Ufgs 33 70 02.00 10 (Manhole Standards)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 67

**************************************************************************

USACE / NAVFAC / AFCEC / NASA UFGS-33 70 02.00 10 (November 2008)


-----------------------------------
Preparing Activity: USACE Superseding
UFGS-33 70 02.00 10 (October 2007)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2013
**************************************************************************
SECTION TABLE OF CONTENTS
DIVISION 33 - UTILITIES
SECTION 33 70 02.00 10
ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND
11/08
PART 1 GENERAL
1.1 REFERENCES
1.2 SYSTEM DESCRIPTION
1.3 SUBMITTALS
1.4 QUALITY ASSURANCE
1.4.1 Detail Drawings
1.4.2 As-Built Drawings
1.5 DELIVERY, STORAGE, AND HANDLING
1.6 EXTRA MATERIALS
PART 2 PRODUCTS
2.1 STANDARD PRODUCT
2.2 NAMEPLATES
2.2.1 General
2.2.2 Liquid-Filled Transformer Nameplates
2.3 CORROSION PROTECTION
2.3.1 Aluminum Materials
2.3.2 Ferrous Metal Materials
2.3.2.1 Hardware
2.3.2.2 Equipment
2.3.3 Finishing
2.4 CABLES
2.4.1 Medium-Voltage Cables
2.4.1.1 General
2.4.1.2 Ratings
2.4.1.3 Conductor Material
2.4.1.4 Insulation
2.4.1.5 Shielding
2.4.1.6 Neutrals
2.4.1.7 Jackets
2.4.2 Low-Voltage Cables
2.4.2.1 Conductor Material
2.4.2.2 Insulation
2.4.2.3 Jackets
SECTION 33 70 02.00 10 Page 1
2.4.2.4 Direct Buried
2.4.2.5 In Duct
2.5 CABLE JOINTS, TERMINATIONS, AND CONNECTORS
2.5.1 Medium-Voltage Cable Joints
2.5.2 Medium-Voltage Separable Insulated Connectors
2.5.3 Low-Voltage Cable Splices
2.5.4 Terminations
2.5.4.1 Factory Preformed Type
2.5.4.2 Taped Terminations
2.6 CONDUIT AND DUCTS
2.6.1 Metallic Conduit
2.6.2 Nonmetallic Ducts
2.6.2.1 Bituminized Fiber Duct
2.6.2.2 Concrete Encased Ducts
2.6.2.3 Direct Burial
2.6.3 Conduit Sealing Compound
2.7 MANHOLES, HANDHOLES, AND PULLBOXES
2.8 POLES AND HARDWARE
2.9 TRANSFORMERS, SUBSTATIONS, AND SWITCHGEAR
2.9.1 Secondary Unit Substation
2.9.1.1 Incoming Section
2.9.1.2 Transformer Section
2.9.1.3 Integral Outgoing Section
2.9.1.4 Nonintegral (Cable Compartment) Outgoing Section
2.9.2 Pad-Mounted Transformers
2.9.2.1 High-Voltage Compartments
2.9.2.2 Load-Break Switch
2.9.2.3 Transformer Tank Sections
2.9.2.4 Low-Voltage Cable Compartments
2.9.2.5 Accessories
2.9.3 Busways
2.9.4 Pad-Mounted, Metal-Enclosed, Switchgear
2.9.4.1 Ratings at 60 Hz shall be:
2.9.4.2 Operators, Devices, and Controls
2.9.4.3 Enclosures
2.9.5 Pad-Mounted Sectionalizers
2.9.5.1 Ratings
2.9.5.2 Enclosures
2.9.6 Cable Terminating Cabinets
2.10 METERING AND PROTECTIVE DEVICES
2.10.1 Circuit Breakers, Low-Voltage
2.10.1.1 Low-Voltage Power Circuit Breakers
2.10.1.2 Molded-Case Circuit Breakers
2.10.2 Fuses, Medium-Voltage, Including Current-Limiting
2.10.2.1 Construction
2.10.2.2 Ratings
2.10.2.3 E-Rated, Current-Limiting Power Fuses
2.10.2.4 C-Rated, Current-Limiting Power Fuses
2.10.3 Fuses, Low-Voltage, Including Current-Limiting
2.10.3.1 Cartridge Fuses
2.10.3.2 Transformer Circuit Fuses
2.10.4 Instrument Transformers
2.10.4.1 General
2.10.4.2 Current Transformers
2.10.4.3 Current Transformers for Power Transformers
2.10.4.4 Current Transformers for Metal-Enclosed Switchgear
2.10.4.5 Current Transformers for Kwh and Demand Metering
(Low-Voltage)
2.10.4.6 Voltage Transformers
SECTION 33 70 02.00 10 Page 2
2.10.5 Watthour Meters
2.10.6 Protective Relaying
2.10.6.1 General
2.10.6.2 Construction
2.10.6.3 Ratings
2.11 SURGE ARRESTERS
2.12 GROUNDING AND BONDING
2.12.1 Driven Ground Rods
2.12.2 Grounding Conductors
2.13 CONCRETE AND REINFORCEMENT
2.14 PADLOCKS
2.15 CABLE FIREPROOFING SYSTEMS
2.15.1 Fireproof Coating
2.15.2 Fireproofing Tape
2.15.3 Plastic Tape
2.16 LIQUID DIELECTRICS
2.17 FACTORY TESTS
2.18 FENCING
2.19 COORDINATED POWER SYSTEM PROTECTION
2.19.1 Scope of Analyses
2.19.2 Determination of Facts
2.19.3 Single Line Diagram
2.19.4 Fault Current Analysis
2.19.4.1 Method
2.19.4.2 Data
2.19.5 Coordination Study
2.19.6 Study Report
PART 3 EXECUTION
3.1 EXAMINATION
3.2 INSTALLATION REQUIREMENTS
3.2.1 Conformance to Codes
3.2.2 Disposal of Liquid Dielectrics
3.3 CABLE AND BUSWAY INSTALLATION
3.3.1 Cable Installation Plan and Procedure
3.3.1.1 Cable Inspection
3.3.1.2 Duct Cleaning
3.3.1.3 Duct Lubrication
3.3.1.4 Cable Installation
3.3.1.5 Cable Installation Plan
3.3.2 Duct Line
3.3.3 Direct-Burial
3.3.3.1 Trenching
3.3.3.2 Cable Burial
3.3.3.3 Other Requirements
3.3.3.4 Cable Joints or Splices
3.3.3.5 Cable Markers
3.3.4 Insect and Rodent Damage
3.3.5 Electric Manholes
3.3.6 Busway Installation
3.4 CABLE JOINTS
3.5 FIREPROOFING
3.5.1 Tape Method
3.5.2 Sprayable Method
3.6 DUCT LINES
3.6.1 Requirements
3.6.2 Treatment
3.6.3 Concrete Encasement
SECTION 33 70 02.00 10 Page 3
3.6.4 Nonencased Direct-Burial
3.6.5 Installation of Couplings
3.6.5.1 Bituminized-Fiber Ducts
3.6.5.2 Plastic Duct
3.6.6 Duct Line Markers
3.7 MANHOLES, HANDHOLES, AND PULLBOXES
3.7.1 General
3.7.2 Electric Manholes
3.7.3 Communications Manholes
3.7.4 Handholes
3.7.5 Pullboxes
3.7.6 Ground Rods
3.8 PAD-MOUNTED EQUIPMENT INSTALLATION
3.8.1 Concrete Pads
3.8.1.1 Construction
3.8.1.2 Concrete and Reinforcement
3.8.1.3 Sealing
3.8.2 Padlocks
3.8.3 Fencing
3.9 CONNECTIONS BETWEEN AERIAL AND UNDERGROUND SYSTEMS
3.10 CONNECTIONS TO BUILDINGS
3.11 GROUNDING
3.11.1 Grounding Electrodes
3.11.2 Grounding and Bonding Connections
3.11.3 Grounding and Bonding Conductors
3.11.4 Surge Arrester Grounding
3.11.5 Manhole, Handhole, or Concrete Pullbox Grounding
3.11.6 Metal Splice Case Grounding
3.11.7 Riser Pole Grounding
3.12 FIELD TESTING
3.12.1 General
3.12.2 Safety
3.12.3 Ground-Resistance Tests
3.12.4 Ground-Mat Connection Inspection
3.12.5 Medium-Voltage Cable Test
3.12.6 Low-Voltage Cable Test
3.12.7 Liquid-Filled Transformer Tests
3.12.8 Dry-Type Transformer Tests
3.12.9 Circuit Breaker Tests
3.12.10 Power Circuit Breaker Tests
3.12.11 Protective Relays
3.12.12 Pre-Energization Services
3.12.13 Operating Tests
3.13 MANUFACTURER'S FIELD SERVICE
3.13.1 Onsite Training
3.13.2 Installation Engineer
3.14 ACCEPTANCE
-- End of Section Table of Contents --
SECTION 33 70 02.00 10 Page 4
**************************************************************************
USACE / NAVFAC / AFCEC / NASA UFGS-33 70 02.00 10 (November 2008)
-----------------------------------
Preparing Activity: USACE Superseding
UFGS-33 70 02.00 10 (October 2007)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2013
**************************************************************************
SECTION 33 70 02.00 10
ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND
11/08
**************************************************************************
NOTE: This guide specification covers the
requirements for underground electrical distribution
systems.
Adhere to UFC 1-300-02 Unified Facilities Guide
Specifications (UFGS) Format Standard when editing
this guide specification or preparing new project
specification sections. Edit this guide
specification for project specific requirements by
adding, deleting, or revising text. For bracketed
items, choose applicable items(s) or insert
appropriate information.
Remove information and requirements not required in
respective project, whether or not brackets are
present.
Comments, suggestions and recommended changes for
this guide specification are welcome and should be
submitted as a Criteria Change Request (CCR).
**************************************************************************
PART 1 GENERAL
1.1 REFERENCES
**************************************************************************
NOTE: This paragraph is used to list the
publications cited in the text of the guide
specification. The publications are referred to in
the text by basic designation only and listed in
this paragraph by organization, designation, date,
and title.
Use the Reference Wizard's Check Reference feature
when you add a RID outside of the Section's
Reference Article to automatically place the
reference in the Reference Article. Also use the
Reference Wizard's Check Reference feature to update
the issue dates.
SECTION 33 70 02.00 10 Page 5
References not used in the text will automatically
be deleted from this section of the project
specification when you choose to reconcile
references in the publish print process.
**************************************************************************
The publications listed below form a part of this specification to the
extent referenced. The publications are referred to within the text by the
basic designation only.
ALLIANCE FOR TELECOMMUNICATIONS INDUSTRY SOLUTIONS (ATIS)
ATIS ANSI O5.1 (2008) Wood Poles -- Specifications &
Dimensions
ASSOCIATION OF EDISON ILLUMINATING COMPANIES (AEIC)
AEIC CS8 (2007) specification for Extruded
Dielectric Shielded Power Cables Rated 5
Through 46 kV
ASTM INTERNATIONAL (ASTM)
ASTM A123/A123M (2012) Standard Specification for Zinc
(Hot-Dip Galvanized) Coatings on Iron and
Steel Products
ASTM A153/A153M (2009) Standard Specification for Zinc
Coating (Hot-Dip) on Iron and Steel
Hardware
ASTM A48/A48M (2003; R 2012) Standard Specification for
Gray Iron Castings
ASTM B117 (2011) Standard Practice for Operating
Salt Spray (Fog) Apparatus
ASTM B231/B231M (2012) Standard Specification for
Concentric-Lay-Stranded Aluminum 1350
Conductors
ASTM B3 (2012) Standard Specification for Soft or
Annealed Copper Wire
ASTM B400 (2008) Standard Specification for Compact
Round Concentric-Lay-Stranded Aluminum
1350 Conductor
ASTM B496 (2013) Standard Specification for Compact
Round Concentric-Lay-Stranded Copper
Conductors
ASTM B609/B609M (2012) Standard Specification for Aluminum
1350 Round Wire, Annealed and Intermediate
Tempers, for Electrical purposes
ASTM B8 (2011) Standard Specification for
Concentric-Lay-Stranded Copper Conductors,
SECTION 33 70 02.00 10 Page 6
Hard, Medium-Hard, or Soft
ASTM B800 (2005; R 2011) Standard Specification for
8000 Series Aluminum Alloy Wire for
Electrical Purposes-Annealed and
Intermediate Tempers
ASTM B801 (2007; R 2012) Standard Specification for
Concentric-Lay-Stranded Conductors of 8000
Series Aluminum Alloy for Subsequent
Covering or Insulation
ASTM C478 (2013) Standard Specification for Precast
Reinforced Concrete Manhole Sections
ASTM C478M (2013) Standard Specification for Precast
Reinforced Concrete Manhole Sections
(Metric)
ASTM D1654 (2008) Evaluation of Painted or Coated
Specimens Subjected to Corrosive
Environments
ASTM D2472 (2000; R 2006) Standard Specification for
Sulphur Hexafluoride
ASTM D4059 (2000; R 2010) Analysis of Polychlorinated
Biphenyls in Insulating Liquids by Gas
Chromatography
ASTM D923 (2007) Standard Practice for Sampling
Electrical Insulating Liquids
FM GLOBAL (FM)
FM APP GUIDE (updated on-line) Approval Guide
http://www.approvalguide.com/
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 242 (2001; Errata 2003) Recommended Practice
for Protection and Coordination of
Industrial and Commercial Power Systems -
Buff Book
IEEE 386 (2006; INT 1 2011) Standard for Separable
Insulated Connector Systems for Power
Distribution Systems Above 600V
IEEE 399 (1997) Brown Book IEEE Recommended
Practice for Power Systems Analysis
IEEE 404 (2012) Standard for Extruded and Laminated
Dielectric Shielded Cable Joints Rated
2500 V to 500,000 V
IEEE 48 (2009) Standard for Test Procedures and
Requirements for Alternating-Current Cable
Terminations Used on Shielded Cables
SECTION 33 70 02.00 10 Page 7
Having Laminated Insulation Rated 2.5 kV
through 765 kV or Extruded Insulation
Rated 2.5 kV through 500 kV
IEEE 81 (2012) Guide for Measuring Earth
Resistivity, Ground Impedance, and Earth
Surface Potentials of a Ground System
IEEE C135.30 (1988) Standard for Zinc-Coated Ferrous
Ground Rods for Overhead or Underground
Line Construction
IEEE C2 (2012; Errata 2012; INT 1-4 2012; INT 5
2013) National Electrical Safety Code
IEEE C37.1 (2007) Standard for Supervisory Control,
Data Acquisition (SCADA) and Automatic
Systems
IEEE C37.121 (2012) American National Standard for
Switchgear-Unit Substations - Requirements
IEEE C37.13 (2008; INT 1 2009; AMD 1 2012) Standard
for Low-Voltage AC Power Circuit Breakers
Used in Enclosures
IEEE C37.16 (2009) Standard for Preferred Ratings,
Related Requirements, and Application
Recommendations for Low-Voltage AC (635 V
and below) and DC 3200 V and below) Power
Circuit Breakers
IEEE C37.2 (2008) Standard for Electrical Power
System Device Function Numbers, Acronyms
and Contact Designations
IEEE C37.20.1 (2002; INT 1 2005; AMD A 2005; AMD B 2006;
R 2007) Standard for Metal-Enclosed
Low-Voltage Power Circuit-Breaker
Switchgear
IEEE C37.20.2 (1999; Corr 2000; R 2005) Standard for
Metal-Clad Switchgear
IEEE C37.20.3 (2001; R 2006) Standard for Metal-Enclosed
Interrupter Switchgear
IEEE C37.23 (2003; R 2008) Standard for Metal-Enclosed
Bus
IEEE C37.30 (1997; INT 1 2011) Standard Requirements
for High-Voltage Switches
IEEE C37.34 (1994) Standard Test Code for High-Voltage
Air Switches
IEEE C37.41 (2008; Errata 2009) Standard Design Tests
for High-Voltage (>1000 V) Fuses, Fuse and
Disconnecting Cutouts, Distribution
SECTION 33 70 02.00 10 Page 8
Enclosed Single-Pole Air Switches, Fuse
Disconnecting Switches, and Accessories
Used with These Devices
IEEE C37.46 (2010) Standard for High Voltage Expulsion
and Current-Limiting Type Power Class
Fuses and Fuse Disconnecting Switches
IEEE C37.63 (2013) Standard Requirements for Overhead,
Pad-Mounted, Dry-Vault, and Submersible
Automatic Line Sectionalizers for AC
Systems
IEEE C37.90 (2005) Standard for Relays and Relay
Systems Associated With Electric Power
Apparatus
IEEE C37.90.1 (2012) Standard for Surge Withstand
Capability (SWC) Tests for Relays and
Relay Systems Associated with Electric
Power Apparatus
IEEE C57.12.00 (2010) Standard General Requirements for
Liquid-Immersed Distribution, Power, and
Regulating Transformers
IEEE C57.12.21 (1992) Pad-Mounted, Compartmental-Type
Self-Cooled, Single-Phase Distribution
Transformers With High Voltage Bushings;
High-voltage, 34,500 GRYD/19,920 Volts
IEEE C57.12.26 (1992) Pad-Mounted Compartmental-Type,
Self-Cooled, Three-Phase Distribution
Transformers for Use with Separable
Insulated High-Voltage Connectors
IEEE C57.12.28 (2005; INT 3 2011) Standard for
Pad-Mounted Equipment - Enclosure Integrity
IEEE C57.13 (2008; INT 2009) Standard Requirements for
Instrument Transformers
IEEE C57.98 (2011) Guide for Transformer Impulse Tests
IEEE C62.11 (2012) Standard for Metal-Oxide Surge
Arresters for Alternating Current Power
Circuits (>1kV)
INTERNATIONAL ELECTROTECHNICAL COMMISSION (IEC)
IEC 60255-21-3 (1993; ED 1.0) Electrical Relays - Part
21: Vibration, Shock, Bump And Seismic
Tests On Measuring Relays And Protection
Equipment - Section 3: Seismic Tests
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
ANSI C119.1 (2011) Electric Connectors - Sealed
Insulated Underground Connector Systems
SECTION 33 70 02.00 10 Page 9
Rated 600 Volts
ANSI C29.1 (1988; R 2012) American National Standard
for Electrical Power Insulators--Test
Methods
ANSI C80.1 (2005) American National Standard for
Electrical Rigid Steel Conduit (ERSC)
NEMA BU 1.1 (2010) General Instructions for Proper
Handling, Installation, Operation and
Maintenance of Busway Rated 600 V or Less
NEMA C12.4 (1984; R 2011) Registers - Mechanical
Demand
NEMA C37.50 (2012) American National Standard for
Switchgear--Low-Voltage AC Power Circuit
Breakers Used in Enclosures - Test
Procedures
NEMA FB 1 (2012) Standard for Fittings, Cast Metal
Boxes, and Conduit Bodies for Conduit,
Electrical Metallic Tubing, and Cable
NEMA FU 1 (2002; R 2007) Low Voltage Cartridge Fuses
NEMA LA 1 (2009) Standard for Surge Arresters
NEMA PB 1 (2011) Panelboards
NEMA PB 2 (2011) Deadfront Distribution Switchboards
NEMA SG 2 (1993) Standard for High-Voltage Fuses
NEMA TC 6 & 8 (2003) Standard for Polyvinyl Chloride
(PVC) Plastic Utilities Duct for
Underground Installations
NEMA TC 7 (2013) Standard for Smooth-Wall Coilable
Electrical Polyethylene Conduit
NEMA/ANSI C12.10 (2011) Physical Aspects of Watthour Meters
- Safety Standards
NEMA/ANSI C12.11 (2007) Instrument Transformers for Revenue
Metering, 10 kV BIL through 350 kV BIL
(0.6 kV NSV through 69 kV NSV)
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2014) National Electrical Code
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 3-310-04 (2012) Seismic Design for Buildings
SECTION 33 70 02.00 10 Page 10
UNDERWRITERS LABORATORIES (UL)
UL 1072 (2006; Reprint Jun 2013) Medium-Voltage
Power Cables
UL 1242 (2006; Reprint Jul 2012) Standard for
Electrical Intermediate Metal Conduit --
Steel
UL 198M (2003; Reprint Feb 2013) Standard for
Mine-Duty Fuses
UL 2420 (2009; Reprint Sep 2012) UL Standard for
Safety Belowground Reinforced
Thermosetting Resin Conduit (RTRC) and
Fittings
UL 2515 (2009; Reprint Sep 2012) UL Standard for
Safety Aboveground Reinforced
Thermosetting Resin Conduit (RTRC) and
Fittings
UL 467 (2007) Grounding and Bonding Equipment
UL 486A-486B (2013) Wire Connectors
UL 489 (2013) Molded-Case Circuit Breakers,
Molded-Case Switches, and Circuit-Breaker
Enclosures
UL 510 (2005; Reprint Jul 2013) Polyvinyl
Chloride, Polyethylene and Rubber
Insulating Tape
UL 514A (2013) Metallic Outlet Boxes
UL 6 (2007; reprint Nov 2010) Electrical Rigid
Metal Conduit-Steel
UL 651 (2011; Reprint Mar 2012) Standard for
Schedule 40 and 80 Rigid PVC Conduit and
Fittings
UL 854 (2004; Reprint Sep 2011) Standard for
Service-Entrance Cables
UL 857 (2009; Reprint Dec 2011) Busways
1.2 SYSTEM DESCRIPTION
**************************************************************************
NOTE: Select the features and fill in blanks with
selections appropriate for the design condition and
in accordance with guidance contained in UFC
3-550-01.
