Calculating Evm in Primavera p6
Calculating Evm in Primavera p6
Primavera P6
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$100
$200
$200
$200
$100
$100
$100
$100
$100
$100
$100
Cost Performance
The baseline indicates that $500 worth of work should be complete
(Planned Value Cost)
As of the Data Date, (Actual cost) is $600 to achieve $300 worth of
work (Earned Value Cost).
This shows the project is over budget
Performance Factors
4 Optional Methods
PF = 1 *Optimistic Result
ETC = (PF * (Budget at Completion Earned Value Cost
PF = 1/CPI *Most likely Result
ETC = (1/CPI)* Budget at Completion Earned Value Cost
PF = 1/CPI*SPI *Pessimistic Result
ETC = [1/(CPI * SPI)] * Budget at Completion Earned Value Cost
PF = ____
ETC = your custom PF * Budget at Completion Earned Value Cost
Key Concepts:
Perform Earned Value Analysis to compare the budgeted cost of the
work to the Actual Cost
Calculate the Planned Value, Earned Value, and Actual Cost to
determine how much work should have been completed, How much
work was completed, and how much the completed work cost to build
Use Estimate to Completion to calculate what the remaining cost of
the activity(s) in progress will be