrete
which is poured continuously in a vertical direction?
A.
B.
C.
D.

21.

Which of the following temporary systems is utilized to support freshly placed concrete
which is poured on the ground as a slab and lifted up to its final horizontal elevation using
hydraulic jacks?
A.
B.
C.
D.

22.

Tremie.
Conveyor.
Direct Chute.
Underpinning.

Which organization has published a new design standard targeting loads on structures
during construction?
A.
B.
C.
D.

24.

Slip form system.


Tilt-up for system.
Flying form system.
Lift slab form system.

What is the concrete pouring method called that is used to pour concrete under water?
A.
B.
C.
D.

23.

Slip form system.


Tilt-up for system.
Flying form system.
Lift slab form system.

American Concrete Institute.


Concrete Reinforcing Steel Institute.
American Society for Testing Materials.
Structural Engineering Institute of the American Society of Civil Engineers.

What is the primary cause for a masonry wall to collapse while under construction?
A.
B.
C.
D.

Poor soil conditions.


Lack of vertical reinforcement.
Lack of horizontal reinforcement.
Lack of masonry wall bracing and a change in wind conditions.

198

Level 1 Construction Fundamentals Study Guide


Temporary Material and Equipment Exercise
25.

Which of the following sling angle ranges is best for lifting without making the lift
extremely dangerous?
A.
B.
C.
D.

26.

1 degree to 14 degrees.
15 degrees to 30 degrees.
31 degrees to 44 degrees.
45 degrees to 90 degrees.

You have an assumed sling angle of 24 degrees but the actual angel is 19 degrees. What
effect does this have on the pounds per leg on the sling?
A.
B.
C.
D.

The pounds per leg will decrease.


The pounds per leg will increase.
The pounds per leg stays constant.
The pounds per leg does not matter since the cranes lifting capacity is not effected

Using the Working Range of a Crane Chart attached, answer questions 27 through 33.
27.

What is the working range of a Clam Shell?


A.
B.
C.
D.

28.

What is the working range of a Lift Crane?


A.
B.
C.
D.

29.

00 - 24 degrees
25 - 39 degrees
40 - 54 degrees
55 - 80 degrees

00 - 24 degrees
25 - 39 degrees
40 - 54 degrees
55 - 80 degrees

What is the working range of a Dragline?


A.
B.
C.
D.

00 - 24 degrees
25 - 39 degrees
40 - 54 degrees
55 - 80 degrees

199

Level 1 Construction Fundamentals Study Guide


Temporary Material and Equipment Exercise
30.

Assume you are lifting an item onto the roof. The Height of the exterior wall is 27 Feet
above the ground and the horizontal distance from the centerline of the rotation is 40 feet.
What is the minimum length of the boom required?
A.
B.
C.
D.

31.

Assume you are lifting an item onto the bridge deck. The Deck is 27 feet above the ground
and the horizontal distance from the centerline of the rotation is 40 feet. What is the
minimum boom angle?
A.
B.
C.
D.

32.

30 degrees.
40 degrees.
57 degrees.
72 degrees.

Assume you are lifting an item onto the bridge deck. The deck is 37 feet above the ground
and the horizontal distance from the centerline of the rotation is 70 feet. What is the
minimum length of the boom required?
A.
B.
C.
D.

33.

20 Feet.
50 Feet.
60 Feet.
70 Feet.

70 Feet.
87 Feet.
110 Feet.
120 Feet.

Assume you are lifting an item onto the bridge deck. The deck is 37 feet above the ground
and the horizontal distance from the centerline of the rotation is 70 feet. What is the
minimum boom angle?
A.
B.
C.
D.

26 degrees.
40 degrees.
47 degrees.
57 degrees.

Check Answers

200

Level 1 Construction Fundamentals Study Guide


Schedules on Plans and in the Technical Specification
Many of the CSI Divisions utilize schedules to represent the work. Therefore, it is essential that a
Constructor be able to identify and interpret information from various schedules as well as from
the technical specifications and the plans. Some of the most common schedules, construction
specifications and plans from various divisions will be discussed below.
Concrete Beam Schedule for Division 03 - Concrete
The Concrete Reinforcing Steel Institute (CRSI) defines reinforced concrete as a combination of
both reinforcing steel and concrete using the best properties of each. They take into consideration
the compression properties of the concrete and the tension strength of reinforcing steel.
The Reinforcing Steel Bars are also referred to as deformed bars. Reinforcing steel is most
common in the form of deformed bars which contains ridges which makes a good bond with the
concrete instead of smooth reinforcing. Each reinforcing bar contains identifying marks. The
uppermost designation is usually a letter identifying the manufacturer, the next mark the bar size
such as a #11. The bar numbers designate eighths of an inch beginning with a No. 3. The rebar
diameter is determined by taking the bar # and dividing by eight. Therefore, a #3 bar is 3/8 inch in
diameter. A #4 bar is 4/8 or inch. The third mark down is type of steel used. Reinforcing bars are
made of either new billet, axle, or rail steel. The fourth identifying mark may be shown on the bar
is the tensile yield point. The tensile yield point indicates the minimum pounds per square inch
(psi). A grade of 40 reinforcing bar has a minimum yield of 40,000 psi. Other grades are 50 and 60.
Welded Wire Fabric (WWF) is used in slabs-on-grade and highways. It is made of wire generally
arranged to cross at right angles at each intersection. The welded wire fabric is made and delivered
in rolls or as sheets. The designation is 6 x 6 - W1.4 x W1.4 (10 x 10). The 6 x 6 means that the
spacing is 6 inches by 6 inches and the W1.4 xW1.4 is the wire (number) size for a 10-gauge
material. The parenthesis indicates the old designation indicating the wire gauge.
Bar supports are normally incorporated by reference and they are not shown on the plans. It is the
Contractors responsibility to ensure that they are placed properly. This requires the contractor to
review the CRSI 65 Recommended Practice for Placing Bar Supports, Specifications and
Nomenclature. Typically they are designed to raise the reinforcing bars to the required height
above the bottom of the forms and to hold the bars in place. Many times bar supports are placed in
the upper third of the slab and the lower third of the slab. This requires two sets of bar supports
placed in a slab or beam. Normally these bar supports are called slab bolsters and beam bolsters
and if their location is in the upper third of the slab or beam, then a U is placed at the end of the
abbreviation. For example, BB means Beam Bolster and BBU means Beam Bolster Upper. The
Concrete Reinforcing Steel Institute (CRSI) publication titled, Manual of Standard Practice and
the adapted table titled Bar Support Designations is shown below.