See UFC 3-550-01 for guidance regarding service
conditions. Retain or add the required conditions.
SECTION 33 70 02.00 10 Page 11
Provide seismic requirements, if a Government
designer is the Engineer of Record, and show on the
drawings. Delete the inappropriate bracketed
phrase. Pertinent portions of UFC 3-310-04 and
Sections 13 48 00 and 26 05 48.00 10, properly
edited, must be included in the contract documents.
**************************************************************************
Items provided under this section shall be specifically suitable for the
following service conditions. Seismic details shall [conform to
UFC 3-310-04 and Sections 13 48 00 SEISMIC PROTECTION FOR MISCELLANEOUS
EQUIPMENT and 26 05 48.00 10 SEISMIC PROTECTION FOR ELECTRICAL EQUIPMENT]
[be as indicated].
a. Fungus Control [_____]
b. Altitude [_____] m feet.
c. Ambient Temperature [_____] degrees C F.
d. Frequency [_____]
e. Ventilation [_____]
f. Seismic Parameters [_____]
g. Humidity Control [_____]
h. Corrosive Areas [_____]
i. [_____]
1.3 SUBMITTALS
**************************************************************************
NOTE: Review submittal description (SD) definitions
in Section 01 33 00 SUBMITTAL PROCEDURES and edit
the following list to reflect only the submittals
required for the project.
The Guide Specification technical editors have
designated those items that require Government
approval, due to their complexity or criticality,
with a "G." Generally, other submittal items can be
reviewed by the Contractor's Quality Control
System. Only add a G to an item, if the submittal
is sufficiently important or complex in context of
the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
SECTION 33 70 02.00 10 Page 12
following the "G" typically are not used for Navy,
Air Force, and NASA projects.
Choose the first bracketed item for Navy, Air Force
and NASA projects, or choose the second bracketed
item for Army projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control
approval.] [information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Detail Drawings[; G][; G, [_____]]
As-Built Drawings[; G][; G, [_____]]
SD-03 Product Data
Fault Current Analysis[; G][; G, [_____]]
Protective Device[; G][; G, [_____]]
Coordination Study[; G][; G, [_____]]
Nameplates[; G][; G, [_____]]
Material and Equipment[; G][; G, [_____]]
Installation Requirements[; G][; G, [_____]]
SD-06 Test Reports
Factory Tests
Field Testing
Operating Tests
Cable Installation
SD-07 Certificates
Material and Equipment
Cable Joints
Installation Engineer
SD-10 Operation and Maintenance Data
Operation and Maintenance Manuals
1.4 QUALITY ASSURANCE
1.4.1 Detail Drawings
Submit detail drawings consisting of equipment drawings, illustrations,
schedules, instructions, diagrams manufacturers standard installation
drawings and other information necessary to define the installation and
enable the Government to check conformity with the requirements of the
contract drawings.
a. If departures from the contract drawings are deemed necessary by the
Contractor, complete details of such departures shall be included with
the detail drawings. Approved departures shall be made at no
SECTION 33 70 02.00 10 Page 13
additional cost to the Government.
b. Detail drawings shall show how components are assembled, function
together and how they will be installed on the project. Data and
drawings for component parts of an item or system shall be coordinated
and submitted as a unit. Data and drawings shall be coordinated and
included in a single submission. Multiple submissions for the same
equipment or system are not acceptable except where prior approval has
been obtained from the Contracting Officer. In such cases, a list of
data to be submitted later shall be included with the first
submission. Detail drawings shall consist of the following:
(1) Detail drawings showing physical arrangement, construction
details, connections, finishes, materials used in fabrication,
provisions for conduit or busway entrance, access requirements for
installation and maintenance, physical size, electrical
characteristics, foundation and support details, and equipment
weight. Drawings shall be drawn to scale and/or dimensioned. All
optional items shall be clearly identified as included or excluded.
(2) Internal wiring diagrams of equipment showing wiring as actually
provided for this project. External wiring connections shall be
clearly identified.
(3) Detail drawings shall as a minimum depict the installation of the
following items:
(a) Medium-voltage cables and accessories including cable
installation plan.
(b) Transformers.
(c) Substations.
(d) Switchgear.
(e) Pad-mounted loadbreak switches.
(f) Busways.
(g) Surge arresters.
1.4.2 As-Built Drawings
The as-built drawings shall be a record of the construction as installed.
The drawings shall include the information shown on the contract drawings
as well as deviations, modifications, and changes from the contract
drawings, however minor. The as-built drawings shall be a full sized set
of prints marked to reflect deviations, modifications, and changes. The
as-built drawings shall be complete and show the location, size,
dimensions, part identification, and other information. Additional sheets
may be added. The as-built drawings shall be jointly inspected for
accuracy and completeness by the Contractor's quality control
representative and by the Contracting Officer prior to the submission of
each monthly pay estimate. Upon completion of the work, provide three full
sized sets of the marked prints to the Contracting Officer for approval.
If upon review, the as-built drawings are found to contain errors and/or
omissions, they will be returned to the Contractor for correction. Correct
and return the as-built drawings to the Contracting Officer for approval
SECTION 33 70 02.00 10 Page 14
within 10 calendar days from the time the drawings are returned to the
Contractor.
1.5 DELIVERY, STORAGE, AND HANDLING
Visually inspect devices and equipment when received and prior to
acceptance from conveyance. Protect stored items from the environment in
accordance with the manufacturer's published instructions. Damaged items
shall be replaced. Store oil filled transformers and switches in
accordance with the manufacturer's requirements. Wood poles held in
storage for more than 2 weeks shall be stored in accordance with
ATIS ANSI O5.1. Handle wood poles in accordance with ATIS ANSI O5.1,
except that pointed tools capable of producing indentations more than 25 mm
1 inch in depth shall not be used. Metal poles shall be handled and stored
in accordance with the manufacturer's instructions.
1.6 EXTRA MATERIALS
One additional spare fuse or fuse element for each furnished fuse or fuse
element shall be delivered to the contracting officer when the electrical
system is accepted. Two complete sets of all special tools required for
maintenance shall be provided, complete with a suitable tool box. Special
tools are those that only the manufacturer provides, for special purposes
(to access compartments, or operate, adjust, or maintain special parts).
PART 2 PRODUCTS
2.1 STANDARD PRODUCT
Provide material and equipment which are the standard product of a
manufacturer regularly engaged in the manufacture of the product and that
essentially duplicate items that have been in satisfactory use for at least
2 years prior to bid opening. Items of the same classification shall be
identical including equipment, assemblies, parts, and components.
a. Submit a complete itemized listing of equipment and materials
proposed for incorporation into the work. Each entry shall include an
item number, the quantity of items proposed, and the name of the
manufacturer of each such item.
b. Where materials or equipment are specified to conform to the
standards of the Underwriters Laboratories (UL) or to be constructed or
tested, or both, in accordance with the standards of the American
National Standards Institute (ANSI), the Institute of Electrical and
Electronics Engineers (IEEE), or the National Electrical Manufacturers
Association (NEMA), submit proof that the items provided conform to
such requirements. The label of, or listing by, UL will be acceptable
as evidence that the items conform. Either a certification or a
published catalog specification data statement, to the effect that the
item is in accordance with the referenced ANSI or IEEE standard, will
be acceptable as evidence that the item conforms. A similar
certification or published catalog specification data statement to the
effect that the item is in accordance with the referenced NEMA
standard, by a company listed as a member company of NEMA, will be
acceptable as evidence that the item conforms.
c. In lieu of such certification or published data, the Contractor may
submit a certificate from a recognized testing agency equipped and
competent to perform such services, stating that the items have been
SECTION 33 70 02.00 10 Page 15
tested and that they conform to the requirements listed, including
methods of testing of the specified agencies. Compliance with
above-named requirements does not relieve the Contractor from
compliance with any other requirements of the specifications.
2.2 NAMEPLATES
Submit catalog cuts, brochures, circulars, specifications, product data,
and printed information in sufficient detail and scope to verify compliance
with the requirements of the contract documents.
2.2.1 General
Each major component of this specification shall have the manufacturer's
name, address, type or style, model or serial number, and catalog number on
a nameplate securely attached to the equipment. Nameplates shall be made
of noncorrosive metal. Equipment containing liquid dielectrics shall have
the type of dielectric on the nameplate. Sectionalizer switch nameplates
shall have a schematic with all switch positions shown and labeled. As a
minimum, nameplates shall be provided for transformers, circuit breakers,
meters, switches, and switchgear.
2.2.2 Liquid-Filled Transformer Nameplates
**************************************************************************
NOTE: Coordinate nameplate information with the
manufacturer. Select 50 ppm for Army projects and 2
ppm for Air Force projects.
**************************************************************************
Power transformers shall be provided with nameplate information in
accordance with IEEE C57.12.00. Nameplates shall indicate the number of
liters gallons and composition of liquid-dielectric, and shall be
permanently marked with a statement that the transformer dielectric to be
supplied is non-polychlorinated biphenyl. If transformer nameplate is not
so marked, furnish manufacturer's certification for each transformer that
the dielectric is non-PCB classified, with less than [50] [2] ppm PCB
content in accordance with paragraph LIQUID DIELECTRICS. Certifications
shall be related to serial numbers on transformer nameplates. Transformer
dielectric exceeding the [50] [2] ppm PCB content or transformers without
certification will be considered as PCB insulated and will not be accepted.
2.3 CORROSION PROTECTION
2.3.1 Aluminum Materials
[Aluminum shall not be used in contact with earth or concrete. Where
aluminum conductors are connected to dissimilar metal, fittings conforming
to UL 486A-486B shall be used.][Aluminum shall not be used.]
2.3.2 Ferrous Metal Materials
2.3.2.1 Hardware
Ferrous metal hardware shall be hot-dip galvanized in accordance with
ASTM A153/A153M and ASTM A123/A123M.
SECTION 33 70 02.00 10 Page 16
2.3.2.2 Equipment
**************************************************************************
NOTE: A 120-hour test will be specified in a
noncorrosive environment and a 480-hour test will be
specified in a corrosive environment.
**************************************************************************
Equipment and component items, including but not limited to transformer
stations and ferrous metal luminaries not hot-dip galvanized or porcelain
enamel finished, shall be provided with corrosion-resistant finishes which
shall withstand [120] [480] [_____] hours of exposure to the salt spray
test specified in ASTM B117 without loss of paint or release of adhesion of
the paint primer coat to the metal surface in excess of 1.6 mm 1/16 inch
from the test mark. The scribed test mark and test evaluation shall be in
accordance with ASTM D1654 with a rating of not less than 7 in accordance
with TABLE 1, (procedure A). Cut edges or otherwise damaged surfaces of
hot-dip galvanized sheet steel or mill galvanized sheet steel shall be
coated with a zinc rich paint conforming to the manufacturer's standard.
2.3.3 Finishing
Painting required for surfaces not otherwise specified and finish painting
of items only primed at the factory shall be as specified in Section
09 90 00 PAINTS AND COATINGS.
2.4 CABLES
**************************************************************************
NOTE: Justify selection of copper or aluminum,
based upon an analysis using life-cycle,
environmental, and cost factors. Refer to UFC
3-550-01 for guidance regarding cables.
**************************************************************************
Cables shall be single conductor type unless otherwise indicated.
2.4.1 Medium-Voltage Cables
**************************************************************************
NOTE: Medium voltage cables are complex and
sophisticated products that can be manufactured to
have very specific properties for the installed
environment. The two most commonly
produced/specified medium voltage cables are Type MV
(as described in UL 1072) and underground
distribution ("UD/URD"), commonly used by electrical
utilities. Type MV is a type designation recognized
by NFPA 70 because it is UL listed. "UD/URD" is not
a recognized type designation because it is utilized
primarily by electrical utilities, who are not
governed by NFPA 70 and for whom a UL listed cable
adds unnecessary expense. Both type MV and "UD/URD"
can be specified for use in duct or direct buried.
Type MV cable are typically manufactured with copper
or aluminum conductors; an extruded semi-conductor
conductor shield; ethylene-propylene rubber (EPR) or
cross-linked polyethylene (XLP) insulation; an
insulation shield consisting of extruded
SECTION 33 70 02.00 10 Page 17
semi-conductor and metal tape; and a polyvinyl
chloride (PVC) jacket. "UD/URD" cables are
typically manufactured with copper or aluminum
conductors; an extruded semi-conductor conductor
shield; an insulation shield consisting of extruded
semi-conductor and metal tape, or extruded
semi-conductor with concentric-wound copper drain
wires; cross-linked polyethylene (XLP) insulation; a
concentric neutral; and a polyethylene jacket. A
cable can be made from almost any combination of
conductors, insulations, shields and jackets;
therefore, the designer needs to specify a cable
that meets the needs of the application. Utilize
either Type MV or "UD/URD" in ducts, keeping in mind
that the concentric neutral affects bending radius
and pulling tensions, therefore limiting the maximum
pull and distance between manholes. Utilize "UD"
for direct buried applications. Select full
ampacity concentric neutral for single-phase
applications and one-third ampacity for three-phase
applications.
**************************************************************************
2.4.1.1 General
Cable construction shall be [Type MV, conforming to NFPA 70 and UL 1072]
[concentric neutral underground distribution cable conforming to AEIC CS8]
[metallic armored cables, consisting of three-conductor, multi-conductor
cables, with insulation and shielding, as specified, using [a galvanized
steel] [an aluminum] interlocked tape armor and thermoplastic jacket].
Cables shall be manufactured for use in [duct] [or] [direct burial]
applications [as indicated].
2.4.1.2 Ratings
Cables shall be rated for a circuit voltage[ of] [5 kV] [15 kV] [25 kV] [28
kV] [35 kV][ as indicated].
2.4.1.3 Conductor Material
**************************************************************************
NOTE: A concentric compressed conductor has a
diameter that is 3 percent less than a regular
concentric conductor. A compact conductor has a
diameter that is 10 percent less than a regular
concentric conductor. Specify compressed or compact
conductors where necessary to limit duct fill (i.e.
where new conductors are installed in existing
dusts). When aluminum is exposed to water,
oxidation occurs. To prevent oxidation, the
conductor is filled with insulation. Add filled
conductor requirement if needed.
**************************************************************************
Underground cables shall be [soft drawn copper complying with ASTM B3 and
ASTM B8 for regular concentric and compressed stranding or ASTM B496 for
compact stranding] [aluminum alloy 1350, 3/4 hard minimum complying with
ASTM B609/B609M and ASTM B231/B231M for regular concentric and compressed
stranding or ASTM B400 for compacted stranding].
SECTION 33 70 02.00 10 Page 18
2.4.1.4 Insulation
**************************************************************************
NOTE: In addition to the standard MV-90, NFPA 70
also lists an MV-105 temperature rating. However,
MV-105 is not available from all manufacturers.
Provide MV-105, only if needed. For projects which
require multiple types of insulations, or special
types of cables, such as submarine cable, indicate
the type for each cable on the project drawings.
Choose XLP or tree retardant XLP for "UD or URD"
cable, and either XLP or EPR for Type MV cable.
**************************************************************************
Cable insulation shall be [cross-linked thermosetting polyethylene (XLP)
insulation conforming to the requirements of AEIC CS8]
[ethylene-propylene-rubber (EPR) insulation conforming to the requirements
of AEIC CS8] [_____]. A 133 percent insulation level shall be used on 5
kV, 15 kV and 25 kV rated cables. Comply with EPA requirements in
accordance with Section 01 62 35 RECYCLED/RECOVERED/BIOBASED MATERIALS.
