Design Aspects of Drinking Water Plant
Design Aspects of Drinking Water Plant
Design Aspects of Drinking Water Plant
Design aspects
of drinking water
treatment plants
percentage not connected and number of deceased due to typhoid
70
60
50
40
30
20
10
0
1900
1920
1940
1960
1980
year
% not connected
Contents
1. The technical setup of drinking water supply
2. Drinking water resources
3. Production
3.1 Groundwater
3.2 Surface water
3.2.1 Surface water using direct treatment
3.2.2 Surface water using soil aquifer recharge
4. Transport and Distribution
4.1 Transport
4.2 Storage
4.3 Distribution network
4.4 Drinking water installations
5. Planning process for public water supply
5.1 Identication
5.2 Denition
5.3 Design
5.4 Contract
5.5 Construction, start-up and operation
5.6 Laws, permits and standards
6. Costs
6.1 Investment costs
Denition
Investment costs and capacity
6.2 Operational (exploitation) costs
Denition
Structure
7. The practice of designing (Heel example)
7.1 Preliminary studies
7.2 Block diagram, site layout plan and sketch design
7.3 Preliminary design
7.4 Final design and detailed design
7.5 Construction and start-up
This handout is based on Drinking Water, Principles and Practices by de Moel et al.
production
abstraction
treatment
distribution
storage
transport
storage
distribution network
3. Production
3.1 Groundwater
Groundwater can be abstracted in substantial
amounts if an extensive, porous aquifer is available
and if recharge from the surface or the surroundings is possible.
For drinking water production it is important that
the aquifer is more or less isolated from the upper
soil (conned aquifer) to avoid contamination.
In order to further prevent contamination, the
abstraction area is marked as such, according to
strict regulations regarding land use and the use
of dangerous compounds (oil, pesticides, etc.).
In areas where the aquifer has an open connection to the upper soil, the water abstraction area is
clay layer
Figure 3- Consumption of oxygen in the soil has an inuence on the composition of groundwater
can signicantly increase (Figure 4) and, in addition, pesticides may enter the groundwater.
Finally, industrial contamination of the soil inuences the quality of the groundwater.
Because of the variety of differences in water quality prior to treatment, there is no uniform treatment
setup for groundwater. In the Netherlands, almost
exclusively well-protected anoxic groundwater is
abstracted, requiring aeration and rapid ltration in
any treatment process (Figures 5 and 6). Aeration
brings oxygen in the water and removes the dissolved gases, like carbon dioxide. After this, iron,
manganese and ammonium oxidize, causing these
compounds to be removed in the subsequent lter.
To reduce the amount of abstracted water, the
water companies also treat and reuse the backwash water from their rapid lters.
.
Being abstracted directly adjacent to surface water,
riverbank groundwater is a mixture of aerobic surface water inltrated into the soil, via the riverbank
, with natural anoxic or anaerobic groundwater.
spray aeration
cascades
pre-filter
clear water storage
abstraction well
post-filter
clear water pump
Figure 6 - Modern design of Welschap pumping station (Noord-Brabant) where anaerobic groundwater is treated to
produce drinking water
There are two systems for the production of drinking water from surface water:
- storage in reservoirs followed by an extensive
treatment process (direct treatment)
- pre-treatment, soil aquifer recharge and
abstraction followed by a limited post-treatment
(surface water using soil aquifer recharge)
Figures 7 and 8 show the production sites of
drinking water and the origin of drinking water,
respectively.
3.2.1 Surface water using direct treatment
When abstracting river water for direct treatment to
drinking water, signicant variations of water discharge and quality should be considered. Besides,
surface water is rather vulnerable to pollution.
For these reasons a storage reservoir is required
before the treatment process itself.
The surface water that is used as a source for
drinking water production is usually located at a
large distance from the distribution area., requiring
long transport distances (see Figure 9).
In order to prevent sedimentation and biological growth in the transport pipes, either the total
treatment process is situated at the inlet site or
a pre-treatment plant is constructed there. The
main treatment plant is then constructed near the
distribution area.
Reservoirs
In the Netherlands, the surface water used for
drinking water production is mainly abstracted from
the Rhine and Meuse rivers. Due to the large uctuations of quality and quantity., water abstraction
from the river is not always possible. In order to
be able to supply drinking water, a storage reservoir should be available to cover periods of intake
interruptions (Figure 10).