201

Level 1 Construction Fundamentals Study Guide


The CSI Master Format has the bar supports under Division 03 CONCRETE, Section 200
REINFORCEMENT and Part 1.03 REFERENCE STANDARDS. A typical specification would
indicate that the Contractor must be in compliance with CRSI 65 Recommended Practice for
Placing Bar Supports, Specifications and Nomenclature. CRSI is an abbreviation for the Concrete
Reinforcing Steel Institute. Some of the typical Types and Sizes of Wire Bar Support with their
abbreviations, the type of support and the typical sizes are identified below.
SYMBOL

TYPE OF SUPPORT

TYPICAL HEIGHTS

SB

Slab Bolster

3/4, 1, 1-1/2, 2 inches

SBU

Slab Bolster Upper

Same as SB

BB

Beam Bolster

1,1-1/2, 2 to 5 inches in 1/4" increments

BBU

Beam Bolster Upper

Same as BB

BC

Individual Bar Chair

3/4, 1, 1-1/2 and 1-3/4 inches

JC

Joist Chair

3/4, 1, and 1-1/2 and 4, 5, 6 inches in widths

HC

Individual High Chair

2 to 15 inches in 1/4" increments

HCM

High Chair for M etal Decking

2 to 15 inches in 1/4" increments

CHC

Continuous High Chair

Same as HC

CHCU

Continuous High Chair Upper

Same as CHC

JCU

Joist Chair Upper

Heights -1 thru +3-1/2 in; 14 inch span

Adapted from the Concrete Reinforcing Steel Institute (M arch 2001). Manual of Standard Practice. Schaumburg, IL:
author.

Column, Beam and Slab Schedules


Are utilized to provide the Constructor with detailed information for placing the reinforcing bars,
the stirrups, and the bar supports. Reinforcing bars are designated as either straight bars or bar
bends which are fabricated by the manufacturer in the shop and shipped to the job site.
Stirrups are also known as ties and they are used to wrap the around the horizontal or vertical bars
at specified on center spacings. A Beam schedule is provided below as an exercise.

202

Level 1 Construction Fundamentals Study Guide


Concrete Beam Exercise
Given the Beam Schedule attached, and Using Mark 1B1. Answer the following questions.
1.

What is the Size of the Beam?


A.
B.
C.
D.

2.

How many total beams for Mark 1B1?


A.
B.
C.
D.

3.

1
2
12
24

What is the Reinforcing in the top mat?


A.
B.
C.
D.

5.

1
2
12
24

How many layers or mats of reinforcement are required for Mark 1B1?
A.
B.
C.
D.

4.

12" wide x 24" deep.


12" wide x 33" deep.
24" wide x 12" deep.
24" wide x 10.5" deep.

4 Pieces - #6 bar, 20' 8 inches long.


12 Pieces - #6 bar - 20' 8 inches long.
2 Pieces - #6 bar - 15' 8 inches long.
2 Pieces - #6 bar - 15' 8 inches long and 4 pieces - #6 - 16' 0 inches long.

What is the size of the rebar in inches of the stirrups?


A.
B.
C.
D.

3/8"
4/6"
6/8"
36"

203

Level 1 Construction Fundamentals Study Guide


Concrete Beam Exercise
6.

How are the stirrups labeled for Mark 1B1 at column #4?
A.
B.
C.
D.

7.

What is the on-center spacing of the stirrups for Mark 1B1 at column #4?
A.
B.
C.
D.

8.

2 each, 15' - 8" long


4 each, 16' - 0" long.
4 each, 20' - 8" long
5 each, 21' - 7" long

What are the size, and type of bar supports?


A.
B.
C.
D.

10.

4" and 8"


6" and 8"
6" and 10"
8" and 12"

What are the quantity and length of the stirrup support bars for Mark 1B1?
A.
B.
C.
D.

9.

IB1
3A2
3A3
6A1

2 inch Slab Bolsters.


2 inch Beam Bolsters.
5 inch High Chairs.
5 inch Beam Bolsters.

What does the bar support abbreviation CHCU mean?


A.
B.
C.
D.

Concrete High Chair Upper.


Continuous High Chair Upper.
Concrete High Chair Unidentified.
Continuous High Chair Unidentified.

204

Level 1 Construction Fundamentals Study Guide


Concrete Beam Exercise
11.

What does the bar support abbreviation BBU mean?


A.
B.
C.
D.

12.

What does the bar support abbreviation SB?


A.
B.
C.
D.

13.

Slab Bar.
Slab Bolster.
Slab Bottom.
Beam Bolster.

Which of the following items are not shown or specified in the construction documents for
a reinforced concrete structure?
A.
B.
C.
D.

14.

Broad Beam Upper.


Beam Bolster Upper.
Bottom Bar Unidentified.
Beam Bolster Unidentified.

Rebar.
Concrete.
Bar Supports.
Welded Wire Mesh.

What is the name of the organization which publishes a manual on the spacing
requirements for bar supports?
A.
B.
C.
D.

American Concrete Institute.


Concrete Reinforcing Steel Institute.
Concrete Reinforcement Standards Institute.
Concrete Reinforcing Specifications Institute.

Check Answers

205

Level 1 Construction Fundamentals Study Guide


Concrete Beam Exercise - Schedule
Mark

No.

Beam Size
(inches)

Reinforcing

#3 Stirrups

Bottom

Top

Total

Support Bars

Col. # O.C.

2"
BB

Width

Depth

No.

Size

Length

No.

Size

Length

Mark

No.

Mark

OC

OC

No.

3
4

6"
6"

10"
8"

2
3

21' -7"

1B1

12

24

20'-8"

2
4

6
6

15' -8"
16' -0"

6A1

17
17

3A3
3A2

1B2

24

10.5

12'-8"

4
7

6
7

9' -4"

6A4

16
16

3A6
3A5

4"
4"

8"
8"

2' 0"

1B2A

24

10.5

12'-8"

4
7

6
7

11' -1"

6A4

16
16

3A6
3A5

4"
4"

8"
8"

2' 0"

1B3

24

10.5

17' -2"

11'- 1"

20
20

3A6
3A5

4"
4"

8"
8"

2' 0"

1B4

24

10.5

13' -4"

11' -1"

10
10

3A6
3A5

4"
4"

8"
8"

-----

-----

1B5

24

10.5

14' -3"

6A7

20
20

3A6
3A5

4"
4"

6"
8"

7' -0"

1B7

24

10.5

22' -9"

4
3

7
8

14' -6"

7A9

26
26

3A6
3A5

6"
6"

8"
8"

11' -0"

1B10

12

33

15' -2"

15' -8"

12
12

3A3
3A11

6"

12"

16' 8"

1B12

12

18

13' -9"

8
8

3A3
3A16

8"
8"

12"
12"

-----

------

5A15

206

Level 1 Construction Fundamentals Study Guide


Door and Window Exercise
Using the door schedule attached. Answer the following questions.
1.

What is the location of Door number 104 B?


A.
B.
C.
D.

2.

What is the door size, type, door material, frame Material for Door No. 104 A?
A.
B.
C.
D.

3.

Half Metal Frame


Hallway Metal Frame
Hollow Metal Frame.
Halloway Metal Frame.

What is the door size, type door material frame material for Door 107?
A.
B.
C.
D.

5.

3' - 6" x 7' -2" x 1-3/4", Type C Solid hollow metal door in a hollow metal frame.
3' - 0" x 7' -0" x 1-3/4", Type A Aluminum glass door in an aluminum frame.
3' - 0" x 7' - 2" x 1-3/4", Type D Wood door, w/sm. Window in a wood frame.
3' - 0" x 7' - 2" x 1-3/4", Type D Wood door w/sm. window, a hollow metal frame.