2.4.1.5 Shielding
**************************************************************************
NOTE: IEEE C2 requires the cable conductor shield
to have sufficient ampacity to withstand the effects
of available fault current without damage to the
conductor (except in the vicinity of the fault).
The designer should provide the expected maximum
available ground fault current, so the cable
manufacturer can size the shield. Testing has shown
that for grounded medium voltage systems where a
bare ground fault return conductor is installed with
phase conductors in metallic duct, 3 percent - 14
percent of the available fault current returns along
the cable shield. A separate ground fault return
conductor (bare copper wire or metallic duct) should
always be provided. For circuits not installed in
metallic duct, with a ground fault return conductor
supplied, the shield can be sized to conduct (until
the protective device operates) 15 percent of the
available fault current per cable. Where the
available fault current is unknown or cannot be
determined, the designer should provide a # 2/0 AWG
bare copper ground conductor and delete the ground
fault ampacity statement.
**************************************************************************
Cables rated for 2 kV and above shall have a semiconducting conductor
shield, a semiconducting insulation shield, and an overall copper [tape]
[wire] shield for each phase. The shield [tape] [wire] shall be sized to
meet IEEE C2 requirements for a ground fault availability of [_____]
amperes.
2.4.1.6 Neutrals
**************************************************************************
NOTE: Where high impedance grounded neutral systems
SECTION 33 70 02.00 10 Page 19
are employed, add the following requirement for the
neutral to be fully insulated. For high impedance
grounded neutral systems, the neutral conductors
from the neutral point of the transformer or
generator to the connection point at the impedance
shall utilize [copper] [aluminum] conductors,
employing the same insulation level and construction
as the phase conductors.
**************************************************************************
[Neutral conductors of shall be [copper] [aluminum]. employing the same
insulation and jacket materials as phase conductors, except that a 600-volt
insulation rating is acceptable.] [Concentric neutrals conductors shall be
tinned copper, having a combined ampacity [equal to] [1/3 of] the phase
conductor ampacity rating.]
2.4.1.7 Jackets
**************************************************************************
NOTE: PVC is acceptable for duct applications.
Polyethylene is exceptional for direct burial and in
duct applications where there is significant amounts
of water. There are many other types of jacket
materials available (neoprene, hypalon,
thermoplastic CPE) for special environments
involving exposure to sunlight, petroleum products,
and corrosive chemicals. Consult local cable
representatives to specify the appropriate jacket
for the application.
**************************************************************************
Cables shall be provided with a [PVC] [polyethylene] [_____] jacket.
Direct buried cables shall be rated for direct burial.
2.4.2 Low-Voltage Cables
**************************************************************************
NOTE: Coilable plastic duct may be used as an
alternative to direct burial where extra physical
protection is required. For project applications
which require a different insulation than those
listed below, reference a Government or industry
standard that the cable must meet. For projects
which require multiple types of insulations,
indicate the type for each cable on the project
drawings. See also UFC 3-520-01.
**************************************************************************
Cables shall be rated 600 volts and shall conform to the requirements of
NFPA 70, and must be UL listed for the application or meet the applicable
section of either ICEA or NEMA standards.
2.4.2.1 Conductor Material
Underground cables shall be [annealed copper complying with ASTM B3 and
ASTM B8] [Type AA-8000 aluminum conductors complying with ASTM B800 and
ASTM B801]. Intermixing of copper and aluminum conductors is not permitted.
SECTION 33 70 02.00 10 Page 20
2.4.2.2 Insulation
Insulation must be in accordance with NFPA 70, and must be UL listed for
the application or meet the applicable sections of either ICEA, or NEMA
standards.
2.4.2.3 Jackets
Multiconductor cables shall have an overall [PVC] [_____] outer jacket.
2.4.2.4 Direct Buried
Single and multi-conductor cables shall of a type identified for direct
burial. Service entrance cables shall conform to UL 854 for Type USE
service entrance cable.
2.4.2.5 In Duct
Cables shall be single-conductor cable, in accordance with NFPA 70.
[Cables in factory-installed, coilable-plastic-duct assemblies shall
conform to NEMA TC 7].
2.5 CABLE JOINTS, TERMINATIONS, AND CONNECTORS
2.5.1 Medium-Voltage Cable Joints
Medium-voltage cable joints shall comply with IEEE 404. Medium-voltage
cable terminations shall comply with IEEE 48. Joints shall be the standard
products of a manufacturer and shall be either of the factory preformed
type or of the kit type containing tapes and other required parts. Joints
shall have ratings not less than the ratings of the cables on which they
are installed. Splice kits may be of the heat-shrinkable type for voltages
up to 15 kV, of the premolded splice and connector type, the conventional
taped type, or the resin pressure-filled overcast taped type for voltages
up to 35 kV; except that for voltages of 7.5 kV or less a resin
pressure-filled type utilizing a plastic-tape mold is acceptable. Joints
used in manholes, handholes, vaults and pull boxes shall be certified by
the manufacturer for waterproof, submersible applications.
2.5.2 Medium-Voltage Separable Insulated Connectors
**************************************************************************
NOTE: Separable connectors shall not be used in
manholes (except where necessary for reason of
clearance at an airfield). Loadbreak types are
rated by IEEE 386 up to 200 amperes. Provide test
points only where the local facilities engineer
indicates that it is an operational requirement. If
loadbreak separable connectors are allowed as
substitutes for conventional permanent splices, the
Using Agency often presumes that the intent was that
they could be used for "switching functions." This
type of generic approach can allow unsafe
configurations with inadequate space for proper
hookstick operation. This substitution is
prohibited.
**************************************************************************
Separable insulated connectors shall comply with IEEE 386 and shall be of
SECTION 33 70 02.00 10 Page 21
suitable construction or standard splice kits shall be used. Separable
insulated connectors are acceptable for voltages up to 35 kV. Connectors
shall be of the loadbreak type as indicated, of suitable construction for
the application and the type of cable connected, and shall include cable
shield adaptors. Separable insulated connectors shall not be used as
substitutes for conventional permanent splices. External clamping points
and test points shall be provided.
2.5.3 Low-Voltage Cable Splices
Low-voltage cable splices and terminations shall be rated at not less than
600 Volts. Splices in conductors No. 10 AWG and smaller shall be made with
an insulated, solderless, pressure type connector, conforming to the
applicable requirements of UL 486A-486B. Splices in conductors No. 8 AWG
and larger shall be made with noninsulated, solderless, pressure type
connector, conforming to the applicable requirements of UL 486A-486B.
Splices shall then be covered with an insulation and jacket material
equivalent to the conductor insulation and jacket. Splices below grade or
in wet locations shall be sealed type conforming to ANSI C119.1 or shall be
waterproofed by a sealant-filled, thick wall, heat shrinkable,
thermosetting tubing or by pouring a thermosetting resin into a mold that
surrounds the joined conductors.
2.5.4 Terminations
Terminations shall be in accordance with IEEE 48, Class 1 or Class 2; of
the molded elastomer, wet-process porcelain, prestretched elastomer,
heat-shrinkable elastomer, or taped type. Acceptable elastomers are
track-resistant silicone rubber or track-resistant ethylene propylene
compounds, such as ethylene propylene rubber or ethylene propylene diene
monomer. Separable insulated connectors may be used for apparatus
terminations, when such apparatus is provided with suitable bushings.
Terminations shall be of the outdoor type, except that where installed
inside outdoor equipment housings which are sealed against normal
infiltration of moisture and outside air, indoor, Class 2 terminations are
acceptable. Class 3 terminations are not acceptable. Terminations, where
required, shall be provided with mounting brackets suitable for the
intended installation and with grounding provisions for the cable
shielding, metallic sheath, and armor.
2.5.4.1 Factory Preformed Type
**************************************************************************
NOTE: Specify IEEE 48 test in areas of heavy fog,
salt air, or industrial contamination. Specify
track resistant tape in high humidity areas with
dust and industrial contaminants.
**************************************************************************
Molded elastomer, wet-process porcelain, prestretched, and heat-shrinkable
terminations shall utilize factory preformed components to the maximum
extent practicable rather than tape build-up. Terminations shall have
basic impulse levels as required for the system voltage level. [Leakage
distances shall comply with wet withstand voltage test requirements of
IEEE 48 for the next higher Basic Insulation Level (BIL) level.]
[Anti-tracking tape shall be applied over exposed insulation of preformed
molded elastomer terminations].
SECTION 33 70 02.00 10 Page 22
2.5.4.2 Taped Terminations
**************************************************************************
NOTE: Normally, specify 317.5 mm (12-1/2 in.) for 5
kV cable, 508.0 mm (20 in.) for 15 kV cable, 635.0
mm (25 in.) for 25 kV cable, and 889.0 mm (35 in.)
for 28 kV or 35 kV cable. In contaminated areas,
specify next higher voltage level lengths, and
1168.4 mm (46 inches) for 28 kV or 35 kV cables.
**************************************************************************
Taped terminations shall use standard termination kits providing terminal
connectors, field-fabricated stress cones, and rain hoods. Terminations
shall be at least [315][510][635][890][1200] mm [12-1/2] [20][25][35][46]
inches long from the end of the tapered cable jacket to the start of the
terminal connector, or not less than the kit manufacturer's
recommendations, whichever is greater.
2.6 CONDUIT AND DUCTS
**************************************************************************
NOTE: Specify thin-wall for encased burial and
thick-wall for direct burial. Communication lines
run elsewhere will comply with communication
agency's policy.
**************************************************************************
[Ducts shall be single, round-bore type, with wall thickness and fittings
suitable for the application.] [Duct lines shall be concrete-encased,
thin-wall type.] [Duct lines shall be nonencased direct-burial, thick-wall
type.][Duct lines shall be concrete-encased, thin-wall type for duct lines
between manholes and for other medium-voltage lines.][[Low-voltage lines]
[or] [Communication lines] run elsewhere may be direct-burial, thick-wall
type.][Where concrete encasement is not required, low-voltage circuits may
utilize factory-installed cable in coilable plastic duct.]
2.6.1 Metallic Conduit
Intermediate metal conduit shall comply with UL 1242. Rigid galvanized
steel conduit shall comply with UL 6 and ANSI C80.1. Metallic conduit
fittings and outlets shall comply with UL 514A and NEMA FB 1.
2.6.2 Nonmetallic Ducts
**************************************************************************
NOTE: Bituminized fiber duct should be specified
only for connection to existing bituminized fiber
duct systems. Delete the paragraph if not
required. Specify thin-wall or schedule 40 plastic
duct for concrete encasement and thick-wall or
schedule 40 or schedule 80 plastic duct for
direct-burial and riser applications (riser bends
should be metallic conduit where cables are to be
pulled into ductline).
**************************************************************************
2.6.2.1 Bituminized Fiber Duct
[UL 2420] [UL 2515] for [Type I (Thinwall)][Type II (Thickwall)].
SECTION 33 70 02.00 10 Page 23
2.6.2.2 Concrete Encased Ducts
UL 651 Schedule 40 or NEMA TC 6 & 8 Type EB.
2.6.2.3 Direct Burial
UL 651 [Schedule 40][and][Schedule 80][as indicated], or NEMA TC 6 & 8 Type
DB.
2.6.3 Conduit Sealing Compound
Compounds for sealing ducts and conduit shall have a putty-like consistency
workable with the hands at temperatures as low as 2 degrees C 35 degrees F,
shall neither slump at a temperature of 150 degrees C 300 degrees F, nor
harden materially when exposed to the air. Compounds shall adhere to clean
surfaces of fiber or plastic ducts; metallic conduits or conduit coatings;
concrete, masonry, or lead; any cable sheaths, jackets, covers, or
insulation materials; and the common metals. Compounds shall form a seal
without dissolving, noticeably changing characteristics, or removing any of
the ingredients. Compounds shall have no injurious effect upon the hands
of workmen or upon materials.
2.7 MANHOLES, HANDHOLES, AND PULLBOXES
**************************************************************************
NOTE: Actual strength figures may need to be
adjusted to accommodate various manufacturers of
glass reinforced polymer boxes.
**************************************************************************
Manholes, handholes, and pullboxes shall be as indicated. Strength of
manholes, handholes, and pullboxes and their frames and covers shall
conform to the requirements of IEEE C2. Precast-concrete manholes shall
have the required strength established by ASTM C478, ASTM C478M. Frames
and covers shall be made of gray cast iron and a machine-finished seat
shall be provided to ensure a matching joint between frame and cover. Cast
iron shall comply with ASTM A48/A48M, Class 30B, minimum. Handholes for
low voltage cables installed in parking lots, sidewalks, and turfed areas
shall be fabricated from an aggregate consisting of sand and with
continuous woven glass strands having an overall compressive strength of at
least [69] [_____] MPa [10,000] [_____] psi and a flexural strength of at
least [34.5] [_____] MPa [5,000] [_____] psi. Pullbox and handhole covers
in sidewalks, and turfed areas shall be of the same material as the box.
Concrete pullboxes shall consist of precast reinforced concrete boxes,
extensions, bases, and covers.
2.8 POLES AND HARDWARE
**************************************************************************
NOTE: For new pole line construction, coordinate
with Section 33 71 01 OVERHEAD TRANSMISSION AND
DISTRIBUTION. Where the scope of the project is
small, such as installation of one or two poles, the
designer may elect to incorporate the pole and
hardware paragraphs from Section 33 71 01 in this
section.
**************************************************************************
SECTION 33 70 02.00 10 Page 24
Poles and hardware shall be in accordance with Section 33 71 01 OVERHEAD
TRANSMISSION AND DISTRIBUTION.
2.9 TRANSFORMERS, SUBSTATIONS, AND SWITCHGEAR
**************************************************************************
NOTE: Specify transformer phase sequence in
accordance with the local practice. Delete tap
setting requirement where transformers do not have
primary tap requirements. Provide tap settings in
accordance with load-flow and voltage drop study
results. Refer to UFC 3-550-01 for guidance.
**************************************************************************
Transformers, substations, and switchgear shall be of the outdoor type
having the ratings and arrangements indicated. Medium-voltage ratings of
cable terminations shall be [5] [15] [25] [28] [35] kV between phases for
133 percent insulation level.
2.9.1 Secondary Unit Substation
Secondary unit substations shall comply with IEEE C37.121 and shall be of
the [radial type] [radial type with an outgoing section mounted integrally
on the transformer] [secondary-selective type] [distributed-network type]
[spot-network type]. Substations shall be subassembled and coordinated by
one manufacturer and shall be shipped in complete sections ready for
connection at the site. Complete sections shall include incoming,
transformer, and outgoing sections and, where practicable, shall be shipped
as one unit.
2.9.1.1 Incoming Section
**************************************************************************
Note: For normal reliability systems, the primary
distribution will be radial, and the incoming
section will be a single metal-enclosed, fused,
load-interrupter switch. Where greater reliability
is required and there are two incoming primary
feeders, a selector switch or a duplex switch will
be specified.
A selector switch contains a non-loadbreak
incoming-line selector switch unit in series with a
separate interrupter unit. The interrupter unit
must be open before the selector unit may be
changed; the entire metal-enclosed switch assembly
is contained in one vertical section of switchgear.
A duplex switch contains 2 fully rated interrupter
switches connected together at their load side, and
requires 2 vertical sections of switchgear.
At installations where space is very tight, the
selector switch should be specified, otherwise the
duplex switch is preferable and should be specified.
Voltage ratings are listed in IEEE C37.20.3, Table
1. See UFC 3-550-01 for guidance. Specify current
ratings based upon short-circuit study.
SECTION 33 70 02.00 10 Page 25
Delete reference to SF6 insulating dielectric when
not required.
**************************************************************************
Metal-enclosed interrupter switchgear consisting of fused, [air-insulated]
[vacuum-insulated] [SF6-insulated], interrupters in series with automatic,
visible blade disconnects shall be provided for protection of incoming
circuits.[ SF6 gas shall conform to ASTM D2472.] Metal-enclosed
interrupter switchgear shall comply with IEEE C37.30 for load-interrupter
switches, NEMA SG 2 for power fuses, and shall be of the outdoor no-aisle
type that meets or exceeds the requirements of applicable publications
listed. Switch construction shall be of the manually-operated,
"OPEN-CLOSED," [air-insulated][vacuum-insulated][SF6-insulated], load
interrupter type equipped with a stored energy operator for quick-make
quick-break to make operating speeds independent of manual switch
operations. Where indicated, suitable bus or lug connections shall be
provided to mount field-installed, slip-on, medium-voltage cable
terminations for cable entering via conduit from below [and a flanged
throat suitable for direct connection to the associated transformer] [and a
bus throat suitable for connection to the associated metal-enclosed bus].
[Surge protection shall be provided in accordance with paragraph SURGE
ARRESTERS.][ Switches shall be of the 2-position type, open-closed.]
[Selector switches shall be of the single-compartment, 3-position type,
Line 1 - Open - Line 2, consisting of an interrupter switch in series with
a selector switch.][ Duplex switches shall be of the dual compartment type
with 2 interrupter switches.]
a. Ratings. Fuse continuous current ratings shall be as indicated for the
transformer for an incoming line unit and for the line tie unit.
Unless otherwise indicated, fuses shall be of the current limiting
type. Switch ratings at 60 Hz shall be:
Nominal voltage [_____]
Rated maximum voltage [_____]
Maximum symmetrical interrupting
capacity
[_____]
Maximum asymmetrical interrupting
capacity
[_____]
3-Second short time current carrying
capacity
[_____]
Rated continuous current [_____]
BIL [_____]
b. Basic Requirements. The electrical devices listed below shall be rated
for the application and voltage and current indicated. Unless
otherwise noted, manufacturer's standard devices shall be provided and
shall include the following:
(1) A switch-operating handle with provisions for locking in either
the open or closed position.
(2) A switch mechanical position indicator.
(3) A heater continuously energized to prevent condensation over an
SECTION 33 70 02.00 10 Page 26
ambient temperature range of [minus [29] [_____] degrees C] to
[[40] [_____] degrees C] [minus [20] [_____] degrees F] to [[40]
[_____] degrees F] at 90 percent relative humidity and wired in
series with a cabinet door-actuated switch, so the heater is
de-energized when doors are open. High-temperature thermal
protection shall be included.
(4) One-pole or 2-pole thermal-magnetic, molded-case circuit breakers
suitable for the operating voltage for heater circuits.
(5) Safety devices as necessary to ensure that the load interrupter
switch is in the open position whenever unit doors are in the open
position.
(6) A key interlock if indicated.
(7) An interface terminal block wired for required exterior
connections.
