Code of Practise
Code of Practise
for
Inspecting and Certifying
Buildings and Works
Building Control
Regulations 2014
February, 2014
Table of Contents
1.
Introduction
1.1
1.2
Overview of Code
1.3
Application
1.4
1.5
Regulatory Oversight
2.
Definitions
3.
3.1
Key Responsibility
3.2
3.3
Builders Role
3.4
Designers Role
3.5
3.6
4.
3.6.1
Overall Role
3.6.2
10
3.6.3
11
3.6.4
Completion stage
11
Certification
12
4.1
Certificates Required
12
4.2
12
4.2.1
12
4.2.2
Ancillary Certifiers
12
4.3
13
4.4
13
4.5
Undertaking by Builder
14
4.6
14
4.7
14
5.
6.
7.
8.
9.
15
5.1
15
5.2
Other Documentation
16
5.3
16
Commencement Stage
17
6.1
17
17
7.1
17
Inspection Plan
7.1.1
18
7.1.2
Inspection
18
7.2
Inspection frequency
19
7.3
19
7.4
Follow up procedures
20
7.5
Tests
20
7.6
Records of inspection
20
Completion Stage
20
8.1
Submission at completion
20
8.2
21
8.3
22
8.4
Phased Completion
23
Archiving of Records
23
10. E-lodgements
23
11.
23
Professional Ethics
12. Insurance
24
25
Code of Practice
1. Introduction
1.1
(1)
(2)
(3)
1.2
Overview of Code
Building owners
Designers
Builders
Certifiers
February, 2014
1.3
Code of Practice
Application
The Code of Practice covers the inspection and certification aspects of the Building
Control Regulations. The Code of Practice applies to buildings and works for which
Certificates of Compliance under the Building Control Regulations are required. The
areas covered include:
1.4
Certification
The overall objective of the revised building control system is to achieve better
building construction. The aim is to ensure that all involved in the construction
process and the regulatory system work effectively to achieve this. A set of design
principles has been used in developing the system of building control and in particular
this code. These principles are summarised as follows:
1) using a number of complementary measures and interventions to achieve
compliance;
2) putting in place reasonable and appropriate interventionist measures as
necessary to ensure quality outcomes are achieved;
3) providing early warning of non-compliance (for the benefit of private sector
and building control authorities) so as to build in regulatory responsiveness
and to increase the dependability of outcomes ;
4) empowering third parties (both commercial and non-commercial) to positively
influence compliance with regulatory requirements, thereby achieving better
outcomes at less cost and deploying available regulatory resources as
effectively as possible; and
5) encouraging all participants to achieve good outcomes and recognising that,
while the legal requirements set minimum standards which must be achieved,
there should be an ambition to exceed these.
1.5
Regulatory Oversight
Oversight is central to the revised arrangements for the control of building activity that
will operate from 1 March 2014. Building Control Regulations require the private
sector to play an active part in achieving compliance and providing better buildings. A
key aim of the Code is for regulatory oversight to ensure a culture of compliance with
February, 2014
Code of Practice
Building Regulations using a risk based approach to target those who are noncompliant.
Building Owners, Designers and Builders are responsible for the notices, certificates,
plans and documentation that are to be lodged with building control authorities.
Regulatory oversight is necessary in order to ensure that any failure of regulation
among the agencies involved be they Building Owners, Designers, Builders and/or
Building Control Authorities is detected and remedied in an effective and timely
manner.
A key element in detection is the system of risk analysis, whereby the online Building
Control Management, having regard to the notices and documents lodged at
commencement, will inform the Building Control Authoritys decisions to deploy
available resources towards the inspection and investigation of those construction
projects where the risk of failure is highest. This will help Building Control Authorities
to escalate findings of non-compliance and, where necessary, effectively use their
powers of inspection, enforcement and prosecution in the event of serious breaches
of Building Regulations. The aim is that the powers of enforcement and prosecution
will become a more credible threat to those who are non-compliant.
2. Definitions
The definitions set out below are for the purpose of explaining terms used in this
Code of Practice. They are not, and should not be construed as being, legal
definitions or interpretations of similar terms which may be used in the Act of 1990 or
any regulations made thereunder.