What does the Abbreviation HM stand for on the door schedule?


A.
B.
C.
D.

4.

Crib.
Women.
Nursing.
Corridor.

3' -0" x 7-2 x 1-3/4, Type D Wood w/sm window in a hollow metal frame.
3' -0" x 7' -0" x 1-3/4", Type A, Aluminum, in an aluminum frame.
3-6" x 7-2 x 1-3/4, Type C, Solid Wood door in a hollow metal frame.
3-6x 7-2 x 1-3/4, Type C, Hollow metal door in a hollow metal frame.

What is the Fire rating of the door and the type of glass for Door No. 108B?
A.
B.
C.
D.

No rating, standard glass.


No rating, 1/4" Tempered
20 minute rating, 1/4" Wired Glass.
45 minute Rating, 1/4" Wired Glass.

207

Level 1 Construction Fundamentals Study Guide


Door and Window Exercise
6.

What is the Fire rating of the door and the type of glass for Door No. 102?
A.
B.
C.
D.

7.

What is the Finish on the Frame for Door No. 111?


A.
B.
C.
D.

8.

Stain.
Paint.
Aluminum.
Dark Bronze.

What is the Finish on the Door No. 108A?


A.
B.
C.
D.

10.

Stain.
Paint.
Aluminum.
Dark Bronze.

What is the Finish on the Door No. 108 B?


A.
B.
C.
D.

9.

No rating, standard glass.


No rating, 1/4" Tempered
20 minute rating, 1/4" Wired Glass.
45 minute Rating, 1/4" Wired Glass.

Stain.
Paint.
Aluminum.
Dark Bronze.

How many sets of Hardware are needed for Door Number 106?
A.
B.
C.
D.

1
3
5
10

Check Answers

208

Level 1 Construction Fundamentals Study Guide

Door and Window Exercise - Door Schedule


Door
No.

Door

Frame

Label

Glass

----

1/4" Temp

Location

Hrdwr
Sets

Size

Type

Material

Finish

Material

Finish

3'x7'x1-3/4"(pr)

Alum

Dk Bronz

Alum

Dk Bronz

W ood

Stain

HM

Paint

45 min

1/4" W ired

101

Lower Narthex

102

Infants

103

Crib

3x7-2x1-3/4

W ood

Stain

HM

Paint

----

1/4" Temp

104A

Nursing

3x7-2x1-3/4

W ood

Stain

HM

Paint

20 min

1/4" W ired

104B

Nursing

3x7-2x1-3/4

W ood

Stain

HM

Paint

-----

1/4" Temp

105

W omen

3x7-2x1-3/4

W ood

Stain

HM

Paint

20 min

-------

106

Men

3x7-2x1-3/4

W ood

Stain

HM

Paint

20 min

-------

107

Mechanical

3-6x7-2x1-3/4

HM

Paint

HM

Paint

20 min

-------

2-10x7-2x1-3/4
(pr)

W ood

Stain

HM

Paint

45 min

1/4" W ired

10

3x7x1-3/4

Alum

Dk. Bronz

Alum

Dk Bronz

-----

1/4" Temp

108A

Corridor

108B

Corridor

3x7-2x1-3/4

109

Classroom

3x7-2x1-3/4

W ood

Stain

HM

Paint

20 min

1/4" W ired

111

Classroom

3x7-2x1-3/4

W ood

Stain

HM

Paint

20 min

1/4" W ired

112

Classroom

3x7-2x1-3/4

W ood

Stain

HM

Paint

20 min

1/4" W ired

113

Storage

3x7-2x1-3/4

W ood

Stain

HM

Paint

20 min

--------

Stair

3x7-2x1-3/4

W ood

Stain

HM

Paint

1 hour

1/4" W ired

114A

209

Level 1 Construction Fundamentals Study Guide


Door and Window Exercise - Diagrams

210

Level 1 Construction Fundamentals Study Guide


Finish and Paint Exercise
Using the Room Schedule attached, answer the following questions.
1.

In room no. 105, which materials will be utilized on the floor?


A.
B.
C.
D.

2.

In Room No. 201, which material and finish will be on the W/NW Wall?
A.
B.
C.
D.

3.

Cast Metal Unit.


Cabinet Metal Unit.
Corrugated Metal Unit.
Concrete Masonry Unit.

What is the height of the ceiling in room No. 107?


A.
B.
C.
D.

5.

CMU and paint.


SF CMU, unpainted.
SF CMU/Wood, stain.
SF CMU/Wood, unpainted.

What does the abbreviation CMU on the Room Finish Schedule mean?
A.
B.
C.
D.

4.

Vinyl.
Concrete.
Carpet #1.
Carpet #2.

8' - 0"
9' - 0"
10' - 3"
13' - 0"

What are the ceiling material and finish in room No. 132?
A.
B.
C.
D.

ACT #1 and paint.


SF CMU and no paint.
ACT #1 and no paint.
Gypsum board and paint.

211

Level 1 Construction Fundamentals Study Guide


Finish and Paint Exercise
Using the Paint Specifications. Answer the following questions.
6.

What types of paint are required on the interior gypsum board with a special finish?
A.
B.
C.
D.

7.

Which room(s) require the special paint finish on gypsum board walls?
A.
B.
C.
D.

8.

Sealer.
Semigloss enamel.
Alkyd flat enamel.
Stain. Use stain filler for open grain wood.

What is the second coat of paint on the Exposed Piping, Hangers, Ductwork, and
Equipment (Galvanized):?
A.
B.
C.
D.

10.

Stairwell 2 room 132.


116, 117, 118, 119, 120, 121, 122, 123, 124, 208, 209, 210, 211, 214 and 132.
104, 107, 108, 109, 110, 111, 112, 113, 114, 115, 201, 205, 206, 207, and 132.
101, 102, 103, 105, 106, 130, 202, 203, 204, 212, 213, 215, 223, 227, and 127.

What is the second coat of paint on the natural finish wood?


A.
B.
C.
D.

9.

First coat stain, second coat sealer, third coat Satin finish varnish.
First coat Vinyl primer-sealer, second coat Multicolored speckled paint.
First coat Vinyl primer-sealer, second coat Latex eggshell or semigloss, third coat
Latex eggshell or semigloss (deep accent colors).
First coat stain, second coat Chemgard Sealer, Guardsman Chemical coatings, I,
third coat Super Chemveer No. 20 Guardsman Chemical Coatings.4 coats.

Alkyd flat enamel.


Vinyl primer-sealer.
Zinc-chromate primer (Federal Spc TTP-57a).
Zinc-dust primer (Federal Spec. TTP641b, Type II).

What is the second coat on the aluminum jackets for the insulated piping?
A.
B.
C.
D.