2.9.1.2 Transformer Section
**************************************************************************
NOTE: Refer to UFC 3-550-01 for guidance. Delete
alarm contacts when not required
**************************************************************************
Transformers shall have two separate windings per phase and shall be of the
[mineral oil-insulated] [less-flammable, liquid-insulated] type with [high
molecular-weight hydrocarbon] [or] [dimethyl silicone] liquid.
Transformers shall be suitable for outdoor use. Liquid-insulated
transformers shall comply with IEEE C57.12.00, and shall have two 2-1/2
percent full capacity taps above and two 2-1/2 percent full capacity taps
below rated voltage. Transformers shall be of the sealed tank type
construction with welded-on cover. High-voltage terminals shall be
provided [in an air terminal chamber for incoming [top] [bottom] entry
cables][for direct connection to the incoming line section] [as shown on
the drawings]. Low-voltage terminals shall be provided [in an air terminal
chamber for incoming [top] [bottom] entry cables] [for direct connection to
the outgoing [switchgear section] [bus duct]] [as shown on the drawings].
Low-voltage terminals shall be [on the [left] [right]] [as shown on the
drawings] when facing the front, accessory side of the transformer.
[Transformers shall be equipped with forced air cooling equipment to give
[_____] kVA capacity. The equipment shall include the necessary fans,
conduit and wiring, motor starters, and top liquid thermometer for fan
control.] [Provision shall be made for the future addition of forced air
cooling equipment to give [_____] kVA capacity. The transformer bushings,
leads, and other components shall be designed to carry the increased load.
A top liquid thermometer for control of future fans shall be furnished.
Provision for future mounting of fans, conduit, and terminal box shall be
provided.] Transformer accessories and ratings at 60 Hz shall be as follows:
1. Three-phase capacity, self-cooled.................[_____] kVA.
2. Three-phase capacity, (future) forced-cooled......[_____] kVA.
3. Impedance.[5.75 percent, stdr.] [[_____] percent nonstdr.].
4. Temperature rise..............[65 degrees C] [55/65 degrees C].
SECTION 33 70 02.00 10 Page 27
5. High-voltage winding.............................[_____] volts.
6. High-voltage winding connection........................[_____].
7. Low-voltage winding..............................[_____] volts.
8. Low-voltage winding connection.........................[_____].
Accessories:
1. drain and filter connection.
2. filling and top filter press connection.
3. pressure-vacuum gauge.
4. dial type thermometer with alarm contacts.
5. magnetic liquid level indicator with high and low level alarm
contacts.
6. pressure relief device with alarm contacts.
7. ground connection pad.
8. provision for jacking, lifting, and towing.
9. diagram and rating nameplate.
2.9.1.3 Integral Outgoing Section
**************************************************************************
NOTE: In Unit Substation construction consisting of
a transformer and low-voltage equipment, the
low-voltage section must be integral or mechanically
connected with the transformer and must be a busway
throat compartment; an integral, dead-front,
distribution switchboard/panelboard compartment; or
a group of low-voltage, metal-enclosed switchgear.
For comparison, nonintegral substation construction
consists of free-standing elements (primary
switch/transformer/secondary protection) connected
by cables. Specify cable compartments when
free-standing elements (nonintegral substation
construction) are used.
Specify a busway throat compartment and associated
busway when the low voltage switchboard or
switchgear must be located remote from the
transformer and a compact, high ampacity connection
is required.
Specify an integral, dead-front, distribution
switchboard (typically front and rear accessible,
with instruments, for larger installations) or
panelboard (typically front accessible only, for
smaller installations) when stationary-mounted,
nondrawout, molded case circuit breakers are
required and the number of feeders/branches requires
SECTION 33 70 02.00 10 Page 28
only one or two panels.
Specify a mechanical, bus-bar-throat connection to a
group of low voltage switchgear when large, high
capacity, drawout type, low voltage power circuit
breakers are required.
Specify individual watthour demand meters for
transformers rated 750 kVA and above.
Specify ground fault protection only when required
by NFPA 70. See UFC 3-520-01 for guidance on GFP
devices with double-ended substations.
Incorporate the low-voltage power circuit breaker
paragraphs from Section 26 28 01.00 10 COORDINATED
POWER SYSTEM PROTECTION if Section 26 28 01.00 10 is
not part of the project specifications. Delete
appropriate paragraphs of this section if Section
26 28 01.00 10 is included.
**************************************************************************
Integral outgoing section shall be of the [busway throat compartment]
[dead-front distribution panelboard/switchboard] [metal-enclosed
switchgear] type. Each circuit breaker and auxiliary compartment shall
have a suitable metal or laminated plastic nameplate with white cut letters
at least 6.4 mm 1/4 inch high on contrasting backgrounds [identifying the
breaker unit and/or circuit number] [as shown on the drawings].
a. Busway Throat Compartment Type: Outgoing section shall consist of an
enclosure containing metering devices on the main secondary circuit and
connections from transformer terminals to suitable busway throats
provided for connections to busway installations entering [from above]
[as shown]. Connection to porcelain bushings shall be made with
flexible jumpers.
b. Dead-Front Distribution Panelboard/Switchboard Type: Outgoing section
shall be of the panelboard/switchboard type mounted integrally with the
transformer and shall consist of metering devices and main and branch
circuit breakers mounted in panelboard/switchboard enclosures.
Panelboards shall comply with NEMA PB 1. Switchboards shall comply
with NEMA PB 2. Molded-case and low-voltage power circuit breakers
shall comply with paragraph METERING AND PROTECTIVE DEVICES. Plug-in
type circuit breakers are not acceptable. Directories to indicate
loads served by each circuit shall be typed and mounted in holders
provided on panelboard doors behind protective coverings.
c. Metal-Enclosed Switchgear Type:[ Outgoing section shall be of the
metal-enclosed drawout circuit breaker type, in accordance with
IEEE C37.20.1.] Low-voltage power circuit breakers shall comply with
the requirements of paragraph METERING AND PROTECTIVE DEVICES.
d. Metering: The main secondary bus of each outgoing section assembly
shall include a watthour demand meter with the necessary instrument
transformers, and VT and CT test blocks. Metering shall be as
specified in paragraph METERING AND PROTECTIVE DEVICES.
e. Ground Fault Protection: Ground fault protection shall be provided
utilizing sensors of the zero-sequence type or by the residual
SECTION 33 70 02.00 10 Page 29
connection of phase and neutral current sensors. Ground fault settings
shall be [as shown] [as determined by the coordination study].
2.9.1.4 Nonintegral (Cable Compartment) Outgoing Section
**************************************************************************
NOTE: Specify cable compartment outgoing section
when the transformer will feed the nonintegral
low-voltage panelboard/switchboard/switchgear via
cables. The cable compartment is actually integral
to the transformer, but by using cables, the
substation is classified as "nonintegral."
**************************************************************************
A cable compartment shall be provided on the transformer for cable
connections as shown. Clamp type terminations for cables entering from
[below] [above] shall be provided for connection to the transformer
bushings. Clamp type cable terminations, suitable for [copper] [aluminum]
conductors, shall be provided [for the circuit sizes shown] [to match
circuit breakers].
2.9.2 Pad-Mounted Transformers
**************************************************************************
NOTE: See UFC 3-550-01 for guidance.
**************************************************************************
Pad-mounted transformers shall comply with IEEE C57.12.26 and shall be of
the [radial][loop feed] type. Pad-mounted transformer stations shall be
assembled and coordinated by one manufacturer and each transformer station
shall be shipped as a complete unit so that field installation requirements
are limited to mounting each unit on a concrete pad and connecting it to
primary and secondary lines. Stainless steel pins and hinges shall be
provided. Barriers shall be provided between high- and low-voltage
compartments. High-voltage compartment doors shall be interlocked with
low-voltage compartment doors to prevent access to any high-voltage section
unless its associated low-voltage section door has first been opened.
Compartments shall be sized to meet the specific dimensional requirements
of IEEE C57.12.26. Pentahead locking bolts shall be provided with
provisions for a padlock.
2.9.2.1 High-Voltage Compartments
**************************************************************************
NOTE: Select transformer fuse type and
characteristics to provide protection of the
transformer and coordination with upstream
protective devices.
There are two types of fuses utilized in deadfront,
pad-mounted transformer protection: expulsion-type,
and current-limiting type. Expulsion-type fuses
contain a fuse link that melts when subjected to
either overload or fault current. The fuse-holding
device operates such that the arc of the melting
fuse link is extinguished under the transformer
insulating dielectric (oil-immersed applications).
Current limiting fuses create a physical circuit gap
by the melting of the fuse. The opening arc is
SECTION 33 70 02.00 10 Page 30
extinguished by the gases created by melting of the
fuse element (drywell applications).
Fuse mounting configurations for deadfront
pad-mounted transformers include: drywell mounting,
where a canister is provided in the transformer tank
(separated and sealed from the insulating
dielectric); and "oil-immersed bayonet" mounting,
where the fuse holder is mounted through the wall of
the transformer tank, such that the fuse element is
immersed in the transformer dielectric.
Drawout, dry-well mounted, current-limiting fuses
are significantly more expensive than expulsion-type
fuses and have more limited voltage- and current
range operating characteristics. When specifying
this fuse type, care must be exercised to ensure
coordination with upstream protective devices.
Although they operate on a more limited voltage
range than other fuses, they are the preferred fuse
type because the current limiting characteristics
provides enhanced fault protection for the
transformer.
Oil-immersed, bayonet-type, current limiting fuses
and oil-immersed, bayonet type, overload fuses in
series with a partial range current-limiting fuse,
may be preferable to the drawout, drywell mounted,
current-limiting fuse because of the operating
characteristics, relative cost, and off-the-shelf
availability. Oil-immersed fuse operation can
contaminate the transformer oil, although numerous
fuse operations are required (on the order of 100)
before the contamination is significant.
Delete faulted circuit indicators unless required by
the operating installation.
**************************************************************************
The high-voltage compartment shall be dead-front construction. Primary
switching and protective devices shall include loadbreak switching,
[drawout, dry-well-mounted, current-limiting fuses] [oil-immersed,
current-limiting, bayonet-type fuses] [oil-immersed, bayonet-type, overload
fuse in series with a partial range current-limiting fuse], medium-voltage
separable loadbreak connectors, universal bushing wells and inserts or
integral one piece bushings and surge arresters. Fuses shall comply with
the requirements of paragraph METERING AND PROTECTIVE DEVICES. The switch
shall be mounted inside transformer tank with switch operating handle
located in high-voltage compartment and equipped with metal loop for hook
stick operation. Fuses shall be interlocked with switches so that fuses
can be removed only when the associated switch is in the "OPEN" position.
Adjacent to medium-voltage cable connections, a nameplate or equivalent
stenciled inscription shall be provided inscribed "DO NOT OPEN CABLE
CONNECTORS UNLESS SWITCH IS OPEN." Surge arresters shall be fully
insulated and configured to terminate on [the same bushing as the primary
cable by means of a loadbreak, feed-through bushing insert] [a second set
of high voltage bushings].
SECTION 33 70 02.00 10 Page 31
2.9.2.2 Load-Break Switch
**************************************************************************
NOTE: Choose one of the following options.
**************************************************************************
a. [Radial-feed oil-immersed type rated at [15] [_____] kV, [95] [_____]
kV BIL, with a continuous current rating and load-break rating of [200]
[_____] ampere, and a make-and-latch rating of 10,000 rms amperes
symmetrical. Locate the switch handle in the high-voltage compartment.]
b. [Loop feed sectionalizer switches: Provide three, two-position,
oil-immersed type switches to permit closed transition loop feed and
sectionalizing. Each switch shall be rated at [15] [_____] kV, [95]
[_____] kV BIL, with a continuous current rating and load-break rating
of [200] [_____] amperes, and a make-and-latch rating of 10,000 rms
amperes symmetrical. Locate the switch handle in the high-voltage
compartment.] Operation of switches shall be as follows:
DESCRIPTION OF SWITCH
ARRANGEMENT
SWITCH POSITION
LINE A SW LINE B SW XFMR SW
OPEN CLOSE OPEN CLOSE OPEN CLOSE
1 Line A connected to Line B and
both lines connected to
transformer
X X X
2 Transformer connected to Line
A only
X X X
3 Transformer connected to Line
B only
X X X
4 Transformer open and loop
closed
X X X
5 Transformer open and loop open X X X
2.9.2.3 Transformer Tank Sections
**************************************************************************
NOTE: For 480Y/277 volt secondaries, 2 primary taps
above and 2 primary taps below are standard. For
208Y/120 volt secondaries, 4 primary taps below are
standard. Normally, the design should use standard
impedances in conjunction with circuit breakers
having adequate interrupting ratings. ANSI
C57.12.26, Table 2, lists 5.75 percent for 750 kVA -
2500 kVA. For 75 kVA - 500 kVA, use manufacturer's
standard.
**************************************************************************
SECTION 33 70 02.00 10 Page 32
Transformers shall comply with IEEE C57.12.00 and IEEE C57.12.21 and shall
be of the [mineral oil-insulated type][less-flammable, liquid-insulated
type with [high molecular-weight hydrocarbon][ or ][dimethyl silicone]
liquid]. Transformers shall be suitable for outdoor use and shall have 2
separate windings per phase. Standard NEMA primary taps shall be
provided. Where primary taps are not specified, 4, 2-1/2 percent rated kVA
high-voltage taps shall be provided [2 above and 2 below][below] rated,
primary voltage. Operating handles for primary tap changers for
de-energized operation shall be located within high-voltage compartments,
externally to transformer tanks. Adjacent to the tap changer operating
handle, a nameplate or equivalent stenciled inscription shall be provided
and inscribed "DO NOT OPERATE UNDER LOAD." Transformer ratings at 60 Hz
shall be as follows:
Three-phase capacity [_____] kVA
Impedance [_____]
Temperature Rise 65 degrees C149 degrees F
High-voltage winding [_____] volts
High-voltage winding connections [_____]
Low-voltage winding [_____] volts
Low-voltage winding connections [_____]
2.9.2.4 Low-Voltage Cable Compartments
Neutrals shall be provided with fully-insulated bushings. Clamp type cable
terminations, suitable for [copper] [aluminum] conductors entering from
below, shall be provided as necessary.
2.9.2.5 Accessories
**************************************************************************
NOTE: Specify thermometer, liquid level gauge, and
a sampling device only where requested by the Using
Agency.
**************************************************************************
High-voltage warning signs shall be permanently attached to each side of
transformer stations. Voltage warning signs shall comply with IEEE C2.
Copper-faced steel or stainless steel ground connection pads shall be
provided in both the high- and low-voltage compartments. Dial-type
thermometer, liquid-level gauge, and drain valve with built-in sampling
device shall be provided for each transformer station.
Insulated-bushing-type parking stands shall be provided adjacent to each
separable load-break elbow to provide for cable isolation during
sectionalizing operations.
2.9.3 Busways
Busways shall comply with NEMA BU 1.1 and UL 857 and shall be of the
voltage, phase, and continuous current ratings indicated. Neutrals shall
SECTION 33 70 02.00 10 Page 33
be [full size] [half size]. Busways shall have short-circuit ratings not
less than the maximum short-circuit currents of associated transformers,
assuming primary sources of infinite capacity. Busways shall be
feeder-low-impedance type and of outdoor or indoor service construction as
suitable to the location. Busways shall be complete with elbows, fittings,
flanges, end-closures, tees, crosses, cable-tap boxes, accessories, and
other devices required for the indicated installation, and shall be
coordinated for connection to the indicated equipment. For wet/damp
locations, bus duct shall be heated, nonventilated enclosure, nonsegregated
phase type in accordance with IEEE C37.23. Detail drawings for busway
supports and bracing shall be submitted in accordance with the detail
drawings portion of paragraph SUBMITTALS and shall indicate that busways
are adequately supported for the seismic forces specified in paragraph
GENERAL REQUIREMENTS (sub-paragraph Service Conditions).
2.9.4 Pad-Mounted, Metal-Enclosed, Switchgear
The switchgear shall be configured with [[2] [_____] incoming compartments
for loop-feed arrangement] [one incoming compartment for radial-feed],
equipped with [air-insulated, load-interrupter switches] [oil-insulated,
load-interrupter switches] [SF6-insulated, load-interrupter switches], as
indicated. The outgoing compartments shall be provided with [fused
disconnects] [non-reclosing vacuum-type interrupters or circuit breakers],
as indicated.
2.9.4.1 Ratings at 60 Hz shall be:
Nominal voltage (kV) [_____]
Rated maximum voltage (kV) [_____]
Rated continuous current (A) [_____]
Maximum symmetrical interrupting capacity (kA) [_____]
Maximum asymmetrical interrupting capacity
(kA)
[_____]
Three-second short-time current-carrying
capacity (kA)
[_____]
BIL (kV) [_____]
2.9.4.2 Operators, Devices, and Controls
Operators and controls shall be provided for the switchgear as follows:
a. Switches shall be provided with a manual, handle-type operator or a
push-button mechanical spring tripping mechanism, utilizing a
stored-energy (spring-driven) mechanism to simultaneously open or close
all phases. The switchgear shall be configured so that the switch
actuator is padlockable, but may be accessed without opening the switch
compartment doors.
b. Fused disconnects shall be hook-stick operated.
c. Switches shall be provided with an automatic switch operator configured
for local and remote opening and closing. An actuator charging motor
shall be provide which operates at [12 V dc], [24 V dc] [120 V ac].
SECTION 33 70 02.00 10 Page 34
Switches shall be provided with remote telemetry units (RTUs) for
remote operation and integration with supervisory, control, and data
acquisition systems. Systems, components, and equipment shall conform
to the requirements and recommendations of IEEE C37.1.
d. Vacuum type interrupters shall be provided with an electronic
controller for trip initiation. Manual trip initiation shall be
provided by a push button or switch. Automatic trip shall be initiated
by detection of excessive current. The electronic controller shall
provide trip current selection capability according to present
time-current response curves, as indicated. Each interrupter shall be
provided with a 3 phase, gang-operated handle mechanism for trip and
reset.
2.9.4.3 Enclosures
Switchgear enclosures shall be of freestanding, self-supporting
construction provided with separate incoming and outgoing compartments
configured for bottom cable entry. Enclosures shall be of deadfront
construction, provided with a hinged door for access to each compartment,
and conform to the requirements of IEEE C57.12.28 and IEEE C37.20.3,
Category A.
2.9.5 Pad-Mounted Sectionalizers
**************************************************************************
NOTE: Sectionalizer operation must be coordinated
with substation recloser operating characteristics.