Act of 1990 means the Building Control Act 1990 (No. 3 of 1990) as amended by
the Building Control Act 2007 (No. 21 of 2007);
Ancillary Certificates means a certificate other than a statutory certificate of
compliance as prescribed in the Building Control Regulations given by a
competent person to confirm compliance of elements of the building,
design or works with Building Regulations; and Ancillary Certifier means a
person proposed to issue such a statement. (Note: a person also includes
a company);
Assigned Certifier means the competent, registered professional person so
assigned, in accordance with the Building Control Regulations;
Builder means a competent builder appointed, for purposes of the Building Control
Regulations, by the building owner, to build and supervise the works;
February, 2014
Code of Practice
February, 2014
Code of Practice
Inspection Plan has the meaning set down in section 7.1 of this Code of Practice;
"the Minister" means the Minister for the Environment, Community and Local
Government;
"works" includes any act or operation in connection with the Construction, extension,
alteration, repair or renewal of a building;
February, 2014
Code of Practice
Code of Practice
Code of Practice
3.4
Designers Role
Designers should: (a) design their respective elements of work in accordance with the applicable
requirements of the Second Schedule to the Building Regulations;
(b) provide the Design Certifier with the necessary plans, specifications and
documentation that is required for lodgement at commencement stage;
(c) arrange to provide sufficient information to the Assigned Certifier to enable
them to fulfil their role;
(d) as agreed with the Assigned Certifier, carry out work inspections which are
pertinent to their elements of the Design, and liaise with the Assigned Certifier
in terms of this and the required ancillary certification;
(e) notify the Assigned Certifier of their proposed inspection regime for inclusion
in the overall Inspection Plan;
(f) provide the Ancillary Certificates when required by the Assigned Certifier and
Design Certifier; and
(g) maintain records of inspection.
3.5
The Assigned Certifier is assigned by the Building Owner as required under the
Building Control Regulations. They undertake to inspect, and to co-ordinate the
inspection activities of others during construction, and to certify the building or works
on completion. The role of Assigned Certifier does not include responsibility for the
supervision of any builder. They may or may not be a member of the design team.
The Assigned Certifier should: (a) provide and sign the relevant statutory certificates - the form of undertaking at
commencement and the Certificate of Compliance on Completion;
(b) co-ordinate the ancillary certification by members of the design team and
other relevant bodies for the Certificate of Compliance on Completion;
February, 2014
Code of Practice
(c) identify all design professionals and specialists, in conjunction with the
Builder, from whom certificates are required;
(d) identify all certificates required and obtain them;
(e) co-ordinate and collate all certification of compliance for completion in
conjunction with the Builder;
(f) in consultation with the members of the design team, plan and oversee the
implementation of the Inspection Plan during Construction;
(g) prepare the Preliminary Inspection Plan and oversee adherence to this plan,
and on completion provide the Inspection Plan as implemented;
(h) on termination or relinquishment of their appointment make available to the
Building Owner all certification prepared and inspection reports carried out;
(i) act as the single point of contact with the Building Control Authority during
construction;
(j) seek advice from the Building Control Authority, in respect of compliance
matters relating to the building or works where disputes or differences of
opinion arise between the parties to the project; and
(k) maintain records of inspection.
3.6
3.6.1
Overall Role
February, 2014
Code of Practice
10
Code of Practice
From the Building Control Authoritys perspective, any plans and documentation
lodged will be readily available should the particular project be selected for a building
control inspection.
3.6.3
Building Control Authorities should adopt a formal policy for the assessment and
inspection of building work as notified on the Building Control Management System.
Authorities should adopt a risk management based approach in undertaking this
work. This will include consideration of matters such as: (a) the use of the building;
(b) the type of construction;
(c) the level of experience of the design team and the Builder; and
(d) past experience regarding compliance by the parties involved in the project.
In addition a level of random assessment and inspection should be carried out.
In line with the agreed Service Indicators for Local Government, Building Control
Authorities are required to carry out a level of inspection equivalent to 12% to 15% of
new buildings for which valid commencement notices have been received.
Building Control Authorities should keep full records of all assessments and
inspections carried out. Inspection reports should be made available to the Assigned
Certifier and the Builder.
3.6.4
Completion stage
The role of the Building Control Authority at completion stage is to validate the
submission of the Certificate of Compliance on Completion and, where appropriate to
include details of same in the statutory register of building control activity. The
validation process will include checking that the certificate was properly completed
and signed by the appropriate persons. The authority will check that there are no
unresolved matters in relation to requests under Section 11 of the Act or Enforcement
Notices or conditions attached to Fire Safety Certificates, Disability Access
Certificates, etc. It is not appropriate for the Building Control Authority to commence a
technical assessment at this stage.
Documents accompanying the certificate of compliance on completion should be
retained on the Building Control Management System by the Building Control
Authority.
February, 2014
11
Code of Practice
4. Certification
4.1 Certificates Required
As set out in the Building Control Regulations, certificates are required for certain
buildings and works. The following four certificates are required to be submitted:
(a) the Design Certificate signed by the Design Certifier at the commencement
stage;
(b) the form of Undertaking signed by the Assigned Certifier at the commencement
stage;
(c) the form of Undertaking signed by the Builder at the commencement stage; and
(d) the Certificate of Compliance on Completion signed by the Builder and by the
Assigned Certifier at completion stage.