No paint.
Epoxy paint.
Alkyd flat enamel.
Vinyl primer-sealer.
212
Check Answers

Level 1 Construction Fundamentals Study Guide

Finish and Paint Exercise - Room Finish Schedule


Rm.
No

Room
Name

Floor
Material

N/NE & S/SW

E/SE W all

W /NW W all

Ceiling

Base

Material

Finish

Material

Finish

Material

Finish

Material

Finish

HT

101

Lower Narthex

Carpet #1

Carpet #1

CM U

Paint

CM U

Paint

CM U

Paint

ACT #1

9' -0"

102

Infants

Carpet #2

Carpet #2

CM U

Paint

CM U

Paint

CM U

Paint

ACT #2

8' -0"

103

Crib

Carpet #2

Carpet #2

CM U

Paint

CM U

Paint

CM U

Paint

ACT #2

8' -0"

104

Nursing

Carpet #2

Carpet #2

CM U

Paint

CM U

Paint

CM U

Paint

ACT #2

8' -0"

105

W omen

Vinyl

Vinyl

CM U

Paint

CM U

Paint

CM U

Paint

Gyp Bd

Paint

8' -0"

106

Men

Vinyl

Vinyl

CM U

Paint

CM U

Paint

CM U

Paint

Gyp Bd

Paint

8' -0"

107

Mechanical

Concrete

-------

CM U

Paint

CM U

Paint

CM U

Paint

Exposed

Paint

10'-3"

127

Stair

Carpet #1

Carpet #1

Glass

- - -- -

SP CMU

----

Glass

---

ACT #1

----

132

Stair

Carpet #1

Carpet #1

SF CMU

-----

SF CMU

----

SF CMU

---

ACT #1

8' -0"

201

Narthex A

Carpet #1

Carpet #1

Glass
SF CM U

- -/ - -

SF CMU

----

SF CMU/
W ood

- / Stain

ACT #1

13'-0"

206

Narthex B

Carpet #1

Carpet #1

SF CMU

-----

SF CMU

----

SF CMU

----

ACT #1

13'-0"

Abbreviations
Acoustical Ceiling Tile

ACT

Concrete Masonry Unit

CMU

Gypsum Board

Gyp Bd

Split Face cmu

SF

Specified cmu

SP

Vinyl Composite Tile

VCT

213

Level 1 Construction Fundamentals Study Guide


Finish and Paint Exercise - Painting Specifications
09900 - PAINTING SPECIFICATIONS
PART 1
GENERAL
1.01 WORK INCLUDED
A.
The term paint or painting as used in this section have reference to
sealers, primers, stains, paints, varnishes, and the application of these
materials.
B.
Surface preparation.
C.
Surface finish.
1.02

1.03

PART 3
3.07

RELATED WORK
A.
Division 3 - Concrete.
B.
Section 04300 - Unit Masonry System.
C.
Division 5 - Metals.
D.
Division 6 - Carpentry.
E.
Section 80111 - Standard Steel Doors and Frames.
F.
Section 09260 - Gypsum Board System.
G.
10522 - Fire Extinguisher Cabinets.
H.
Division 15 - Mechanical Equipment, Identification.
I.
Division 16 - Electrical Equipment, Identification.
REFERENCES
A.
ANSI/ASTM D16 - Definitions of terms Relating to Paint, Varnishes,
Lacquer, and Related Products.
EXECUTION
SCHEDULE - EXTERIOR SURFACES
A.
Exterior Metal (Ungalvanized Ferrous):
1.
First Coat:
Zinc-chromate primer (Federal Spec TTP-57a).
2.
Second Coat: Exterior latex enamel (semigloss or gloss).
3.
Both coats in addition to any factory primer.
B.

Exterior Metal (Galvanized):


1.
Treat metal with Galva-prep, as manufactured by Am-chem, Inc.
2.
First Coat:
Zinc-dust primer (Federal Spec. TTP641b, Type II).
3.
Second Coat: Exterior latex enamel (semigloss or gloss).

C.

Exterior Metal (Aluminum):


1.
Treat metal with Galva-prep, as manufactured by Am-chem, Inc.
2.
First Coat:
Zinc-chromate primer (Federal Spec TTP-57a).
3.
Second Coat: Exterior latex enamel (semigloss or gloss).

214

Level 1 Construction Fundamentals Study Guide


Finish and Paint Exercise - Painting Specifications
3.08

SCHEDULE - INTERIOR SURFACES


A.
Interior Gypsum Board (Standard Finish):
1.
First Coat:
Vinyl primer-sealer.
2.
Second Coat: Latex eggshell or semigloss.
3.
Third Coat: Latex eggshell or semigloss (deep accent colors).
B.

Interior Gypsum Board (Special Finish):


1.
First Coat:
Vinyl primer sealer.
2.
Second Coat: Multicolored speckled paint.
3.
Apply per manufacturers instructions.

C.

Interior Block.
1.
First Coat:
Clear Block Sealer.
2.
Spray finish.

D.

Interior Roof Deck (Exposed Deck, Beams, and Joists).


1.
1 coat of spray flat.

E.

Interior Metal (Ungalvanized Ferrous):


1.
Both coast in Addition to any factory primer.
2.
First Coat:
Zinc-chromate primer (Federal Spc TTP-57a) tinted
3.
Second Coat: Alkyd flat enamel.

F.

Interior Metal (Galvanized):


1.
Treat metal with Galva-prep, as manufactured by Am-chem, Inc
2.
First Coat:
Zinc-dust primer (Federal Spec. TTP641b, Type II).
3.
Second Coat: Alkyd flat enamel.

G.

Interior Wood - Natural Finish:


1.
First Coat:
Stain. Use stain filler for open grain wood.
2.
Second Coat: Sealer.
3.
Third Coat: Satin finish varnish.
Or in lieu of the above, Contractor has the option of using:
1.
First Coat: Stain.
Use stain filler for open grain wood.
2.
Second Coat: Chemgard Sealer, Guardsman Chemical Coatings, I
3.
Third Coat: Super Chemveer No. 20 Guardsman Chemical Coatings.

215

Level 1 Construction Fundamentals Study Guide


Finish and Paint Exercise - Painting Specifications
H.

Interior Wood Painted:


1.
First Coat:
Wood primer undercoater.
2.
Second Coat: Semigloss enamel.
3.
Third Coat: Semigloss enamel.

I.

Exposed Piping, Hangers, and Equipment (Ungalvanized):


1.
First Coat:
Zinc-chromate primer (Federal Spc TTP-57a)
2.
Second Coat: Alkyd flat enamel.
3.
Note: Cast iron pipe shall first be throughly cleaned with rags soaked in
mineral spirits to remove oily film, then primed and finished as indicated
above.

J.

Exposed Piping, Hangers, Ductwork, and Equipment (Galvanized):


1.
Treat metal with Galva-prep, as manufactured by Am-chem, Inc
2.
First Coat:
Zinc-dust primer (Federal Spec. TTP641b, Type II).
3.
Second Coat: Alkyd flat enamel.
4.
Note: Use epoxy paint for PVC pipe.

K.

Covered (Insulated) Piping and Ductwork (Unprimed):


1.
First Coat:
Vinyl primer-sealer.
2.
Second Coat: Alkyd flat enamel.
3.
Note: Aluminum jackets for insulated piping shall not be painted

L.

Back Priming (Interior Millwork and Trim):


1.
1 coat of white oil base primer for wood to receive paint finish.
2.
Clear sealer for wood to receive natural finish.
3.
Back prime interior millwork on unexposed areas as specified in Div.6.