In most cases, the results of a contamination are
only known a week after doing analysis. Therefore,
there is usually an analysis reservoir or compartment situated before the storage reservoir..
Moreover, these reservoirs are also large to allow
for a long retention time. The ow velocity in a
reservoir is much slower than the ow velocity in
a river, causing the settlement of suspended solids. A dampening of concentration peaks is also
groundwater
groundwater
surface water
surface water
mixed
intake
treatment
intake and treatment
Groningen
transport
Andijk
Weesperkaspel
Loenen
Berenplaat
Kralingen
Baanhoek
Brabantse Biesbosch
Zevenbergen
Braakman
Figure 10 - The three Biesbosch reservoirs for the drinking water supply in the southwestern part of the Netherlands
ozone
caustic soda
ferric salt
floc aid
post-disinfection
ferric salt
pump
pump
flocculation
basin
double-layered filters
precipitation
Figure 11 - The production of drinking water from surface water with direct treatment
After the water has been re-abstracted, it is posttreated, because it has become anoxic during
the soil passage and therefore contains iron,
manganese and ammonium. The post-treatment
is thus similar to the set-up of the treatment of
groundwater.
The inltration areas act as a storage system to
cover periods in which the surface water is contaminated and to reduce quality uctuations.
After the post-treatment, the water is transported to
a reservoir near the distribution area, from where
it is distributed.
Table 1 shows the total amounts of drinking water
produced from surface water through soil aquifer
recharge in The Netherlands.
Table 1
Amount
(million m3/y)
213
219
181
38
-6
4.2 Storage
The setup in Figure 1 shows that storage takes
place in (drinking water) reservoirs. These reservoirs are often called clear water tanks. They
achieve a dampening of the daily use uctuations,
so that production and transport can continue on a
more or less constant level. The required capacity of clear water reservoirs is roughly 25% of the
daily use (or the daily production), or the production of 6 hours.
activated carbon
filters
dunes
aeration
post-disinfection
transportation pump
clear water pump
rubbish grid
fish excluding
flocculation
basin
intake
microsieve
sand filters
filtration storage
infiltration
sand filter
clear water storage
chemical dosing
sedimentation
10
Figure 16- The round and square clear water reservoirs at the Berenplaat production site (Zuid-Holland)
11
stenenkamer
teuge
twello
consumption (m3/h)
pumping station
300
250
200
150
100
50
wilp
12
18
24
time (h)
voorst
klarenbeek
12
Table 2
Piping material
PVC
Asbestos cement
Cast iron
PE
Steel
Nodulair cast iron
Concrete
Other
Total
Length
(1000 km)
50
35
12
4
3
2
1
1
108
(%)
46
32
11
4
3
2
1
1
100
Diameter
(mm)
100 - 400
250 600
50 200
50 100
> 500
> 500
> 800
-
pump
13
Table 3
Identication
- Hierarchical planning process for the public drinking water supply in the Netherlands
Planning level
National policy plan
National section plan
Provincial plan
Regional plan
Municipal plan
Company plan
14
5.1
Name
Policy plan for drinking and industrial water supply
Ten-year plan
Provincial policy plans
Provincial management plans
Regional plans
Land use plans
Water supply plan
Multi-year investment plan
Business plan
Timeframe (years)
20 30
5 10
5 10
5 10
5 10
5 10
10 30
5 10
5
Organization
Ministry VROM
VEWIN
Province
Province
Province
Municipality
Company
Company
Company
- specialist research (hydraulics, (soil) mechanics, ergonomics, material science, control engineering, physics, chemistry, environmental
science, social aspects, etc.)
- system design studies (comparison of different
treatment methods)
During these preliminary studies, the following data
should be collected:
- existing plants (raw water source, process ow
diagram, hydraulic scheme, drawings, operating
experiences)
- surrounding area (drawings, descriptions,
measurements, photographs) concerning foundations, soil conditions, groundwater levels, wires,
pipes, roads, working areas, property rights, obligations, utility company connections, etc.
- necessary permits (provincial, municipal, water
boards, spatial planning legislation, utility companies, public services, etc.)
The nal part of the identication phase is the decision to start a new construction project.
5.2
Denition
To be able to begin a construction project, the following documents need to be drawn up::
- requirements program
- sketch design
- building scheme
Requirements program
The term requirements program is broadly used
and has many different meanings, varying from a
precise contract document to a general wish list.
