Microsoft Project Tutorial
Microsoft Project Tutorial
calendars
Working with resources and assignments,
3
Clustering tasks for FAZ Software Project
Requirements and Design
◦ System specification (5 days)
◦ Architectural design (10 days)
◦ Systems design (4 days)
Coding the FAZ Software system
◦ Coding (20 days)
Produce systems documentation
◦ Produce technical manual (8 days)
Testing the system and documentation
◦ Unit and functional test (4 days)
◦ Integrated Test (3 days)
◦ Produce user manual (6 days)
Deployment
◦ Install systems and operations (5 days)
Gantt Charts
• Allows all key stages of the project, their duration and who
is responsible to be reviewed
• It is useful to create a project by entering tasks and the
amount of time each task will take.
• Establish sequential dependencies between tasks by linking
them.
– When you link tasks, you can see how a change in the duration
of one task affects the start and finish dates of other tasks
and the project finish date.
• Assign personnel and other resources to tasks.
• See how tasks progress across time.
– track progress by comparing planned and actual start and finish
dates
– Track progress by checking the completion percentage of each
task.
• View tasks graphically while still having access to detailed
information about the tasks.
• Split a task so that the task is interrupted and then resumes
later in the schedule; You can include milestones
Example of Gantt Chart
2004 2005 2006 2007
ID Task Name Duration Start Finish Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3
1 Scaling Up Commitment Control System 315 days? Mon 20/09/04 Fri 02/12/05
and FMS
2 FMS implemented in ABB format 1 day Mon 20/09/04 Mon 20/09/04
3 Appoint Commitment Control Officers in all 1 day? Mon 20/09/04 Mon 20/09/04
ministries
4 Print and Distribute Commitment Control 1 day? Mon 20/09/04 Mon 20/09/04
User Manual
5 Complete Sensitization workshops 1 day? Mon 20/09/04 Mon 20/09/04
6 Procurement of Computers and printers 100 days? Mon 03/01/05 Fri 20/05/05
7 Develop technical requirements and tender document
5 days? Mon 03/01/05 Fri 07/01/05
8 Advertise 20 days? Mon 10/01/05 Fri 04/02/05
9 Evaluation of tenders 10 days? Mon 07/02/05 Fri 18/02/05
10 Ministerial Tender/ ZNTB Approval 10 days? Mon 21/02/05 Fri 04/03/05
11 Award and sign contract 10 days? Mon 07/03/05 Fri 18/03/05
12 Delivery of Computer Equipment 45 days? Mon 21/03/05 Fri 20/05/05
13 Computers delivered and installed in Provincial0 depts
days andFri
Missions
20/05/05abroadFri 20/05/05 20/05
14 Implement FMS in Provincial Departments 43 days? Wed 01/06/05 Fri 29/07/05
15 FMS implemented and operational in Provincial Depts
0 days? Fri 30/09/05 Fri 30/09/05 30/09
16 Implement FMS in Missions Abroad 45 days? Mon 03/10/05 Fri 02/12/05
17 FMS implemented and operational in Mission Abroad
0 days Fri 02/12/05 Fri 02/12/05 02/12
Create a new project
To start Microsoft Project. Click on Start Button, All
Programs, Microsoft Office, then Microsoft Project
Do the following Tasks
1. Click Project from the menu.
2. Click Project Information, type or select a start date
eg 17/07/2011 or a finish date for your project, and
then click OK.
2. Click Save.
3. In the File name box, type a name for your project eg
FAZ Software Project, and then click Save.
You can change your project information at any time by
clicking Project Information on the Project menu.
Enter key project information
Each project has a unique set of ingredients: the
tasks involved, the people who do them, and the
project goal.
1.On the File menu, click Properties, and then
click the Summary tab.
2.Enter any information you'd like about your
project, such as the people who will manage
it and maintain the project file, the project
goal, any known limitations that may make it
difficult to reach that goal, and other general
project notes.
3.Click OK.
Set up the project calendar
You can specify nonworking times, such as weekends
and evenings, as well as special days off, such as
holidays.
1. On the View menu, click Gantt Chart.
2. On the Tools menu, click Change Working Time.
3. Select a date on the calendar. To change one day of
the week for the entire calendar, for example, to
have Fridays end at 4:00 P.M., click the
abbreviation for that day at the top of the calendar.
4. Click Nonworking time for days off, or Nondefault
working time to change the hours worked.
4. If you clicked Nondefault working time in step 3,
type the times you want work to start in the From
boxes, and the times you want work to end in the
To boxes.
5. Click OK.
Enter tasks and their durations
Enter tasks in the order they will occur. Then estimate
how long it will take to complete each task, and enter
your estimate as the duration.
1. On the View menu, click Gantt Chart.
2. In the Task Name field, type a task name, and then
press TAB.
3. In the Duration field, type the amount of time each
task will take in months, weeks, days, hours, or
minutes, not counting nonworking time. You can
use the following abbreviations: months = mo;
weeks = w; days = d; hours = h; minutes = m. To
show an estimated duration, type a question mark
after the duration.
4. Press ENTER.
You can indent related tasks. You can also add a note
about a task.
Enter tasks and their durations
Enter tasks in the order they will occur. Then estimate
how long it will take to complete each task, and enter
your estimate as the duration.
