Design and Construction of Geocell Mattress As Embankment Foundation
Design and Construction of Geocell Mattress As Embankment Foundation
Design and Construction of Geocell Mattress As Embankment Foundation
SYNOPSIS: This paper describes the use of a high strength Geocell mattress as a new solution to
the problem of the construction of embankments on soft foundations.
The paper deals in detail with the design of the Geocell mattress to support and distribute the
imposed loading onto soft foundation. It considers the plastic condition of the soft clay to
determine the factor of safety against foundation failure.
Two case studies will be examined to illustrate the construction techniques. Monitoring of
settlement during construction of the Geocell and during embankment filling is compared with
predicted values.
This ther,efore pushed the realignment to the
north into an area of marsh which once formed
the southern part of the Dougalston Loch which
had been drained many years before. This area
was also very heavily wooded and to achieve the
required vertical alignment and embankment, of
some 4.5m in height, was required to be
constructed across this marshland.
INTRODUCTION
The A807 Auchenhowie Road runs to the north of
the City of Glasgow, Strathclyde, Scotland and
follows a very torturous route with some very
narrow right angled bends.
The general poor alignment and the sub standard
condition of the road has contributed to a high
accident record, thus the local Highway
Authority embarked on a capital works scheme to
re-align the road along a new route (Fig 1).
SITE INVESTIGATION
scale 1-10.000
Figure 1
627
Figure 2
Bore hole number 101 was sunk into the bank of
the loch and penetrated 2.2m of firm to stiff
friable reddish brown very sandy clay underlain
by 1.35m of dense to very dense, very clayey
sand and gravel over decomposed mudstone.
Laboratory Results
Due t6 the poor nature of the underlying soils
many undisturbed samples proved unsuitable for
testing.
Where triaxial testing was possible, values of
apparent cohesion of between 12 and 19 kN/sq m
were recorded.
105
.,..,,.o.:D.
0.80-M0~5)
1.10 J1
0.70 :B1
1.0.5- 1. (2)
1-4,-1.,cl TJ1
"'
"'
1.80- 2.25 V1
....
Ii
~,,1
..
4..25-455 (!10)~1
I
Figure 3
628
0.4 m thick
1.50 m thick
Cost Comparisons
2.50 m thick
EMBANKMENT FOUNDATIONS
Substituting these soil strengths into
Terzaghi's equation:
To ta 1
cost
Quantity
cu m
Rate
1840
1. 00
1840.00
21460
21460
0.50
3.00
10730.00
64380.00
21460
3.50
75110.00
TOTAL =152,060.00
Construction of Geocell mattress
qu
= CU X
Nc +
taking D = 0, Nq
following value
~ X
0, Nc
Nq +
(~ X
B/2)
X N~
Quantity
Provide, assemble
and infill Geocell
Free draining
infill
6132 sq m 11.00
67452.00
6132 cum
49056.00
Rate
Total
cost
8.00
TOTAL = 116,508.00
Less cost of
10.m of
embankment
6132 cu m 2.00
Therefore effective
cost of Geocell
12264.00
104,244.00
DESIGN CONSIDERATIONS
A number of design alternatives were looked at
for the embankment, although only two are
considered further by the author.
(a) Removal of the soft 1 ayer of material and
replacing with suitable rock fill.
This method would have involved a
considerable increase in traffic on and off
the site. No rock cut was locally
available on the site so all rock fill
would have to be imported.
Item
629
DESIGN PHILOSOPHY
A Geocell mattress is a very stiff rigid
foundation mattress designed to support an
embankment over very soft ground. It is
generally installed at existing ground level
and with no soil strip (Fig 4).
Figure 4
The mattress is constructed from high strength
Tensar geogrids to form a cellular construction.
Cu
4.0 m
15.0 kN/sq m
4.2 m
27.4 m
7.3mwide
carriageway
~-------------------
--=---/--- ------------------Embankment
toe
Figure 5
l.Omcoll,
0.5mcells
630
CONSTRUCTION
The Geocell foundation mattress was constructed
insitu during January and February 1986. The
dense vegetation of shrubs and trees was
removed in order to gain access to the site.
