Pipelines LOC
Pipelines LOC
Pipelines LOC
Scope
This Section provides guidance for the assessment of safety case content, with respect to
pipelines connected or close to an offshore installation, from hazard identification and risk
evaluation to risk management measures. It covers the major accident hazards associated
with pipelines. The pipeline is defined from pig trap to pig trap, from/to the ESD valve where
a pig trap is not fitted, from subsea wellhead(s) to surface installation. Interplatform and
pipeline system effects must be considered.
Interfaces with other disciplines are relevant, such as with fire explosion and impact
protection, well and compressor / pump pressures, oil / gas processing, safety systems,
damage prevention, corrosion, emergency response, diving activities, human factors and
others. The scope includes not only pipeline containment and protection etc but may also
include the effects of a failure: e.g. of a riser jet fire.
2. Adequacy of Demonstration
The safety case should include the identification of all hazards from the initiators, and the
risk evaluation and management arrangements. See the Pipelines Hazard Categorisation
List
The safety case should include an adequate description of all pipelines, including design
parameters as necessary, and evaluate the impact of pipelines and their inventories on the
overall case for safety. The safety case should demonstrate that the Pipelines Safety
Regulations (and other relevant statutory provisions) are complied with. By including the
summary of the Major Accident Prevention Document (prepared in accordance with the
Pipelines Safety Regulations, Regulation 23) for each relevant pipeline, the risk
assessment in the safety case is interfaced with that for the pipelines.
3. Pipelines Hazard Categorisation List.
Loss of Containment Pipelines
Location of Hazard
HS1 - Rigid Riser
HS2 - Flexible and comliant Risers
HS3 - Pipeline - Tie-in spools, Seabed pipeline, tees
HS4 - Riser Emergency shutdown valves (ESDV)
HS5 - Subsea Isolation Valves (SSIVs)
HS6 - Pig Trap
Subsea systems: manifolds, well flowlines, process equipment
Initiators
G1 - External Corrosion, coating damage, cathodic protection failure
G2 - Internal Corrosion, water, wax, scale
G3 - Erosion, sand, scale
G4 - Overpressure
G5 - High Temperature
G6 - Low Temperature Joule Thomson effect
G7 - Fatigue / vibration
G8 - Fire [Section 2.3.3]
G9 - Fitting failure
G10 - Incorrect installation or fabrication
Operator error [Section 11]
G11 - Inadequate Training [Section 11]
G12 - Inadequate competency [Section 11]
G13 - Violation [Section 11]
F4 - Equipment layout
F5 - Company standards / competence
F6 - Corrosion / erosion allowance
F7 - Operations and maintenance procedures
F8 - Safety Integrity Level (SIL) standards
F9 - Equipment selection
Riser jet fire effects
Risk Management Measures
F14 - Inherent Safety
fully rated pipelines & risers
riser and pipeline routing
Riser ESDV locations
Concrete ballast + protection coating
Pipe protection trenching burial rock dump covers
Fire protection
Damage Prevention
F15 - Relief systems
F16 - High Integrity Pressure Protection Systems (HIPPS)
F17 - Shutdown systems ESD system ESDVs
F18 - Alarms / trips
F19 - Cathodic protection anodes impressed current systems
F20 - operational procedures - control of erosion / internal corrosion, temperature during
blowdown, pigging, chemical inhibition
Performance Standards
Temperature & Pressure Rating
Material specification: strength, corrosion resistance, impact resistance
Cathodic protection (CP) potential
Remaining fatigue life
Frequency and type of inspection
Pressure relief arrangements, set point, capacity
Reliability of protective systems
Supports: number, locations, adequacy
Integrity of pig trap closures and seals
Fire protection, risers, ESDVs
Valves: closure mode, seal type, leak rate, fire resistance
pipeline pigging philosophy and practice: scale and wax removal, biociding, inhibitor
distribution, intelligent pigging, liquids removal, semi-intelligent pigging, tethered riser
inspection etc
Specific pipeline data in the safety case should include:
pipe diameter;
wall thickness (including thicknesses for different parts of the pipeline where these
vary), stating any allowance for corrosion;
the pipeline to platform approach route;