1. On the View menu, click Gantt Chart.
2. In the Task Name field, type a task name, and then
press TAB.
3. In the Duration field, type the amount of time each
task will take in months, weeks, days, hours, or
minutes, not counting nonworking time. You can
use the following abbreviations: months = mo;
weeks = w; days = d; hours = h; minutes = m. To
show an estimated duration, type a question mark
after the duration.
4. Press ENTER.
You can indent related tasks. You can also add a note
about a task.
Create a milestone
A milestone is a task you use to identify significant
events in your schedule, such as the completion of a
major phase. When you enter a duration of zero days
for a task, Microsoft Project displays the milestone
symbol (diamond) on the Gantt Chart at the start of
that day.
1. In the Duration field, click the duration of the task
you want to make a milestone, and then type 0d.
2. Press ENTER.
3. Create three milestones for the project
Another way is to mark a task as a milestone, click the
task in the Task Name field. Click Task Information,
click the Advanced tab, and then select the Mark task
as milestone check box.
To see all milestones, click Milestones in the Filter list.
Create a recurring task
Recurring tasks are tasks that repeat regularly, such as weekly
meetings. A recurring task can take place daily, weekly,
monthly, or yearly. To create a recurring task:
1. In the Task Name field, click the row below where you
want the recurring task to appear.
2. On the Insert menu, click Recurring Task.
3. In the Task Name box, type the task name: Progress Report
4. In the Duration box, type or select the duration of a single
occurrence of the task.
5. Under Recurrence pattern, click Weekly and every
Mondays.
6. Under Range of recurrence, type a start date in the Start
box and then select End after or End by.
7. If you select End after, type the number of occurrences for
the task (eg 6 occurrences). If you select End by, type the
date you want the recurring task to end (eg 30/10/09).
8. Click OK.
Create relationships between tasks
To establish relationships between tasks, use task
dependencies. Select the related tasks, link them,
and then change the dependency type, if necessary.
The task whose start or finish depends on another
task is the successor. The task that the successor is
dependent on is the predecessor.
After the tasks are linked, changes to the
predecessor's dates affect the successor's dates.
Microsoft Project creates a finish-to-start task
dependency by default.
To unlink tasks, select the tasks you want to unlink
in the Task Name field, and then click Unlink
Tasks. The tasks are rescheduled based on existing
links to other tasks, or constraints.
Overlap tasks or add lag time between them
To create overlap or lag time:
1.In the Task Name field, click the task you want to
add lead or lag time to (it must have
predecessors), and then click Task Information
2.Click the Predecessors tab.
3.In the Lag column, type the lead time or lag time
you want, as a duration or as a percentage of the
predecessor task duration. Type lead time as a
negative number (for example, –2d for two days
lead time) or as a percentage. Or type lag time as
a positive number or as a percentage.
4.Click OK.
Set a specific start or finish date for a task
You can schedule your tasks most effectively by
entering task durations, creating dependencies between
tasks, and then letting Microsoft Project calculate the
start and finish dates for you. However, you can set a
specific start or finish date for a task if necessary.
To set specific start date
1.In the Task Name field, click the task you want to set
a start or finish date for, and then click Task
Information.
2.Click the Advanced tab.
3.In the Constraint type box, click a constraint type eg
Must Finish On
4.Type or select a date in the Constraint date box, and
then click OK.
Add a deadline to a task
When you set a deadline for a task, Microsoft Project displays
an indicator if the task is scheduled to finish after the
deadline.
Setting a deadline doesn't affect how tasks are scheduled. It's
just a way to have Microsoft Project inform you that a task
will finish past its deadline. You then have the option of
adjusting the schedule to meet that deadline.
1. On the View menu, click Gantt Chart.
2. In the Task Name field, click the task that you want to set a
deadline for.
3. Click Task Information and then click the Advanced tab.
4. Under Constrain task, type or select the deadline date in the
Deadline box, and then click OK.
You can drag the deadline symbol on the Gantt Chart to
change the deadline date.
Split a task into segments
You can split a task if work on the task is interrupted
and then resumes later in the schedule. This is useful,
for example, when you need to temporarily stop work
on a task to work on another task. You can split a task as
many times as necessary.
1. On the View menu, click Gantt Chart.
2. Click Split Task.
3. On the task's Gantt bar, click the date where you want
the split to occur and drag the second part of the bar
to the date that you want work to begin again.
Splitting a task into parts is not the same as entering a
recurring task. You can remove the split by dragging a
portion of a split task so that it touches another portion.
Exercise 1. Create the Gantt Chart
19
Contents
Creating a project, Gantt chart, adding tasks and
duration, linking tasks
Critical Path/ Network diagram. Working with
calendars
Working with resources and assignments,
Purchase
Planning
order
5 days Design
phase 1 20 days
9 days
Start Design Install Finish
0 days phase 2 5 days 0 days
25 days
Client
Survey Testing
15 days 7 days
Design Train
training Staff
5 days 15 days
Identifying the critical path for the
project
The critical path is = start – client survey- design
phase 1 – design phase 2 – install – testing –
finish
Duration = 61 days
Let us now use Microsoft Project to generate the
25
Contents
Creating a project, Gantt chart, adding tasks and
duration, linking tasks
Critical Path/ Network diagram. Working with
calendars
Working with resources and assignments,
calendars
Working with resources and assignments,