M.

Apply special paint finish on gypsum board walls in the following rooms: 101, 102,
103, 105, 106, 130, 202, 203, 204, 212, 213, 215, 223, 227, and 127 (stair 1). See
Item B above.

N.

Exposed piping, hangers, ductwork, and equipment shall be painted the same color
as adjacent structure and deck.
END OF SECTION

216

Level 1 Construction Fundamentals Study Guide


Plumbing Schedule Exercise
1.

The plumbing plans have the abbreviation DWV on them. What does the DWV mean?
A.
B.
C.
D.

2.

The plumbing plans have the abbreviation DS on them. What does DS mean?
A.
B.
C.
D.

3.

Storm Sewer.
Sanitary Sewer.
Domestic Water.
Sprinkler System.

The Site utility plans have the abbreviation I.E. on them. What does I.E. mean?
A.
B.
C.
D.

5.

Drain Spigot.
Down Spout.
Drain System.
Domestic System.

What system is the DS connected to?


A.
B.
C.
D.

4.

Drain Waste and Vent.


Drain, Water and Vent.
Domestic Waste Valve.
Domestic Water Valve

Invert Elevation.
Inside Elevation.
Initial Elevation.
Interior Elevations.

At what point is the I.E. calculate to:


A.
B.
C.
D.

Top inside of the pipe.


Top outside of the pipe.
Bottom inside of the pipe.
Bottom outside of the pipe.

217

Level 1 Construction Fundamentals Study Guide


Plumbing Schedule Exercise
6.

What is the purpose of a water hammer arrestor?


A.
B.
C.
D.

Reduce the pressure in the line.


Reduce the vibration in the line.
Maintain a constant flow in the line.
Maintain a constant pressure in the line.

Given the Plumbing Pipe Size Schedule and the Natatorium Plumbing Plan, Answer the following
questions.
7.

What does the plumbing abbreviation VTR mean?


A.
B.
C.
D.

8.

What system is the VTR connected to?


A.
B.
C.
D.

9.

Storm Sewer.
Sanitary Sewer.
Domestic Water.
Sprinkler System.

What system is the CO connected to?


A.
B.
C.
D.

10.

Vent Thru Roof.


Vent Top Return.
Vertical Top of Roof.
Vertical Transfer Run.

Storm Sewer.
Sanitary Sewer.
Domestic Water.
Sprinkler System.

What is the size of the connection to the HB?


A.
B.
C.
D.

0"
"
3/4"
1"

218

Level 1 Construction Fundamentals Study Guide


Plumbing Schedule Exercise
11.

What is the size of the Domestic hot water connection to the EWC?
A.
B.
C.
D.

12.

What is the size of the waste line connection to the WC-2?

A.
B.
C.
D.
13.

0"
"
3/4"
1"

0"
1"
2"
4"

What is the size of the cold water connection to the LAV-1?


A.
B.
C.
D.

0"
"
3/4"
1-1/2"

Check Answers
Plumbing Exercise - Pipe Size Schedule

FIXTURE

COLD

HOT

W ASTE

RE
VENT

MAIN
VENT

TRAP
SIZE

1"

---

4"

2"

3"

4"

FLUSH
VALVE

URINAL

3/4"

---

2"

2"

2"

2"

W ALL MTD.

LAVATORY

1/2"

1/2"

1-1/2"

1-1/2"

1-1/2"

1-1/4"

SINK

1/2"

1/2"

1-1/2"

1-1/2"

2"

1-1/2"

ELECTRIC W ATER COOLER

1/2"

---

1-1/4"

1-1/4"

---

1-1/4"

HOSE BIB

3/4"

---

---

---

---

---

NON-FREEZE

FLOOR DRAIN

---

---

3"

2"

3"

3"

OR A NOTED

SERVICE SINK

3/4"

3/4"

3"

2"

2"

3"

W ATER CLOSET

219

REMARKS

Or as Noted

Level 1 Construction Fundamentals Study Guide


Plumbing Schedule Exercise - Natatorium Plans

220

Level 1 Construction Fundamentals Study Guide


Mechanical Equipment Exercise
Using the Mechanical Equipment tables provided, answer the following questions.
1.

What does the mechanical abbreviation FT mean?


A.
B.
C.
D.

2.

What are the Depth and Height of FT-4?


A.
B.
C.
D.

3.

Toilet Room 105.


Toilet Room 125.
Toilet Room 209.
Prayer Room 205.

Where is AHU-1 located?


A.
B.
C.
D.

5.

4" D, 5" Height.


5" D, 12" Height.
4" D, 14" Height.
4" D, 12" Height.

What room does EF -3 service?


A.
B.
C.
D.

4.

Fan Tube.
Fin Tube.
Fire Tube.
Furnace Tube.

Narthex 201.
Prayer Room 205.
Sanctuary Room 202.
Mechanical Room 107.

Where is CC -1 located?
A.
B.
C.
D.

Inside B-1.
Inside AHU-1.
Inside CUH-1.
Inside RTU-1.

221

Level 1 Construction Fundamentals Study Guide


Mechanical Equipment Exercise
6.

What service is P-3 connected to?


A.
B.
C.
D.

7.

What does the mechanical abbreviation CUH mean?


A.
B.
C.
D.

8.

Narthex 201.
Lower Level.
Sanctuary 202.
Prayer Room 205.

What service is L-2 connected to?


A.
B.
C.
D.

10.

Cabinet Unit Heater.


Chiller Unit Handler.
Cooling Unit Handler.
Convector Unit Heater.

What area does RTU-3 service?


A.
C.
D.
D.

9.

B-1
HC-1.
Heating Loop.
Chilled Water.

AHU-1 INTAKE.
EF-3 EXHAUST.
AHU-1 EXHAUST.
CEILING SUPPLY DIFFUSER.

What are the length and height in inches of L-1?


A.
B.
C.
D.

16" L and 16" H.


24" L and 18" H.
42" L and 84" H.
60" L and 84" H.

Check Answers

222

Level 1 Construction Fundamentals Study Guide


Mechanical Equipment Exercise - Fan and Fin Tube Schedules
FAN SCHEDULE
Mark

Service

Model

CFM

S.P.

HP/AMPS.

RPM

T.S./O.V.

W HEEL DIA.

SONES

VOLTAGE

EF-1

TOILET
105,106

DB-8

825

1/4

1000

2100

----

9.2

120v-1PH

EF-2

TOILET
125

360

125

1/8"

1.2

1200

0000

0000

120V-1PH

EF-3

PRAYER
205

GN-720

500

1/4"

1/4

1325

2200

0000

3.5

120V-1PH

EF-4

TOILET
208,209

GN-820

600

1/4"

1/4

700

1600

----

2.3

120v-1PH

1 Based on Cook

2 Based on Broan, Provide with wall cap

FIN TUBE SCHEDULE


MARK

LOCATION

ELEMENT

BTH/FT

FIN LENGTH

GPM

ROW S

ENCLOSURE
STYLE

D.

HT.

