0% found this document useful (0 votes)
243 views16 pages

% Progres

This document outlines the schedule for the Al Wasl Box Park project from October 2013 to July 2014. It provides details on over 100 individual activities related to design, subcontractor work, site preparation, and construction. The schedule shows planned start and finish dates for each activity as well as actual progress. Overall, the project was 0% complete as of the schedule date and planned to be finished by July 10, 2014.

Uploaded by

ankitch123
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
243 views16 pages

% Progres

This document outlines the schedule for the Al Wasl Box Park project from October 2013 to July 2014. It provides details on over 100 individual activities related to design, subcontractor work, site preparation, and construction. The schedule shows planned start and finish dates for each activity as well as actual progress. Overall, the project was 0% complete as of the schedule date and planned to be finished by July 10, 2014.

Uploaded by

ankitch123
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 16

Al Wasl Box Park

Activity ID

Activity Name

Al Wasl Box Park


General

BL1 Start

BL1 Finish

Actual Start

Actual Finish

264

24-Oct-13

10-Jul-14

24-Oct-13

0%

93

24-Oct-13

25-Jan-14

24-Oct-13

0%

1000

Award project

24-Oct-13

1010

Conceptual design

15

24-Oct-13

07-Nov-13

24-Oct-13

1012

Soil investigation

18

08-Nov-13

25-Nov-13

08-Nov-13

1018

Appoint design consultants

10

08-Nov-13

17-Nov-13

08-Nov-13

1028

Receive Infrastructure Design Drawings

25-Jan-14

91

24-Oct-13

22-Jan-14

24-Oct-13

22-Jan-14

Authorities NOC

24-Oct-13

Activity %
Complete

Schedule %
Complete

100%

100%

07-Nov-13

100%

100%

25-Nov-13

100%

100%

17-Nov-13

100%

100%

0%

100%
0%

2000

Trial trenches NOC

15

24-Oct-13

07-Nov-13

24-Oct-13

07-Nov-13

100%

100%

2010

Survay & trial trenches

15

07-Nov-13

21-Nov-13

07-Nov-13

21-Nov-13

100%

100%

2012

Existing services drawings

15

09-Nov-13

23-Nov-13

09-Nov-13

23-Nov-13

100%

100%

2020

Obtain design / construction NOC

30

24-Nov-13

23-Dec-13

24-Nov-13

23-Dec-13

100%

100%

2030

Obtain building permit

30

24-Dec-13

22-Jan-14

24-Dec-13

22-Jan-14

100%

100%

55

07-Jan-14

18-Feb-14

08-Jan-14

18-Jan-14

08-Jan-14

Subcontrators and Suppliers Schedule

0%

24

07-Jan-14

2040

Subcontractor Submission

07-Jan-14

08-Jan-14

100%

100%

2050

Subcontactor Approval

14-Jan-14

21-Jan-14

100%

100%

2060

Placing Order

18-Jan-14

0%

100%

21

09-Jan-14

Steel Structure Works

Precast Building Element Works

18-Jan-14

0%

08-Jan-14

0%

c2660

Subcontractor Submission

09-Jan-14

08-Jan-14

100%

100%

c2670

Subcontactor Approval

14-Jan-14

21-Jan-14

100%

100%

c2680

Placing Order

18-Jan-14

0%

100%

21

09-Jan-14

Precast Boundary Wall Works

18-Jan-14

08-Jan-14

0%

d1000

Subcontractor Submission

09-Jan-14

08-Jan-14

100%

100%

d1010

Subcontactor Approval

14-Jan-14

21-Jan-14

100%

100%

d1020

Placing Order

18-Jan-14

0%

100%

30-Jan-14

MEP Works

06-Feb-14

0%

c2690

Subcontractor Submission

30-Jan-14

0%

0%

c2700

Subcontactor Approval

04-Feb-14

0%

0%

c2710

Placing Order

06-Feb-14

0%

0%

10

23-Jan-14

GRC Cladding Works

02-Feb-14

0%

e1020

Placing Order

02-Feb-14

0%

0%

e1000

Subcontractor Submission

23-Jan-14

0%

100%

e1010

Subcontactor Approval

0%

100%

Hardscape Works

28-Jan-14

24

16-Jan-14

10-Feb-14

0%

f1000

Subcontractor Submission

01-Feb-14

0%

0%

f1010

Subcontactor Approval

08-Feb-14

0%

0%

f1020

Placing Order

10-Feb-14

0%

0%

A7300

Received Design from Consultant

16-Jan-14

0%

100%

17

16-Jan-14

Aluminium and Glazing Works


g1000

Subcontractor Submission

16-Jan-14

g1010

Subcontactor Approval

22-Jan-14

g1020

Placing Order

Container Works

25-Jan-14

24

23-Jan-14

25-Jan-14

23-Jan-14
23-Jan-14

09-Feb-14

0%
100%

100%

0%

100%

0%

100%

30-Jan-14

0%

z1010

Subcontactor Approval

06-Feb-14

0%

0%

z1020

Placing Order

09-Feb-14

0%

0%

z1000

Subcontractor Submission

23-Jan-14

100%

100%

30-Jan-14

23-Jan-14

r1020

Placing Order

30-Jan-14

0%

0%

r1000

Subcontractor Submission

23-Jan-14

0%

100%

r1010

Subcontactor Approval

28-Jan-14

0%

100%

Aircell Insulation

14

23-Jan-14

a7120

Placing Order

30-Jan-14

a7100

Subcontractor Submission

23-Jan-14

a7110

Subcontactor Approval

27-Jan-14

10

01-Feb-14

Roof Waterproofing Works

Stone Cladding Works

30-Jan-14

30-Jan-14

0%

30-Jan-14

30-Jan-14

0%
0%

0%

100%

100%

0%

100%

10-Feb-14

0%

k1000

Subcontractor Submission

01-Feb-14

0%

0%

k1010

Subcontactor Approval

08-Feb-14

0%

0%

k1020

Placing Order

10-Feb-14

0%

0%

16-Jan-14

EIFS System Works

25-Jan-14

0%

m1000

Subcontractor Submission

16-Jan-14

0%

100%

m1010

Subcontactor Approval

22-Jan-14

0%

100%

m1020

Placing Order

25-Jan-14

0%

100%

Canopy and Louvers Works

11

22-Jan-14

01-Feb-14

a7150

1/16

OD

Placing Order

Date
24-Oct-13
10-Jul-14

01-Feb-14

16-Jan-14

0%
0%

Revision
Project Start Date
Project Finish Date

Checked

0%
Approved

Al Wasl Box Park


Activity ID

Activity Name

OD

BL1 Start

a7130

Subcontractor Submission

22-Jan-14

a7140

Subcontactor Approval

29-Jan-14

31

19-Jan-14

External Lighting Works

BL1 Finish

Actual Start

Actual Finish

16-Jan-14

Activity %
Complete

Schedule %
Complete

100%

100%

0%

100%

18-Feb-14

0%

a7160

Subcontractor Submission

09-Feb-14

0%

0%

a7170

Subcontactor Approval

16-Feb-14

0%

0%

a7180

Placing Order

18-Feb-14

0%

0%

a7280

Received Design from Consultant

19-Jan-14

0%

100%

31

19-Jan-14

Sanitary Ware Works

18-Feb-14

0%

a7190

