100% found this document useful (1 vote)
446 views6 pages

Cost Estimation

Rft 650.00 1,36,500.00 6200.00 Sft 35.00 2,17,000.00 6200.00 Sft 40.00 2,48,000.00 440.00 Sft 115.00 50,600.00 1.00 Qtl 4700.00 4,700.00 Total Estimated Cost Rs. 30,00,000/- (Rupees Thirty Lakhs only) This document provides an estimation and quotation for construction work. It includes

Uploaded by

civilsadiq
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
446 views6 pages

Cost Estimation

Rft 650.00 1,36,500.00 6200.00 Sft 35.00 2,17,000.00 6200.00 Sft 40.00 2,48,000.00 440.00 Sft 115.00 50,600.00 1.00 Qtl 4700.00 4,700.00 Total Estimated Cost Rs. 30,00,000/- (Rupees Thirty Lakhs only) This document provides an estimation and quotation for construction work. It includes

Uploaded by

civilsadiq
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 6

Sl

01.

02.
03.

04.

05.

06.

07.

08.
09.
10.
11.

ESTIMATION/QUOTATION
-------------------------------------------------DESCRIPTIONS OF ITEMS
QUANTITY
Earth work excavation for leveling and lowering the
ground (other than foundation work) and removing the
excavated earth to a distance not exceeding 50 mtr and
spreading , leveling etc.. complete wherever necessary
in ordinary soil
up to 50level Above 50 to 80 level Earth work filling to Foundations and Basement with
available approved earth including watering and
compaction in layers of 15 cm thick up 50mt lead.
Providing and laying Plain cement concrete for
Foundation and Plinth slab of 1:4:8 granite, basalt or
trap jelly concrete using 40mm and down size laid in
100mm thick layers and well compacted including
curing etc.. complete.
Providing and constructing Size stone masonry for
basement Retaining wall and Foundation, below
and above Ground level up to Plinth beam bottom, in
CM 1:6 not less than 200mm high with bond stones
2mt apart in each course including pointing for exposed
surface, curing etc.. complete. For Foundation work :
Providing and laying Cement concrete 1:1.5:3 using
20mm and down size granite, basalt or trap jelly for
Column Footings, Main and Secondary Beams,
Pedestals in foundation , basement and step footings
laid in 150mm thick layers and well compacting,
vibrating , curing and steel or plank centering or
Plastering in CM 1:6 to mud susface wherever
necessary etc.. complete. (Excluding the cost of steel
and fabrication charges. )
Providing and laying Cement concrete 1:1.5:3 for
Columns using 20mm and down size granite, basalt,
or trap jelly with steel, plywood or plank centering
including mixing, compacting, vibrating and curing
etc.. complete. (Excluding the cost of steel and
fabrication work)
Providing and laying Cement concrete 1:1.5:3 for
Plinth beams (Other specification is same as item
No-06
Providing and laying Cement concrete 1:2:4 for Lintel.
(Other specification is same as item No 06)
Providing and laying Cement concrete 1:1.5:3 for Roof
beams, Flat and Slope roof Slabs. (Other
specification is same as item No 06)
Providing and laying Cement concrete 1:1.5:3 for
Staircase. (Other specification is same as item No -06)
Providing and laying Cement concrete1:2:4 for
Window Sill

UNIT

RATE

4200.00
1500.00

Cft
Cft

8.00
10.00

33,600.00
15,000.00

1000.00

Cft

5.00

5,000.00

440.00

Cft

120.00

52,800.00

1160.00

Cft

130.00

1,50,800.00

610 .00

Cft

230.00

1,40,300.00

285.00

Cft

260.00

74,100.00

Cft

260.00

31,200.00

110.00

Cft

220.00

24,200.00

1753.00

Cft

260.00

4,55,780.00

90.00

Cft

265.00

23,850.00

20.00

Cft

100.00

2,000.00

120.00

AMOUNT

12.

13.

14.

15.

16.

17.

18.