**************************************************************************
Pad-mounted, sectionalizing switches shall conform to the requirements of
IEEE C37.63. The switchgear shall be configured with [[2] [_____] incoming
compartments for loop-feed arrangement] [one incoming compartment for
radial-feed] equipped with [air-insulated, load-interrupter switches]
[oil-insulated, load-interrupters switches] [SF6-insulated load-interrupter
switches], as indicated. The outgoing compartments shall be provided with
non-reclosing sectionalizers.
2.9.5.1 Ratings
Ratings at 60 Hz shall be:
Nominal voltage (kV) [_____]
Rated maximum voltage (kV [_____]
Rated continuous current (A) [_____]
Three-second short-time current-carrying
capacity (kA)
[_____]
BIL (kV) [_____]
2.9.5.2 Enclosures
Switchgear enclosures shall be of freestanding, self-supporting
construction provided with separate incoming and outgoing compartments
configured for bottom cable entry. Enclosures shall be of deadfront
SECTION 33 70 02.00 10 Page 35
construction, provided with a hinged door for access to each compartment,
and conform to the requirements of IEEE C57.12.28 and IEEE C37.20.3,
Category A.
2.9.6 Cable Terminating Cabinets
**************************************************************************
NOTE: Cable terminating cabinets may be used for
above ground applications only. They may be
utilized in place of manholes for cable splicing
where the local water table does not allow for
manhole drainage, or in limited applications where
it is desirable to provide a dead-break circuit
sectionalizing point for circuit isolation.
Loadbreak connectors are not available for
applications above 200 A.
**************************************************************************
Cable terminating cabinets shall be hook-stick operable, deadfront
construction conforming to the requirements of IEEE C37.20.3, Category A.
Cabinets shall be provided with [with 200 A. loadbreak junctions and
elbow-type separable loadbreak connectors, cable parking stands, and
grounding lugs] [with 600 A. dead-break junctions and elbow-type separable
dead-break connectors, cable parking stands, and grounding lugs]. The
cable terminating equipments shall conform to IEEE 386.
Ratings at 60 Hz shall be:
Nominal voltage (kV) [_____]
Rated maximum voltage (kV [_____]
Rated continuous current (A) [_____]
Three-second short-time current-carrying
capacity (kA)
[_____]
BIL (kV) [_____]
2.10 METERING AND PROTECTIVE DEVICES
2.10.1 Circuit Breakers, Low-Voltage
2.10.1.1 Low-Voltage Power Circuit Breakers
a. Construction. Low-voltage power circuit breakers shall conform to
IEEE C37.13 and IEEE C37.16, and shall be three-pole, single-throw,
stored energy, [manually][electrically] operated, with drawout
mounting. Solid-state trip elements which require no external power
connections shall be provided. Circuit breakers shall have an
open/close contact indicator, primary disconnect devices, and a
mechanical interlock to prevent making or breaking contact of primary
disconnections when the circuit breaker is closed. Control voltage
shall be [[24][48][125] V dc][120 V ac][as indicated]. The circuit
breaker enclosure shall be suitable for its intended location.
b. Ratings. Voltage ratings shall be not less than the applicable circuit
voltage. Circuit breakers shall be rated for 100 percent continuous
SECTION 33 70 02.00 10 Page 36
duty and shall have trip current ratings and frame sizes as shown.
Nominal voltage ratings, maximum continuous-current ratings, and
maximum short-circuit interrupting ratings shall be in accordance with
IEEE C37.16. Tripping features shall be as follows:
(1) Long-time current pick-up, adjustable from 50 percent to 100
percent of sensor current rating.
(2) Adjustable long-time delay.
(3) Short-time current pick-up, adjustable from 1.5 to 9 times
long-time current setting.
(4) Adjustable short-time delay.
(5) [Short-time I2t switch.]
(6) Instantaneous current pick-up, adjustable from 1.5 to 9 times
long-time current setting.
(7) Ground-fault pick-up, adjustable from 20 percent to 60 percent of
sensor rating, but in no case greater than 1200 amperes. Sensing
of ground-fault current at the main bonding jumper or ground strap
shall not be permitted. [Zone-selective interlocking shall be
provided as shown.]
(8) [Fixed][Adjustable] ground-fault delay.
(9) [Ground-fault I2t switch.]
(10) [Overload][ and ][short-circuit][ and ][ground-fault] trip
indicators shall be provided.
2.10.1.2 Molded-Case Circuit Breakers
UL 489 and UL 489.
2.10.2 Fuses, Medium-Voltage, Including Current-Limiting
2.10.2.1 Construction
Units shall be suitable for outdoor use. Fuses shall have integral
blown-fuse indicators. All ratings shall be clearly visible.
2.10.2.2 Ratings
[Expulsion-type] [Current-limiting] power fuses shall have ratings in
accordance with IEEE C37.46 and as follows:
Nominal voltage (kV) [_____]
Rated maximum voltage (kV [_____]
Rated continuous current (A) [_____]
Maximum symmetrical interrupting capacity
(kA)
[_____]
SECTION 33 70 02.00 10 Page 37
BIL (kV) [_____]
2.10.2.3 E-Rated, Current-Limiting Power Fuses
E-rated, current-limiting, power fuses shall conform to IEEE C37.46.
2.10.2.4 C-Rated, Current-Limiting Power Fuses
C-rated, current-limiting power fuses shall open in 1000 seconds at
currents between 170 and 240 percent of the C rating.
2.10.3 Fuses, Low-Voltage, Including Current-Limiting
Low-voltage fuses shall conform to NEMA FU 1. Time delay and nontime delay
options shall be as [shown] [specified]. Equipment provided under this
contract shall be provided with a complete set of properly rated fuses when
the equipment manufacturer utilizes fuses in the manufacture of the
equipment, or if current-limiting fuses are required to be installed to
limit the ampere-interrupting capacity of circuit breakers or equipment to
less than the maximum available fault current at the location of the
equipment to be installed. Fuses shall have a voltage rating of not less
than the phase-to-phase circuit voltage, and shall have the time-current
characteristics required for effective power system coordination.
2.10.3.1 Cartridge Fuses
**************************************************************************
NOTE: Class RK1 provides high current limitation
with both time-delay and nontime-delay. RK5
provides moderate current limitation, time-delay
option.
**************************************************************************
Cartridge fuses, current-limiting type, Class [G] [J] [K] [L] [RK1] [RK5]
[RK9] [T] [CC] shall have tested interrupting capacity not less than
[100,000] [200,000] amperes. Fuse holders shall be the type that will
reject Class H fuses.
a. Class [G] [J] [L] [CC] fuses shall conform to UL 198M.
b. Class K fuses shall conform to UL 198M.
c. Class R fuses shall conform to UL 198M.
d. Class T fuses shall conform to UL 198M.
2.10.3.2 Transformer Circuit Fuses
Transformer circuit fuses shall be Class RK1 or RK5, current-limiting,
time-delay with 200,000 amperes interrupting capacity.
2.10.4 Instrument Transformers
2.10.4.1 General
Instrument transformers shall comply with NEMA/ANSI C12.11 and IEEE C57.13.
Instrument transformers shall be configured for mounting in/on the device
SECTION 33 70 02.00 10 Page 38
to which they are applied. Polarity marks on instrument transformers shall
be visually evident and shown on drawings.
2.10.4.2 Current Transformers
**************************************************************************
NOTE: See UFC 3-550-01 regarding guidance on
current transformers. Accuracy class ratings of
current transformers (CTs) at standard burdens are
listed in IEEE C57.13. The minimum standard current
transformer accuracies for metal-clad switchgear are
listed in ANSI C37.20.2. In general, NEMA/ANSI
C12.11 requires a 0.3 accuracy class for up to a
B-0.5 burden, except for some 200 and 400 ampere
units. Where metering current transformers are
provided, this accuracy class should be specified,
if available for the ampere rating and burden
needed. A "C" classification means the ratio error
can be calculated, whereas a "T" classification is
one which has to be derived by testing. IEEE
C37.20.2 permits either classification up to the
indicated ratings.
**************************************************************************
Unless otherwise indicated, bar, wound, or window-type transformers are
acceptable; and except for window-type units installed over insulated
buses, transformers shall have a BIL rating consistent with the rated BIL
of the associated switchgear or electric power apparatus bushings, buses or
conductors. Current transformers shall have the indicated ratios. The
continuous thermal-current rating factor shall not be less than [1.0] [1.2]
[1.5] [2.0] [3.0] [4.0]. Other thermal and mechanical ratings of current
transformers and their primary leads shall be coordinated with the design
of the circuit breaker and shall be not less than the momentary rating of
the associated circuit breaker. Circuit protectors shall be provided
across secondary leads of the current transformers to prevent the accident
open-circuiting of the transformers while energized. Each terminal of each
current transformer shall be connected to a short-circuiting terminal block
in the circuit interrupting mechanism cabinet, power transformer terminal
cabinet, and in the associated instrument and relay cabinets.
2.10.4.3 Current Transformers for Power Transformers
**************************************************************************
NOTE: IEEE C57.12.10, Table 20 gives recommended
values.
**************************************************************************
[Single-ratio] [Multi-ratio] bushing type current transformers shall be
provided internally around power transformer bushings as shown.
[Single-ratio units shall have a minimum relaying accuracy class of
[0.6B-0.5] [0.3B-0.5].] [Multi-ratio units shall have a minimum relaying
accuracy voltage class of [_____] for either a C or T classification.]
2.10.4.4 Current Transformers for Metal-Enclosed Switchgear
Single-ratio units, used for metering and relaying, shall have a metering
accuracy class rating of [_____] [B._____]. Single-ratio units, used only
for relaying, shall have a relaying accuracy class rating of [_____] for
[either] a C [or T] classification.
SECTION 33 70 02.00 10 Page 39
2.10.4.5 Current Transformers for Kwh and Demand Metering (Low-Voltage)
**************************************************************************
NOTE: Use the following guidelines for specifying
current transformers.
1. Select the standard current transformer (CT)
primary rating which is just below the full load
current of the serving power transformer, i.e., for
a 500 kVA transformer with a full load of 1387 amps
at 208 volts-select a 1200/5 CT ratio; for a 750 kVA
transformer with a full load of 902 amps at 480
volts-select a 800/5 CT ratio.
2. Select a continuous-thermal-current rating
factor (RF) in accordance with the following Table:
RATIO RF at 30
degrees C
200/5 4.0
300/5 3.0
400/5 4.0
600/5 3.0
800/5 2.0
1200/5 1.5
1500/5 1.5
2000/5 1.5
3000/5 1.33
3. Select an ANSI Metering Accuracy Class in
accordance with the following Table:
Primary Amp
Rating (of CT)
Accuracy Class
200 0.3 thru B-0.1
300-400 0.3 thru B-0.2
600-1200 0.3 thru B-0.5
1500 0.3 thru B-0.9
2000-3000 0.3 thru B-1.8
**************************************************************************
Current transformers shall conform to IEEE C57.13. Provide current
SECTION 33 70 02.00 10 Page 40
transformers with a metering accuracy Class of 0.3 through [_____], with a
minimum RF of [_____] at 30 degrees C, with 600-volt insulations, and 10 kV
BIL. Provide butyl-molded, window-type current transformers mounted [on
the transformer low-voltage bushings. Route current transformer leads in a
location as remote as possible from the power transformer secondary cables
to permit current measurements to be taken with hook-on-ammeters.] [in the
current transformer cabinet.]
2.10.4.6 Voltage Transformers
**************************************************************************
NOTE: See UFC 3-550-01 for guidance regarding
voltage transformers. Minimum standard potential
transformer accuracies for metal-clad switchgear are
not listed in IEEE C37.20.2. Accuracy classes as
listed in IEEE C57.13 are 0.3, 0.6, and 1.2.
Standard burdens for each accuracy class are W, X,
Y, ZZ, and M. The designer should check the burdens
connected to determine the actual accuracy class and
burden required. In general, NEMA/ANSI C12.11
requires 0.3 accuracy class for up to Y burdens,
except for voltages of 5 kV and below. Where
metering potential transformers are provided, a 0.3
accuracy class should be specified, if available for
the voltage rating and burden needed.
**************************************************************************
Voltage transformers shall have indicated ratios. Units shall have an
accuracy class rating of [_____]. Voltage transformers shall be of the
drawout type having current-limiting fuses in both primary and secondary
circuits. Mechanical interlocks shall prevent removal of fuses, unless the
associated voltage transformer is in a drawout position. Voltage
transformer compartments shall have hinged doors.
2.10.5 Watthour Meters
**************************************************************************
NOTE: Coordinate demand interval with local
utility. Coordinate devices with EMCS equipment.
For small, non-critical installations,
residential-type watthour meters may be adequate.
Revise paragraph as required.
**************************************************************************
Watthour meters shall conform to NEMA/ANSI C12.10, except numbered terminal
wiring sequence and case size may be the manufacturer's standard. Watthour
meters shall be of the [drawout switchboard type] [socket mounted [outdoor]
[indoor] type] having a [15] [30] [60] [_____] minute, cumulative form,
demand register meeting NEMA C12.4 and provided with not less than 2-1/2
stators. [Watthour demand meters shall have factory-installed electronic
pulse initiators. Pulse initiators shall be solid-state devices
incorporating light-emitting diodes, phototransistors, and power
transistors, except that mercury-wetted output contacts are acceptable.
Initiators shall be totally contained within watthour demand meter
enclosures, shall be capable of operating up to speeds of 500 pulses per
minute with no false pulses, and shall require no field adjustments.
Initiators shall be calibrated for a pulse rate output of 1 pulse per 1/4
disc revolution of the associated meter and shall be compatible with the
indicated equipment].
SECTION 33 70 02.00 10 Page 41
2.10.6 Protective Relaying
**************************************************************************
NOTE: Ranges selected will be based on the
coordination study. Refer to UFC 3-550-0 and UFC
3-520-01 for guidance regarding protective relays.
**************************************************************************
2.10.6.1 General
[Solid-state] [Microprocessor-based] protective relays shall be provided as
shown and shall be of a type specifically designed for use on power
switchgear or associated electric power apparatus. Protective relays shall
conform to IEEE C37.90. Relays and auxiliaries shall be suitable for
operation with the instrument transformer ratios and connections provided.
2.10.6.2 Construction
Relays shall be dustproof and moisture resistant. Necessary test devices
shall be incorporated within each relay and shall provide a means for
testing either from an external source of electric power or from associated
instrument transformers. Each relay shall be provided with an operation
indicator and an external target reset device. Relays shall have necessary
auxiliaries for proper operation. Relays and auxiliaries shall be suitable
for operation with the instrument transformer ratios and connections
provided.
2.10.6.3 Ratings
Relays shall be the manufacturer's standard items of equipment with
appropriate ranges for time dial, tap, and other settings. Relay device
numbers shall correspond to the function names and descriptions of
IEEE C37.2.
2.11 SURGE ARRESTERS
**************************************************************************
NOTE: Surge arresters should be located at both the
riser pole and at the equipment. Dead front
transformer primary compartments may require special
provisions to accommodate the arresters.
**************************************************************************
Surge arresters shall comply with NEMA LA 1, and IEEE C62.11 and shall be
provided where indicated. Arresters shall be
[station][intermediate][distribution] class, rated as shown. Arresters for
use at elevations in excess of 1.8 km 6000 feet above mean sea level shall
be specifically rated for that purpose. Arresters shall be equipped with
mounting brackets suitable for the indicated installations. Arresters
shall be of the [valve][ or ][metal-oxide varistor][ or ][combination
valve-metal-oxide varistor] type.
2.12 GROUNDING AND BONDING
2.12.1 Driven Ground Rods
Ground rods shall be [copper-clad steel conforming to UL 467][zinc-coated
steel conforming to IEEE C135.30][solid stainless steel] not less than [
SECTION 33 70 02.00 10 Page 42
15.9 mm 5/8 inch][19 mm 3/4 inch] in diameter by [3.1 m 10 feet] [2.44 m 8
feet] in length. Sectional type rods may be used.
2.12.2 Grounding Conductors
Grounding conductors shall be bare, except where installed in conduit with
associated phase conductors. Insulated conductors shall be of the same
material as phase conductors and green color-coded, except that conductors
shall be rated no more than 600 volts. Bare conductors shall be ASTM B8
soft-drawn unless otherwise indicated. Aluminum is not acceptable.
2.13 CONCRETE AND REINFORCEMENT
Concrete work shall have minimum 20 MPa 3000 psi compressive strength and
conform to the requirements of Section 03 30 00.00 10 CAST-IN-PLACE
CONCRETE. Concrete reinforcing shall be as specified in Section
03 20 00.00 10 CONCRETE REINFORCING.
2.14 PADLOCKS
Padlocks shall comply with Section 08 71 00 DOOR HARDWARE.
2.15 CABLE FIREPROOFING SYSTEMS
Cable fireproofing systems shall be listed in FM APP GUIDE as a
fire-protective coating or tape approved for grouped electrical conductors
and shall be suitable for application on the type of medium-voltage cables
provided. After being fully cured, materials shall be suitable for use
where exposed to oil, water, gases, salt water, sewage, and fungus and
shall not damage cable jackets or insulation. Asbestos materials are not
acceptable.
2.15.1 Fireproof Coating
Cable fireproofing coatings shall be compounded of water-based
thermoplastic resins, flame-retardant chemicals, and inorganic
noncombustible fibers and shall be suitable for the application methods
used. Coatings applied on bundled cables shall have a derating factor of
less than 5 percent, and a dielectric strength of 95 volts per mil minimum
after curing.
2.15.2 Fireproofing Tape
Fireproofing tape shall be at least 50 mm 2 inches wide and shall be a
flexible, conformable, polymeric, elastomer tape designed specifically for
fireproofing cables.
2.15.3 Plastic Tape
Preapplication plastic tape shall be pressure sensitive, 0.254 mm 10 mil
thick, conforming to UL 510.
2.16 LIQUID DIELECTRICS
**************************************************************************
NOTE: Select 2 ppm for Air Force projects.
**************************************************************************
Liquid dielectrics for transformers, capacitors, reclosers, and other
SECTION 33 70 02.00 10 Page 43
liquid-filled electrical equipment shall be non-polychlorinated biphenyl
(PCB) mineral-oil or less-flammable liquid as specified. Nonflammable
fluids shall not be used. Tetrachloroethylene (perchloroethylene) and 1,
2, 4 trichlorobenzene fluids shall not be used. Liquid dielectrics in
retrofitted equipment shall be certified by the manufacturer as having less
than [50] [2] parts per million (ppm) PCB content. In lieu of the
manufacturer's certification, the Contractor may submit a test sample of
the dielectric in accordance with ASTM D923 and have tests performed in
accordance with ASTM D4059 at a testing facility approved by the
Contracting Officer. Equipment with test results indicating PCB level
exceeding [50] [2] ppm shall be replaced.