Subcontractor Submission

09-Feb-14

0%

0%

a7200

Subcontactor Approval

16-Feb-14

0%

0%

a7210

Placing Order

18-Feb-14

0%

0%

a7290

Received Design from Consultant

19-Jan-14

0%

100%

Plot M4

215

16-Dec-13

03-Jul-14

06-Dec-13

Design

16-Dec-13

16-Dec-13

16-Dec-13

16-Dec-13

A7080

FC-01 Received Design Drawings from Consultant

A7090

FC-02 Received Design Drawings from Consultant

Building Works
FC-01
Facility Start Date
c1210

Facility start date

Shop Drawings Schedule


Construction Shop Drawings

16-Dec-13

0%

16-Dec-13

100%

100%

16-Dec-13

100%

100%

16-Dec-13

206

23-Dec-13

03-Jul-14

06-Dec-13

0%

189

23-Dec-13

25-Jun-14

24-Dec-13

0%

24-Dec-13

24-Dec-13

24-Dec-13
24-Dec-13

24-Dec-13

0%

24-Dec-13

45

23-Dec-13

09-Mar-14

100%

100%
0%

23-Dec-13

30-Dec-13

0%

2400

Shop Drawings Submission

23-Dec-13

0%

100%

2410

Shop Drawings Approval

30-Dec-13

0%

100%

23-Jan-14

2080

Shop Drawings Approval

30-Jan-14

0%

0%

2070

Shop Drawings Submission

23-Jan-14

0%

100%

23-Jan-14

Steel Structure Works

Precast Building Element Works


2090

Shop Drawings Submission

23-Jan-14

2390

Shop Drawings Approval

28-Jan-14

23-Jan-14

Precast Boundary Wall Works

30-Jan-14

0%

28-Jan-14

0%
0%

100%

0%

100%

28-Jan-14

0%

2110

Shop Drawings Submission

23-Jan-14

0%

100%

2380

Shop Drawings Approval

28-Jan-14

0%

100%

11-Feb-14

2130

Shop Drawings Submission

11-Feb-14

0%

0%

2140

Shop Drawings Approval

18-Feb-14

0%

0%

06-Feb-14

MEP Works

GRC Cladding Works


2150

Shop Drawings Submission

06-Feb-14

2160

Shop Drawings Approval

13-Feb-14

16-Feb-14

Hardscape Works

18-Feb-14

0%

13-Feb-14

0%
0%

0%

0%

0%

23-Feb-14

0%

2170

Shop Drawings Submission

16-Feb-14

0%

0%

2180

Shop Drawings Approval

23-Feb-14

0%

0%

29-Jan-14

2200

Shop Drawings Approval

03-Feb-14

0%

0%

2190

Shop Drawings Submission

29-Jan-14

0%

100%

13-Feb-14

Aluminium and Glazing Works

Container Works
2210

Shop Drawings Submission

13-Feb-14

2220

Shop Drawings Approval

18-Feb-14

05-Mar-14

Aircell Insulation

03-Feb-14

0%

18-Feb-14

0%
0%

0%

0%

0%

09-Mar-14

0%

2230

Shop Drawings Submission

05-Mar-14

0%

0%

2240

Shop Drawings Approval

09-Mar-14

0%

0%

15

29-Jan-14

Roof Waterproofing Works

23-Feb-14

0%

2350

Shop Drawings Submission

30-Jan-14

0%

0%

2360

Shop Drawings Approval

02-Feb-14

0%

0%

16-Feb-14

Stone Cladding Works


3700

Shop Drawings Submission

16-Feb-14

3710

Shop Drawings Approval

23-Feb-14

29-Jan-14

EIFS System Works

23-Feb-14

0%
0%

0%

0%

0%

03-Feb-14

0%

3730

Shop Drawings Approval

03-Feb-14

0%

0%

3720

Shop Drawings Submission

29-Jan-14

0%

100%

16-Feb-14

Stone Cladding Works

23-Feb-14

0%

2250

Shop Drawings Submission

16-Feb-14

0%

0%

2260

Shop Drawings Approval

23-Feb-14

0%

0%

29-Jan-14

03-Feb-14

EIFS System Works


2280

2/16

0%

Shop Drawings Approval

Date
24-Oct-13
10-Jul-14

03-Feb-14

0%
0%

Revision
Project Start Date
Project Finish Date

Checked

0%

Approved

Al Wasl Box Park


Activity ID

Activity Name
2270

Shop Drawings Submission

Canopy and Louvers Works

BL1 Start

29-Jan-14

05-Feb-14

BL1 Finish

Actual Start

Actual Finish

Activity %
Complete

Schedule %
Complete

0%

100%

10-Feb-14

0%

2290

Shop Drawings Submission

05-Feb-14

0%

0%

2300

Shop Drawings Approval

10-Feb-14

0%

0%

23-Feb-14

External Lighting Works

03-Mar-14

0%

2310

Shop Drawings Submission

23-Feb-14

0%

0%

2320

Shop Drawings Approval

03-Mar-14

0%

0%

23-Feb-14

23-Feb-14

Sanitary Ware Works


2330

Shop Drawings Submission

2340

Shop Drawings Approval

Site Work/Preparations
c1080

Site Setting out

Site Work/ Under Foundation Level (A-H)

03-Mar-14

0%

03-Mar-14

59

24-Dec-13

10-Feb-14

23-Jan-14

24-Dec-13

26-Dec-13

25-Jan-14

26-Jan-14

28-Dec-13

01-Jan-14

27-Jan-14

30-Jan-14

0%

0%

0%

0%
0%

100%

100%
0%

c1220

Excavation up to level 1.45m & Compaction

28-Dec-13

29-Dec-13

27-Jan-14

28-Jan-14

100%

100%

c1230

Anti-termitte Works

28-Dec-13

28-Dec-13

29-Jan-14

29-Jan-14

100%

100%

c1240

(200mm) Backfilling by roadbase , compaction & polythene sheet

30-Dec-13

01-Jan-14

28-Jan-14

30-Jan-14

100%

100%

05-Feb-14

10-Feb-14

23-Jan-14
25-Jan-14

Site Work First Stage (A-E)


c1360

(200)mm Backfilling by excavated materials, compaction.

06-Feb-14

09-Feb-14

c1370

Anti-termite Works

06-Feb-14

08-Feb-14

c1480

(200)mm Backfilling by roadbase, compaction & polythene sheet

08-Feb-14

10-Feb-14

c1650

Waterproofing for for isolated footings and pedestal (A-E)

05-Feb-14

06-Feb-14

27-Jan-14

30-Jan-14

Site Work Second Stage (F-H)

0%

23-Jan-14

50%

0%

0%

0%

0%

0%

50%

0%
0%

c1700

Anti-termite Works

29-Jan-14

30-Jan-14

0%

75%

c1500

Backfilling by excavated materials & compaction (F-H)

27-Jan-14

29-Jan-14

0%

100%

c1660

Waterproofing for isolated footings and pedestal (F-H)

27-Jan-14

27-Jan-14

0%

100%

90

01-Jan-14

26-Mar-14

28-Dec-13

0%

29

01-Jan-14

14-Jan-14

28-Dec-13

0%

01-Jan-14

09-Jan-14

28-Dec-13

21-Jan-14

Subrstructure Works
Footing Works
Footings First Stage

0%

c1090

PCC for Isolated footing (A-E)

01-Jan-14

02-Jan-14

28-Dec-13

28-Dec-13

100%

100%

c1250

Steel work for Isolated footing (A-E)

04-Jan-14

06-Jan-14

09-Jan-14

12-Jan-14

100%

100%

c1260

Formwork for Isolated footing (A-E)

06-Jan-14

08-Jan-14

10-Jan-14

13-Jan-14

100%

100%

c1270

Casting Concrete for Isolated footing (A-E)

09-Jan-14

09-Jan-14

21-Jan-14

21-Jan-14

100%

100%

c1670

Waterproofing for PCC (A-E)

05-Jan-14

100%

100%

Footing Seond Stage

02-Jan-14

02-Jan-14

04-Jan-14

24

06-Jan-14

14-Jan-14

28-Dec-13

0%

c1280

PCC for Isolated Footings (F-H)