the riser route including the topsides part of it and any demarcation points;
the riser ESD valve location(s) and any subsea isolation valves;
the fluids in the pipeline;
pipeline inventory at maximum allowable operating pressure between the pipeline
extremities (i.e. from installation to installation, including any branches connected
subsea);
design configurations: rigid pipe, flexible, bundle, piggy back, internal cladding,
weight coating, with key dimensions etc
construction methods used: conventional lay, reeled, towed, pipe-in-pipe, riser
caisson (wet/dry), J-tube etc
the standard or code used to design the pipeline;
the current safe operating pressure;
the safe operating temperature range;
the grade(s) of steel and materials of construction of the pipeline, riser and topsides
pipework, sour/non-sour service rating, types of corrosion resistant alloys
corrosion management arrangements, including monitoring and control of corrosion,
internally and externally, reliability of corrosion inhibition, cathodic protection etc
systems, sand and scale management, inspection arrangements
any other element of the design or operation of the pipeline which is critical to the
safety of the installation.
4. Design of the Pipeline
The duty holder and pipeline operator should ensure that the pipeline riser has been
designed and constructed and is operated safely in accordance with recognised standards
and guidance.
Where a recognised standard/code of practice has not been employed, the duty holder
should provide justification on a case-by-case basis that the applied standard or code or
method is appropriate.
5. Design for Extreme Weather
Most North Seainstallations are designed to withstand a wave which occurs on average
every 100 years or every 50 years. However structural design standards now require
design for a wave that occurs every 10,000 years. Further information is available via this
link: http://www.hse.gov.uk/offshore/extremeweather.htm.
The 10,000 year wave level can rise well above the current elevations of riser ESD valves.
Floating installations being restrained by moorings and inertia can be likewise affected. The
safety case should demonstrate that dutyholders and pipeline operators have assessed the
ability of risers, ESD valves and other facilities to survive such extreme weather.
6. Pipeline Damage Prevention
The safety case should include a description of pipeline damage prevention arrangements,
including: a list of identified hazards (e.g. dropped freight, caissons, tubulars, equipment,
anchors, mooring lines, vessels, submerged flexible risers etc.); pipeline route information
issued; operational measures (no anchoring areas, vessel size limitations, approach routes,
etc); and permanent protection measures. The pipeline should be protected from third party
or construction damage caused by vessel anchors and mooring wires and chains, by pipe
lay abandon and retrieval wires, and by fishing trawls.
HSE has issued guidance on the management of anchor hazards for pipeline operators,
this is available via the following link: http://www.hse.gov.uk/pipelines/pipeline-anchorhazards.pdf
Anchoring procedures for standby vessels, supply vessels, diving support vessels, heavy
lift crane vessels, flotels, drilling rigs, etc should be included in the safety case. Risks come
from dropped objects such as freight being loaded and from vessel collisions with risers,
and from dropped objects such as caissons. Pipelines and risers should be routed safely or
protected. Procedures should limit vessel sizes and types, weather conditions for loading,
etc.
Pipelines located under platform cranes should be protected from dropped freight
containers, tubulars, etc. Procedures should limit the types and weights of freight to be
handled so as to not exceed the design capabilities of the pipeline protection.
Safety cases for non-production installations should include a description of arrangements
for identifying the routes and locations of pipelines, wells and other subsea equipment and
assessing the risks that they pose to the installation (SCR05 Schedule 3 para 12).
Particulars of the plant and arrangements to minimise the effects of damage to subsea
equipment by drilling equipment should be included (SCR05 Schedule 3 para 6).