FT-1

SEE PLANS

3/4"C.-2 3/4"X3-48

720

SEE PLAN

SEE PLAN

FS-210

4"

14"

FT-2

SEE PLANS

3/4"C-2 3/4"X3-48

720

SEE PLAN

SEE PLAN

FS-210

4"

14"

FT-3

SEE PLANS

1"C.-3 1/4" -48

750

SEE PLAN

SEE PLAN

AA-1r2

4"

5"

FT-4

SEE PLANS

3/4"C.-2 3/4" X 4 1/4"

1050

SEE PLAN

SEE PLAN

DV4

5"

12"

1 BASED ON VULCAN, 180 * EWT, 160* LWT, 65* EAT


2 MOUNT INVERT AT 7'-6: A.F.F.
3 PROVIDE W/ 14GA PIPE ENCLOSURE AND PRESSURE CLIP FASTENERS AT LOCATIONS SHOWN ON PLANS

223

Level 1 Construction Fundamentals Study Guide


Mechanical Equipment Exercise - Convector, Unit Heaters and Cabinet Unit Heater Schedules
CONVECTOR SCHEDULE
MARK

C-1

MODEL

FW G-A-24

LOCATON

SEE PLANS

MBH

2.1

GPM

CABINET DIMENSIONS

1.0

24"

24"

4"

CONTROL

REMARKS

REC
4"

DAMPER

1 BASED ON VULCAN, 180* EWT, 160* LWT, 65* EAT

UNIT HEATER SCHEDULE


MARK

SERVICE

MODEL

CFM

MBH

GPM

LAT

RPM

HP

UH-1

MECH RM 107

HV-24

350

15.6

2.0

98

1350

1/20

REMARKS

1 BASED ON VULCAN, 180* EWT, 160* LWT, 65* EAT

CABINET UNIT HEATER SCHEDULE


MARK

CUH-1

MODEL

RW I-1130-06

CFM

630

MBH

38.4

GPM

3.0

LAT

125

CABINET DIMENSIONS
L

REC.

59"

25'

9 "

6"

1 BASED ON VULCAN, 180* EWT, 160* LWT, 65* EAT

224

RPM

HP

REMARKS

1050

1/10

Level 1 Construction Fundamentals Study Guide


Mechanical Equipment Exercise - Air Handling, Cooling Coil and Heating Coil Schedules
AIR HANDLING UNIT SCHEDULE
MARK

AHU-1

LOCATION

SERVICE

MECH RM 107

MODEL

LOW ER LEVEL

CFM

LML-122

10,100

S.P.
EXT.

TOTAL

1 1/4"

2 1/4"

O.V.

RPM

H.P.

REMARKS

1417

1291

1,2

1 BASED ON McQUAY
2 PROVIDE 4" HIGH RAIL UNDER UNIT

COOLING COIL SCHEDULE


MK

CC-1

Location

AHU-1

CFM

10,100

MBH
TOT/
SEN
340/282

CHILLED W ATER

AIR
P.D.

GPM

LW T

EWT

78

55*

458

.56

W ATER
P.D.

EDB

15.9

80*

EW B

65*

LDB

55*

LW B

54*

COIL
ROW S

FPF

F.V.

144

478

1 BASED ON MCQUAY

HEATING COIL SCHEDULE


MK

HC-1

Location

AHU-1

CFM

10,100

MBH

403

GPM

39

W ATER
P.D.
11.7

EW T

140*

LW T

119*

1 BASED ON McQUAY
2 MODEL #5WH1102C

225

AIR P.D.

.72

EAT

55*

LAT

90*

COIL
TYPE

ROW S

FPF

F.V.

132

819

Level 1 Construction Fundamentals Study Guide


Mechanical Equipment Exercise - Boiler and Pump Schedules
BOILER SCHEDULE
MARK

B-1

MODEL

CHN0990

MBH
INPUT

OUTPUT

990

831

RECOVERY
GPH

SUPPLY TEMP.

FULL SIZE

REMARKS

00

180*

10"

1,2,3

1 BASED ON LOCHINAR COPPER - FIN II


2 PROVIDE POWERED VENT CAP FOR SIDEWALL VENT & SEALED COMBUSTION
3 PROVIDE TEKMAR #254 4-STAGE BOILER CONTROL, INSTALLED & WIRED BY T.C.C.

PUMP SCHEDULE
MARK

SERVICE

MODEL

GPM

FT. HEAD

RPM

IMPELLER DIA.

HP

VOLTAGE

REMARKS

P-1

HEATING LOOP

1510-2 "AB

65

45'

1750

7"

480V-3PH

P-2

HEATING LOOP

1510-2 "AB

65

45'

1750

7"

480V-3PH

P-3

HC-1

60-2"A

39

30'

1750

6 "

480V-3PH

P-4

CHILLED W ATER

1510-2 "AB

78

45'

1750

7"

480V-3PH

1 BASED ON BELL & GOSSETT

226

Level 1 Construction Fundamentals Study Guide


Mechanical Equipment Exercise - Gas Fired Package Rooftop Unit Schedules

GAS FIRED PACKAGE ROOFTOP UNIT SCHEDULE


MK

LOCATION

MODEL

CFM

EXT
S.P.

SAF
HP

SAF
RPM

VOLTAGE

HTG. MBH
IN/OUT

COOLING
TOT/SEN

COM PRESSORS
Notes
KW

RLA

LRA

RTU-1

SANC. 202

558DE240

7500

1"

1210

480v-3PH

270/216

235/173

20.6

31.4

223

1,2,3

RTU-2

SANC. 202

558DE240

7500

1"

1210

480v-3PH

270/216

235/173

20.6

31.4

223

1,2,3

RTU-3

Narthex 201

558DE090

3000

3/4"

1470

480V-3PH

180/144

73/84

7.69

6.2

37.7

1,3

1 BASED ON BRYANT
2 PROVIDE W/INSULATED 24" HIGH ROOF CURB FOR SIDEWALL SUPPLY & RETURN
3 PROVIDE 2/100% ECONOMIZER

227

Level 1 Construction Fundamentals Study Guide


Mechanical Equipment Exercise - Louver, Diffuser, Register and Grille Schedules
LOUVER SCHEDULE
MARK

SERVICE

DIMENSIONS
LENGTH

HEIGHT

CFM

FREE AREA
SQ. FT.

S.P.
IN W .G.

AIR
VELOCITY
FPM

Notes

L-1

AHU -1 INTAKE

60"

84"

10,100

19.85

.05

510

L-2

AHU -1 EXHAUST

42'

84"

9,100

13.69

.07

660

L-3

EF - 3 EXHAUST

16"

16"

500

0.81

.06

620

L-4

EF -4 EXHAUST

24"

18"

600

1.11

.05

540

1 Based on Rusken
DIFFUSER, REGISTER AND GRILLE SCHEDULE
MARK

SERVICE

MODEL

VOLUME DAMPER

FINISH

REMARKS

D -1

CEILING SUPPLY DIFFUSER

TDC -3

-------

OFF-W HITE

1,2

D -2

CEILING SUPPLY DIFFUSER

TDC -1

-------

OFF-W HITE

D -3

FLOOR SUPPLY DIFFUSER

CT - PP - 0

AG - 35

CLEAR ANODIZED

1, 3

R -1

SIDEW ALL SUPPLY REGISTER

1700

AG - 15

OFF-W HITE

R -2

CEILING EXHAUST REGISTER

350FL

AG - 15

OFF-W HITE

G -1

CEILING RETURN GRILLE

50F

-------

OFF-W HITE

228

Level 1 Construction Fundamentals Study Guide


Electrical Exercise
Using the Electrical Plans, Schedules provided below and the Mechanical Equipment Schedules
previously attached, answer the following questions.
1.

