Various Tendering Systems: and Their Implication in Project Cost, Time, Quality and Performance
Various Tendering Systems: and Their Implication in Project Cost, Time, Quality and Performance
Various Tendering Systems: and Their Implication in Project Cost, Time, Quality and Performance
Before any of the construction project activities start, there will always be an initial process of submitting a
proposal (tender) to manage the undertaking of the project. This process is called tendering process. In
construction context, the tender is treated as an offer to do the work for a certain amount of money or a
certain amount of profit. They are the very first stage in any construction project processes.
Tendering process also serves as the employers way to select the contractor. The selection of a contractor
to carry out a project is an important matter to do. It requires careful thought of the employer and his
advisors (consultants). A wrong choice may lead to an unhappy relationship between the employer and also
the contractor, which will eventually make the appearance of disputes.
Since construction industry is a large and complex industry, any one contractor will not be suitable for any
one job. A contracting organization will be geared to work for a particular size or price range and will be
unsuitable for contracts outside that range. For example, contractor grade A may not be suitable to carry
out projects which are deemed for contractor grade B. Or a State-Owned Construction Company would
probably not be suitable to carry out a small construction project or to build a single house in an urban
Various Tendering Systems
And Their Implication in Project Cost, Time, Quality and Performance
Seng Hansen
Master Student of Construction Contract Management UTM
Email: [email protected]
probably not be suitable to carry out a small construction project or to build a single house in an urban
location. The overhead costs of that size of organization would make it impossible for the company to carry
out the work for an economic price. Therefore, we need to have the knowledge of tendering system. The
main purpose of tendering system is to select a particular contractor for a certain project.
The employers professional advisers should aim to find a contractor which is:
1. Financially stable
2. Has a good business record
3. Suitable for the project (experience, size, method, complexity, etc)
4. Efficient organization
5. Has a good record of industrial relations
6. Has a reputation for good quality workmanship
7. Able to start when required
The above requirements may be added more by the employer.
There are various tendering systems in construction industry. Below are brief explanations of some
tendering systems, their merits and demerits, and eventually a comparison in relation to cost, time, quality
and performance.
1
Tendering Systems
Open Tendering
Selective Tendering
Two Stage Tendering
Serial Tendering
Negotiated Tendering
Open Tendering
This type of tendering system is initiated by the employers project manager, architect or quantity surveyor
by advertising the desired project in newspapers and other press, inviting contractors to apply for tender
documents and to tender in competition for carrying out the work. Usually, a deposit is required in order to
discourage frivolous applications, the deposit being returnable on the submission of a bona fide tender.
Since it is open for all tenderers, this system may require a long process for the employer and consultants to
evaluate the tenders.
Advantages Disadvantages
There can be no charge of favouritism as
might be brought where a selected list is
drawn up
Can result in a large number of unsuitable
firms tendering for the work
An opportunity is provided for a capable
firm to submit a tender, which might not be
included on a selected list
Can result in wasted time and effort in the
selection process, and therefore, it can
increase the total cost of tendering
It is a competitive process, therefore the
employer may get the best prices
There is a danger that the lowest or best
tender may be submitted by an
inexperienced contractor
There is no guarantee for the chosen
contractor is sufficiently capable of
financially stable
Selective Tendering
Under this system, a short list is drawn up of contractors who are considered to be suitable to carry out the
proposed project. Experienced employers and consultants will normally have a list of contractors who
undertake different types of contracts and their records. Contractors are invited to tender on their proven
record in relation to the type and size of contract and their reliability. The contractors may also be invited
2
record in relation to the type and size of contract and their reliability. The contractors may also be invited
through suitably worded advertisements in the press, to apply to be considered for inclusion in the tender
list. This gives the employer the opportunity to exclude any unsuitable contractors, and to limit the number
of tenderers. At the same time, it also gives any contractor the opportunity to apply to be considered.
The criteria that an employer may use to decide upon the suitability of a contractor are:
1. Whether the company has had recent experience of similar projects of a similar standard and completed
within the envisaged time scale
2. Whether the company has the skills necessary for the delivery of the project
3. The quality of the company management structure and personnel employed by the company
4. Whether the company has the spare capacity to carry out the work within the proposed time scale
5. The financial standing and record of the company
It is recommended that the number of tenderers should be limited to between five and eight, depending on
the size and complexity of the project. If all tenderers are reputable, well-established and suitable for the
proposed project, the employer then may select based on the best offered price. This system is commonly
preferred method where the employer wishes to save time in assessing the technical and financial aspects
of candidates.
Advantages Disadvantages
It tends to reduce time and effort, and
eventually will reduce the cost of tendering
process
The submit prices will be higher since there
being less competition and also due to the
higher caliber of the tenderers
It ensure that only capable and suitable
contractors submit their tenders
Has produced problems of ringing
(contractors phone the employer or
consultants in order to get the project)
Nomination
This is a special kind of selective tendering, where the list of candidates contains only one name. It is
sometimes referred to as single tendering. It is used when the employer has a preference for a particular
company, often because it has done satisfactory work for the employer before.
If only one contractor tenders for the job, there is no competition and it leads to a higher price. The
employer may think it is worth paying more, however, in return for a quicker and better quality job. When a
contractor is nominated, the contract sum will be arrived at by a process of negotiation. Usually the
negotiation will be conducted between one of the contractors estimators and the surveyor on behalf of the
employer. When agreement on the whole contract is reached, a contract will be entered and signed by both
parties.