Combined operations notifications should include a suitable diagram(s) showing the
location of risers, pipelines and other subsea equipment in relation to the layout of the
combined operation. Safe operating limits of the installations, mooring lines, crane radii etc
should also be provided (A guide to the Offshore Installations (Safety Case) Regulations
2005 L30 para 295 page 69).
Jack-up spud cans making deep holes in the seabed into which a pipeline can slip should
be considered within the safety case as appropriate.
7. Modifications and Repairs
The safety case should include a description of procedures to be followed for modifications
and repairs, including hazard identification, risk assessment, notifications, isolation
arrangements (topsides and subsea), standards of work inspection and testing.
A description should be included of past modifications and repairs to the pipelines that
could affect the safety case hazard identification and risk assessment: i.e. where
modifications fall below the standard of the rest of the pipeline.
8.
The safety case should describe the type and operation of any pipeline over-pressure
protection
Pressure breaks should be examined critically. The primary protection should be by design
for the highest foreseeable pressure (inherently safe design). Secondary protection may
include relief valves, High Integrity Pressure Protection System (HIPPS) (section
2.3.1.F16), etc.
The well head shut-in pressure of a subsea well connected to the installation should be at
or below the safe operating pressure of the relevant riser. The maximum output pressure or
the high pressure shut down set points for pumps and compressors and other pressure
sources connected to the pipeline should be at or less than the riser safe operating
pressure. The maximum allowable operating pressures (or safe operating pressure) of
pipelines connected subsea to a riser should be so as to prevent overpressurisation from or
of a third party pipeline or installation.
The considerations mentioned above must be satisfied, using a suitable HIPPS system or
similar if necessary. See Safety Instrumented Systems for the Overpressure Protection of
Pipeline Risers, SPC/Tech/ED/31 at
http://www.hse.gov.uk/foi/internalops/hid/spc/spctED31.htm. SPC/Tech/ED/31 describes
various levels of pipeline and riser design, additional protection measures, HIPPS design,
operational testing and maintenance.
9. Pipeline Safety Systems
The safety case should include a hazard identification that identifies the critical safety
system components. The duty holder should describe all the safety systems in place for
safe operation, safety of personnel and prevention of hazard escalation. The performance
standards required of these systems should be described, stating for example the action
and shutdown levels. These components should be tested and maintained. The safety
systems should cover the greatest and most frequent hazards, and they should provide the
fastest response and warning of hazards. Emergency procedures are intended to cover the
rest.
10. Pipeline Emergency Shut-Down Functions
The safety case should describe the emergency shut-down facilities. The levels of shutdown should be clearly defined. The level at which the riser ESD valves are closed should
be stated. ESD system data (e.g. riser valve closure) transmitted to or from connected
installations should be described. If SSIVs are installed, their mode of operation should be
described: i.e. automatic or manual.
11. Connection to Pipeline Systems
When communication data or control links between installations connected by pipeline are
lost there are usually temporary manual procedures after which the pipeline should be shut
down. In some cases remotely controlled action can be taken under major accident
conditions by connected installations. The sequence and timing of such actions, including
emergency shut-down arrangements should be described in the safety case.
12. Pipeline Leak Detection
The safety case should describe the type and operation of the pipeline leak detection
system, including data and control functions monitored, monitoring locations (e.g. at each
end of the pipeline) and the alarm and shutdown set points for these functions.
13. Emergency Response
The safety case should describe emergency arrangements, which should cover all
identified hazards and interfaces and roles of other operators (at other installations) for the
safety of the installation and of other installations.
14.
Integrity Management
The safety case should confirm that the inspection, maintenance and integrity management
arrangements in place for the pipeline include the entire length of the pipeline.
A description should be included in the safety case of the inspection assessment and
maintenance arrangements. This should summarise: the methods of inspection of the
pipelines and risers; the management system for carrying out the inspection work; and
decision making processes used to determine the scope and programme for remedial work
or operations.
A description should be included in the safety case of procedures to satisfy the operation,
maintenance and testing requirements for the emergency shutdown (ESD) valves,
demonstrating that seat leakage is measured, assessed and remedial action taken if
required.