06-Jan-14

07-Jan-14

28-Dec-13

28-Dec-13

100%

100%

c1290

Steel work for Isolated Footings (F-H)

08-Jan-14

11-Jan-14

09-Jan-14

12-Jan-14

100%

100%

c1300

Formwork for Isolated Footings (F-H)

12-Jan-14

13-Jan-14

10-Jan-14

13-Jan-14

100%

100%

c1310

Casting Concrete for Isolated Footings (F-H)

13-Jan-14

14-Jan-14

21-Jan-14

21-Jan-14

100%

100%

c1350

Approval of Canopy Super Structure Drawings

06-Jan-14

0%

100%

c1690

Waterproofing for PCC

07-Jan-14

08-Jan-14

100%

100%

19

11-Jan-14

05-Feb-14

0%

19

11-Jan-14

05-Feb-14

0%

Pedestal Works
Pedestal First Stage

05-Jan-14

07-Jan-14

c1730

(75)mm Mass concrete

04-Feb-14

05-Feb-14

0%

0%

c1320

Steel work for Pedestal (A-E)

11-Jan-14

14-Jan-14

0%

100%

c1330

Formwork for Pedestal (A-E)

14-Jan-14

16-Jan-14

0%

100%

c1340

Casting Concrete for Pedestal (A-E)

14-Jan-14

15-Jan-14

0%

100%

14-Jan-14

21-Jan-14

c1450

Steel work for Pedestal (F-H)

14-Jan-14

18-Jan-14

0%

100%

c1460

Formwork for Pedestal (F-H)

19-Jan-14

21-Jan-14

0%

100%

c1470

Casting Concrete for Pedestal (F-H)

19-Jan-14

19-Jan-14

0%

100%

39

10-Feb-14

26-Mar-14

Pedestal Second Stage

Ground Slab

0%

0%

c1380

PCC for Ground Beams (A-E) and Ground Slab

10-Feb-14

10-Feb-14

0%

0%

c1390

Steel work for Ground Beams (A-E), Embedded Plates and (Groun...

18-Feb-14

26-Feb-14

0%

0%

c1400

Formwork for Ground Beams (A-E) and (Ground Slab-1st layer)

26-Feb-14

05-Mar-14

0%

0%

c1410

Casting Concrete for Ground Beams (A-E) and (Ground Slab-1st l...