4.2 Who can sign as the Design Certifier and/or as the Assigned Certifier
4.2.1
The following may be appointed and sign as the Assigned Certifier, provided they are
competent in relation to the particular works involved:
(a)
Architects that are on the register maintained by the RIAI under Part 3 of the
Building Control Act 2007; or
(b)
Building Surveyors that are on the register maintained by the SCSI under
Part 5 of the Building Control Act 2007; or
(c)
Similarly, the Design Certifier must be one of the above registered professionals and
must be competent to carry out their design and to co-ordinate the design activities of
others for the works concerned.
4.2.2
Ancillary Certifiers
Apart from the Assigned Certifier and Design Certifier there is likely to be a range of
certifiers on most projects, including certifiers appointed by the Building Owner, by his
design team and/or by the Builder. Ancillary certifiers may include:
February, 2014
12
Code of Practice
Designers (e.g. for piling, for mechanical/electrical work, for soil and waste
pipework or for precast concrete elements) appointed by the Builder to design
and certify the relevant elements of the works;
other competent technical and trade persons that install products and/or test
on completion; and/or
Every certifier should exercise reasonable skill, care and diligence in the exercise of
their duties.
February, 2014
13
Code of Practice
February, 2014
14
Code of Practice
Certifier is required to provide to the Building Owner and to the Building Control
Authority the records of inspection up to the date on which their appointment ends,
along with any available certification of compliance of Design and/or Construction up
to that date. Measures should be taken during the course of the building or works to
ensure that matters relating to the payment of fees do not hinder this possible
eventuality.
A change of either the Assigned Certifier and/or the Builder will require liaison with
the Building Control Authority, who are expected to advise and assist the relevant
parties in relation to any action that may be required, having regard to the
circumstances involved, in order that the building or works notified at commencement
may be subject to a valid Certificate of Compliance on Completion.
This may involve a new Commencement Notice including a new Preliminary
Inspection Plan, so as to enable both the Assigned Certifier and the Builder to
appropriately describe the building or works for which they are responsible, and the
basis upon which a Completion Certificate will be issued.
The new Preliminary Inspection Plan will set out the necessary agreed additional
inspections, testing or reports, if any, to be carried out, so far as is reasonably
practicable, on the already built works.
The Assigned Certifier and the Builder are required to notify the Building Control
Authority before ceasing their role; other than where this is not physically possible, in
which case the Building Owner is required to undertake this duty.
A change of Assigned Certifier or Builder during the course of the works is a
significant alert to the risk analysis system of the Building Control Authority, which
may trigger an inspection of the Design and other documents and a site inspection.
February, 2014
15
Code of Practice
The plans and documentation required at commencement stage where the works
involve a new dwelling, an extension (to a dwelling) with a total floor area greater
than 40 square metres or require a Fire Safety Certificate will include:
(a) general arrangement drawings plans, sections and elevations
prepared for building control purposes;
(b) a schedule of such plans, calculations, specifications and particulars as
are currently designed or as are to be prepared at a later date;
(c) the completion of an online assessment, via the Building Control
Management System, of the proposed approach to compliance with the
requirements of the Second Schedule to the Building Regulations (Parts A
to M);
(d) the Preliminary Inspection Plan prepared by the Assigned Certifier;
and may, typically, also include:
(e) drawings of particular details as appropriate;
(f) drawings showing work that is below ground;
(g) general arrangement structural drawings showing the main structural
elements
(h) specifications including materials and products; and performance
specification for elements that may be the subject of ancillary certification.
February, 2014
16
Code of Practice
6. Commencement Stage
6.1 Online submission to Building Control Authority
The online submission at commencement stage will typically include the following: a)
b)
c)
d)
e)
f)
g)
h)
i)
February, 2014
17
Code of Practice
work to which the Building Regulations relate to be examined. The supervision by the
Builder is, therefore, of critical importance. The test of the Inspection Plan will be its
success in achieving reasonable standards of health and safety in or about buildings,
and of energy conservation, accessibility and sustainability for building users.
Inspection staff should use professional skill and judgement in their selection of
priorities for inspection. Depending on the complexity of the project, such inspections
may need to be carried out by personnel with greater expertise. Inspection staff
should be briefed by their employer and, where necessary, by the Assigned Certifier
on the Design lodged to the Building Control Authority and on appropriate inspections
and tests to carry out.
7.1.1
Inspection
18
Code of Practice
February, 2014
19
Code of Practice
persons referred to above may carry out unannounced inspections between the
stages identified in the INF and/or in the Inspection Plan.