It is also applied to the collection of documents in
the construction phase.
A requirements program is, preferably, limited to
the purpose and outlines of the construction project, including:
- motivation for the project
- summary of preliminary studies
- purpose of the project
- wishes and side purposes
- future developments after construction
Based on the requirements program, a sketch
design can be formulated.
Sketch design
In the sketch design, general options are considered, and the chosen one is sketched in terms of
its technical and spatial outline. A sketch design
can consist of the collection of relevant preliminary
studies and reviews, as well as a more detailed
items such as:
- treatment scheme (i.e., block diagram)
- rough hydraulic line scheme
- rough terrain arrangement
- phasing of construction
- cost estimation
A sketch design gives a good indication of the
dimensions of the construction project. It includes,
not only the construction phases but also the plan
and terrain arrangements for future expansions
. This design is important to inform all parties
involved in the projects next phases.
The building scheme can be formulated on the
basis of the sketch design.
Building scheme
The building scheme is the general project plan,
covering all aspects of the construction phase. It
contains the full project denition and consists of:
- requirements program
- sketch design
- time schedule for design, contracting and construction
- design of the project organization (task setting
between different parties involved in future studies
and construction)
- estimation of investment costs (total project
costs)
The building scheme is also important for internal decision making of the water company itself,
including considerations such as the project mandate for organizational, technical, contractual and
nancial aspects.
5.3
Design
15
16
Table 4
Phase
Identication
Sketch design
Preliminary design
Final design
Detailed design
Building
Accuracy Changeability
of costs
of design
50%
30%
100%
25%
40%
15%
10%
5%
2%
1%
-
Change
in costs
1%
5%
10%
25%
100%
information flow
initiative stage
life cycle
building
information flow
design stage
information flow
building stage
information flow
operation stage
5.4
Contract
17
- it is the chief source of information for describing the work to be conducted, so an accurate price
can be set
- it is one of the instruments for steering, controlling and supervising the building process
- it is part of the contract, together with a description of tasks, rights and obligations of both parties
5.5
Figure 22 - The building area is 3-6 times larger than the building
18
Residence time
Surface load
Surface load
Empty bed contact time
Volume
Capacity
20 min
15 m / h
7m/h
15 min
20,000 m3
5,760 m3 / h
1,070 m3
215 m2
460 m2
800 m3
Volume
Surface
Surface
Volume of carbon
Based on these process units, the investment costs (level of policy plan or sketch design) are estimated
using the cost functions for the process units. The table below gives the result of the cost estimation.
Cost element
Costs
(million )
2.3
2.8
6.8
6.7
3.7
7.3
29.6
12.1
41.7
19
Standards
Many permit procedures require the design to
comply with specic standards. These standards
Energy
Energy
Energy
Energy
24 Wh / m3
50 Wh / m3
12 Wh / m3
8 Wh / m3
Energy
200 Wh / m3
Dosing Fe
Suspended solids (sludge)
Suspended solids (sludge)
Regeneration
5 mg / l
20 mg / l
5 mg / l
15,000 BV
Based on this, operational costs (sketch design phase) can be estimated as given below.
Process unit
Flocculation
Flotation
Filtration
Activated carbon ltration
Clear water storage
Clear water pumping station
Total
20
( / m3)
0.017
0.022
0.046
0.051
0.025
0.058
0.220
( / m3)
0.017
0.017
0.004
0.030
0.000
0.012
0.081
Maintenance
( / m3)
0.002
0.002
0.006
0.005
0.001
0.007
0.024
Specic Administrative
operational costs
costs
( / m3)
( / m3)
0.006
0.005
0.008
0.005
0.018
0.009
0.018
0.010
0.010
0.003
0.020
0.010
0.081
0.042
6. Costs
Scale factor
Of course, the capacity of the plant determines, to
an important extent, its investment costs.
For the relation between capacity and investment
costs, cost functions can be formulated.
