Job Knowledge 97
Job Knowledge 97
Job Knowledge 97
Welding Costs
Welding Costs Part II
The previous two Connect articles dealt with
the mechanics of costing a weld: how to
calculate the weld volume and how to
calculate the amount of welding consumables
required to fill a weld preparation.
The final step in costing a weld is to
determine the length of time to deposit this
weight of weld metal. This is obviously a
function of the deposition rate of the process.
The deposition rate is generally expressed as
kgs/hr or lbs/hr deposited at a given welding
current, welding continuously and without
any breaks for electrode changing or
deslagging.
The deposition rate will be affected by many factors and it will not be possible
within the limitations of these articles to list the precise deposition rates for any
specific process or welding current. Such data can be found in publications
referenced below or by a web search. The ranges of approximate deposition rates
for the commoner arc welding processes are listed in Table 1.
Table 1 Indicative deposition rates - arc welding processes
Deposition Rate kgs/hr
Welding Process
min max
MMA 0.4 5.5
MAG 0.6 12
FCAW 1.0 15
Single wire SAW 3 16
To obtain an accurate figure for the specific parameters to be used is a relatively
simple exercise. Weighing a plate, depositing weld metal using the required
parameters on this plate for a fixed time and then re-weighing the plate will give
an accurate figure that may be used for estimating purposes.
There is one golden rule for minimising the cost of making a weld and, whilst this
may seem to be self-evident, it is worth repeating: deposit the minimum amount
of the highest quality weld metal with the largest gauge electrode or wire at the
highest current in the shortest possible time. This is obviously the ideal and can
seldom be achieved in practice because of limitations on heat input, access etc.
The implications of applying the golden rule are:
a. To deposit the minimum amount of weld metal the designer, aided by the
welding engineer, must select the smallest weld preparation that is capable of
providing the required weld quality. If the included angle is too narrow then
Flux cored arc welding
lack of side wall fusion is a possibility with the consequent costs of repair; too
wide an angle is wasteful in terms of deposited weld metal. Remember,
though, that the cost of providing a weld preparation (by flame-cutting, edge
planning, milling etc) must also be included in any costing exercise as must
the cost of assembly. Machined weld preparations are more accurate than
flame cut edges and this may result in faster set-up times and a reduced weld
repair rate.
It may be possible to use a square edge preparation by using the deep
penetration characteristics of some of the welding processes; electron
beam and laser welding are the best examples of this technique. Plasma-
TIG and activated flux TIG can penetrate up to 10mm in a single pass; the
'finger' penetration of spray transfer MAG welding can penetrate up to
6mm and a submerged arc weld can penetrate up to 15mm. There is also
the benefit when using a square edge preparation in that the consumption
of filler metal is substantially reduced, the bulk of the weld metal being
provided by the parent material.
The final option on reducing costs when butt welding is for the designer to
specify a partial penetration joint. The most expensive weld pass in any full
penetration butt weld is the root pass and if this can be eliminated by
using partial penetration joints then substantial savings can be made.
However, the decision to use partial penetration welds should not be taken
lightly but only if service conditions permit the presence of a large crevice
at the weld root. The designer will therefore need to consider whether
fatigue, creep, corrosion etc are likely to occur and must clearly specify
where the joints are permitted and the minimum acceptable weld throat.
b. Depositing the highest quality weld metal infers that the weld repair rate will
be reduced. Repair weld metal is very costly, particularly if the unacceptable
defects are detected late in the fabrication programme; perhaps after final
assembly where access is difficult or after post weld heat treatment. Accurate
weld preparations and fit-up, easy access for the welder, welds made in the
flat position and well trained welders will all help to minimise the weld repair
rate.
c. Depositing weld metal with the largest electrode or wire at the highest current
will obviously give the highest weld deposition rate and shortest joint
completion time. The deposition rate figures in Table 1 give the minimum and
maximum deposition rates at minimum and maximum welding currents. As
an example, a 1.2mm diameter MAG wire at 120amps will deposit around 1.2
kgs/hr, at 380amps around 8 kgs/hr. To enable high welding currents to be
used the item must be placed in the flat position and there must be easy
access for the welder. One benefit of using the high welding currents is that
the number of weld runs to fill the joint will be reduced and this, in most
circumstances, will result in less distortion than a large number of low current
weld passes. Remedial work to correct distortion can therefore be reduced. A
further benefit when welding the ferritic steels is that high current and
therefore high heat input may allow any preheat to be reduced or eliminated
entirely.
However, there are limitations to this approach to improving productivity. If
achieving high toughness is a factor then it is likely that heat input will need to be
controlled when welding the ferritic steels, placing a limit on the welding current
and travel speed. High welding currents also imply a large, fluid weld pool and it
may not be possible to control this pool when welding in any other than the flat
position - for example, MAG welding cannot be performed using spray transfer
(high welding current) in the vertical position due to the absence of a flux to hold
the pool in place. Using a manual process at such high currents also results in
increased welder fatigue resulting in a reduced duty cycle. A solution to this
problem is to mechanise or automate the process.
To achieve the most cost effective solution to producing a welded structure is
therefore not simply to increase duty cycle or deposition rate but to consider all
aspects of fabrication from the design stage to final inspection, involving all
members of the team from designer to welder.
This article was written by Gene Mathers.
References:
Procedure Handbook of Arc Welding, Publ Lincoln Co.
Standard Data for Arc Welding, Publ TWI (out of print)
Welding Handbook Vol 2 Welding Processes, Publ American Welding Society
Copyright 2008 TWI Ltd
Information and advice from TWI and its partners are provided in good faith and based, where appropriate,
on the best engineering knowledge available at the time and incorporated into TWI's website in
accordance with TWI's ISO 9001:2000 accredited status. No warranty expressed or implied is given
regarding the results or effects of applying information or advice obtained from the website, nor is any
responsibility accepted for any consequential loss or damage.