06-Mar-14

06-Mar-14

0%

0%

c1420

BRC Mesh for the Ground Slab- 2nd layer and embeded plates

10-Mar-14

18-Mar-14

0%

0%

c1430

Concrete casting for Ground Slab-2nd layer

26-Mar-14

26-Mar-14

0%

0%

c1440

(50)mm Rigid Floor Insulation

06-Mar-14

09-Mar-14

0%

0%

c1680

Waterproofing for PCC for Ground Beams (A-E) and ground slab

11-Feb-14

11-Feb-14

0%

0%

c1710

Formwork for Ground Slab-2nd layer

18-Mar-14

26-Mar-14

0%

0%

134

21-Jan-14

15-Jun-14

0%

92

30-Jan-14

10-May-14

0%

Superstructure Works
Steel Structure Works

3/16

OD

c1120

Steel structure - Steel Columns works

30-Jan-14

04-Feb-14

0%

0%

c1490

Steel structure -Steel Tie Beams Works

27-Mar-14

29-Mar-14

0%

0%

c1720

Steel Sheet @ Roof

07-May-14

10-May-14

0%

0%

Date
24-Oct-13
10-Jul-14

Revision
Project Start Date
Project Finish Date

Checked

Approved

Al Wasl Box Park


Activity ID

Activity Name

BL1 Start

BL1 Finish

Actual Start

Actual Finish

Activity %
Complete

Schedule %
Complete

14

21-Jan-14

04-Feb-14

c1740

Canopy Shade Structure balance work

30-Jan-14

04-Feb-14

0%

0%

c1620

Canopy Shade Structure Colunms

21-Jan-14

26-Jan-14

0%

100%

26

10-Mar-14

05-Apr-14

10-Mar-14

15-Mar-14

0%

0%

0%

0%

Canopy Shade Works

Container Works
c1100

Placing of the containers for the ground level

c1110

Placing of the containers for the first and roof level

Concrete Works
Concrete Works @ Container Roof Level

0%

0%

29-Mar-14

05-Apr-14

14

06-Apr-14

20-Apr-14

0%

14

06-Apr-14

20-Apr-14

0%

c1510

Steel work for the roof slab

12-Apr-14

17-Apr-14

0%

0%

c1520

Formwork for the roof slab

06-Apr-14

10-Apr-14

0%

0%

c1530

Casting concrete for the roof slab

19-Apr-14

20-Apr-14

0%

0%

20-Apr-14

27-Apr-14

20-Apr-14

27-Apr-14

53

15-Mar-14

07-May-14

Thermal & Insulation Works


c1130

Thermal insulations

Roofing Works

0%
0%

0%
0%

10

27-Apr-14

07-May-14

c1160

Light weight screed

27-Apr-14

29-Apr-14

0%

0%

c1540

Gravel

05-May-14

07-May-14

0%

0%

c1550

Waterproof memebrane

03-May-14

05-May-14

0%

0%

c1560

Glass Foam Insulation

01-May-14

03-May-14

0%

0%

c1570

Bitumen waterproofing

30-Apr-14

30-Apr-14

0%

0%

15-Mar-14

24-Mar-14

Roofing Works for Roof Container

Roofing Works for Ground Container

0%

0%

c1580

WBP plywood backing

15-Mar-14

17-Mar-14

0%

0%

c1590

Roof Finishes

22-Mar-14

24-Mar-14

0%

0%

c1600

Waterproof membrane

20-Mar-14

22-Mar-14

0%

0%

c1610

Insulation

18-Mar-14

19-Mar-14

0%

0%

49

27-Apr-14

15-Jun-14

Facade Works

0%

c1140

Fixing C channel on the containers level 1 and 2

27-Apr-14

01-May-14

0%

0%

c1150

Aluminium Louver Panel & Container Panel Facade Finish

15

01-May-14

17-May-14

0%

0%

c1180

Glazing works

17-May-14

24-May-14

0%

0%

c1630

Bitumen, Aluminium cladding, Pergola and Canopy

15

28-May-14

12-Jun-14

0%

0%

c1640

Steel Cat Ladder

12-Jun-14

15-Jun-14

0%

0%

c1750

Alminium & Steel Doors

24-May-14

28-May-14

0%

0%

27-Apr-14

01-May-14

0%

27-Apr-14

01-May-14

0%

27-Apr-14

01-May-14

117

18-Feb-14

15-Jun-14

117

18-Feb-14

15-Jun-14

11

15-Jun-14

25-Jun-14

Finishes
Internal Finishes
c1170

Screed Floor finishes

MEP Works
c1190

MEP Works & External Lighting

Facility Finish Date


c1200

Facility finish date

c2720

Facility Testing and Commissioning

10

c2740

Handingover to Tenant

FC-02
Facility Start Date
c1850

Facility start date

Shop Drawings Schedule


Construction Shop Drawings

15-Jun-14

0%

0%
0%

0%

0%
0%

24-Jun-14

0%

0%

24-Jun-14

0%

0%

25-Jun-14

0%

0%

206

23-Dec-13

03-Jul-14

06-Dec-13

82

23-Dec-13

09-Mar-14

24-Dec-13

24-Dec-13

45

23-Dec-13

09-Mar-14

0%

23-Dec-13

30-Dec-13

0%

24-Dec-13

0%
0%
100%

100%

2720

Shop Drawings Submission

23-Dec-13

0%

100%

2730

Shop Drawings Approval

30-Dec-13

0%

100%

23-Jan-14

Steel Structure Works

30-Jan-14

0%

2430

Shop Drawings Approval

30-Jan-14

0%

0%

2420

Shop Drawings Submission

23-Jan-14

0%

100%

23-Jan-14

2440

Shop Drawings Submission

23-Jan-14

0%

100%

2710

Shop Drawings Approval

28-Jan-14

0%

100%

23-Jan-14

Precast Building Element Works

Precast Boundary Wall Works

28-Jan-14

0%

28-Jan-14

0%

2450

Shop Drawings Submission

23-Jan-14

0%

100%

2700

Shop Drawings Approval

28-Jan-14

0%

100%

11-Feb-14

MEP Works

18-Feb-14

0%

2460

Shop Drawings Submission

11-Feb-14

0%

0%

2470

Shop Drawings Approval

18-Feb-14

0%

0%

06-Feb-14

2480

Shop Drawings Submission

06-Feb-14

0%

0%

2490

Shop Drawings Approval

13-Feb-14

0%

0%

16-Feb-14

16-Feb-14

GRC Cladding Works

Hardscape Works
2500

4/16

OD

Shop Drawings Submission

Date
24-Oct-13
10-Jul-14

13-Feb-14

0%

23-Feb-14

0%
0%

Revision
Project Start Date
Project Finish Date

Checked

0%

Approved

Al Wasl Box Park


Activity ID

Activity Name
2510

Shop Drawings Approval

Aluminium and Glazing Works

BL1 Start

23-Feb-14

29-Jan-14

BL1 Finish

Actual Start

Actual Finish

Activity %
Complete

Schedule %
Complete

0%

0%

03-Feb-14

0%

2530

Shop Drawings Approval

03-Feb-14

0%

0%

2520

Shop Drawings Submission

29-Jan-14

0%

100%

13-Feb-14

Container Works

18-Feb-14

0%

2540

Shop Drawings Submission

13-Feb-14

0%

0%

2550

Shop Drawings Approval

18-Feb-14

0%

0%

05-Mar-14

Aircell Insulation
2560

Shop Drawings Submission

05-Mar-14

2570

Shop Drawings Approval

09-Mar-14

30-Jan-14

Roof Waterproofing Works

09-Mar-14

0%
0%

0%

0%

0%

02-Feb-14

0%

2680

Shop Drawings Submission

30-Jan-14

0%

0%

2690

Shop Drawings Approval

02-Feb-14

0%

0%

16-Feb-14

Stone Cladding Works

23-Feb-14

0%

2580

Shop Drawings Submission

16-Feb-14

0%

0%

2590

Shop Drawings Approval

23-Feb-14

0%

0%

29-Jan-14

EIFS System Works

03-Feb-14

0%

2610

Shop Drawings Approval

03-Feb-14

0%

0%

2600

Shop Drawings Submission

29-Jan-14

0%

100%

05-Feb-14

2620

Shop Drawings Submission

05-Feb-14

0%

0%

2630

Shop Drawings Approval

10-Feb-14

0%

0%

23-Feb-14

Canopy and Louvers Works

External Lighting Works

10-Feb-14

0%

03-Mar-14

0%

2640

Shop Drawings Submission

23-Feb-14

0%

0%

2650

Shop Drawings Approval

03-Mar-14

0%

0%

23-Feb-14

Sanitary Ware Works

03-Mar-14

0%

2660

Shop Drawings Submission

23-Feb-14

0%

0%

2670

Shop Drawings Approval

03-Mar-14

0%

0%

64

24-Dec-13

11-Feb-14

24-Dec-13

24-Dec-13

26-Dec-13

24-Dec-13

26-Dec-13

100%

100%

28-Dec-13

02-Jan-14

28-Dec-13

06-Jan-14

Site Work/Preparations
c1760

Site Setting out

Site Work/ Under Foundation Level

0%

0%

c1860

Excavation up to level 1.45m & Compaction

28-Dec-13

29-Dec-13

28-Dec-13

29-Dec-13

100%

100%

c1870

Anti-termitte Works

29-Dec-13

29-Dec-13

06-Jan-14

06-Jan-14

100%

100%

c1880

(200mm) Backfilling by roadbase , compaction & polythene sheet

30-Dec-13

02-Jan-14

30-Dec-13

04-Jan-14

100%

100%

04-Feb-14

11-Feb-14

Site Work First Stage (Precast & Conatiner Areas)

0%

c2000

(200)mm Backfilling by excavated materials, compaction.

05-Feb-14

08-Feb-14

0%

0%

c2010

Anti-termite Works

06-Feb-14

06-Feb-14

0%

0%

c2120

(200)mm Backfilling by roadbase, compaction & polythene sheet

08-Feb-14

11-Feb-14

0%

0%

c2210

Waterproofing for for isolated, strip footings and pedestals

04-Feb-14

05-Feb-14

0%

0%

03-Feb-14

08-Feb-14

Site Work Second Stage (Canopy Area)

0%

c2130

Backfilling by excavated materials & compaction

04-Feb-14

06-Feb-14

0%

0%

c2220

Waterproofing for isolated footings and pedestal

03-Feb-14

04-Feb-14

0%

0%

c2260

Anti-termite Works

0%

0%

Subrstructure Works
Footing Works
Footings First Stage (Precast & Conatiner Areas)

08-Feb-14

08-Feb-14

103

02-Jan-14

01-Apr-14

06-Dec-13

0%

45

02-Jan-14

23-Jan-14

06-Dec-13

0%

45

02-Jan-14

19-Jan-14

06-Jan-14

0%

c1770

PCC for Isolated footing

02-Jan-14

04-Jan-14

06-Jan-14

c1890

Steel work for Isolated & Strip footings

10

06-Jan-14

15-Jan-14

22-Jan-14

c1900

Formwork for Isolated & Strip footings

10

07-Jan-14

16-Jan-14

20-Jan-14

c1910

Casting Concrete for Isolated & Strip footings

19-Jan-14

19-Jan-14

c2230

Waterproofing for PCC

05-Jan-14

05-Jan-14

13-Jan-14

06-Jan-14

100%

100%

70%

100%

100%

100%

0%

100%

15-Jan-14

100%

100%

06-Dec-13

100%

100%

0%

100%

100%

100%

0%

100%

0%

100%

100%

100%

27-Jan-14

27

13-Jan-14

23-Jan-14

06-Dec-13

c1920

PCC for Isolated Footings

14-Jan-14

15-Jan-14

06-Dec-13

c1930

Steel work for Isolated Footings

16-Jan-14

19-Jan-14

c1940

Formwork for Isolated Footings

20-Jan-14

22-Jan-14

c1950

Casting Concrete for Isolated Footings

22-Jan-14

23-Jan-14

c1990

Approval of Canopy Super Structure Drawings

13-Jan-14

c2250

Waterproofing for PCC

15-Jan-14

16-Jan-14

16

20-Jan-14

04-Feb-14

0%

16

20-Jan-14

04-Feb-14

0%

Footing Seond Stage (Canopy Area)

Pedestal Works
Pedestal First Stage (Precast & Conatiner Areas)

20-Jan-14

14-Jan-14

0%

27-Jan-14

15-Jan-14

c2280

(75)mm Mass concrete for isolated footing

03-Feb-14

04-Feb-14

0%

0%

c1980

Casting Concrete for Pedestal

29-Jan-14

30-Jan-14

0%

75%

c1970

Formwork for Pedestal

10

21-Jan-14

30-Jan-14

0%

87.5%

c1960

Steel work for Pedestal

10

20-Jan-14

29-Jan-14

0%

100%

23-Jan-14

30-Jan-14

Pedestal Second Stage (Canopy Area)

5/16

OD

Date
24-Oct-13
10-Jul-14

0%

Revision
Project Start Date
Project Finish Date

Checked

Approved

Al Wasl Box Park


Activity ID

Activity Name

BL1 Start

BL1 Finish

Actual Start

Actual Finish

Activity %
Complete

Schedule %
Complete

c2100

Formwork for Pedestal

27-Jan-14

30-Jan-14

0%

68.75%

c2090

Steel work for Pedestal

23-Jan-14

27-Jan-14

0%

100%

c2110

Casting Concrete for Pedestal

27-Jan-14

28-Jan-14

0%

100%

48

11-Feb-14

01-Apr-14

Ground Slab (Precast & Conatiner Areas)

0%

c2020

PCC for Ground Beams and Ground Slab

11-Feb-14

13-Feb-14

0%

0%

c2030

Steel work for Ground Beams, Embedded Plate and (Ground Slab...