15. Subsea Operations
The safety case should describe pipeline and control connections between the installation
and subsea manifolds wells and other installations.
The safety case should contain a summary description of procedures for simultaneous
production (if applicable) and diving, or other pipeline works or maintenance, on a pipeline,
at a subsea manifold or well connected by pipeline to the installation. This should detail the
measures in place to control any pipeline hazards that could affect the diving support
vessel, its crew or divers, the installation or another installation.
Taking a pipeline out of use involves cleaning out of hazardous substances from pipelines,
risers and topsides, and ensuring safe disconnection from live plant, and decommissioning
or removal of facilities as required. This involves ensuring the safety of divers and that of
other personnel involved with platform abandonment, and leaving the facilities in a safe
state. The safety case should address these issues as appropriate.
ESDV location;
Mechanical joints, e.g. flanged and insulation joints;
Splash zone corrosion resistant cladding;
Any branches outboard of the ESDV as far as their respective isolation valve(s) and
their nominal diameter; and
Fire, explosion, impact or other protection provided for the riser and ESDV.
1. Riser Routing and Design
The safety case should, with the aid of diagrams, describe the riser routing in relation to the
topsides layout, installation structure, pipeline to installation approaches and field layout.
This enables assessment of the full impact of layout versus topsides and vessel activities.
The riser should, where possible, be routed away from fire, explosion and impact hazards.
The riser route should be chosen so as where possible to obtain a good ESDV location and
pig trap arrangement (such that the ESDV is located as low as reasonably practicable
along the length of the riser), such that, subject to other design constraints, the ESDV is
close to the top end of the vertical part of the riser.
Riser routes are sometimes chosen with little consideration of the ESDV location, this may
be because subsea and topsides design are considered separately. The constraints of the
topsides layout can result in a poor ESDV location, with a horizontal section of outboard
riser below deck that cannot be isolated by the ESDV.
Caisson risers should be terminated on the topside of the installation as low as is
reasonably practicable, so that the ESDVs can be located as required.
Specific issues to be addressed include:
position of cranes for loading vessels;
external risers located on the prevailing weather side of the installation, (being
vulnerable to impacts from drifting vessels);
fire protection;
access for inspection, i.e. when located in caissons, J-tubes or platform legs;
gas risers in concrete platform legs, which could leak and pressurise the leg causing
it to collapse;
adequate support of the riser, especially in the wave zone;
dead weight supports should be with an anchor flange or similar, located out of the
splash zone (for inspection).
Risers should ideally be located in-board of jacket braces or other structural members to
protect them from vessel impact. If not, there should be fenders or other means installed
which can absorb impact energy without touching the riser. Parts of risers routed inboard of
jacket frames are vulnerable to impact by objects dropped from the topsides; there have
been instances of caissons falling and landing near to a riser.
Where risers are located in J-tubes (conduits) or in caissons, the J-tubes or caissons
should be sealed off at both ends and filled with inhibited water to protect the riser from
corrosion. A number of incidents have resulted from the failure to properly manage the
integrity of pipelines in J-tubes of caissons. HSE guidance Hydrocarbon Risers in
Caissons and I/J Tubes Inspection issues and become potential sources of leakage in a
fire.
Riser stress analysis should cover extreme static installation offsets from its station, static
wind, wave and current loading, natural frequency analysis, dynamic response to wave
frequencies (stresses and fatigue damage assessment) and dynamic transient responses.
Operators should demonstrate awareness of the fatigue lives of their flexible risers,
including in damaged condition, and the limiting sea states for the riser system.
A description of fire, explosion and impact protection should address:
passive fire protection;
explosion protection - blast walls and plated decks;
dropped object protection;
operational protection against dropped objects: avoiding lifting over risers.
