b. The underwriters are truly math geniuses. Therefore, the time it takes to calculate the issue price
decreases to 4 weeks.
The calculate the issue price task has a start slack of 2.5 weeks. Hence decreasing the duration of this task
from 5-4 weeks will not impact the overall duration of the project. But it increases the slack to 3.5 weeks.
Critical path remains the same.
Critical Path: A-B-D-E-F-J-K-L-O-P
d. The new issue does not comply with the blue sky laws of a handful states. The time it takes to edit the
issue for each state to ensure compliance increases to 4 weeks.
The Confirm that the new issue complies with the 'blue sky' laws task has a start slack of 2.5 weeks. Hence
increasing the duration of this task from 1-4 weeks will impact the overall duration of the project by 0.5
weeks increase to 28 weeks. This introduces two new critical paths
Critical path 1: A-B-D-E-F-G-M-P
Critical path 2: A-B-D-E-F-J-K-L-M-P
Janet and Gilbert must reduce the time for the following tasks to finish the project within 24 weeks at a minimum cost of
$260,800,
Task A by 1.5 weeks,
Task B by 1 week,
Task K by 0.5 week
Task N by 1.5 weeks
Task O by 2 weeks and
Task P by 0.5 week
Karthik Arumugham [1311299]
Janet and Gilbert must reduce the time for the following tasks to finish the project within 24 weeks at a minimum cost of
$236,000,
Task A by 1.5 weeks,
Task B by 1 week,
Task K by 0.5 week and
Task O by 0.5 week