15

18-Feb-14

05-Mar-14

0%

0%

c2040

Formwork for Ground Beams and (Ground Slab-1st layer)

15

20-Feb-14

06-Mar-14

0%

0%

c2050

Casting Concrete for Ground Beams and (Ground Slab-1st layer)

06-Mar-14

08-Mar-14

0%

0%

c2060

BRC Mesh for the Ground Slab- 2nd layer and embeded plates

15

12-Mar-14

26-Mar-14

0%

0%

c2070

Concrete casting for Ground Slab-2nd layer

31-Mar-14

01-Apr-14

0%

0%

c2080

(50)mm Rigid Floor Insulation

08-Mar-14

11-Mar-14

0%

0%

c2240

Waterproofing for PCC for Ground Beams and ground slab

15-Feb-14

17-Feb-14

0%

0%

c2270

Formwork for Ground Slab-2nd layer

15

16-Mar-14

31-Mar-14

0%

0%

142

01-Feb-14

23-Jun-14

Superstructure Works

0%

91

01-Feb-14

03-May-14

c2420

Steel structure - Steel Columns works

01-Feb-14

03-Feb-14

0%

0%

c2430

Steel structure -Steel Tie Beams Works

01-Apr-14

02-Apr-14

0%

0%

c2440

Steel Sheet @ Roof

30-Apr-14

03-May-14

0%

0%

10

01-Apr-14

10-Apr-14

Steel Structure Works

Precast Works

0%

0%

c2300

Precast Colunm & Panels Fixing - Stage 1

01-Apr-14

08-Apr-14

0%

0%

c2450

Hollow Core Slab @ level 5.186 m

08-Apr-14

10-Apr-14

0%

0%

12

01-Feb-14

12-Feb-14

01-Feb-14

03-Feb-14

0%

0%

0%

0%

Canopy Shade Works


c2180

Canopy Shade Structure Colunms

c2290

Canopy Shade Structure balance work

Container Works

09-Feb-14

12-Feb-14

49

12-Mar-14

30-Apr-14

0%

0%

c2390

Placing of the containers for the ground level

12-Mar-14

16-Mar-14

0%

0%

c2400

Placing of the containers for the first and roof level

03-Apr-14

07-Apr-14

0%

0%

c2410

Placing of the container for the roof level for precast area

28-Apr-14

30-Apr-14

0%

0%

12

08-Apr-14

20-Apr-14

0%

08-Apr-14

14-Apr-14

0%

Concrete Works
Concrete Works @ Container Roof Level
c2460

Steel work for the roof slab

10-Apr-14

12-Apr-14

0%

0%

c2470

Formwork for the roof slab

08-Apr-14

09-Apr-14

0%

0%

c2480

Casting concrete for the roof slab

13-Apr-14

14-Apr-14

0%

0%

Concrete Works @ Precast Roof Level 5.186

14-Apr-14

20-Apr-14

0%

c2360

Steel work for the roof slab

16-Apr-14

17-Apr-14

0%

0%

c2370

Formwork for the roof slab

14-Apr-14

15-Apr-14

0%

0%

c2380

Casting concrete for the roof slab

19-Apr-14

20-Apr-14

0%

0%

14-Apr-14

19-Apr-14

14-Apr-14

19-Apr-14

21

07-Apr-14

28-Apr-14

0%

20-Apr-14

28-Apr-14

0%

Thermal & Insulation Works


c1780

Thermal insulations

Roofing Works
Roofing Works (Precast Roof Area Level 5.186)

0%
0%

0%

c2490

Light weight screed with BRC Mesh

20-Apr-14

22-Apr-14

0%

0%

c2500

Gravel

27-Apr-14

28-Apr-14

0%

0%

c2510

Waterproof memebrane

26-Apr-14

27-Apr-14

0%

0%

c2520

Glass Foam Insulation

24-Apr-14

26-Apr-14

0%

0%

c2530

Bitumen waterproofing

23-Apr-14

23-Apr-14

0%

0%

14-Apr-14

22-Apr-14

c2310

Light weight screed

14-Apr-14

16-Apr-14

0%

0%

c2320

Gravel

21-Apr-14

22-Apr-14

0%

0%

c2330

Waterproof memebrane

20-Apr-14

21-Apr-14

0%

0%

c2340

Glass Foam Insulation

17-Apr-14

20-Apr-14

0%

0%

c2350

Bitumen waterproofing

17-Apr-14

17-Apr-14

0%

0%

07-Apr-14

14-Apr-14

Roofing Works (Roof Conatiner Areas)

Roofing Works (Upper Roof Container)

0%

0%

c2140

WBP plywood backing

07-Apr-14

08-Apr-14

0%

0%

c2150

Roof Finishes

12-Apr-14

14-Apr-14

0%

0%

c2160

Waterproof membrane

10-Apr-14

12-Apr-14

0%

0%

c2170

Insulation

09-Apr-14

10-Apr-14

0%

0%

51

03-May-14

23-Jun-14

Facade Works

0%

c1790

Fixing C channel on the containers level 1 and 2

03-May-14

06-May-14

0%

0%

c1800

Aluminium Louver Panel , Signages, Dry Walls& Container Paint F...

23

06-May-14

28-May-14

0%

0%

c1820

Glazing works

10

07-May-14

17-May-14

0%

0%

c2190

Bitumen Aluminium cladding, Pergola, Laminated Glass, Canopy, ...