Providing and laying CC 1:2:4 for Plain Chejjas/


Lofts of 75mm average thickness as per design, cement
concrete in granite or trap jelly of 20mm and down size
with the front beading and drip molding including form
work centering, curing and downsize including
plastering with cement mortar 1:3 etc.. complete.
Providing and constructing Superstructure walls in
CM 1:6 with Table Mould Brick of 150mm thick of
approved quality with mild steel reinforcement, 2 rows
of 8mm dia at sill level with necessary scaffolding and
curing etc.. complete as per technical specification.
(Basic rate of Brick Rs-10.50/Brick).
Providing and constructing Partition walls in CM 1:4
with Table mould bricks of 4.5 thick and R.C.C
1:2:4 band with mild steel reinforcement, 2 rows of
8mm dia for every eighth course and distribution at
600mm center to center with all necessary scaffolding,
racking out joints, curing etc..complete as per technical
specification. (Basic rate of Brick Rs-7.00/ Brick )
Providing and fixing Teak wood Door, at Main
Entrance Door 6x3 and Pooja Room Door 5x3
thick frame work fixed in masonry with
40 x5mm
flat iron hold fast 30cms long embedded in 15cms thick
CC 1:3:6 with fully paneled door shutters of 1. 25
thick as per design including labor charges and cost of
necessary Brass or Stainless steel fittings, French
polishing for wooden surfaces as per specification.
(Basic Rate of Burma Teak wood,
Section
Rs- 3000.00/Cft & Planks Rs- 3500/Cft)
Providing and fixing Water Proof Flush Doors with
Red Salwood Doors frame work, of 5x 3 thick
fixed with masonry 40 x 5mm flat iron hold fast 30cms
long embedded with CC 1:3:6 & 1.25 thick Water
Proof Flush Door shutters of ( Rs- 90.00/Sft) with
Enamel painting including labor charges and cost of
necessary Powder coated Ms/Aluminum fittings, as
per specification
(Basic Rate of Red sal wood Rs- 1100.00/Cft )
Providing and fixing Red Salwood Windows and
Ventilators of 5x 3 thick frame work, fixed with
masonry 40 x 5mm flat iron hold fast 30cms long
embedded with CC 1:3:6 & 1.25 thick Plain type
Honne wood shutters with 4 mm thick Pin headed
Glass, 12mm hexagonal rods at 2.5 to 3spacing with
Enamel painting including labor charges and cost of
necessary Powder coated Ms/Aluminum fittings, as
per specification
(Basic Rate of Red sal wood Rs- 1100.00/Cft )
(Basic Rate of Honne wood Rs- 1900.00/Cft )
Providing and Plastering 12mm thick cement mortar
1:3 to Ceilings of slabs including providing and
removing scaffolding and rounding of all corners
wherever required, smooth lime rendering, curing etc..
complete

230.00

Sft

110.00

25,300.00

2259.00

Cft

140.00

3,16,260.00

1063.00

Sft

85.00

90,355.00

52.25

Sft

1300.00

67,925.00

158.00

Sft

650.00

1,02,700.00

333.00

Sft

750.00

2,49,750.00

2745.00

Sft

32.00

87,840.00

19.

20.

21.

22.

23.

24.
25.

26.

27.