In operation each flexible riser annulus should be piped separately (to avoid interaction
between risers) to a safe area to vent gas pressure. Operator inspection should include
periodic testing of each flexible riser annulus by vacuum and positive pressure testing as
applicable, to test for and find a failed external polymer layer. Where the outer layer has
failed there should be measures to prolong the life of the outer tensile wires, fatigue
analysis to determine the remaining life of the outer tensile wires, and replacement of the
riser when required.
The safety case should assess the interaction between the installation and others linked by
pipeline(s) and the effect an interconnected pipeline system could have on the installation
or upon other installations.
1. Pipeline to Platform Approaches
The duty holder should describe, with suitable diagrams:
the layout and configuration of the plant;
the connections to any pipeline or installation; and
any wells connected or to be connected to the installation.
The plan of the location should be large enough to show any features that may be
significant in the assessment of the hazard or risk associated with the site.
The safety case should include a pipeline to installation approaches plan from the hazard
distance to the installation, showing the installation(s), pipelines (including any not
connected to the installation), direction of geographical (true /grid) and installation north, no
-anchoring areas, subsea wells, manifolds, control umbilicals, anchor patterns for vessels
normally moored in the vicinity, layout of tie-ins, spool-pieces, crossovers, SSIVs, extent of
protection measures such as mattresses, rock dump, trenching, protection covers, supports
and any significant changes in the seabed elevation.
For a flotel located over the pipelines, dropped object and anchor/ mooring line damage
should be considered. Similarly jack-up temporary moorings used during jacking
operations, construction vessels, diving support vessels, and standby vessels should be
considered.
Moorings for drilling semis (usually but not always located away from fixed platforms) and
jack-ups drilling satellite wells and exploration wells should be considered in connection
with the in-field pipeline layout. Pipelay initiation, abandon and recovery lines should be
considered.
The pipeline integrity management system should address spans, including those close to
the installation.
The duty holder should demonstrate, through description and general layout drawings, that
adequate fire, explosion and impact protection is provided for the ESDV and its actuating
mechanism. The actuator and any stored energy device (e.g. spring return or accumulator
and hydraulic piping) required for fail-safe close purposes should be protected. A
description of the protection of these items should be included in the safety case.
Risers and riser supports should be protected against fire where necessary. At locations
close to ESDVs the riser should be protected as for the ESDV against fire, explosion and
impact.
4. Fire Protection
The safety case should provide assurance that the ESDV actuator and all components
necessary for ESDV fail-safe closure will remain fully operable under anticipated fire
conditions. The pressure containing capability of the ESDV, including any out-board
maintenance valves and any flanged connections to the riser, should survive the
anticipated fire conditions.
Whilst both passive and active fire protection systems may be used, it should be noted that
passive systems (coatings, covers, etc) do not require prime movers, distribution systems
and an initiation signal, and are therefore likely to be more reliable and have higher integrity
(subject to proper inspection and maintenance) than active systems (deluge, etc).
Accordingly, active fire protection systems acting on their own may not be sufficient.
There should be fire and gas detection in the vicinity of the ESDV.
5. Explosion Protection
Explosion protection measures in place should be described in the safety case. Explosion
protection is usually best achieved by locating the ESDV well outside congested equipment
modules and away from entries to these areas, to avoid high explosion over-pressures and
damage. In many cases blast walls are provided.
6. Impact Protection
The main impacts to be considered by the safety case are:
dropped and falling objects;
missiles resulting from explosions; and
vessels/ships.
Protection from impacts may be achieved by blast walls and plated decks.
The operator should carry out a study of the possible impacts, including those which could
be experienced following another incident, such as heavy machinery falling from above,
and should assess what protection is necessary.
Some of the protection may be in the form of procedural control, e.g. for crane handling,
boat approach, etc.
7. ESDV Operation and Testing
The duty holder should assess and mitigate the risks of the ESDV failing to operate on
demand; An SSIV can only partly address this risk.
The safety case should describe arrangements for periodic valve seat leakage testing and
timing of closure tests. The associated performance standards should take account of
potential escalation of an incident and be consistent with the risk assessment for the
installation.