Negotiated Tendering
It is almost same with nomination. The only difference is that in nomination, which is considered as a
special kind of selective tendering, consists of only one name and then the only contractor will negotiate
the whole matters in contract with the employer. While in negotiated tendering, there may be more than
one contractor.
In this system, detailed discussions are held with each of the chosen contractors during which their
experience and management expertise is assessed and the contractor offering the skills and knowledge best
suited to the project is selected in order to participate, with the employers consultants, during the design
stage so as to provide advice on buildability, value engineering and construction methods and eventually
agree a price for the project which will subsequently form the basis of a contract which will be entered into
prior to construction work commencing on site. This system is usually used to employ contractors of a prior to construction work commencing on site. This system is usually used to employ contractors of a
specialist nature, or to extend an existing contract, i.e. where a new tower is added to a building after the
construction has been started.
However, it is always possible that the negotiations may break down and both parties reach deadlock and
thus necessary to ensure that the employer has the option of being able to break off the negotiation if the
impediment to an equitable solution cannot be removed.
3
Advantages Disadvantages
The system is useful where other systems
cannot attract sufficient tenders or realistic
prices, where a special expertise is required
or where project costs can be reduced as a
result of the contractor already being
established on site
The submit prices will be higher since there
being less competition and also due to the
specialist nature of the tenderers
Modest savings in time can be achieved
using this system
Serial Tendering
This system is normally used on large projects. When a large project is to be carried out in successive
phases, there will be a number of contracts. The contractor is chosen for the first phase by means of
selective competitive tendering. The accepted tender forms the basis of payment for the resulting contract
in the normal way. The tender is also used for the second and later phases, provision being made for so
doing in the initial contract by the inclusion of a formula for updating the prices. Alternatively, the contract
for the first phase may specify negotiation of new rates, based upon the tendered prices, as the means of
determining the payment for each successive phase in the series.
The purpose of this system is to gain the benefits of continuity. The contractor for the first phase will have
his site organization set up, his offices, mess and storage huts, etc., already in use and plant of various kinds
on the site. When the second phase commences, these facilities will be already available, thus allowing a
smooth transition with much less additional expense than if a different contractor were to be employed. In
addition, the contractors workers will be familiar with the details of the construction after building the first
phase, and thus should be able to work more speedily and efficiently.
Two Stage Tendering (Early Contractor Involvement)
It is also a special kind of selective tendering but with different involvement of contractor. This procedure is
used when it is desired to obtain the benefits of competition and at the same time to have the advantage of
bringing a contractor into the planning of the project, thus making use of his practical knowledge and
expertise. It may also result in an earlier start on site.
Advantages Disadvantages
Avoids the need to dismantle experienced
project teams after the completion of one
project and allows their accumulated
knowledge and expertise to be utilized on
the subsequent stages
This system can only be used if the
employer has a substantial and an on-going
building program where the individual
projects are sufficiently similar in design
Tender prices are able to be reduced as
contractors are given continuity of work
4
As has been indicated in the name of the system, there are two stages in implementing this system. The
first stage aims to select a suitable contractor by means of limited competition. The second stage is a
process of negotiation with the selected contractor on the basis of the first-stage tender.
Stage 1
Tenderers bid on basis of capability, resources, track records, order-of magnitude price, overheads and
profits, outline program and fee for pre-construction services. Preferred contractor identified and an
agreement executed to record pre-construction services to be performed.
Stage 2
Employer and contractor continually develop design, jointly procure competitive tenders for major sub-
contracts, and agree price (after most major sub-contracts tendered). Second stage concludes with the
agreement of a lump-sum contract price (based on negotiation).
Advantages Disadvantages
Saving in time can be achieved, early start Less competition
Contractors early involvement will open
more advices from practical knowledge to
be implemented in the project
The employer can be vulnerable to any
change in the level of contractors pricing
from that contained within the first stage
tender (employer does not obtain the best
price)
Comparison of Various Tendering Systems
From the above advantages and disadvantages of each types of tendering system, we can summarize them
into a comparison table. Below is the comparison table of various types of tendering system in relation to
cost, time, quality and performance.
Cost Time Quality Performance
Open Tendering A C C C
Selective Tendering B B B B
Negotiated Tendering B B A A
Serial Tendering B A A A
Two Stage Tendering C A B A
A : strongly desirable
B : desirable
C : not desirable
Conclusion
The above comparison is only served as a brief comparison of various tendering systems. It does not give
the overall best tendering system for all types of project. It just serves as the general approach for selecting
the best tendering system for a certain type of project only.
Usually in a competitive tendering situation, price tends to be the only criterion for selection. But in the
case of two stage tendering where the contractor has more involvement with the project through a design
or management input, it may effect to the tender price and project quality. If such approach is adopted,
5
or management input, it may effect to the tender price and project quality. If such approach is adopted,
then the employer should be fully informed of the selection criteria.
Despites of so many tendering systems adopt in construction industry, the employer and consultant must
remember that they should conduct the tendering process fairly. As in the case of Harmon CFEM Facades
(UK) Ltd v Corporate Officer of the House of Commons (1999) 67 Con LR 1, the court held that the
defendant was in breach of its obligation to conduct the tendering process fairly and openly, and the
claimant was entitled to recover the wasted costs of tendering.
References
Masterman, J.W.E. 1996. An Introduction to Building Procurement Systems. London: E & FN Spon.
Ramus, J., Birchall, S., and Griggiths, P. 2006. Contract Practice for Surveyors. Fourth Edition. Oxford:
Butterworth-Heinemann.