Using the One-line Diagram, what are the electrical power requirements to the Chiller?
A.
B.
C.
D.

2.

Using the One-line Diagram, what are the electrical power requirements from the Pad
Mounted Transformer to the Main Switchboard?
A.
B.
C.
D.

3.

Panel PP, Panel DP.


Panel PP, Panel DP and the Existing Service Panel.
Panel DM, Panel E, Panel F, Panel C and Panel D
Panel PP, Panel DP, Existing Service Panel, and the Chiller.

Using the One-line Diagram, what are the Feeders on the Distribution Panel going to?
A.
B.
C.
D.

5.

3 #4, 1"C
3 #4/0, 2" C
4 #1/0, 2-1/2" C
(4) #350 MCM & #2 Ground, 3" PVC

Using the One-line Diagram, what are the Feeders on the Main Switch Board going to?
A.
B.
C.
D.

4.

3 #4, 1"C
3 #4/0, 2" C
4 #1/0, 2-1/2" C
(4) #350 MCM & #2 Ground, 3" PVC

Panel PP, Panel DP.


Panel DM, Panel E, Panel F, Panel C and Panel D
Panel PP, Panel DP, Existing Service Panel, and the Chiller.
Panel DM, Panel E, Panel F, Panel C, Panel D, Existing Service Panel.

Using the One-line Diagram, what phase motor is required for the Chiller?
A.
B.
C.
D.

1
3
4
17
229

Level 1 Construction Fundamentals Study Guide


Electrical Exercise
6.

Using the Diagrams, you will see the symbol and the abbreviations EF-4 and 17, F.
What phase motor is required?
A.
B.
C.
D.

7.

What does the abbreviation 17, F refer to?


A.
B.
C.
D.

8.

RTU-3, 201.
Outlets Room 201.
Outlets in Room 206.
EF-3, Outlets in Room 205.

What is the horsepower for UH-1?


A.
B.
C.
D.

10.

Fan #17.
EF #17 on Panel F.
Circuit # 17 on Panel F.
Panel # 17 on Circuit F.

Which one of the following electrical receptacles is attached to 20, F?


A.
B.
C.
D.

9.

1
3
4
17

1/10
1/20
1.0
7-1/2

What is the voltage requirement for RTU-2?


A.
B.
C.
D.

120
208
240
480

230

Level 1 Construction Fundamentals Study Guide


Electrical Exercise
11.

What phase motor is required for P-2?


A.
B.
C.
D.

12.

What is the horse power required for P-3?


A.
B.
C.
D.

13.

1
3
20
50.

What is the mounting height of the outlet near the Narthex and on the south wall referred to
as 18, F?
A.
B.
C.
D.

15.

1/10
1.0
2.0
7-1/2

What size breaker in amperes is required for RTU-1?


A.
B.
C.
D.

14.

1
2
3
480

16 inches.
40 inches.
42 inches.
80 inches.

What is the mounting height of the Fire Alarm Smoke detector?


A.
B.
C.
D.

16 inches.
40 inches.
42 inches.
80 inches.

231

Level 1 Construction Fundamentals Study Guide


Electrical Exercise
16.

Which of the following pieces of electrical equipment has a disconnect switch?


A.
B.
C
D.

17.

What does the abbreviation GFI, WP mean?


A.
B.
C.
D.

18.

Eye Wash Container.


Electric Water Cooler.
Exhaust Waste Convenience.
Equalization Water Container.

Where are the lighting fixtures C 4 located?


A.
B.
C.
D.

20.

Ground Fixture Inside and Waterproof.


Ground Fault Interrupter and Waterproof.
Ground Fault Interrupter and Weatherproof.
Ground Fluorescent Inside and Weatherproof.

What does the abbreviation EWC mean?


A.
B.
C.
D.

19.

EF-3
CUH
EWC
RTU-2.

Narthex.
Exterior.
Bathrooms.
Stairs and Entrances.

Which Fixture types are attached to a Photo-cell?


A.
B.
C.
D.

A1 and EM1.
B2. and K.
E and EM1.
M and N.

232

Level 1 Construction Fundamentals Study Guide


Electrical Exercise
21.

What type of light is a B2 light?


A.
B.
C.
D.

22.

How are the EM-2 lights mounted?


A.
B.
C.
D.

23.

1
2
3
4

What is the electrical symbol


A.
B.
C.
D.

25.

Ceiling.
Surface.
Pendant.
Recessed.

How many lamp(s) are in fixture A2?


A.
B.
C.
D.

24.

2' x 2' Fluorescent Troffer with Prismatic lens.


2' x 4' Fluorescent Troffer with Prismatic lens.
2' x 4' Fluorescent Troffer with Prismatic lens with 3 lamps.
2' x 2' Fluorescent Troffer with Parabolic lens and 30K lamps.

with an E inside the circle mean?

Exit Sign.
Existing Sign.
Electrical Fixture.
Emergency Fixture.

Which of the following wire sizes has the greatest diameter?


A.
B.
C.
D.

#0
#1
#10
#14.

Check Answers

233

Level 1 Construction Fundamentals Study Guide


Electrical Exercise - Electrical Symbols Legend and Mounting Heights
ELECTRICAL SYM BOL LEGEND
SYM BOL

S
S3
D
O
O GFI
O WP
O
.

,,

J
1
2
3
4
5

e
|--------|
(
EM
ETR
ETBR

DESCRIPTION

SINGLE POLE SWITCH


THREE-WAY SWITCH
DIMMER SWITCH
CONVENIENCE OUTLET
CONVENIENCE OUTLET WITH GFI
WEATHERPROOF OUTLET
SAFETY CONVENIENCE OUTLET
DISCONNECT SWITCH
SINGLE PHASE MOTOR
3-PHASE MOTOR
BRANCH CIRCUIT PANEL BOARD
TELEPHONE OUTLET
DATA OUTLET
MAGNETIC DOOR HOLDER
JUNCTION BOX
FIRE ALARM PULL STATION
FIRE ALARM AUDIO/VISUAL DEVICE
FIRE ALARM VISUAL DEVICE
FIRE ALARM SMOKE DETECTOR
FIRE ALARM DUCT SMOKE DETECTOR
RECESSED INCAND. OR FLUORESCENT
HID FIXTURE, SURFACE OR PENDANT
INCAND. FIXTURE, SURFACE OR PENDANT
EXIT SIGN
RECESSED FLUORESCENT TROFFER
STRIP FLUORESCENT FIXTURE
SURFACE FLUORESCENT FIXTURE
BATTERY EMERGENCY FIXTURE
EMERGENCY FIXTURE
EXISTING TO REMAIN
EXISTING TO BE REMOVED

Note: All Mounting Heights are to Bottom.