2.17 FACTORY TESTS
**************************************************************************
NOTE: Delete tests that are not applicable to the
project. Refer to UFC 3-550-01. Tests must be
justified.
**************************************************************************
Submit certified factory test reports when the manufacturer performs
routine factory tests, including tests required by standards listed in
paragraph REFERENCES. Results of factory tests performed shall be
certified by the manufacturer, or an approved testing laboratory, and
submitted within 7 days following successful completion of the tests. The
manufacturer's pass-fail criteria for tests specified in paragraph FIELD
TESTING shall be included. Factory tests shall be performed, as follows,
in accordance with the applicable publications and with other requirements
of these specifications. The Contracting Officer shall be notified at
least [10] [_____] days before the equipment is ready for testing. The
Contracting Officer reserves the right to witness the tests.
a. Transformers: Manufacturer's standard [routine] [design] [and] [other]
tests in accordance with IEEE C57.12.00.
b. Transformers rated 200 kVA and above: Reduced full-wave, chopped-wave,
and full-wave impulse test on each line and neutral terminal, in
accordance with IEEE C57.98.
c. High-Voltage Air Switches: Manufacturer's standard tests in accordance
with IEEE C37.34 and IEEE C37.41.
d. Protective Relays: Seismic tests in accordance with IEC 60255-21-3.
Surge withstand tests in accordance with IEEE C37.90.1.
e. Relaying Current Transformers: Manufacturer's standard tests in
accordance with IEEE C57.13.
f. Instrument Current Transformers: Manufacturer's standard tests in
accordance with IEEE C57.13.
g. Factory Preformed Terminations: Wet withstand voltage tests in
accordance with IEEE 48 for the next higher BIL level.
h. Outdoor Switchgear: Manufacturer's standard tests in accordance with
IEEE C37.20.1, IEEE C37.20.2, and IEEE C37.20.3.
i. Electrical Power Insulators: Manufacturer's standard tests in
accordance with ANSI C29.1.
SECTION 33 70 02.00 10 Page 44
j. [_____].
2.18 FENCING
Fencing shall conform to the requirements of Section [32 31 13 CHAIN LINK
FENCES AND GATES][32 31 26 WIRE FENCES AND GATES].
2.19 COORDINATED POWER SYSTEM PROTECTION
**************************************************************************
NOTE: The requirement for the studies in this
section depends on the complexity and extent of the
power system. Delete this requirement for: project
of limited scope; projects having protective devices
which are not adjustable or for which coordination
is not possible (standard molded case circuit
breakers); projects involving simple extension of
600 volt level service to a building or facility
from an existing transformer (750 kVA or less); or
projects involving simple extension of 600 volt
level service to a building or facility from a new
transformer (750 kVA or less).
The designer will be responsible for specifying the
requirement for fuses, circuit breakers, protective
relays, or other protective devices associated with
the project and depicting them on the drawings. The
protective devices should be selected and specified
to protect electrical power system conductors or
equipment against sustained overloads, in-rush
conditions, electrical faults, or other abnormal
power system or equipment operating conditions, in
accordance with UFC 3-520-01 COORDINATED POWER
SYSTEMS PROTECTION and IEEE 242, and IEEE Std 141.
The complexity and extent of coordinated power
system protection depends on the type of buildings
or facilities or utilities required, on the load
demand of facilities, and on the quantity and types
of facilities to be constructed. Facilities having
a relatively-low power demand (e.g., 2500 kVA or
less) generally require protection of an incoming
aerial distribution line or underground,
medium-voltage feeder, low-voltage feeders to
individual items of equipment, or to power
distribution equipment, and branch circuits. More
complex projects such as facilities with generating
capacity, large motors, or larger load demands, will
require more detailed and extensive coordinated
power system protection.
Independent of the type or types of facilities or
load demands, the coordinated power system
protection will be based on: economics, simplicity,
and the electrical power availability dictated by
the Using Agency or Service, or by the functional
use of the facilities or utilities; required to
provide maximum power service with a minimum of
SECTION 33 70 02.00 10 Page 45
power interruptions; and the operating speed of
protective devices required to minimize damage to
electrical components or items of equipment and to
prevent injury to personnel and nuisance tripping.
Unless otherwise approved, a dc power source will be
shown and specified to ensure proper closing and
tripping of protective devices which require a
reliable power source during outage of the normal
alternating-current power source.
**************************************************************************
Analyses shall be prepared to demonstrate that the equipment selected and
system constructed meet the contract requirements for equipment ratings,
coordination, and protection. They shall include a load flow analysis, a
fault current analysis, and a protective device coordination study. The
studies shall be performed by a registered professional engineer with
demonstrated experience in power system coordination in the last three
years. Provide a list of references complete with points of contact,
addresses and telephone numbers. The selection of the engineer is subject
to the approval of the Contracting Officer.
2.19.1 Scope of Analyses
The fault current analysis, and protective device coordination study shall
begin at: [the source bus and extend down to system bused where fault
availability is 10,000 amperes (symmetrical) for building/facility 600 volt
level distribution buses.] [the source bus and extended through the
secondary side of transformers for medium voltage distribution feeders.]
[the source bus and extend through [outgoing breakers] [outgoing medium
voltage feeders, down to the individual protective devices for medium
voltage radial taps] [outgoing medium voltage feeders, through the
secondary side of transformers] [as indicated] for main electric supply
substations.] [the nearest upstream device in the existing source system
and extend through the downstream devices at the load end.]
2.19.2 Determination of Facts
**************************************************************************
NOTE: Require the Contractor to obtain an available
fault capacity at the power source or provide a
fault capacity on which he is to base his analysis.
Delete the unused option.
**************************************************************************
The time-current characteristics, features, and nameplate data for each
existing protective device shall be determined and documented. [Coordinate
with the [commercial power company] [_____] for fault current availability
at the site.] [Utilize the fault current availability indicated as a basis
for fault current studies.]
2.19.3 Single Line Diagram
A single line diagram shall be prepared to show the electrical system
buses, devices, transformation points, and all sources of fault current
(including generator and motor contributions). A fault-impedance diagram
or a computer analysis diagram may be provided. Each bus, device or
transformation point shall have a unique identifier. If a fault-impedance
diagram is provided, impedance data shall be shown. Locations of switches,
SECTION 33 70 02.00 10 Page 46
breakers, and circuit interrupting devices shall be shown on the diagram
together with available fault data, and the device interrupting rating.
2.19.4 Fault Current Analysis
2.19.4.1 Method
The fault current analysis shall be performed in accordance with methods
described in IEEE 242, and IEEE 399.
2.19.4.2 Data
Actual data shall be utilized in fault calculations. Bus characteristics
and transformer impedances shall be those proposed. Data shall be
documented in the report.
2.19.5 Coordination Study
Submit the study with protective device equipment submittals. No time
extension or similar contract modifications will be granted for work
arising out of the requirements for this study. Approval of protective
devices proposed shall be based on recommendations of this study. The
Government will not be responsible for any changes to equipment, device
ratings, settings, or additional labor for installation of equipment or
devices ordered and/or procured prior to approval of the study. The study
shall demonstrate that the maximum possible degree of selectively has been
obtained between devices specified, consistent with protection of equipment
and conductors from damage from overloads and fault conditions. The study
shall include a description of the coordination of the protective devices
in this project. Provide a written narrative that describes: which devices
may operate in the event of a fault at each bus; the logic used to arrive
at device ratings and settings; situations where system coordination is not
achievable due to device limitations (an analysis of any device curves
which overlap); coordination between upstream and downstream devices; and
any relay settings. Recommendations to improve or enhance system
reliability, and detail where such changes would involve additions or
modifications to the contract and cost changes (addition or reduction)
shall be provided. Composite coordination plots shall be provided on
log-log graph paper.
2.19.6 Study Report
a. The report shall include a narrative describing: the analyses
performed; the bases and methods used; and the desired method of
coordinated protection of the power system.
b. The study shall include descriptive and technical data for existing
devices and new protective devices proposed. The data shall include
manufacturers published data, nameplate data, and definition of the
fixed or adjustable features of the existing or new protective devices.
c. The report shall document [utility company data including system
voltages, fault MVA, system X/R ratio, time-current characteristics
curves, current transformer ratios, and relay device numbers and
settings;] [and] [existing power system data including time-current
characteristic curves and protective device ratings and settings.]
d. The report shall contain fully coordinated composite time-current
characteristic curves for each bus in the system, as required to ensure
SECTION 33 70 02.00 10 Page 47
coordinated power system protection between protective devices or
equipment. The report shall include recommended ratings and settings
of all protective devices in tabulated form.
e. The report shall provide the calculation performed for the analyses,
including computer analysis programs utilized. The name of the
software package, developer, and version number shall be provided.
PART 3 EXECUTION
3.1 EXAMINATION
After becoming familiar with details of the work, verify dimensions in the
field, and advise the Contracting Officer of any discrepancy before
performing any work.
3.2 INSTALLATION REQUIREMENTS
As a minimum, submit installation procedures for transformers, substations,
switchgear, and splices. Procedures shall include cable pulling plans,
diagrams, instructions, and precautions required to install, adjust,
calibrate, and test the devices and equipment. Equipment and devices shall
be installed and energized in accordance with the manufacturer's published
instructions. Circuits installed aerially shall conform to the
requirements of Section 33 71 01 OVERHEAD TRANSMISSION AND DISTRIBUTION.
Steel conduits installed underground shall be installed and protected from
corrosion in conformance with the requirements of Section 26 20 00 INTERIOR
DISTRIBUTION SYSTEM. Except as covered herein, excavation, trenching, and
backfilling shall conform to the requirements of Section 31 00 00
EARTHWORK. Concrete work shall have minimum 20 MPa 3000 psi compressive
strength and conform to the requirements of Section 03 30 00.00 10
CAST-IN-PLACE CONCRETE.
3.2.1 Conformance to Codes
The installation shall comply with the requirements and recommendations of
NFPA 70 and IEEE C2 as applicable.
3.2.2 Disposal of Liquid Dielectrics
PCB-contaminated dielectrics must be marked as PCB and transported to and
incinerated by an approved EPA waste disposal facility. Furnish
certification of proper disposal. Contaminated dielectrics shall not be
diluted to lower the contamination level.
3.3 CABLE AND BUSWAY INSTALLATION
Obtain from the manufacturer an installation manual or set of instructions
which addresses such aspects as cable construction, insulation type, cable
diameter, bending radius, cable temperature, lubricants, coefficient of
friction, conduit cleaning, storage procedures, moisture seals, testing for
and purging moisture, etc. And then [prepare a checklist of significant
requirements] [perform pulling calculations and prepare a pulling plan]
which shall be submitted along with the manufacturers instructions in
accordance with SUBMITTALS.
3.3.1 Cable Installation Plan and Procedure
Cable shall be installed strictly in accordance with the cable
SECTION 33 70 02.00 10 Page 48
manufacturer's recommendations. Each circuit shall be identified by means
of a fiber, laminated plastic, or non-ferrous metal tags, or approved
equal, in each manhole, handhole, junction box, and each terminal. Each
tag shall contain the following information; cable type, conductor size,
circuit number, circuit voltage, cable destination and phase identification.
3.3.1.1 Cable Inspection
The cable reel shall be inspected for correct storage positions, signs of
physical damage, and broken end seals. If end seal is broken, moisture
shall be removed from cable in accordance with the cable manufacturer's
recommendations.
3.3.1.2 Duct Cleaning
Duct shall be cleaned with an assembly that consists of a flexible mandrel
(manufacturers standard product in lengths recommended for the specific
size and type of duct) that is 6.4 mm 1/4 inch less than inside diameter of
duct, 2 wire brushes, and a rag. The cleaning assembly shall be pulled
through conduit a minimum of 2 times or until less than a volume of 131
cubic centimeters 8 cubic inches of debris is expelled from the duct.
3.3.1.3 Duct Lubrication
The cable lubricant shall be compatible with the cable jacket for cable
that is being installed. Application of lubricant shall be in accordance
with lubricant manufacturer's recommendations.
3.3.1.4 Cable Installation
Provide a cable feeding truck and a cable pulling winch as required.
Provide a pulling grip or pulling eye in accordance with cable
manufacturer's recommendations. The pulling grip or pulling eye apparatus
shall be attached to polypropylene or manila rope followed by lubricant
front end packs and then by power cables. A dynamometer shall be used to
monitor pulling tension. Pulling tension shall not exceed cable
manufacturer's recommendations. Do not allow cables to cross over while
cables are being fed into duct. For cable installation in cold weather,
cables shall be kept at 10 degrees C 50 degrees F temperature for at least
24 hours before installation. Submit [6] [_____] copies of the information
described below in 215.9 by 279.4 mm 8-1/2 by 11 inch binders having a
minimum of three rings from which material may readily be removed and
replaced, including a separate section for each cable pull. Sections shall
be separated by heavy plastic dividers with tabs, with all data sheets
signed and dated by the person supervising the pull.
a. Site layout drawing with cable pulls numerically identified.
b. A list of equipment used, with calibration certifications. The
manufacturer and quantity of lubricant used on pull.
c. The cable manufacturer and type of cable.
d. The dates of cable pulls, time of day, and ambient temperature.
e. The length of cable pull and calculated cable pulling tensions.
f. The actual cable pulling tensions encountered during pull.
SECTION 33 70 02.00 10 Page 49
3.3.1.5 Cable Installation Plan
Submit a cable installation plan for all cable pulls in accordance with the
detail drawings portion of paragraph SUBMITTALS. Cable installation plan
shall include:
a. Site layout drawing with cable pulls identified in numeric order of
expected pulling sequence and direction of cable pull.
b. List of cable installation equipment.
c. Lubricant manufacturer's application instructions.
d. Procedure for resealing cable ends to prevent moisture from entering
cable.
e. Cable pulling tension calculations of all cable pulls.
f. Cable percentage conduit fill.
g. Cable sidewall thrust pressure.
h. Cable minimum bend radius and minimum diameter of pulling wheels used.
i. Cable jam ratio.
j. Maximum allowable pulling tension on each different type and size of
conductor.
k. Maximum allowable pulling tension on pulling device.
3.3.2 Duct Line
[Low-voltage cables] [Cables] shall be installed in duct lines where
indicated. [Cable splices in low-voltage cables shall be made in manholes
and handholes only, except as otherwise noted.] [Cable joints in
medium-voltage cables shall be made in manholes or approved pullboxes
only.] Neutral and grounding conductors shall be installed in the same
duct with their associated phase conductors.
3.3.3 Direct-Burial
**************************************************************************
NOTE: Specify cover requirements in accordance with
NFPA 70 and IEEE C2. Specify depth of frost line.
Coordinate with Section 31 00 00 EARTHWORK for
trenching and backfilling requirements.
**************************************************************************
[Medium-voltage cables] [Cables] shall be buried directly in the earth as
indicated. Minimum cover from the top of a cable to finished grade shall
be [_____] mm inches but not less than the depth of the frost line, [_____].
3.3.3.1 Trenching
Trenches for direct-burial cables shall be excavated to depths required to
provide the minimum necessary cable cover. Bottoms of trenches shall be
smooth and free of stones and sharp objects. Where bottoms of trenches
comprise materials other than sand, a 75 mm 3 inch layer of sand shall be
SECTION 33 70 02.00 10 Page 50
laid first and compacted to approximate densities of surrounding firm soil.
3.3.3.2 Cable Burial
**************************************************************************
NOTE: Where soil is known to be rocky, provide
selected backfill for cable protection. Specify
bend radius in accordance with NFPA 70.
**************************************************************************
Cables shall be unreeled along the sides of or in trenches and carefully
placed on sand or earth bottoms. Pulling cables into direct-burial
trenches from a fixed reel position will not be permitted, except as
required to pull cables through conduits under paving or railroad tracks.
Where cables cross, a separation of at least 75 mm 3 inches shall be
provided, unless each cable circuit is protected by a nonmetallic conduit
sleeve at the crossing. Where single-conductor cable is installed, all 3
phases and the neutral shall be installed in the same sleeve. Bend radius
of any cable shall be not less than [8] [12] [_____] times the diameter of
the cable. In no case shall cables be left under longitudinal tension.
The first 150 mm 6 inch layer of backfill shall be of sand. Machine
compaction shall not be used within 150 mm 6 inches of the cable.
3.3.3.3 Other Requirements
Where direct-burial cables cross under roads or other paving exceeding 1.5 m
5 feet in width, such cables shall be installed in concrete-encased
ducts. Where direct-burial cables cross under railroad tracks, such cables
shall be installed in reinforced concrete-encased ducts. Ducts shall
extend at least 300 mm 1 foot beyond each edge of any paving and at least
1.5 m 5 feet beyond each side of any railroad tracks. Cables may be pulled
into duct from a fixed reel where suitable rollers are provided in the
trench. Where direct burial cable transitions to duct-enclosed cable,
direct-burial cables shall be centered in duct entrances, and a waterproof
nonhardening mastic compound shall be used to facilitate such centering.
If paving or railroad tracks are in place where cables are to be installed,
coated rigid steel conduits driven under the paving or railroad tracks may
be used in lieu of concrete-encased ducts. Damage to conduit coatings
shall be prevented by providing ferrous pipe jackets or by predrilling.
Where cuts are made in any paving, the paving and subbase shall be restored
to their original condition.
3.3.3.4 Cable Joints or Splices
Cable joints or splices for Medium-Voltage Cable Joints or Low-Voltage
Cable Splices in direct-burial cables are not permitted in runs of 305 m
1000 feet or less, nor at intervals of less than 305 m 1000 feet in longer
runs, except as required for taps. Locations of cable joints or splices in
shorter intervals, where required to avoid obstructions or damage to
cables, shall be approved. Cable joints or splices in direct burial
installations shall be installed in above-ground junction boxes or in cast
metal splice boxes suitable for direct burial use. Cable joints or splices
in duct banks shall be made only in manholes, handholes, or pullboxes.
3.3.3.5 Cable Markers
**************************************************************************
NOTE: Coordinate with Section 31 00 00 EARTHWORK,
for underground marking requirements.