Providing and Plastering 12mm thick cement mortar


1:6 to Internal brick masonry including providing
and removing scaffolding and rounding of all corners
wherever required, smooth lime rendering, curing etc..
complete.
Providing and Plastering 20mm thick cement mortar
1:6 to External brick masonry including providing
removing scaffoldings and smooth sponge finishing,
curing etc.. complete.
Providing and laying Granite flooring of approved
quality and shade of 20mm minimum thickness laid on
20 to 25mm thick CM 1:5 base jointed with neat
cement slurry including necessary curing, polishing
etc.. complete as directed ( TP + Basic rate of
Granite- Rs- 60/sft )
Ground Floor First Floor Second Floor Providing and laying Granite skirting, of 04 wide
including half Nosing.( Other specification is same as
item No -20 )
Ground Floor First Floor Second Floor Providing and laying Vitrified tile Flooring of
approved quality, color, shade and make laid in cement
slurry over bedding of 12mm thick CM 1:5 laid to
proper line level as specified including filling the joints
with white cement mix pigment and pointed nicely
including curing etc.. complete as per specification.
(TP + Basic rate of tile Rs 60 / sft )
Providing and Laying Vitrified Tile Skirting of
04wide as per technical Specification Basic rate of
tile Rs 60 / sft )
Providing and laying Ceramic tile Flooring for bath
rooms, w/c, utility, Passage area & sit out areas and
Dadoing for bath rooms, w/c, Kitchen & utility area
of approved quality, color, shade and make laid in
cement slurry over bedding of 12mm thick CM 1:3 laid
to proper line level as specified including filling the
joints with white cement mixiee pigment and pointed
nicely including curing etc.. complete as per
specification.
( Basic rate of Floor tiles Rs- 40 / Sft ) Flooring ( Basic rate of Wall tiles Rs-35/Sft ) Dadoing Providing and fixing Granite Kitchen Counter of
40mm thick slab and Steel Sink of size 26x20x 8,
fixed on masonry wall including plastering and finished
with white cement by using required pigment etc..
complete as per design and detail
Providing and laying Marble/Granite Staircase
Treads & Risers for Internal portion of approved
quality and shade of 20mm minimum thickness laid on
20 to 25mm thick CM 1:5 base jointed with neat
cement slurry including Bull Nosing for Treads &
Half Nosing for Skirting necessary curing, polishing
etc.. complete as directed
( Basic rate of Marble/ Granite- Rs- 60 /sft )

6270.00

Sft

28.00

1,75,560.00

4460.00

Sft

32.00

1,42,720.00

RO
RO
RO

Sft
Sft
Sft

145.00
145.00
155.00

RO
RO
RO

Rft
Rft
Rft

110.00
110.00
110.00

1193.00

Sft

120.00

1,43,160.00

4340

Rft

88.00

38,192.00

100.00
633.00

Sft
Sft

90.00
100.00

9,000.00
63,300.00

39.00

Sft

450.00

17,550.00

240.00

Sft

230.00

55,200.00

28.

29.

30.

31.

32.

Providing and fixing M.S. Pipe Railing of 30 ht


Top row of 2 round & Pillers of 2 square with
couplings, center 3 rows of 3/4 round pipes with
end caps in position as per design & details.
Providing and applying Paint for Internal walls and
Ceilings of required shade and approved make on
new / old surface including the preparation of surface
for painting ( 2 coats of cement primer, 2 to 3 coats of
chalk powder patti ) applying Plastic Emulsion paint in
2 coats to give uniform covering by using roller for last
coat at all heights, etc..complet. ( Asian make )
.
a)Oil Bound Distemper
.
OR
b) Tractor Emulsion OR
c) Premium Emulsion OR
d) Royal Emulsion Providing and applying Water proof Cement Paint of
2 coats for External walls of required color and
shade as per technical specification.
OR
- Apex paint
Providing and constructing Parapet wall at Terrace,
and Balconies of 30 height and 115mm thick brick or
4 tk Solid Block masonry in CM 1:4 including
plastering, R.C.C coping, etc.. complete.
Providing and HYSD steel reinforcement including
straightening, cutting, bending, hooking, lapping and /
or wielding wherever required placing in position
typing with binding wire of approved quality and guage
including the cost of binding wire and anchoring to the
adjoining members wherever necessary including all
laps and wastages etc.. complete as per design and
specification and directions ( laps and wastages not to
be measured and paid )
( Basic rate of steel Rs 47.00/Kg).

210.00

Sft

250.00

52,500.00

9015.00
RO
RO
RO

Sft
Sft
Sft
Sft

16.00
20.00
24.00
30.00

1,44,240.00

5280.00
RO

Sft
Sft

14.00
20.00

73,920.00

1800

Rft

160.00

28,800.00

10.50

MT

57,000.00

5,98,500.00

A.

B.

C.

D.

33.

34.

35.

36.