The relation between capacity and investment
costs are usually well described by the general
formula:
K = a * (capacity)b
where:
K = investment costs
a = costs factor ( - )
b = scale factor ( - )
(E)
Table 5
Cost factor
( / m3 yearly capacity)
1.5 - 3.5
2.0 - 4.0
3.0 - 5.0
4.0 - 8.0
0.10 - 0.15
0.10 - 0.15
0.20 - 0.30
0.30 - 0.55
0.05 - 0.15
0.10 - 0.15
0.05 - 0.15
0.10 - 0.25
0.5 - 0.25
0.30 - 0.55
0.50 - 0.90
0.35 - 0.60
0.05 - 0.20
1.00 - 2.00
0.70 - 1.50
0.40 - 0.70
0.20 - 0.35
21
investment costs
These costs are made during (parts of) the operation period of the installation or plant and after
completion of the construction.
4
3
2
1
0
0
4
capacity
b = 1.0
b = 0.75
b = 0.5
Figure 23 - Relationship between capacity and investment costs for different scale factors
22
Table 6
Part
1 Fixed costs
Consumables
Maintenance costs
Sub part
a1
a2
a3
a4
a5
a6
c1
c2
c3
c4
b1
c5
b2
b3
c6
c7
a7
b4
b5
b6
c8
c9
c10
a8
b7
c11
Interest
Replacement reserve (depreciation of actual building costs)
Ground rent
Owners part real estate tax
Assurance costs (re, glass, etc.)
Governmental contribution (taxes, levies, etc.)
Rent
Loss of rent
Environmental tax
Users part real estate tax
Energy costs (electricity and fuels) (maintain)
Energy costs (electricity and fuels) (use)
Water
Chemicals
Other consumables (regeneration activated carbon, seeding material, etc.)
Removal waste products
Technical maintenance (maintain)
Cleaning maintenance (maintain)
Technical maintenance (use)
Cleaning maintenance (use)
Accounting costs (property)
Accounting costs (maintain)
Rental costs
Administrative staff costs
Moving costs
Mediation costs
Accounting costs (use)
Surveillance costs (property)
Surveillance and security (maintain)
Surveillance and security (use)
Operation installations
Quality monitoring
23
24
capacity
Venray
Breehei
over capacity
Houthuizen
reserve
Californi
Venlo
Tegelen
Helden
Reuver
time
Weert
Beegden
Heel
Roermond
Herten
t Reutje
Susteren
25
Abstraction
Aeration
ration
Filtration
ration
UV-disinfection
infect
ter storage
stor
Clear water
Figure 27 - Global setup of the treatment scheme
Sketch design
In addition to the documents named above, formulating some very rough design drawings to present
the intended construction to third parties may be
desirable. Usually, a single oor plan and one or
two sections will sufce.
abstraction
well
basin
aeration
pumping station 1
rapid filter
activated carbon filter
clear water storage
pump
UV-disinfection
pump
26
pumping station 2
1998
1999
2000
execution
start drilling
well field
start execution
production plant
A PFD indicates installations, by means of standardized symbols, and the ow of mass and energy
between them. At a minimum, it consists of the
following blocks:
- type of equipment necessary for the process
- coding of the installation
2001
testing
start building
intake work
and pipeline
delivery
2002
start-up
start production
27
pre-filtration
cascade
34.00+
pre-filtration
buffer
25.7+ (max)
25.3+ (min)
31.5+
32.00+
28.6+ (max)
28.3+ (min)
30.00+
28.2+
(max)
27.1+
(min)
activated
carbon filter
clear water
UVstorage
disinfection
30.8+ (max)
30.5+ (min)
26.5+ (max)
25.8+ (min)
28.00+
26.00+
field level
24.00+
groundwater level
22.00+
1/4 Q
1/4 Q
FIC
1/4 Q
1/4 Q
FIC
1/4 Q
1/4 Q
FIC
1/4 Q
1/4 Q
28
Structural aspects
During the preliminary design phase, the dimensions of the structural elements cannot be determined accurately yet because the loads are only
approximated. Nevertheless, it has proven feasible
to make some realistic assumptions instead. For
concrete constructions, the oor and wall sizes are
mostly estimated at 0.4-0.6 m.
UV-units
aeration
circulation
transport pumps/
rinse water pumps
clear water
UV
1
clear water
UV
2
UV
pre-filtrate
UV
4
rinse water
UV
pre-filtrate
5
UV
5
6
UV
7
UV
Architecture
Adjustment of the design because of architectural
considerations may be desirable. Therefore, it
is useful to indicate the functional relationships
between the different components. This will give
a better indication to the architect of the degrees
of freedom and of the consequences of breaking
them (Figures 36 and 37).
29
30
31