Economic Operation of Power Systems: Dr. Ahmed Mohamed Azmy
Economic Operation of Power Systems: Dr. Ahmed Mohamed Azmy
OF POWER SYSTEMS
Dr. Ahmed Mohamed Azmy
Department of Electrical Power and Machine Engineering
Tanta University - Egypt
Faculty of
Engineering
Tanta University
System Constraints
The technical limitations that have not to be violated
under any condition
The violation of these constraints affects the power
quality and the general operation of the power
system and causes stability problems
The constraints can be divided into two groups:
equality constraints and inequality constraints
Inequality constraints can have a hard nature,
where the variables are definite and specific like the
tap-changing transformer, or a soft nature, where
the variables are smoothly varied within a specific
range like the nodal voltages
System Constraints
Constraints
Equality constraints
Inequality constraints
hard nature
The variables are
definite and specific
like the tap-changing
transformer
soft nature
The variables are
smoothly varied within
a specific range like
the nodal voltages
System Constraints
Equality Constraints
The main equality constraints are the basic load flow
equations that establish the flow balance equations
For example, the equality constrains according to
Newton-Raphson Method are
n
Pi Vi V j y ij cos( i - j - ij )
j1
n
Q i Vi Vj y ij sin( i - j - ij )
j1
System Constraints
Inequality Constraints
Generator constraints
The thermal stability of generators requires that the
total VA "Sg" loading of any generator has not to
exceed a certain maximum value Sg-max:
System Constraints
Inequality Constraints
Generator constraints
The upper limit of the active power Pmax is
constrained by the thermal consideration
The lower limit Pmin is constrained by the flame
instability of the boiler
Consequently, the generated power from any unit
"Pg" has to be kept within the limits:
Pmin Pg Pmax
System Constraints
Inequality Constraints
Generator constraints
There are upper and lower limits for the reactive
power of the generator
These limitations are defined by the overheating of
the rotor for the upper limit and the stability limit of
the machine for the lower limit
Q min Qg Qmax
System Constraints
Inequality Constraints
Voltage constraints
Both the magnitudes and angles of node voltages
have to be controlled in order to keep them within
acceptable limits
The power quality necessitates that the voltage
magnitudes at load terminals are kept within
specific limits or else the equipments will not
operate satisfactorily
The regulation of the voltage starts from the
generators (exciters) to reduce the cost of extra
voltage regulating devices
System Constraints
Inequality Constraints
Voltage constraints
The upper limit of phase angles is defined
regarding the transient stability of power systems
On the other hand, the lower limit of the angles is
defined taking into account achieving an efficient
utilization of transmission facility
Typical operating angle of transmission line lies
between 30 - 45
System Constraints
Inequality Constraints
Voltage constraints
Vmin Vn Vmax
min n max
where: is the magnitude of node angle with an
angle of dn at node n
System Constraints
Inequality Constraints
Running spare capacity constraints
To ensure the existence of enough spinning reserve
to overcome any emergency situation
The generation should guarantee a minimum spare
capacity in addition to load demand and power losses
Pg > PLoad + Ploss
This difference, i.e. spare capacity, is defined
according to economic issues and technical aspects
like the ramping rates of the generators
System Constraints
Inequality Constraints
Transmission line constraints
There is a thermal capability of each transmission
line that defines the allowed flow of active and
reactive power
The transmitted power is limited as follows
System Constraints
Inequality Constraints
Network security constraints
Violation of constrains can take place subsequent to
abnormal conditions like a line outage, either
scheduled or forced, which affects the security of the
network
Sometimes a so called (x-1 study) is performed to
examine the reliability and security of the system
The x-1 study means that the network is studied with
outage of one branch at a time
System Constraints
Inequality Constraints
Transformer tap settings
Sometimes, there is a possibility to change the
voltage in steps, i.e. to chose between different
values rather than varying the voltage smoothly
0 t t max
For auto-transformers, tmax can be unity
System Constraints
Inequality Constraints
Transformer tap settings
Phase shift-ing transformers have phase shift limits
min max
input-output curve
Input fuel (Btu/h)
Pmin
Pmax
Output power (MW)
Minimum
heat rate
Pmin
Pmax
Output power (MW)
(Btu/MWh)
Example
The input fuel in (Btu/h) for a power plant with
minimum and maximum power of 10 and 100 MW
respectively is given by:
F=(40+4*P + 0.012*P2)*106
where P is the generated power in (MW). Plot the
input-output curve of the plant. Calculate the heat
rate and plot its curve against the output power.
Assuming a fuel cost of 0.12*10-6 $/Btu, calculate
the incremental fuel cost in $/MWh and plot its
curve against the output power.
P (MW)
10
20
30
70
80
90
100
0.73 0.76
40
70
100
40
70
100
40
70
100
F1
F2
Fn
P1
1
2
P2
.
.
.
PD
Pn
n
n
n
Min FT =
Fi
i 1
Subject to
PD Pi
i 1
Pmin,i Pi Pmax,i
n
Min FT =
Fi
i 1
PD Pi
Subject to
i 1
Pmin,i Pi Pmax,i
PD = P 1 + P 2
FT = F1 + F2
FT = F1 + F2
dF1
dP1
F2
P1
dF1
dP1
dF2 P2
dP2 P1
PD = P 1 + P 2
P2
P1
P2
P1
dF1
dP1
dF2
dP2
dF2
dP2
P2
P1
...
dFn
dPn
P2
P1
P2
P1
Condition of
optimal operation
dFi
The term
represents the incremental production
dPi cost of the ith plant in $/MWh
All generators have to operate at the same
incremental cost of production to achieve an
economic operation
B1+21P1=b2+22P2=...=bn+2nPn=
Thus, the optimal generated power from each unit is
bi
Pi
2 i
i=1,n
1 2 n
PD
...
2 1
2 2
2 n
...
2 1
2 2
2 n
1
1
1 b1 b2
bn
P D
...
...
2 n 21 2 2
2 n
21 2 2
n
bi
PD
i 1 2 i
n 1
i 1 2 i