The work on the dome started the 21st November 1998 with the
construction of the entrance vault, built with granite stones and on a
centering done with laterite blocks. The dome was completed 9
weeks later, the 31st January 1999.
THE DOME
A tight schedule was set from the beginning by the Guru, Sadhguru Jaggi Vasudev. The dome had to be completed before a certain deadline related with his yogic practices and planetary aspects. Therefore the use
of CSEB had been eliminated from the beginning. The time requested for the production, curing and drying of the blocks (3 - 4 months compulsory for arches, vaults and domes) would have been too long! Thus the
choice went for fired bricks, which were laid with a stabilised earth mortar. The foundations and walls were built in random rubble masonry with granite stones in lime mortar.
Around 214,000 fired bricks were laid and the construction site had a working force of more than 220 workers (110 workers at the most on the scaffoldings, including 25 masons). The large amount of fired bricks
required could not be supplied by the same brick factory. Therefore the fired bricks came from about 20 different kilns. As a result, they had different sizes and most of the time they had odd shapes (belly, cracks
and other irregularities). Therefore, nearly 200,000 bricks had to be checked one by one. It became a pain to use such bricks when it would have been so easy to use the accurate CSEB produced by the Auram
press 3000. In most of cultures hell is related with fire, and indeed it was a hell to build with these fired bricks!
No reinforce concrete had been used in any part of the building: neither for the foundations, plinth nor tie for the dome. Sadhguru Jaggi wanted the dome to last 1,000 years and reinforced concrete has not yet
proved to be able to last so long. Therefore the dome stability has been studied in order to have only compression forces.
Finally the dome was studied like a vault, which is more sensitive to a wrong shape than a dome: if a vault is stable, a dome will be stable…when the opposite is not necessarily true. As no reinforced concrete was
used for any tie, it was compulsory to get the resultant of the trust within the middle third of the ring wall and the foundations. To do so, granite stones were used to load the haunch of the dome.
Stability study with Gernot Minke’s method (triangular arch). The line Stability study without load (arch of 21 cm wide). The line of thrust is Stability study with load (arch of 21 cm wide).
of thrust is outside. This method is not satisfactory to optimise LT outside the middle third. The dome has to be loaded outside The line of thrust is in the middle third and the dome is stable
MORTAR SPECIFICATIONS
With the dome rising, the mortar specification needed regularly to be adapted: adding more soil, in 3 steps, so as to have the ideal adhesion according to the angle of the layers. The different mortars were over
stabilised so as to get a fast setting and strength: 13 to 13.37% of cement and 19% of lime.
Starting the dome and the granite vault on the 21st November 1998 Granite vault completed and dome after 1 week Dome after 2 weeks
Dome after 3 weeks Dome after 3.5 weeks, under the rain Dome after 5 weeks
Starting the entrance vault with granite blocks Block touching the springer at the intrados Keystone touching at the intrados
Beginning the dome Dome with the Linga and the ropes to check the elliptical shape Laying keystones
Grouting the stabilised earth glue in the joints Filling tightly mortar with stone chips Starting the dome with 29 cm thick blocks
Bonds of the first of courses, 53 cm thick Bonds of the second rows of courses, 42 cm thick Bond for the third rows of courses, 31.5 cm thick
Bond for the fourth rows of courses, 21 cm thick Grinding the parts of the course which are too high
Plastering the parts of the course which are too low Inserting the pipe for an acoustic corrector to absorb 220 Hz Closing the pipe of an acoustic corrector
Inserting a pipe for an acoustic corrector to absorb 620 Hz Working with an average of 25 masons Loading the haunches with granite stones
Smoothening the granite steps with an earth concrete Smoothening the earth concrete with a stabilised earth plaster Full moon after a night work
Adjusting the compass for the upper courses Laying the last courses, 21 cm thick Dome near completion
The last team who completed the dome on the 31st January 1999
Sadhguru Jaggi laying the last brick Sadhguru Jaggi during the first consecration of the temple