An island across the line of the mattress was
partially levelled. Other than this no site
preparation was required. The site was
waterlogged and under standing water during the
period of construction.
Figure 7
The infill material is not compacted and slight
overfilling compensates for any slight
settlement and also protects the top of the
diaphragms from damage.
Figure 6
Figure 8
~1
Figure 9
SETTLEMENT
Using the information from the site
investigation, the overall settlement of the
completed embankment was expected to be in the
order of 175mm over 1 year. The expected
settlement during the 3 month construction
period was expected to be 140mm.
Tubular settlement pins, welded to .metal base
plates, were placed onto the top of the
completed Geocell base grid and supported by
the infill material of the embankment. They
were levelled every week as infilling and
embankment construction progressed and the
settlement recorded and plotted on a graph. An
average initial settlement of approximately
90mm was recorded after the embankment was
complete and before carriageway construction
was started.
The settlement was noted to be even across the
width of the embankment. No differential
settlement has been monitored along the length
of the completed road.
CONCLUSIONS
1. By using the Geocell mattress there was no
need to remove large quantities of
unsuitable material from the site with the
resulting problems of handling and disposal.
There was also no appreciable increase in
the off site traffic and environmental
nuisance.
2. The factor of safety against foundation
failure was significantly increased and
embankment constuction continued rapidly
without having to incorporate rest periods
into the construction programme to allow
excess pore water pressures to dissipate.
APPENDIX 1
In this design, reference is made to
"Engineering Plasticity" by W Johnson and P B
Mellor, (Chapter 12.5: pages 392 to 401).
This considers the plastic failure of material
compressed between two rough, rigid parallel
platens being brought together. The platen
widths exceed the soft material layer thickness
(Fig 10).
The Geocell mattress represents the upper
platen with the weathered mudstone representing
the lower.
Figure 10
DESIGN PARAMETERS
Weight of embankment
Embankment width
Depth of soft material
Strength of soft layer
4.2m
27.4m
d
4.0m
Cu = 15.0 kN/sq m
1
Cllt offload9271cN/m
..
~,:
t ._....ar--..
12
d Dlplllareolt-.
14
18
11
cu-81111........
PNamlll..-..anft1191._
..J-2.8m--tio---- 5.8m---+---S.Om--l
Figure 12
Figure 11
Calculation of the average base pressure over
the rigid zone:AX
1.966
1. 707
1.259
X = 4.932
yrad.
0.654
0.393
0.131
h = 0.4m
yxAX
1.286
0.671
0.165
%YXAX 2.122
p = 6. 0 Cu + 2.0 Cu = 8. 0 Cu .
Y 2X AX
+ h
J !;
+
4.57 CU
190.40
9.67 .Cu .
W((3.2x7.15)+(1.0x13.6)+(0.5x3.2x4.8))
X 20.0 = 883.2
Surcharge 3.65 x 12.0 = 43.8
Therefore Total Imposed Load= 927.0 kN/m
Therefore factor of safety against foundation
failure:F.o.S = 1.58
Consider load within the diaphragms of the
Geocell.
For the factor of safety reduced to 1.0. at the
centre of the embankment, the equivalent
apparent cohesion for the soft layer would
become:15.0 1 1.50 = 9.49 kN/sq m
9.67 cu
= 725.25
m-J
Based on the infill material properties 9 30
degrees. Therefore for a factor of safety of
1.0 the horizontal load is:T1 0 = 9.49= 18.98 kN/m run
~
Sin 30
= 21.48
kN/m
(Ref 5)
rr
T2 0 = 18.98
= 37.96 kN/m run
Sin 30
ACKNOWLEDGEMENTS
The author wishes to thank Mr W S McAlonan, MSc
DipTp CEng, Director of Roads,
StrathclydeRegional Council and Mr D L Hynd,
CEng MICE,Divisional Engineer, Dumbarton, and
to othermembers of the Roads Department for
their help. The author would point out that the
views and opinions expressed are his own and
notnecessarily those of the Regional Council.