22

28-May-14

19-Jun-14

0%

0%

c2200

Steel Cat Ladder & LED Screen

19-Jun-14

23-Jun-14

0%

0%

c2540

Aluminium, Steel Doors and Wooden Doors

17-May-14

24-May-14

0%

0%

30-Apr-14

07-May-14

Finishes

6/16

OD

Date
24-Oct-13
10-Jul-14

0%

Revision
Project Start Date
Project Finish Date

Checked

Approved

Al Wasl Box Park


Activity ID

Activity Name

Internal Finishes
c1810

Screed Floor finishes for the ground level

MEP Works
c1830

MEP Works & External Lighting

Facility Finish Date

OD

BL1 Start

BL1 Finish

30-Apr-14

07-May-14

30-Apr-14

07-May-14

125

18-Feb-14

23-Jun-14

125

18-Feb-14

23-Jun-14

11

23-Jun-14

03-Jul-14

c1840

Facility finish date

c2760

Testing and Commissioning Works

10

c2770

Handingover to Tenant

23-Jun-14

Actual Start

Actual Finish

Activity %
Complete

Schedule %
Complete
0%

0%

0%
0%

0%

0%
0%

02-Jul-14

0%

0%

02-Jul-14

0%

0%

03-Jul-14

0%

0%

Plot M1

201

16-Dec-13

25-Jun-14

16-Dec-13

0%

Design

46

16-Dec-13

26-Jan-14

16-Dec-13

0%

c2550

FC-01 Received Design Drawings from Consultant

29-Dec-13

29-Dec-13

100%

100%

c2560

FC-02 Received Design Drawings from Consultant

16-Dec-13

16-Dec-13

100%

100%

c2570

FC-03 Received Design Drawings from Consultant

15-Jan-14

27-Jan-14

100%

100%

c2580

FC-04 Received Design Drawings from Consultant

21-Jan-14

27-Jan-14

100%

100%

c2590

FC-05 Received Design Drawings from Consultant

21-Jan-14

0%

100%

c2600

FC-06 Received Design Drawings from Consultant

0%

100%

Building Works
FC-02
Facility Start Date
A 0520

Facility start date

Shop Drawings Schedule


Construction Shop Drawings

26-Jan-14
23-Dec-13

12-Jun-14

24-Dec-13

0%

192

23-Dec-13

12-Jun-14

24-Dec-13

0%

82

23-Dec-13

09-Mar-14

24-Dec-13

0%

24-Dec-13

45

23-Dec-13

09-Mar-14

24-Dec-13

100%

100%
0%

23-Dec-13

30-Dec-13

0%

3040

Shop Drawings Submission

23-Dec-13

0%

100%

3050

Shop Drawings Approval

30-Dec-13

0%

100%

23-Jan-14

2750

Shop Drawings Approval

30-Jan-14

0%

0%

2740

Shop Drawings Submission

23-Jan-14

0%

100%

23-Jan-14

Steel Structure Works

Precast Building Element Works


2760

Shop Drawings Submission

23-Jan-14

3030

Shop Drawings Approval

28-Jan-14

23-Jan-14

Precast Boundary Wall Works

30-Jan-14

0%

28-Jan-14

0%
0%

100%

0%

100%

28-Jan-14

0%

2770

Shop Drawings Submission

23-Jan-14

0%

100%

3020

Shop Drawings Approval

28-Jan-14

0%

100%

11-Feb-14

2780

Shop Drawings Submission

11-Feb-14

0%

0%

2790

Shop Drawings Approval

18-Feb-14

0%

0%

06-Feb-14

MEP Works

GRC Cladding Works


2800

Shop Drawings Submission

06-Feb-14

2810

Shop Drawings Approval

13-Feb-14

16-Feb-14

Hardscape Works

18-Feb-14

0%

13-Feb-14

0%
0%

0%

0%

0%

23-Feb-14

0%

2820

Shop Drawings Submission

16-Feb-14

0%

0%

2830

Shop Drawings Approval

23-Feb-14

0%

0%

29-Jan-14

2850

Shop Drawings Approval

03-Feb-14

0%

0%

2840

Shop Drawings Submission

29-Jan-14

0%

100%

13-Feb-14

Aluminium and Glazing Works

Container Works
2860

Shop Drawings Submission

13-Feb-14

2870

Shop Drawings Approval

18-Feb-14

05-Mar-14

Aircell Insulation

03-Feb-14

0%

18-Feb-14

0%
0%

0%

0%

0%

09-Mar-14

0%

2880

Shop Drawings Submission

05-Mar-14

0%

0%

2890

Shop Drawings Approval

09-Mar-14

0%

0%

30-Jan-14

Roof Waterproofing Works

02-Feb-14

0%

3000

Shop Drawings Submission

30-Jan-14

0%

0%

3010

Shop Drawings Approval

02-Feb-14

0%

0%

16-Feb-14

Stone Cladding Works


2900

Shop Drawings Submission

16-Feb-14

2910

Shop Drawings Approval

23-Feb-14

29-Jan-14

EIFS System Works

23-Feb-14

0%
0%

0%

0%

0%

03-Feb-14

0%

2930

Shop Drawings Approval

03-Feb-14

0%

0%

2920

Shop Drawings Submission

29-Jan-14

0%

100%

05-Feb-14

Canopy and Louvers Works

10-Feb-14

0%

2940

Shop Drawings Submission

05-Feb-14

0%

0%

2950

Shop Drawings Approval

10-Feb-14

0%

0%

23-Feb-14

23-Feb-14

External Lighting Works


2960

7/16

0
192

Shop Drawings Submission

Date
24-Oct-13
10-Jul-14

03-Mar-14

0%
0%

Revision
Project Start Date
Project Finish Date

Checked

0%

Approved

Al Wasl Box Park


Activity ID

Activity Name
2970

Shop Drawings Approval

Sanitary Ware Works

BL1 Start

03-Mar-14

23-Feb-14

BL1 Finish

Actual Start

Actual Finish

Activity %
Complete

Schedule %
Complete

0%

0%

03-Mar-14

0%

2980

Shop Drawings Submission

23-Feb-14

0%

0%

2990

Shop Drawings Approval

03-Mar-14

0%

0%

73

24-Dec-13

10-Feb-14

24-Dec-13

Site Work/Preparations
A4180

Site Setting out

Site Work/ Under Foundation Level

24-Dec-13

26-Dec-13

24-Dec-13

31

28-Dec-13

01-Jan-14

28-Dec-13

0%
26-Dec-13

100%

100%
0%

A4330

Excavation up to level 1.45m & Compaction

28-Dec-13

29-Dec-13

28-Dec-13

80%

100%

A4340

Anti-termitte Works

29-Dec-13

29-Dec-13

30-Jan-14

80%

100%

A4350

(200mm) Backfilling by roadbase , compaction & polythene sheet

30-Dec-13

01-Jan-14

25-Jan-14

80%

100%

04-Feb-14

10-Feb-14

Site Work First Stage (Precast & Conatiner Areas)

0%

A4470

(200)mm Backfilling by excavated materials, compaction.

04-Feb-14

06-Feb-14

0%

0%

A4480

Anti-termite Works

05-Feb-14

06-Feb-14

0%

0%

A4590

(200)mm Backfilling by roadbase, compaction & polythene sheet

06-Feb-14

10-Feb-14

0%

0%

A4760

Waterproofing for for isolated, strip footings and pedestals

04-Feb-14

04-Feb-14

0%

0%

03-Feb-14

05-Feb-14

Site Work Second Stage (Canopy Area)

0%

A4610

Backfilling by excavated materials & compaction

04-Feb-14

04-Feb-14

0%

0%

A4770

Waterproofing for isolated footings and pedestal

03-Feb-14

03-Feb-14

0%

0%

A4810

Anti-termite Works

04-Feb-14

05-Feb-14

0%

0%

73

01-Jan-14

20-Mar-14

30-Jan-14

0%

19

01-Jan-14

19-Jan-14

30-Jan-14

0%

19

01-Jan-14

14-Jan-14

30-Jan-14

0%

30-Jan-14

Subrstructure Works
Footing Works
Footings First Stage (Precast & Conatiner Areas)
A4190

PCC for Isolated footing

01-Jan-14

02-Jan-14

A4360

Steel work for Isolated & Strip footings

05-Jan-14

A4370

Formwork for Isolated & Strip footings

06-Jan-14

A4380

Casting Concrete for Isolated & Strip footings

A4780

Waterproofing for PCC

Footing Seond Stage (Canopy Area)

80%

100%

09-Jan-14

0%

100%

12-Jan-14

0%

100%

13-Jan-14

14-Jan-14

0%

100%

04-Jan-14

04-Jan-14

0%

100%

11

13-Jan-14

19-Jan-14

30-Jan-14
30-Jan-14

0%

A4390

PCC for Isolated Footings

14-Jan-14

15-Jan-14

100%

100%

A4400

Steel work for Isolated Footings

16-Jan-14

16-Jan-14

0%

100%

A4410

Formwork for Isolated Footings

18-Jan-14

18-Jan-14

0%

100%

A4420

Casting Concrete for Isolated Footings

19-Jan-14

19-Jan-14

0%

100%

A4460

Approval of Canopy Super Structure Drawings

13-Jan-14

0%

100%

A4800

Waterproofing for PCC

15-Jan-14

16-Jan-14

0%

100%

20

14-Jan-14

03-Feb-14

0%

13

14-Jan-14

03-Feb-14

0%

Pedestal Works
Pedestal First Stage (Precast & Conatiner Areas)