234

M OUNTING HEIGHT

40"
40"
40"
16" OR AS NOTED
16" OR AS NOTED
16" OR AS NOTED
16" OR AS NOTED
------------16" OR AS NOTED
16" OR AS NOTED
------40"
80"
80"
----------------------------------------

Level 1 Construction Fundamentals Study Guide


Electrical Exercise - One Line Diagram

235

Level 1 Construction Fundamentals Study Guide


Electrical Exercise - Power Plan Upper Level

236

Level 1 Construction Fundamentals Study Guide


Electrical Exercise - Panel Board Load Sheet
PANEL: F

LOCATION

MOUNTING: RECESSED

MAINS: 3P100A MLD

PANEL LOCATION: 209

VOLTAGE: 120/480 -3

FEEDER SIZE: 4#3, 1-1/4 C

FEEDER FROM: DP

LOAD IN VOLT AMPS


LIGHT

RTU-1, 202

OUTLET

MOTOR
480

LIGHTING, 209
RTU-2, 202

480

BKR

CKT

CKT

BKR
P

AMP

LOAD IN VOLT AMPS


LIGHT

OUTLET

LOCATION

AMP

NO

NO

MOTOR

50

LIGHTING, 206

P. CELL, 201A, B, C

20

OUTLET 201, P. CEL

50

WP GFI, 202C

10

OUTLET 201, WP GFI

EF -3, 205

20

11

12

WP GFI ROOF

EWC

20

13

14

OUTLET R 206, 202B

CUH

20

15

16

OUTLET ROOM 209

EF-4 208, 209

20

17

18

OUTLETS ROOM 206

OUTLETS 201

20

19

20

21

22

23

24

25

26

27

28

29

30

237

70

480

RTU-3

Level 1 Construction Fundamentals Study Guide


Electrical Exercise - Lighting Plan Upper Level

238

Level 1 Construction Fundamentals Study Guide


Electrical Exercise - Lighting Fixture Legend
DESCRIPTION

MOUNTING

LAMPS

MANUFACTURER

A1

2' X 4' FLUORESCENT TOFFER


W / PRISMATIC LENS

RECESSED

(2) F40CW /RS/W M

LITHONIA #2SPG240

A2

2' x 4' SIMILAR TO A1


EXCEPT W / 3 LAMPS

RECESSED

(3) F40CW /RS/W M

LITHONIA #2SPG340

B1

2' X 2' FLUORESCENT


TROFFER W /PRISMATIC LEN

RECESSED

(2) FB40CW /6

LITHONIA #2SPG2U40

B2

SIMILAR TO B1 EXCEPT W /
PARABOLIC LENS & 30K
LAMPS

RECESSED

(2) F40SPX30/U/6

LITHONIA #2PM 3

6, 4

C1

INCANDESCENT DOW NLIGHT

RECESSED

(1)15ORFL120W M

KURT VERSEN #150

C2

SIMILAR TO C1 EXCEPT W /
LAMP

RECESSED

(1)300RFL

KURT VERSEN #300

C3

SIMILAR TO C1 EXCEPTW /
LAMP

RECESSED

(1)Q500 T4

KURT VERSEN #500

C4

SIMILAR TO C1 EXCEPT W /
FLUORESCENT LAM P

RECESSED

(2)PLC26W /27

KURT VERSEN #120

C5

SIMILAR TO C1 EXCEPT
W ALLWASH

RECESSED

(2)PLC26W /27

KURT VERSEN #120

PENDANT INCANDESCENT
FIXTURE, ACRYLIC DIFFUSER

PENDANT

(8)N150

VISA #CB3616

13

INCANDESCENT UP/DOW N
LIGHT

W ALL PER
DETAIL

(1)100A21/99

MANNING #DS89

10

HID DOW NLIGHT

RECESSED

(1)MS100BU/BDW

HALO #M6024

HID W ELL UPLIGHT

W ELL IN
GROUND

(1)MS100BU/BDW

HYDREL #9305

EM
1

EMERGENCY BATTERY
FIXTURE

SURFACE

PER UNIT

LITHONIA #ELM-H

EM
2

SAME AS EM1 EXCEPT


CEILING M OUNTED

CEILING

PER UNIT

LITHONIA #ELM-H

239

12

Level 1 Construction Fundamentals Study Guide


Electrical Exercise - Lighting Fixture Notes
1.

ALL BALLAST SHALL BE ENERGY SAVING TYPE, FLUORESCENT (T12) BALLAST.

2.

HID LAMPS BY VENTURE, PL LAMPS BY OSRAM AND ALL OTHER LAMPS BY G.E. W ITH
EQUAL BY SYLVANIA.

3.

EXIT SIGNS ARE BATTERY POW ERED LED TYPE.

4.

PARTIALLY SHADED FIXTURES SHALL INCLUDE 1/3 OR OF LAMPS ON BATTERY BACKUP


EMERGENCY PACK SUCH FIXTURES ARE NORMALLY MANUALLY CONTROLLED AND
AUTOMATICALLY LIGHT DURING LOSS OF POW ER.

5.

EQUAL FIXTURES BY LITHONIA, DAYBRITE, METALUX, HALO, AND CAPRI, ARE APPROVED.
FIXTURE CUTS MUST BE SUBM ITTED FOR SPECIFIC FIXTURES NOT LISTED ABOVE.

6.

NOT THE USE OF 30K LAMPS FOR THE PARABOLIC 2 X 2 FIXTURES.

7.

FIXTURES TYPE E1' & E2' SHALL MATCH D, INCLUDING THE BRASS RING AROUND THE
UPPER PART OF THE FIXTURE. FIXTURE E2' IS ONLY 1/4 OF A SPHERE FOR CORNER
MOUNTING, ACRYLIC OR M ATCHING PAINT FINISH. FIXTURE TO SET OUT FROM W ALL.

8.

OF THE 18 TYPE F FIXTURES, PROVIDING AT LEAST THREE (3) FIXTURES OF EACH BEAM
TYPE CL, VNSP, NSP, MFL, & W FL. INCLUDE THREE (3) SETS OF SPARE LENS #S4PAR-LS.
EQUAL FIXTURES BY STRAND SHALL BE APPROVED EQUALS. SEE ELEC. & ARCH DETAILS
FOR INSTALLATION.

9.

FIXTURE G TO HAVE CLEAR LENS TO PREVENT COLLECTION OF DUST IN REFLECTOR.


PROVIDE PHOTOMETRICS OF SIDE, FRONT & REAR W ITH FIXTURE INVERTED PER DETAIL #7
ON DW G. E2.

10.

UP/DOW N FIXTURE K TO MOUNT DIRECTLY TO W ALL PER DETAIL #1 ON DW G. E2.

11.

FLOOD LIGHTING FIXTURE P COLOR TO MATCH ROOF FINISH.

12.

FIXTURE MUST BE IC RATED.

13.

D FIXTURE BY VISA W ITH W HITE PENDANT, LBZ RING & NO FINAL. D FIXTURE BY
MANNING W ITH W HITE PENDANT DB RING & NO FINAL.

240

You might also like