8. Actuators and Control Panel
The duty holder should describe the types of actuators used on the ESDVs.
The ESDV, its actuator, the local control panel, and where fitted, its accumulators and any
ESDV dedicated maintenance valves, should be located close together.
For liquids pipelines with a significant gas content a riser failure can lead to a major release
of liquid driven out by the expansion of the gas. Specialised software can quantify such a
release. A major part of a release can occur in the time taken for systems to be shut down
to depressurise the pipeline, especially where such systems are located elsewhere.
The decision as to whether or not an SSIV is to be fitted should be taken based upon an
analysis of the potential consequences and risks of a riser release, and of damage due to
escalation from another riser.
The safety case should fully assess the consequences of a failure. The cost of an SSIV
must be compared to the far greater cost if one is not fitted but is needed in an emergency.
In addition to fire/explosion risks, major pipeline releases can upset the stability/buoyancy
of floating production installations and vessels.
Where pipelines are branched into main transportation lines or third-party imports, without
an SSIV, there can be an unlimited supply of fuel into a fire. Emergency actions required by
third parties can take a considerable amount of time to achieve and tests have shown lack
of reliability; this must be factored into the assessment of whether an SSIV should be fitted.
The risk of the riser ESDV failing to operate on demand should be considered in the
assessment
Dutyholders/operators should consider combining several SSIVs into a single skid to
reduce installation costs and so make the fitting more reasonably practicable. Combining
import and export riser SSIVs can be done such that the flow goes from import pipeline to
export pipeline without going to the risers, thus reducing risks, the risers only being used for
pigging. Connection points for future pipelines can be added at negligible cost.
Pipelines to comment please? What is meant by this paragraph?
Due to the location of an SSIV, a significant inventory of hydrocarbons will be present
between the subsea valve and the top of the riser. Therefore, failure of the riser or
connected pipeline (at the installation) will result in an unavoidable discharge of
hydrocarbons under pressure, with the potential for a serious fire or vapour cloud explosion.
An SSIV cannot prevent this initial discharge from taking place and cannot protect
personnel in the open or working near the riser. Where the riser ESDV seat leaks the SSIV
cannot affect the short and medium term leakage rate in an incident. SSIVs are often only
function tested and not tested for valve seat leakage.
1. Non-return or Check Valves
close to an installation, SSIV skids serving several pipelines, spool-piece flanges being
used to avoid the cost of hyperbaric welds, etc.
The pipeline to platform approach layout should be considered carefully to ensure that each
SSIV is located on a sound risk-balancing basis, and that the overall layout addresses all
risks.
3. Description of SSIV
The duty holder should describe the SSIVs installed. There should be a description with
layout giving the location, modes of operation, type of valve and actuator and failure modes
(e.g. fail close on loss of hydraulics/signal).
The description must include the modes of closure/operation and the failure modes.
Dutyholders/Operators are sometimes reluctant to install fail-safe closed valves in case,
during a test or following a spurious failure, they close and remain jammed shut. It is
however, of no benefit to fit an SSIV that is almost impossible to use or is functionally
locked open.
There should be fail safe modes of closure or similar in event of loss of hydraulics/other
platform signals. The system should include local energy storage (such as a spring or
hydraulic accumulator) to close the valve, and it should not rely on platform based hydraulic
or other power supply for closure in an emergency.
4. Protection
The safety case should demonstrate that the SSIV is protected from impact and snag loads
from anchor lines and fishing trawls. Usually a structure is provided for this purpose.
5. Inspection, Testing and Maintenance
The duty holder should describe the philosophy for carrying out inspection, testing and
maintenance on SSIVs and NRVs.