30-Jan-14

A4840

(75)mm Mass concrete for isolated footing

03-Feb-14

03-Feb-14

0%

0%

A4430

Steel work for Pedestal

14-Jan-14

21-Jan-14

0%

100%

A4440

Formwork for Pedestal

16-Jan-14

23-Jan-14

0%

100%

A4450

Casting Concrete for Pedestal

21-Jan-14

22-Jan-14

0%

100%

20-Jan-14

21-Jan-14

Pedestal Second Stage (Canopy Area)

0%

A4560

Steel work for Pedestal

20-Jan-14

20-Jan-14

0%

100%

A4570

Formwork for Pedestal

20-Jan-14

21-Jan-14

0%

100%

A4580

Casting Concrete for Pedestal

20-Jan-14

21-Jan-14

0%

100%

35

10-Feb-14

20-Mar-14

Ground Slab (Precast & Conatiner Areas)

0%

A4490

PCC for Ground Beams and Ground Slab

10-Feb-14

11-Feb-14

0%

0%

A4500

Steel work for Ground Beams, Embedded Plate and (Ground Slab...

10

18-Feb-14

27-Feb-14

0%

0%

A4510

Formwork for Ground Beams and (Ground Slab-1st layer)

10

20-Feb-14

02-Mar-14

0%

0%

A4520

Casting Concrete for Ground Beams and (Ground Slab-1st layer)

02-Mar-14

03-Mar-14

0%

0%

A4530

BRC Mesh for the Ground Slab- 2nd layer and embeded plates

10

06-Mar-14

16-Mar-14

0%

0%

A4540

Concrete casting for Ground Slab-2nd layer

20-Mar-14

20-Mar-14

0%

0%

A4550

(50)mm Rigid Floor Insulation

03-Mar-14

05-Mar-14

0%

0%

A4790

Waterproofing for PCC for Ground Beams and ground slab

11-Feb-14

13-Feb-14

0%

0%

A4820

Formwork for Ground Slab-2nd layer

10

10-Mar-14

19-Mar-14

0%

0%

144

08-Jan-14

02-Jun-14

Superstructure Works

0%

93

08-Jan-14

12-Apr-14

A4980

Steel structure - Steel Columns works

30-Jan-14

03-Feb-14

0%

0%

A4990

Steel structure -Steel Tie Beams Works

20-Mar-14

22-Mar-14

0%

0%

A5000

Steel Sheet @ Roof & Shade

09-Apr-14

10-Apr-14

0%

0%

A6080

Steel Staircase Fixing

09-Apr-14

12-Apr-14

0%

0%

A6030

Approval of Steel Staircase Drawings

08-Jan-14

0%

100%

20-Mar-14

30-Mar-14

Steel Structure Works

Precast Works

8/16

OD

0%

0%

A4860

Precast Colunm & Panels Fixing

20-Mar-14

26-Mar-14

0%

0%

A5020

Hollow Core Slab @ level 5.186 m

26-Mar-14

27-Mar-14

0%

0%

A5160

Hollow Core Slab @ level 7.9 m with parapet

27-Mar-14

30-Mar-14

0%

0%

Date
24-Oct-13
10-Jul-14

Revision
Project Start Date
Project Finish Date

Checked

Approved

Al Wasl Box Park


Activity ID

Activity Name

BL1 Start

BL1 Finish

Actual Start

Actual Finish

Activity %
Complete

Schedule %
Complete

24

21-Jan-14

10-Feb-14

A4850

Canopy Shade Structure balance work

05-Feb-14

10-Feb-14

0%

0%

A4730

Canopy Shade Structure Colunms

21-Jan-14

23-Jan-14

0%

100%

22

06-Mar-14

27-Mar-14

Canopy Shade Works

Container Works

0%

0%

A4950

Placing of the containers for the ground level

06-Mar-14

10-Mar-14

0%

0%

A4960

Placing of the containers for the first and roof level

22-Mar-14

25-Mar-14

0%

0%

A4970

Hardly cladding & Block Works

25-Mar-14

27-Mar-14

0%

0%

18

26-Mar-14

13-Apr-14

0%

26-Mar-14

01-Apr-14

0%

Concrete Works
Concrete Works @ Container Roof Level
A5040

Steel work for the roof slab

27-Mar-14

30-Mar-14

0%

0%

A5030

Formwork for the roof slab

26-Mar-14

26-Mar-14

0%

0%

A5050

Casting concrete for the roof slab

31-Mar-14

01-Apr-14

0%

0%

Concrete Works @ Precast Roof Level 5.186

01-Apr-14

07-Apr-14

0%

A4930

Steel work for the roof slab

03-Apr-14

05-Apr-14

0%

0%

A4920

Formwork for the roof slab

01-Apr-14

02-Apr-14

0%

0%

A4940

Casting concrete for the roof slab

06-Apr-14

07-Apr-14

0%

0%

07-Apr-14

13-Apr-14

Concrete Works @ Precast Roof Level 7.9

0%

A5180

Steel work for the roof slab

09-Apr-14

10-Apr-14

0%

0%

A5170

Formwork for the roof slab

07-Apr-14

08-Apr-14

0%

0%

A5190

Casting concrete for the roof slab

12-Apr-14

13-Apr-14

0%

0%

01-Apr-14

06-Apr-14

01-Apr-14

06-Apr-14

50

10-Mar-14

29-Apr-14

Thermal & Insulation Works


A4240

Thermal insulations

Roofing Works

0%
0%

0%
0%

13-Apr-14

21-Apr-14

A5060

Light weight screed with BRC Mesh

13-Apr-14

15-Apr-14

0%

0%

A5100

Gravel

20-Apr-14

21-Apr-14

0%

0%

A5090

Waterproof memebrane

19-Apr-14

20-Apr-14

0%

0%

A5080

Glass Foam Insulation

17-Apr-14

19-Apr-14

0%

0%

A5070

Bitumen waterproofing

16-Apr-14

16-Apr-14

0%

0%

01-Apr-14

09-Apr-14

Roofing Works (Precast Roof Area Level 5.186)

Roofing Works (Roof Conatiner Areas)

0%

0%

A4870

Light weight screed with BRC Mesh

01-Apr-14

02-Apr-14

0%

0%

A4910

Gravel

08-Apr-14

09-Apr-14

0%

0%

A4900

Waterproof memebrane

07-Apr-14

08-Apr-14

0%

0%

A4890

Glass Foam Insulation

05-Apr-14

07-Apr-14

0%

0%

A4880

Bitumen waterproofing

03-Apr-14

05-Apr-14

0%

0%

21-Apr-14

29-Apr-14

Roofing Works (Precast Roof Area Level 7.9)

0%

A5110

Light weight screed

21-Apr-14

23-Apr-14

0%

0%

A5150

Gravel

28-Apr-14

29-Apr-14

0%

0%

A5140

Waterproof memebrane

27-Apr-14

28-Apr-14

0%

0%

A5130

Glass Foam Insulation

24-Apr-14

27-Apr-14

0%

0%

A5120

Bitumen waterproofing

24-Apr-14

24-Apr-14

0%

0%

Roofing Works (Ground Container)

10-Mar-14

17-Mar-14

0%

A4690

WBP plywood backing

10-Mar-14

11-Mar-14

0%

0%

A4700

Roof Finishes

15-Mar-14

17-Mar-14

0%

0%

A4710

Waterproof membrane

13-Mar-14

15-Mar-14

0%

0%

A4720

Insulation

12-Mar-14

13-Mar-14

0%

0%

50

13-Apr-14

02-Jun-14

A4250

Fixing C channel on the containers level 1 and 2

13-Apr-14

16-Apr-14

0%

0%

A4260

Aluminium Louver Panel , Signages, Dry Walls& Container Paint F...