7.5 Tests
Certain tests may need to be carried out, as necessary, in order to demonstrate
compliance. In some cases such tests may be ones referred to in the Technical
Guidance Documents published to accompany the various parts (A to M) of the
Building Regulations. The Assigned Certifier and Ancillary Certifiers should consider
and identify the need for such tests at the earliest possible stage and as far in
advance as possible. They should include them, as far as possible, in the building
contract documentation where there is a contract in place.
The Inspection Plan and the INF should indicate the tests that the Certifiers wish to
monitor periodically and, where necessary, the Building Owner should be notified
about test requirements.
8. Completion Stage
8.1 Submission at completion
At completion stage, the Assigned Certifier is required to submit the following to the
Building Control Authority:
(a) a Certificate of Compliance on Completion signed by the Builder (at Part A) and
by the Assigned Certifier (at Part B);
February, 2014
20
Code of Practice
(b) plans, calculations, specifications and particulars, showing how the completed
building has achieved compliance with the Building Regulations must be lodged
on the Building Control Management System when the Certificate of Compliance
on Completion is submitted or at an earlier date. Where design documents have
changed or supersede design documents previously lodged with the Building
Control Authority with the Commencement Notice or at a later date, any such
difference should be clearly identified;
(c) the Inspection Plan as implemented by the Assigned Certifier in accordance with
this Code of Practice.
NB: The Certificate of Compliance on Completion must be validated and registered
by the Building Control Authority before the building it relates to may be opened, used
or occupied. If rejected by Building Control Authority within 21 days, the certificate is
not valid.
February, 2014
21
Code of Practice
February, 2014
22
Code of Practice
9.
Archiving of Records
Arrangements should be put in place by the Assigned Certifier and the Builder to
ensure that records relating to the full service they provided to individual projects are
retained for a minimum period of 6 years after completion. This should include
ancillary certificates, plans, calculations, specifications, documents and records of
inspection. A significant amount of these records may form part of the Safety File
provided for under the Safety, Health and Welfare at Work (Construction) Regulations
2013, in which case these records do not need to be retained separately.
Arrangements should be made by all relevant parties for their transfer into safe
keeping in the event of the holder of any relevant records ceasing to trade.
10. E-lodgements
The online Building Control Management System hosted by the Local Government
Management Agency has been developed for use by all building control authorities as
the preferred means of administration of building control functions. Owners, builders
and professionals who seek to make paper-based submissions after 1 March 2014
will be required to pay an administrative charge to cover the cost of scanning and
uploading their submissions. Statutory notice periods and validation timelines may
also be affected.
February, 2014
23
Code of Practice
12. Insurance
There are various types of insurances that are provided in the construction industry.
Apart from general insurances such as employers liability and public liability
insurances there are other insurances including professional indemnity insurance,
and latent defects insurance policies provided by insurers who specialise in
construction related insurance. The provision of guidance in relation to insurance is
an important matter for consideration but it is outside the scope of this Code of
Practice. Owners, and homeowners in particular, who commission works should
generally satisfy themselves as to the adequacy of the insurances held by contractors
or professionals they may wish to consider engaging. Often the level and scope of
insurance cover held by other parties to a construction project will have a bearing on
the willingness or otherwise of other industry practitioners to become involved.
February, 2014
24
Appendix:
Ref.
Code of Practice
Description
Apply
Does not
apply
Partially
applies
Comment
Part A - Structure
A1
Loading
A2
Ground movement
A3
Disproportionate
Collapse
Means of Escape
B2
B3
B4
B5
Preparation of Site
C2
Subsoil Drainage
C3
Dangerous Substances
Materials and
Workmanship
February, 2014
25
Ref.
Description
Code of Practice
Apply
Does not
apply
Partially
applies
Comment
Part E - Sound
E1
E2
E3
Part F - Ventilation
F1
Means of Ventilation
F2
Condensation in Roofs
Part G - Hygiene
G1
Bathrooms and
Kitchens
G2
Sanitary Conveniences
and Washing Facilities
Drainage System
H2
Septic Tanks
Air Supply
J2
Discharge of products
of Combustion
J3
Protection of Building
J4
February, 2014
26
Ref.
Description
Code of Practice
Apply
Does not
apply
Partially
applies
Comment
K2
K3
Vehicle Ramps
Conservation of Fuel
and Energy
L2
Conservation of Fuel
and Energy in Existing
Dwellings
L3
Conservation of Fuel
and Energy in New
Dwellings
L4
Conservation of Fuel
and Energy in Buildings
other than Dwellings
M2
Sanitary Conveniences
M3
Audience or Spectator
Facilities
February, 2014
27