As with any safety system, the reliability needs to be assured, and this is normally done by
carrying out periodic tests. The duty holder should describe the extent, type and frequency
of these tests. There should be detailed procedures in place for this purpose. Some
dutyholders/operators are reluctant to carry out tests in case the valves are damaged or
cannot be opened again. Regular testing however improves the reliability of valves. Testing
should include:
ISO 15589 Petroleum and Natural Gas Industries Cathodic Protection for Pipeline
Transportation Systems Part 2: Offshore Pipelines
ISO 3183 Petroleum and Natural Gas Industries Steel Pipe for Pipeline
Transportation Systems
API 5L Specification for Line Pipe (equivalent to ISO 3183)
API Specification 17J Specification for Unbonded Flexible Pipe
NACE Standard MR0175-2002 Sulphide Stress Cracking Resistant Metallic
Materials for Oilfield Equipment
BS EN ISO 13628-2 Petroleum and natural gas industries Design and operation
of subsea production systems Part 2: Unbonded flexible pipe systems for subsea
and marine applications
BS EN ISO 13628-10 Petroleum and natural gas industries Design and operation
of subsea production systems Part 10: Specification for bonded flexible pipe
BS EN ISO 15156-1:2009 Petroleum and natural gas industries. Materials for use in
H2S-containing environments in oil and gas production.
BS EN ISO 15156-2:2009 Petroleum and natural gas industries. Materials for use in
H2S-containing environments in oil and gas production. Cracking-resistant carbon
and low-alloy steels, and the use of cast irons.
BS EN ISO 15156-3:2009 Petroleum and natural gas industries. Materials for use in
H2S-containing environments in oil and gas production. Cracking-resistant CRAs
(corrosion-resistant alloys) and other alloys.
3. Safety systems standards
API RP 14C Recommended Practice for Analysis, Design, Installation and Testing of
Basic Surface Safety Systems for Offshore Production Platforms 7th Edition March
2001
BS EN ISO 13628-14 (Draft) Petroleum and Natural Gas Industries: Design and
Operation of Subsea Production Systems. Part 14. Subsea High Integrity Pressure
Protection Systems (HIPPS)
SPC/TECH/ED/31 Safety instrumented systems for the overpressure protection of
pipeline risers
API Spec 6D Specification of Pipeline Valves
ISO 14313 Petroleum and Natural Gas Industries Pipeline Transportation Systems
- Pipeline Valves
Department of Energy Guidance Notes in Support of the Offshore Installations
(Emergency Pipeline Valve) Regulations 1989 SI 1989/1029
SPC/TECH/ED/49 Riser Emergency Shut Down Valve (ESDV) Leakage Assessment
Pipeline Riser emergency shut down valves - Inspection issues and
recommendations
(http://www.hse.gov.uk/pipelines/resources/emergencyshutdown.htm)
BS EN ISO 14723 Petroleum and natural gas industries. Pipeline transportation
systems. Subsea pipeline valves
4. Pipeline Integrity management standards
DNV Recommended Practice DNV-RP-F116 Integrity Management of Submarine
Pipeline Systems, 2009
DNV Recommended Practice DNV-RP-F206 Riser Integrity Management
Oil and GasUKGuidance Note: Monitoring Methods and Integrity Assurance for
Unbonded Flexible Pipe Rev 5 Oct 2002
API Technical Report 17TR2 The Ageing of PA-11 in Flexible Pipes
Oil and GasUKOP010 State of the Art Report on Flexible Pipe Integrity and
Guidance Note on Monitoring Methods and Integrity Assurance for Unbonded
Flexible Pipes
Energy Institute: Guidelines on integrity management of subsea facilities
PD 8010 Part 4 Risk-based integrity management of steel pipelines on land and
subsea pipelines (in preparation)
5. Pipeline operations
ISO 21329 Petroleum and natural gas industries. Pipeline transportation systems.
Test procedures for mechanical connectors
SPC/TECH/ED/18 Health & Safety Issues Associated with Changes from Dry Gas to
Wet Gas Operations
HSG 253 The safe isolation of plant and equipment, HSE Books, 2006, ISBN
9780717661718
HSE SPC/TECH/GEN/18 Underlagging Corrosion of Plant & Pipework