TOTAL COST OF CIVIL WORK :


(Work Excludes the Cost of Approval for the
construction from the Government, Deposits, Plan
Sanctioning charges, Office Documentation
charges, landscaping, interior decoration etc..,)
TOTAL COST OF ELECTRICAL WORK :(Work
includes Anchor Roma Modular Switches, Anchor,
Phynolex or V-GUARD Cabals, ISI MCB, & ELCB
AC points for bed rooms.)(Work Excludes Deposits,
Temporary Power connection, Electrical Fittings
like FANS, TUBE LIGTES, GYESERS, BULBS
AND OTHER FANCY LITE FITTINGS, Office
documentation and sanctioning charges, Road
Cutting and Under ground Caballing from Miter
Board to Electric Pole, Meter Board/Box)
TOTAL COST OF SANITARY AND PLUMBING
WORK :(Work includes CPVC & PVC6Kg/sqm.
ESS/Jaquar SS fittings, CPVC (Supreem/aashirvad) for
Hot & cold piping , PVC Supreem make &
Hindware/cera/periware Ceramic wash basins &
Comods, PVC Over Head Tank of 1000 liter capacity,
One Hot water Line to Each Bath rooms, & One
Cold water line for the required points Internal Solar
Unit / Geyser Piping.) ( Work Excludes the Cost of,
Septic Tank and 6 dia Pipe connection from
building main sanitary chamber outlet to Septic
tank or Road Sanitary Pipe line, SUMP MOTOR,
SOLAR UNITS WITH FIXTURES, EXTERNAL
SOLAR PIPING, Rain water Harvesting, Office
documentation, Sanctioning and Road Cutting
charges )
TOTAL -

Rs -

34,91,402.00

Rs -

1,60,000.00

Rs -

1,80,000.00
38,31,402.00

MISCELLANEOUS ITEMS :
Providing and Constructing BBM Sump Tank
including excavation as per technical specification
Providing and Making Water proofing for the Toilet
Sunken floor by applying 2 coats of water proofing
compound to top surface by laying R.C.C 1:2:4 and
finished by cement mortar 1:4 by giving the finish with
proper slope etc.. complete as per specification.
Providing and fixing M.S. Safety Grills with Grill
Door at Main/Utility area by using 9mm MS Square
rod @ 4/ 6c/c horizontal and Vertical bars and
1x1/4 angels for the frame in position including
enamel painting as per design & details.
Providing and Laying Ultra Pre cast Step tiles at
External Steps and Car Entrance Sit Out area as
per technical specification. ( Basic rate of Ecocrete
tile Rs- 40/Sft)
Providing and fixing MS Gate of 46 height
including Enamel Painting as per specification.

6000.00

Ltr

9.00

54,000.00

990.00

Sft

40.00

39,600.00

RO

Sft

160.00

100.00

Sft

110.00

11,000.00

64.00

Sft

280.00

17,920.00

37.

38.

Providing and Making Damp proof Kalai Finished


Flooring in CM 1:6 above Existing PCC 1:4:8 Bed
Concrete at Car parking, Path way area as per
technical specification

700.00

Providing and Laying 12x12 Anti skid vitrified


tiles at Car parking, Path way area as per technical
specification.
( Basic rate of Anti skid vitrified tiles Rs- 45 /Sft )

RO

39.

Road side Drainage Covering

40.

Elevation work Like, STONE/WOODEEN


CLADDING or MESH WORK fins, Boxes and
Drops etc;.. Providing and Constructing 46 height & 40 thick
Solid Block Compound wall above Basement
Retaining wall with 1:3:6 DPC and 1:2:4 RCC
Coping, 1:6 CM Plastering, & W P cement Painting
as per technical specification
TOTAL COST OF MISCELLANEOUS WORK :

41.

Sft

30.00

21,000.00

115.00

PENDING

PENDING

100.00

Rft

500.00

GRAND TOTAL :
STILT + GROUND + FIRST + SECOND STAIR ROOM + MISCELLANEOUS ITEMS -

50,000.00
1,93,520.00
40,24,922.00

( Rupees Forty Lakhs, Twenty Four Thousand, Nine Hundred Twenty Two Only)
RATE PER SQUR CALCULATION TOTAL AREA CONSIDERED : STILT FLOOR+GROUND FLOOR+FIRST FLOOR+SECOND FLOOR
STAIR ROOM -2430.00 Sft
TOTAL COST CONSIDERED : STILT FLOOR+GROUND FLOOR+FIRST FLOOR+SECOND FLOOR
STAIR ROOM Rs-38,31,402.00
38,31,402.00
------------------ X 100 = Rs-1,57,670.86 / Squr
2430.00

You might also like