SECTION 33 70 02.00 10 Page 51
**************************************************************************
Markers shall be located [as indicated] [near the ends of cable runs, at
each cable joint or splice, at approximately every 150 m 500 feet along
cable runs, and at changes in direction of cable runs]. In addition to
markers, a 0.127 mm 5 mil, brightly colored plastic tape not less than 75 mm
3 inches in width and suitably inscribed at not more than 3 m 10 feet on
centers, or other approved dig-in warning indication, shall be placed
approximately 300 mm 12 inches below finished grade levels of trenches.
3.3.4 Insect and Rodent Damage
**************************************************************************
NOTE: In areas where insect and rodent damage to
buried cable is a problem, the following steps
should be considered:
a. Specify armored cable.
b. Specify next higher cable voltage rating.
Utility company research indicates that the greater
dielectric strength is effective.
c. Specify full concentric neutral.
d. Specify animal guards around existing concrete
pads. Animal guards include fences, and also guards
to close holes in concrete pads.
e. On new installations, specify buried fiberglass
pads that animals cannot get under.
f. Avoid toxic chemicals.
g. Specify fenced enclosure where required.
**************************************************************************
[Animal guards shall be installed as shown.] [Buried fiberglass pads shall
be installed as shown.]
3.3.5 Electric Manholes
Cables shall be routed around the interior walls and securely supported
from walls on cables racks. Cable routing shall minimize cable crossover,
provide access space for maintenance and installation of additional cables,
and maintain cable separation in accordance with IEEE C2.
3.3.6 Busway Installation
Busways penetrating walls shall have wall flanges installed on both
surfaces of walls. Wall openings shall be approximately 6.4 mm 1/4 inch
larger than the busway on each of the 4 busway sides, and openings shall be
sealed with a suitable compound. Fire barriers shall be provided when
penetrating fire rated walls. Fire barriers shall have a rating equal to
the fire wall rating. A weather barrier shall be used when a busway
penetrates an exterior wall. Busways shall be supported at intervals not
exceeding 3 m 10 feet and shall be braced to prevent lateral movement.
SECTION 33 70 02.00 10 Page 52
3.4 CABLE JOINTS
Medium-voltage cable joints shall be made by qualified cable splicers
only. Qualifications of cable splicers shall be submitted with a
certification that contains the names of people recommended to perform the
splicing and termination of medium-voltage cables approved for installation
under this contract. The certification shall indicate that any person
recommended to perform actual splicing and terminations has been adequately
trained in the proper techniques and have had at least three recent years
of experience in splicing and terminating the same or similar types of
cables approved for installation. In addition, any person recommended by
the Contractor may be required to perform a practice splice and
termination, in the presence of the Contracting Officer, before being
approved as a qualified installer of medium-voltage cables. If that
additional requirement is imposed, provide short sections of the approved
types of cables along with the approved type of splice and termination
kits, and detailed manufacturer's instruction for the proper splicing and
termination of the approved cable types.. Shields shall be applied as
required to continue the shielding system through each entire cable joint.
Shields may be integrally molded parts of preformed joints. Shields shall
be grounded at each joint or in accordance with manufacturer's recommended
practice. Cable joints shall provide insulation and jacket equivalent to
that of the associated cable. Armored cable joints shall be enclosed in
compound-filled, cast-iron or alloy, splice boxes equipped with stuffing
boxes and armor clamps of a suitable type and size for the cable being
installed.
3.5 FIREPROOFING
**************************************************************************
NOTE: Refer to UFC 3-550-01 for guidance regarding
flameproofing of cables in manholes.
**************************************************************************
[Each medium-voltage cable and conductor in manholes shall be fire-proofed
for their entire length within the manhole. Where cables and conductors
have been lubricated to enhance pulling into ducts, the lubricant shall be
removed from cables and conductors exposed in the manhole before
fireproofing.] [Fire-stops shall be installed in each conduit entering or
leaving a manhole.]
3.5.1 Tape Method
Before application of fireproofing tape, plastic tape wrapping shall be
applied over exposed metallic items such as the cable ground wire, metallic
outer covering, or armor to minimize the possibility of corrosion from the
fireproofing materials and moisture. Before applying fireproofing tape,
irregularities of cables, such as at cable joints, shall be evened out with
insulation putty. A flexible conformable polymeric elastomer fireproof
tape shall be wrapped tightly around each cable spirally in 1/2 lapped
wrapping or in 2 butt-jointed wrappings with the second wrapping covering
the joints of the first.
3.5.2 Sprayable Method
Manholes shall be power ventilated until coatings are dry and dewatered and
the coatings are cured. Ventilation requirements shall be in accordance
with the manufacturer's instruction, but not less than 10 air changes per
hour shall be provided. Cable coatings shall be applied by spray, brush,
SECTION 33 70 02.00 10 Page 53
or glove to a wet film thickness that reduces to the dry film thickness
approved for fireproofing by FM APP GUIDE. Application methods and
necessary safety precautions shall be in accordance with the manufacturers
instructions. After application, cable coatings shall be dry to the touch
in 1 to 2 hours and fully cured in 48 hours, except where the manufacturer
has stated that because of unusual humidity or temperature, longer periods
may be necessary.
3.6 DUCT LINES
3.6.1 Requirements
Numbers and sizes of ducts shall be as indicated. Duct lines shall be laid
with a minimum slope of 100 mm per 30 m 4 inches per 100 feet. Depending
on the contour of the finished grade, the high-point may be at a terminal,
a manhole, a handhole, or between manholes or handholes. Short-radius
manufactured 90-degree duct bends may be used only for pole or equipment
risers, unless specifically indicated as acceptable. The minimum
manufactured bend radius shall be 450 mm 18 inches for ducts of less than
80 mm 3 inch diameter, and 900 mm 36 inches for ducts 80 mm 3 inches or
greater in diameter. Otherwise, long sweep bends having a minimum radius of
7.6 m 25 feet shall be used for a change of direction of more than 5
degrees, either horizontally or vertically. Both curved and straight
sections may be used to form long sweep bends, but the maximum curve used
shall be 30 degrees and manufactured bends shall be used. Ducts shall be
provided with end bells whenever duct lines terminate in manholes or
handholes.
3.6.2 Treatment
Ducts shall be kept clean of concrete, dirt, or foreign substances during
construction. Field cuts requiring tapers shall be made with proper tools
and match factory tapers. A coupling recommended by the duct manufacturer
shall be used whenever an existing duct is connected to a duct of different
material or shape. Ducts shall be stored to avoid warping and
deterioration with ends sufficiently plugged to prevent entry of any water
or solid substances. Ducts shall be thoroughly cleaned before being laid.
Plastic ducts shall be stored on a flat surface and protected from the
direct rays of the sun.
3.6.3 Concrete Encasement
**************************************************************************
NOTE: For crossings of existing railroads and
airfield pavements greater than 15.2 m (50 feet) in
length, the pre-drilling method or the
jack-and-sleeve method will be used.
**************************************************************************
Ducts requiring concrete encasements shall comply with NFPA 70, except that
electrical duct bank configurations for ducts 150 mm 6 inches in diameter
shall be determined by calculation and as shown on the drawings. The
separation between adjacent electric power and communication ducts shall
conform to IEEE C2. Duct line encasements shall be monolithic
construction. Where a connection is made to a previously poured
encasement, the new encasement shall be well bonded or doweled to the
existing encasement. Submit proposed bonding method for approval in
accordance with the detail drawing portion of paragraph SUBMITTALS. At any
point, except railroad and airfield crossings, tops of concrete encasements
SECTION 33 70 02.00 10 Page 54
shall be not less than the cover requirements listed in NFPA 70. At
railroad and airfield crossings, duct lines shall be encased with concrete
and reinforced as indicated to withstand specified surface loadings. Tops
of concrete encasements shall be not less than 1.5 m 5 feet below tops of
rails or airfield paving unless otherwise indicated. Where ducts are
jacked under existing pavement, rigid steel conduit will be installed
because of its strength. To protect the corrosion-resistant conduit
coating, predrilling or installing conduit inside a larger iron pipe sleeve
(jack-and-sleeve) is required. For crossings of existing railroads and
airfield pavements greater than 15 m 50 feet in length, the predrilling
method or the jack-and-sleeve method will be used. Separators or spacing
blocks shall be made of steel, concrete, plastic, or a combination of these
materials placed not farther apart than 1.2 m 4 feet on centers. Ducts
shall be securely anchored to prevent movement during the placement of
concrete and joints shall be staggered at least 150 mm 6 inches vertically.
3.6.4 Nonencased Direct-Burial
**************************************************************************
NOTE: Specify cover requirements in accordance with
NFPA 70 and IEEE C2. Specify frost line depth.
**************************************************************************
Top of duct lines shall be below the frost line depth of [_____] mm inches,
but not less than [_____] mm inches below finished grade and shall be
installed with a minimum of 75 mm 3 inches of earth around each duct,
except that between adjacent electric power and communication ducts, 300 mm
12 inches of earth is required. Bottoms of trenches shall be graded toward
manholes or handholes and shall be smooth and free of stones, soft spots,
and sharp objects. Where bottoms of trenches comprise materials other than
sand, a 75 mm 3 inch layer of sand shall be laid first and compacted to
approximate densities of surrounding firm soil before installing ducts.
Joints in adjacent tiers of duct shall be vertically staggered at least 150
mm 6 inches. The first 150 mm 6 inch layer of backfill cover shall be sand
compacted as previously specified. The rest of the excavation shall be
backfilled and compacted in 75 to 150 mm 3 to 6 inch layers. Duct banks
may be held in alignment with earth. However, high-tiered banks shall use
a wooden frame or equivalent form to hold ducts in alignment prior to
backfilling.
3.6.5 Installation of Couplings
Joints in each type of duct shall be made up in accordance with the
manufacturer's recommendations for the particular type of duct and coupling
selected and as approved.
3.6.5.1 Bituminized-Fiber Ducts
**************************************************************************
NOTE: Bituminized fiber duct should be specified
only for connection to existing bituminized fiber
duct systems. Delete the paragraph if not
required. Specify thin-wall or schedule 40 plastic
duct for concrete encasement and thick-wall or
schedule 40 or schedule 80 plastic duct for
direct-burial and riser applications (riser bends
should be metallic conduit where cables are to be
pulled into ductline).
**************************************************************************
SECTION 33 70 02.00 10 Page 55
Bituminized-fiber ducts shall be used to interface with existing
bituminized-fiber duct as shown. To ensure a watertight joint, tapered
ends or joints of the same material as the ducts shall be swabbed with
bituminous or joint-sealing compound before couplings are applied. Plastic
or nonmetallic couplings shall be tightly driven onto unswabbed ducts. Due
to the brittleness of plastic couplings at low temperatures, such couplings
shall not be installed when temperatures are below minus 18 degrees C 0
degrees F. Couplings shall be warmed in hot water or by another approved
method when installed at temperatures below 0 degrees C 32 degrees F.
3.6.5.2 Plastic Duct
Duct joints shall be made by brushing a plastic solvent cement on insides
of plastic coupling fittings and on outsides of duct ends. Each duct and
fitting shall then be slipped together with a quick 1/4-turn twist to set
the joint tightly.
3.6.6 Duct Line Markers
**************************************************************************
NOTE: Coordinate with UF-02300 for underground
marking requirements.
**************************************************************************
Duct line markers shall be provided [as indicated] [at the ends of long
duct line stubouts or for other ducts whose locations are indeterminate
because of duct curvature or terminations at completely below-grade
structures]. In addition to markers, a 0.127 mm 5 mil brightly colored
plastic tape, not less than 75 mm 3 inches in width and suitably inscribed
at not more than 3 m 10 feet on centers with a continuous metallic backing
and a corrosion-resistant 0.0254 mm 1 mil metallic foil core to permit easy
location of the duct line, shall be placed approximately 300 mm 12 inches
below finished grade levels of such lines.
3.7 MANHOLES, HANDHOLES, AND PULLBOXES
3.7.1 General
Manholes shall be constructed approximately where shown. The exact
location of each manhole shall be determined after careful consideration
has been given to the location of other utilities, grading, and paving.
The location of each manhole shall be approved by the Contracting Officer
before construction of the manhole is started. Manholes shall be the type
noted on the drawings and shall be constructed in accordance with the
applicable details as indicated. Top, walls, and bottom shall consist of
reinforced concrete. Walls and bottom shall be of monolithic concrete
construction. The Contractor may, as an option, utilize monolithically
constructed precast-concrete manholes having the required strength and
inside dimensions as required by the drawings or specifications. In paved
areas, frames and covers for manhole and handhole entrances in vehicular
traffic areas shall be flush with the finished surface of the paving. In
unpaved areas, the top of manhole covers shall be approximately 15 mm 1/2
inch above the finished grade. Where existing grades that are higher than
finished grades are encountered, concrete assemblies designed for the
purpose shall be installed to elevate temporarily the manhole cover to
existing grade level. All duct lines entering manholes must be installed
on compact soil or otherwise supported when entering a manhole to prevent
shear stress on the duct at the point of entrance to the manhole. Duct
SECTION 33 70 02.00 10 Page 56
lines entering cast-in-place concrete manholes shall be cast in-place with
the manhole. Duct lines entering precast concrete manholes through a
precast knockout penetration shall be grouted tight with a portland cement
mortar. PVC duct lines entering precast manholes through a PVC endbell
shall be solvent welded to the endbell. A cast metal grille-type sump
frame and cover shall be installed over the manhole sump. A cable-pulling
iron shall be installed in the wall opposite each duct line entrance.
3.7.2 Electric Manholes
**************************************************************************
NOTE: Provide the plastic coating or supports where
corrosive conditions in manholes are anticipated.
Determine from the Using Agency what types of
communication cables the Contractor should provide.
**************************************************************************
Cables shall be securely supported from walls by hot-dip galvanized cable
racks with a plastic coating over the galvanizing and equipped with
adjustable hooks and insulators. The number of cable racks indicated shall
be installed in each manhole and not less than 2 spare hooks shall be
installed on each cable rack. Insulators shall be made of high-glazed
porcelain. Insulators will not be required on spare hooks.
3.7.3 Communications Manholes
The number of hot-dip galvanized cable racks with a plastic coating over
the galvanizing indicated shall be installed in each telephone manhole.
Each cable rack shall be provided with 2 cable hooks. Cables for the
telephone and communication systems will be installed by others.
3.7.4 Handholes
Handholes shall be located approximately as shown. Handholes shall be of
the type noted on the drawings and shall be constructed in accordance with
the details shown.
3.7.5 Pullboxes
Pullbox tops shall be flush with sidewalks or curbs or placed 15 mm 1/2 inch
above surrounding grades when remote from curbed roadways or sidewalks.
Covers shall be marked "Low-Voltage" and provided with 2 lifting eyes and 2
hold-down bolts. Each box shall have a suitable opening for a ground rod.
Conduit, cable, ground rod entrances, and unused openings shall be sealed
with mortar.
3.7.6 Ground Rods
A ground rod shall be installed at the manholes, handholes and pullboxes.
Ground rods shall be driven into the earth before the manhole floor is
poured so that approximately 100 mm 4 inches of the ground rod will extend
above the manhole floor. When precast concrete manholes are used, the top
of the ground rod may be below the manhole floor and a No. 1/0 AWG ground
conductor brought into the manhole through a watertight sleeve in the
manhole wall.
3.8 PAD-MOUNTED EQUIPMENT INSTALLATION
**************************************************************************
SECTION 33 70 02.00 10 Page 57
NOTE: Provide a typical concrete pad detail for
each different piece of equipment by size range
(typical dimensions and weight). The pad detail
should depict welded wire fabric or steel
reinforcing bars, sized and spaced as required to
support the equipment. Exact pad dimensions are
equipment specific and are the responsibility of the
Contractor. Require grouting of rectangular holes
(windows) in the concrete pad if rodent intrusion is
a problem.
**************************************************************************
Pad-mounted equipment, shall be installed on concrete pads in accordance
with the manufacturer's published, standard installation drawings and
procedures, except that they shall be modified to meet the requirements of
this document. Units shall be installed so that they do not damage
equipment or scratch painted or coated surfaces. After installation,
surfaces shall be inspected and scratches touched up with a paint or
coating provided by the manufacturer especially for this purpose.
Three-phase transformers shall be installed with [_____] phase sequence.
Primary taps shall be set at [_____].
3.8.1 Concrete Pads
3.8.1.1 Construction
Concrete pads for pad-mounted electrical equipment [may be either
pre-fabricated or] [shall be] poured-in-place. Pads shall be constructed
as indicated, except that exact pad dimensions and mounting details are
equipment specific and are the responsibility of the Contractor. Tops of
concrete pads shall be level and shall project 100 mm 4 inches above
finished [floor] [paving or grade] and sloped to drain. Edges of concrete
pads shall have 19 mm 3/4 inch chamfer. Conduits for primary, secondary,
and grounding conductors shall be set in place prior to placement of
concrete pads. Where grounding electrode conductors are installed through
concrete pads, PVC conduit sleeves shall be installed through the concrete
to provide physical protection. To facilitate cable installation and
termination, the concrete pad shall be provided with a rectangular hole
below the primary and secondary compartments, sized in accordance with the
manufacturer's recommended dimensions. Upon completion of equipment
installation the rectangular hole shall be filled with masonry grout.
3.8.1.2 Concrete and Reinforcement
Concrete work shall have minimum 20 MPa 3000 psi compressive strength and
conform to the requirements of Section 03 30 00.00 10 CAST-IN-PLACE
CONCRETE. Concrete pad reinforcement shall be in accordance with Section
03 20 00.00 10 CONCRETE REINFORCING.
3.8.1.3 Sealing
When the installation is complete, seal all conduit and other entries into
the equipment enclosure with an approved sealing compound. Seals shall be
of sufficient strength and durability to protect all energized live parts
of the equipment from rodents, insects, or other foreign matter.
3.8.2 Padlocks
Padlocks shall be provided for pad-mounted equipment and for each fence
SECTION 33 70 02.00 10 Page 58
gate. Padlocks shall be keyed [alike] [as directed by the Contracting
Officer].
3.8.3 Fencing
**************************************************************************
NOTE: Delete this paragraph when fencing is not
required. Ensure adequate space between the
transformer and the fence for equipment operation in
accordance with IEEE C2.
**************************************************************************
Fencing shall conform to the requirement of and be installed in accordance
with Section [32 31 13 CHAIN LINK FENCES AND GATES][32 31 26 WIRE FENCES
AND GATES]. Fences shall provide working clearances for operation and
maintenance in accordance with IEEE C2. The entire space between fences
and concrete pads shall be excavated to a minimum depth of 100 mm 4 inches
below finished gradelines, shall be graded to reasonably level surfaces,
and filled with well-compacted clean coarse gravel or crushed stone of 13
to 40 mm 1/2 to 1-1/2 inches graded size up to finished gradelines. Space
between fences and concrete pads shall be excavated to a minimum depth of
100 mm 4 inches below finished gradelines, shall be graded to reasonably
level surfaces, and filled with well-compacted clean coarse gravel or
crushed stone of 13 to 40 mm 1/2 to 1-1/2 inches graded size up to finished
gradelines.
