M S Project
M S Project
M S Project
1.1 To start with Microsoft Project, navigate to Start - All programs Microsoft
Office Microsoft Office Project 2007.
1.2 After starting the project , the Gantt chart view appears by default (same as Figure
below):
1.3 Depending on the information needed, it is possible to work in different views of the
project data. When starting a list of tasks or activities, it is easiest to start with Task
Sheet View (WBS View).
1.4 To display Task Sheet View, navigate to View (Menu item) More Views.
1.5 A new screen appears then select task sheet and click Apply (see Figure below).
1.6 Task sheet view appears with only few columns of data (see Figure below).
5.3 For example, if we want to create four levels of hierarchy (like 1.1.1.1),
o select Numbers (ordered) in the first four rows of the sequence columns of the
WBS code definition dialog box.
o To separate the numbers using periods, select the period in the separator
column.
o Leave the two items Checked at the bottom of the screen as shown below
INDENT buttons
7.3 If your project WBS codes are not in correct sequence, you can Renumber WBS
codes of all tasks or selected task. To do so go to Project (Menu Item) WBS
Renumber. WBS Renumber dialog box appears as shown below, select Entire
project and click OK.
1
0
1
1
A note: As a result, the first three OUTCOMES of your project should look like
Figures 1, 2, 3
Figure 1 Team0_Lab1_Outcome_1a: Task Sheet View
1
2
1
3
NOTE: MS Project 2007 will only accept ID numbers (Column # 0) but not WBS Codes
(Column # 1)
For example, Task 1.2.4 Develop Schedule in Lab Assignment has ID number 12 and
Task 1.2.8 Project Plan Complete has ID number 16 and one of its Predecessors is ID
12.
9.3 Now save it as Team#_Lab1_outcome2a.mpp ( Figure 4) - In order to save a
current status of the project, Go to File (Menu item) Save As. Enter the filename
as Team#_Lab1_Outcome_2a.mpp
1
4
1
5
10.2
10.3
10.4
To do so, Navigate to View (Menu item) Resource sheet and enter the Human
resources as specified in column # 5 of Lab1 Assignment. Also enter Material
resources as specified in column # 6 of Lab1 Assignment by changing the
TYPE of resource from Work to Material.
10.3
textbox, change the TYPE of the resource from Work to Material (if resource is
material), then click OK.
10.4
1
7
1
8
Save
As.
Enter
the
filename
as
Team#_Lab1_Outcome_3c.mpp
11.4 Now, come back to Resource sheet again and see any Over-allocated resources
exist (shown in red color). Then save it as Lab1_outcome3d.mpp (Figure 9) - In
order to save a current status of the project, goto File (Menu item) Save As.
Enter the filename as Team#_Lab1_Outcome_3d.mpp
1
9
2
0
2
1
2)
3)
4)
5)
6)
Day-by-day basis,
Clear leveling values before leveling,
Level entire project,
Leveling can adjust individual assignments on a task,
Leveling can create splits in remaining work. Then click Level now.
13.3 If a resource view that has selected resources was showing when you opened
the Resource Leveling dialog box, the Level Now dialog box appears as shown
below. Select Entire pool and then click OK.
13.4 Now you will see a difference in the duration column as number of days is
increased (Compare data in original Figure 7 to resulting Figure 9).
13.5 Switch to the Task Sheet view. Save it as Team#_Lab1_Outcome_3e.mpp.
(Figure 10) - In order to save a current status of the project, go to File (Menu
item) Save As. Enter the filename as Team#_Lab1_Outcome3e.mpp
2
2
13.6 Go back to the Resource sheet view. There you will see that the problem with the
over allocated resources has been resolved. This means that the information in
RED has disappeared from the Resource sheet.
Figure 10 Team0_Lab1_Outcome_3e: Task sheet view after leveling the
resources
2
3
14.2 Click Next to continue, since our assignment is to show the critical path, Select
Critical Path radio button and then click Next.
14.3 Based on information that you want to display with Gantt bars, select the
corresponding radio button and click Next.
2
4
14.4 To show the links between the tasks, select yes and then click Next.
14.5
Click Format It
2
5
14.6
2
6
15.2 ZOOM the Report to maximum by clicking Zoom button in the toolbar or by
pressing keys Alt+1.
15.3 Take the screenshot of the report. To do so press keys Ctrl+Alt+PrntScr.
15.4 Open Microsoft Office Word and paste the screenshot in the document as shown
in the figure below.
2
7
Save
As.
Give
the
filename
as
15.6 In order to save a current status of the project, go to File (Menu item) Save As.
Enter the filename as Team#_Lab1_Outcome6a.doc. Type should be Microsoft
Office Word Document (*.doc) and then click save. The outcome should be
similar to Figure 12 Project Summary Document.
15.5 Return back to Task Sheet View. Navigate to Report (Menu item) Reports
Overview Critical Tasks. Repeat the same procedure from 15.2 15.4. Save
the filename as Team#_Lab1_Outcome_6b.doc. The outcome should be similar to
Figure 13 Critical Tasks Document
2
8
2
9
Start Date
Final Date
Duration
(Days)
12/1/2011
12/27/2011
19
12/28/2011
1/16/2012
14
1.3.1 Release 1
1/17/2012
4/10/2012
61
1.3.2 Release 2
4/11/2012
5/22/2012
30
Overall Project
12/1/2011
5/23/2012
125
Phases
3
0
3
1