3.9 CONNECTIONS BETWEEN AERIAL AND UNDERGROUND SYSTEMS
Connections between aerial and underground systems shall be made as shown.
Underground cables shall be extended up poles in [guards] [conduit] to
cable terminations. Conduits shall be secured to the poles by 2-hole
galvanized steel pipe straps spaced not more than 3 m 10 feet apart and
with 1 strap not more than 300 mm 12 inches from any bend or termination.
Cable guards shall be secured to poles in accordance with the
manufacturer's published procedures. Conduits shall be equipped with
bushings to protect cables and minimize water entry. Capnut potheads shall
be used to terminate medium-voltage multiple-conductor cable. Cables shall
be supported by devices separate from the conduit or guard, near their
point of exit from the conduit or guard. Pole installation shall be in
accordance with Section 33 71 01 OVERHEAD TRANSMISSION AND DISTRIBUTION.
3.10 CONNECTIONS TO BUILDINGS
**************************************************************************
NOTE: Specify a depth below the frost line and
coordinate with Section 26 20 00 INTERIOR
DISTRIBUTION SYSTEM. Specify or depict conduit
sealing method.
**************************************************************************
Cables shall be extended into the various buildings as indicated, and shall
be connected to the first applicable termination point in each building.
Interfacing with building interior conduit systems shall be at conduit
stubouts terminating 1.5 m 5 feet outside of a building and [600] [_____] mm
[2] [_____] feet below finished grade as specified and provided under
Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM. After installation of
cables, conduits shall be sealed [with caulking compound] [_____] to
prevent entrance of moisture or gases into buildings.
SECTION 33 70 02.00 10 Page 59
3.11 GROUNDING
**************************************************************************
NOTE: The designer will specify the grounding
configuration and the number and type of electrodes
required. See UFC 3-550-01 for guidance.
Coordinate with NFPA 70 and IEEE C2.
**************************************************************************
A ground [mat] [ring] consisting of the indicated configuration of bare
copper conductors and driven ground rods shall be installed [under]
[around] pad-mounted equipment as shown. Equipment frames of
metal-enclosed equipment, and other noncurrent-carrying metal parts, such
as cable shields, cable sheaths and armor, and metallic conduit shall be
grounded. At least 2 connections shall be provided from [a transformer,]
[a switchgear ground bus,] [and] [a unit substation] to the ground mat.
Metallic frames and covers of handholes and pull boxes shall be grounded by
use of a braided, copper ground strap with equivalent ampacity of No. 6 AWG.
3.11.1 Grounding Electrodes
**************************************************************************
NOTE: Modify and/or delete in accordance with
project requirements.
The designer should investigate the soil resistivity
during the preliminary design phase to determine the
design required to ensure that the grounding values
are obtained. For areas where the water table is
low and/or the soil resistivity is high (such as
volcanic soils, sand, or rock), delete the
additional electrode provisions and provide a design
to meet the site requirements.
**************************************************************************
Grounding electrodes shall be installed as shown on the drawings and as
follows:
a. Driven rod electrodes - Unless otherwise indicated, ground rods shall
be driven into the earth until the tops of the rods are approximately
300 mm 1 foot below finished grade.
b. Ground mat - A ground mat shall be installed as shown consisting of
bare copper conductors installed [300] [450] [600] mm [12] [18] [24]
inches, plus or minus 75 mm 3 inches, below the finished top of soil
grade. Mat conductors shall be bonded to all rod electrodes,
electrolytic electrodes, and to all other intersecting mat conductors.
Mat conductors shall be sized as shown on the drawings.
c. Ground ring - A ground ring shall be installed as shown consisting of
bare copper conductors installed not less than 750 mm30 inches below
finished top of soil grade. Ground ring conductors shall be [sized as
shown] [No. 2 AWG, minimum].
d. Additional electrodes - When the required ground resistance is not met,
additional electrodes shall be provided [interconnected with grounding
conductors] [as indicated] to achieve the specified ground resistance.
The additional electrodes will be [up to three, [2.4] [3] m [8] [10]
feet rods spaced a minimum of [3] [3.7] m [10] [12] feet apart] [a
SECTION 33 70 02.00 10 Page 60
single extension-type rod, [15.9] [19.1] mm [5/8] [3/4] inch diameter,
up to 9.1 m 30 feet long, [driven perpendicular to grade] [coupled and
driven with the first rod]]. In high ground resistance, UL listed
chemically charged ground rods may be used. If the resultant
resistance exceeds 25 ohms measured not less than 48 hours after
rainfall, the Contracting Officer shall be notified immediately.
3.11.2 Grounding and Bonding Connections
Connections above grade shall be made by the fusion-welding process or with
bolted solderless connectors, in compliance with UL 467, and those below
grade shall be made by a fusion-welding process. Where grounding
conductors are connected to aluminum-composition conductors, specially
treated or lined copper-to-aluminum connectors suitable for this purpose
shall be used.
3.11.3 Grounding and Bonding Conductors
Grounding and bonding conductors include conductors used to bond
transformer enclosures and equipment frames to the grounding electrode
system. Grounding and bonding conductors shall be sized as shown, and
located to provide maximum physical protection. Bends greater than 45
degrees in ground conductors are not permitted. Routing of ground
conductors through concrete shall be avoided. When concrete penetration is
necessary, nonmetallic conduit shall be cast flush with the points of
concrete entrance and exit so as to provide an opening for the ground
conductor, and the opening shall be sealed with a suitable compound after
installation.
3.11.4 Surge Arrester Grounding
**************************************************************************
NOTE: Provide a "detail" for surge arrester
grounding. See UFC 3-550-01 for guidance. For
ungrounded and single-grounded systems, modify
paragraph in accordance with IEEE C2 and UFC
3-550-01.
**************************************************************************
Surge arresters and neutrals shall be bonded directly to the transformer
enclosure and then to the grounding electrode system with a bare copper
conductor, sized as shown. Lead lengths shall be kept as short as
practicable with no kinks or sharp bends.
3.11.5 Manhole, Handhole, or Concrete Pullbox Grounding
Ground rods installed in manholes, handholes, or concrete pullboxes shall
be connected to cable racks, cable-pulling irons, the cable shielding,
metallic sheath, and armor at each cable joint or splice by means of a No.
4 AWG braided tinned copper wire. Connections to metallic cable sheaths
shall be by means of tinned terminals soldered to ground wires and to cable
sheaths. Care shall be taken in soldering not to damage metallic cable
sheaths or shields. Ground rods shall be protected with a double wrapping
of pressure-sensitive plastic tape for a distance of 50 mm 2 inches above
and 150 mm 6 inches below concrete penetrations. Grounding electrode
conductors shall be neatly and firmly attached to manhole or handhole walls
and the amount of exposed bare wire shall be held to a minimum.
SECTION 33 70 02.00 10 Page 61
3.11.6 Metal Splice Case Grounding
Metal splice cases for medium-voltage direct-burial cable shall be grounded
by connection to a driven ground rod located within 600 mm 2 feet of each
splice box using a grounding electrode conductor having a current-carrying
capacity of at least 20 percent of the individual phase conductors in the
associated splice box, but not less than No. 6 AWG.
3.11.7 Riser Pole Grounding
A single continuous vertical grounding electrode conductor shall be
installed on each riser pole and connected directly to the grounding
electrodes indicated on the drawings or required by these specifications.
All equipment, neutrals, surge arresters, and items required to be grounded
shall be connected directly to this vertical conductor. The grounding
electrode conductor shall be sized as shown. Grounding electrode
conductors shall be stapled to wood poles at intervals not exceeding 600 mm
2 feet.
3.12 FIELD TESTING
**************************************************************************
NOTE: Select types to suit project conditions and
delete all others. Delete all paragraphs not
applicable. Tests must be justified.
**************************************************************************
Submit a proposed field test plan, [20] [30] [_____] days prior to testing
the installed system. No field test shall be performed until the test plan
is approved. The test plan shall consist of complete field test procedures
including tests to be performed, test equipment required, and tolerance
limits.
3.12.1 General
Field testing shall be performed in the presence of the Contracting
Officer. Notify the Contracting Officer [_____] days prior to conducting
tests. Furnish all materials, labor, and equipment necessary to conduct
field tests. Perform all tests and inspections recommended by the
manufacturer unless specifically waived by the Contracting Officer.
Maintain a written record of all tests which includes date, test performed,
personnel involved, devices tested, serial number and name of test
equipment, and test results. Field test reports shall be signed and dated
by the Contractor.
3.12.2 Safety
Provide and use safety devices such as rubber gloves, protective barriers,
and danger signs to protect and warn personnel in the test vicinity.
Replace any devices or equipment which are damaged due to improper test
procedures or handling.
3.12.3 Ground-Resistance Tests
The resistance of [each grounding electrode] [each grounding electrode
system] [the ground mat] [the ground ring] shall be measured using the
fall-of-potential method defined in IEEE 81. Ground resistance
measurements shall be made before the electrical distribution system is
energized and shall be made in normally dry conditions not less than 48
SECTION 33 70 02.00 10 Page 62
hours after the last rainfall. Resistance measurements of separate
grounding electrode systems shall be made before the systems are bonded
together below grade. The combined resistance of separate systems may be
used to meet the required resistance, but the specified number of
electrodes must still be provided.
a. Single rod electrode - [25] [_____] ohms.
b. Multiple rod electrodes - [_____] ohms.
c. Ground mat - [_____] ohms.
d. Ground ring - [_____] ohms.
3.12.4 Ground-Mat Connection Inspection
All below-grade ground-mat connections will be visually inspected by the
Contracting Officer before backfilling. Notify the Contracting Officer
[_____] hours before the site is ready for inspection.
3.12.5 Medium-Voltage Cable Test
**************************************************************************
NOTE: If the installation is tapping a new feeder
to an existing feeder using a "T" splice, modify the
paragraph to indicate that when existing cable
cannot be readily disconnected, the system should
only be tested to the lower (after installation)
voltage.
**************************************************************************
After installation and before the operating test or connection to an
existing system, the medium-voltage cable system shall be given a high
potential test. Direct-current voltage shall be applied on each phase
conductor of the system by connecting conductors as one terminal and
connecting grounds or metallic shieldings or sheaths of the cable as the
other terminal for each test. Prior to making the test, the cables shall
be isolated by opening applicable protective devices and disconnecting
equipment. The test shall be conducted with all splices, connectors, and
terminations in place. The method, voltage, length of time, and other
characteristics of the test for initial installation shall be for the
particular type of cable installed, except that 28 kV and 35 kV insulation
test voltages shall be in accordance with either AEIC CS8 or AEIC CS8 as
applicable, and shall not exceed the recommendations of IEEE 404 for cable
joints and IEEE 48 for cable terminations unless the cable and accessory
manufacturers indicate higher voltages are acceptable for testing. Should
any cable fail due to a weakness of conductor insulation or due to defects
or injuries incidental to the installation or because of improper
installation of cable, cable joints, terminations, or other connections,
make necessary repairs or replace cables as directed. Repaired or replaced
cables shall be retested.
3.12.6 Low-Voltage Cable Test
**************************************************************************
NOTE: The insulation resistance test (dielectric
test) value is based on the recommendation contained
in IEEE 525, IEEE Guide for the Design and
Installation of Cable Systems in Substations.
SECTION 33 70 02.00 10 Page 63
**************************************************************************
Low-voltage cable, complete with splices, shall be tested for insulation
resistance after the cables are installed, in their final configuration,
ready for connection to the equipment, and prior to energization. The test
voltage shall be 500 volts dc, applied for one minute between each
conductor and ground and between all possible combinations conductors in
the same trench, duct, or cable, with all other conductors in the same
trench, duct, or conduit. The minimum value of insulation shall be:
R in megohms = (rated voltage in kV + 1) x 304.8/(length of cable in meters)
R in megohms = (rated voltage in kV + 1) x 1000/(length of cable in feet
Each cable failing this test shall be repaired or replaced. The repaired
cable shall be retested until failures have been eliminated.
3.12.7 Liquid-Filled Transformer Tests
The following field tests shall be performed on [all liquid-filled
transformers] [liquid-filled transformers [_____] kVA and above].
Pass-fail criteria shall be in accordance with transformer manufacturer's
specifications.
a. Insulation resistance test phase-to-ground.
b. Turns ratio test.
c. Correct phase sequence.
d. Correct operation of tap changer.
e. [_____]
3.12.8 Dry-Type Transformer Tests
The following field tests shall be performed on [all dry-type transformers]
[dry-type transformer [_____] kVA and above]. Pass-fail criteria shall be
in accordance with the transformer manufacturer's specifications.
a. Insulation resistance test phase-to-ground.
b. Turns ratio test.
c. [_____]
3.12.9 Circuit Breaker Tests
The following field tests shall be performed on circuit breakers.
Pass-fail criteria shall be in accordance with the circuit breaker
manufacturer's specifications.
a. Insulation resistance test phase-to-phase.
b. Insulation resistance test phase-to-ground.
c. Closed breaker contact resistance test.
d. Power factor test.
SECTION 33 70 02.00 10 Page 64
e. High-potential test.
f. [Manual][ and ][electrical] operation of the breaker.
3.12.10 Power Circuit Breaker Tests
**************************************************************************
NOTE: List specific breakers to be tested. Delete
entirely if test not required.
**************************************************************************
The following power circuit breakers shall be tested in accordance with
NEMA C37.50.
a. [_____].
b. [_____].
c. [_____].
3.12.11 Protective Relays
Protective relays shall be visually and mechanically inspected, adjusted,
tested, and calibrated in accordance with the manufacturer's published
instructions. Tests shall include pick-up, timing, contact action,
restraint, and other aspects necessary to ensure proper calibration and
operation. Relay settings shall be implemented in accordance with the
coordination study. Relay contacts shall be manually or electrically
operated to verify that the proper breakers and alarms initiate. Relaying
current transformers shall be field tested in accordance with IEEE C57.13.
3.12.12 Pre-Energization Services
Calibration, testing, adjustment, and placing into service of the
installation shall be accomplished by a manufacturer's product field
service engineer or independent testing company with a minimum of 2 years
of current product experience. The following services shall be performed
on the equipment listed below. These services shall be performed
subsequent to testing but prior to the initial energization. The equipment
shall be inspected to ensure that installation is in compliance with the
recommendations of the manufacturer and as shown on the detail drawings.
Terminations of conductors at major equipment shall be inspected to ensure
the adequacy of connections. Bare and insulated conductors between such
terminations shall be inspected to detect possible damage during
installation. If factory tests were not performed on completed assemblies,
tests shall be performed after the installation of completed assemblies.
Components shall be inspected for damage caused during installation or
shipment to ensure packaging materials have been removed. Components
capable of being both manually and electrically operated shall be operated
manually prior to the first electrical operation. Components capable of
being calibrated, adjusted, and tested shall be calibrated, adjusted, and
tested in accordance with the instructions of the equipment manufacturer.
Items for which such services shall be provided, but are not limited to,
are the following:
a. Secondary unit substation
b. Pad-mounted transformers
c. Panelboards
d. Switchboards
SECTION 33 70 02.00 10 Page 65
e. Metal-enclosed switchgear
f. Busways
g. Switches
3.12.13 Operating Tests
After the installation is completed, and at such times as the Contracting
Officer may direct, conduct operating tests for approval. The equipment
shall be demonstrated to operate in accordance with the requirements
herein. Submit [6] [_____] copies of the tests report in 215.9 by 279.4 mm
8-1/2 by 11 inch binders having a minimum of three rings, including a
separate section for each test. Sections shall be separated by heavy
plastic dividers with tabs. The operating test report shall include the
following:
a. A list of equipment used, with calibration certifications.
b. A copy of measurements taken.
c. The dates of testing.
d. The equipment and values to be verified.
e. The condition specified for the test.
f. The test results, signed and dated.
g. A description of adjustments made.
3.13 MANUFACTURER'S FIELD SERVICE
**************************************************************************
NOTE: Delete if not required.
**************************************************************************
3.13.1 Onsite Training
Conduct a training course for the operating staff as designated by the
Contracting Officer. The training period shall consist of a total of
[_____] hours of normal working time and shall start after the system is
functionally completed but prior to final acceptance tests. The course
instructions shall demonstrate all routine maintenance operations. A
[_____] [VHS] format video tape of the entire training session shall be
submitted.
a. The course instruction shall cover pertinent points involved in
operating, starting, stopping, and servicing the equipment, as well as
all major elements of the operation and maintenance manuals. Submit
[6] [_____] copies of operation and maintenance manuals, within [7]
[_____] calendar days following the completion of tests and including
assembly, installation, operation and maintenance instructions, spare
parts data which provides supplier name, current cost, catalog order
number, and a recommended list of spare parts to be stocked.
b. Manuals shall also include data outlining detailed procedures for
system startup and operation, and a troubleshooting guide which lists
possible operational problems and corrective action to be taken. A
brief description of all equipment, basic operating features, and
routine maintenance requirements shall also be included.
c. Documents shall be bound in a binder marked or identified on the
spine and front cover. A table of contents page shall be included and
marked with pertinent contract information and contents of the manual.
Tabs shall be provided to separate different types of documents, such
as catalog ordering information, drawings, instructions, and spare
SECTION 33 70 02.00 10 Page 66
parts data. Index sheets shall be provided for each section of the
manual when warranted by the quantity of documents included under
separate tabs or dividers. Three additional copies of the instructions
manual shall be provided within 30 calendar days following the manuals.
3.13.2 Installation Engineer
Provide at least one onsite person in a supervisory position with a
documentable level of competency and experience to supervise all cable
pulling operations. A resume shall be provided showing the cable
installers' experience in the last three years, including a list of
references complete with points of contact, addresses and telephone
numbers. After delivery of the equipment, furnish one or more field
engineers, regularly employed by the equipment manufacturer to supervise
the installation of the equipment, assist in the performance of the onsite
tests, initial operation, and instruct personnel as to the operational and
maintenance features of the equipment.
3.14 ACCEPTANCE
Final acceptance of the facility will not be given until the Contractor has
successfully completed all tests and after all defects in installation,
material or operation have been corrected.
-- End of Section --
SECTION 33 70 02.00 10 Page 67

You might also like