16

16-Apr-14

01-May-14

0%

0%

A4300

Glazing works

04-May-14

11-May-14

0%

0%

A4740

Bitumen, Aluminium cladding, Pergola, Laminated Glass, Canopy, ...

13

18-May-14

31-May-14

0%

0%

A4750

Steel Cat Ladder & LED Screen

31-May-14

02-Jun-14

0%

0%

A5200

Aluminium, Steel Doors and Rolling Shutter Door Fixing

11-May-14

18-May-14

0%

0%

29-Apr-14

04-May-14

0%

29-Apr-14

04-May-14

0%

Facade Works

Finishes
Internal Finishes
A4280

Screed Floor finishes for the ground level

MEP Works
A4310

MEP Works & External Lighting

Facility Finish Date

29-Apr-14

04-May-14

104

18-Feb-14

02-Jun-14

104

18-Feb-14

02-Jun-14

11

02-Jun-14

12-Jun-14

A4320

Facility finish date

A7230

Testing and Commissioning Works

10

A7240

Handingover to Tenant

FC-01
A7310

FC-03

9/16

OD

FC-01 Building Works

02-Jun-14

0%

0%

0%
0%

0%
0%

11-Jun-14

0%

0%

11-Jun-14

0%

0%

12-Jun-14

0%

0%

164

29-Dec-13

10-Jun-14

29-Dec-13

164

29-Dec-13

10-Jun-14

29-Dec-13

151

15-Jan-14

15-Jun-14

Date
24-Oct-13
10-Jul-14

0%

5%

19.97%
0%

Revision
Project Start Date
Project Finish Date

0%

Checked

Approved

Al Wasl Box Park


Activity ID

Activity Name

OD

BL1 Start

BL1 Finish

FC-03 Building Works

151

15-Jan-14

15-Jun-14

149

21-Jan-14

18-Jun-14

149

21-Jan-14

18-Jun-14

152

21-Jan-14

21-Jun-14

152

21-Jan-14

21-Jun-14

151

26-Jan-14

25-Jun-14

151

26-Jan-14

25-Jun-14

Plot M9

116

23-Dec-13

05-May-14

23-Dec-13

Design

23-Dec-13

23-Dec-13

23-Dec-13

23-Dec-13

110

23-Dec-13

05-May-14

03-Jan-14

0%

110

23-Dec-13

05-May-14

03-Jan-14

0%

52

23-Dec-13

09-Mar-14

03-Jan-14

0%

29-Dec-13

45

23-Dec-13

09-Mar-14
30-Dec-13

A7320

FC-04
A7330

FC-04 Building Works

FC-05
A7340

FC-05 Building Works

FC-06
A7350

FC-06 Building Works

c2610

FC-01 Received Design Drawings from Consultant

Building Works
FC-01
Facility Start Date
A 0540

Facility start date

Shop Drawings Schedule

Actual Finish

Activity %
Complete

Schedule %
Complete

0%

10.1%
0%

0%

6.38%
0%

0%

6.25%

0%

3.15%

0%

0%
23-Dec-13

23-Dec-13

0%
100%

03-Jan-14

100%

100%

100%
0%

23-Dec-13

3360

Shop Drawings Submission

23-Dec-13

0%

100%

3370

Shop Drawings Approval

30-Dec-13

0%

100%

23-Jan-14

Construction Shop Drawings

Steel Structure Works

0%

30-Jan-14

0%

3070

Shop Drawings Approval

30-Jan-14

0%

0%

3060

Shop Drawings Submission

23-Jan-14

0%

100%

23-Jan-14

Precast Building Element Works

28-Jan-14

0%

3080

Shop Drawings Submission

23-Jan-14

0%

100%

3350

Shop Drawings Approval

28-Jan-14

0%

100%

23-Jan-14

3090

Shop Drawings Submission

23-Jan-14

0%

100%

3340

Shop Drawings Approval

28-Jan-14

0%

100%

11-Feb-14

Precast Boundary Wall Works

MEP Works
3100

Shop Drawings Submission

11-Feb-14

3110

Shop Drawings Approval

18-Feb-14

06-Feb-14

GRC Cladding Works

28-Jan-14

0%

18-Feb-14

0%
0%

0%

0%

0%

13-Feb-14

0%

3120

Shop Drawings Submission

06-Feb-14

0%

0%

3130

Shop Drawings Approval

13-Feb-14

0%

0%

16-Feb-14

3140

Shop Drawings Submission

16-Feb-14

0%

0%

3150

Shop Drawings Approval

23-Feb-14

0%

0%

29-Jan-14

Hardscape Works

Aluminium and Glazing Works


3170

Shop Drawings Approval

03-Feb-14

3160

Shop Drawings Submission

29-Jan-14

13-Feb-14

Container Works

23-Feb-14

0%

03-Feb-14

0%
0%

0%

0%

100%

18-Feb-14

0%

3180

Shop Drawings Submission

13-Feb-14

0%

0%

3190

Shop Drawings Approval

18-Feb-14

0%

0%

05-Mar-14

3200

Shop Drawings Submission

05-Mar-14

0%

0%

3210

Shop Drawings Approval

09-Mar-14

0%

0%

30-Jan-14

Aircell Insulation

Roof Waterproofing Works


3320

Shop Drawings Submission

30-Jan-14

3330

Shop Drawings Approval

02-Feb-14

16-Feb-14

Stone Cladding Works

09-Mar-14

0%

02-Feb-14

0%
0%

0%

0%

0%

23-Feb-14

0%

3220

Shop Drawings Submission

16-Feb-14

0%

0%

3230

Shop Drawings Approval

23-Feb-14

0%

0%

29-Jan-14

EIFS System Works

03-Feb-14

0%

3250

Shop Drawings Approval

03-Feb-14

0%

0%

3240

Shop Drawings Submission

29-Jan-14

0%

100%

05-Feb-14

Canopy and Louvers Works


3260

Shop Drawings Submission

05-Feb-14

3270

Shop Drawings Approval

10-Feb-14

23-Feb-14

External Lighting Works

10-Feb-14

0%
0%

0%

0%

0%

03-Mar-14

0%

3280

Shop Drawings Submission

23-Feb-14

0%

0%

3290

Shop Drawings Approval

03-Mar-14

0%

0%

23-Feb-14

Sanitary Ware Works

03-Mar-14

0%

3300

Shop Drawings Submission

23-Feb-14

0%

0%

3310

Shop Drawings Approval

03-Mar-14

0%

0%

30

29-Dec-13

10-Feb-14

03-Jan-14

29-Dec-13

30-Dec-13

03-Jan-14

Site Work/Preparations
A6090

10/16

Actual Start

Site Setting out

Date
24-Oct-13
10-Jul-14

Revision
Project Start Date
Project Finish Date

0%
03-Jan-14

100%

Checked

100%

Approved

Al Wasl Box Park


Activity ID

Activity Name

BL1 Start

BL1 Finish

Actual Start

Actual Finish

Activity %
Complete

Schedule %
Complete

31-Dec-13

05-Jan-14

03-Jan-14

22-Jan-14

A6180

Excavation up to level 1.45m & Compaction

31-Dec-13

02-Jan-14

03-Jan-14

03-Jan-14

100%

100%

A6190

Anti-termitte Works

01-Jan-14

02-Jan-14

22-Jan-14

22-Jan-14

100%

100%

A6200

(200mm) Backfilling by roadbase , compaction & polythene sheet

02-Jan-14

05-Jan-14

17-Jan-14

19-Jan-14

100%

100%

04-Feb-14

10-Feb-14

Site Work/ Under Foundation Level

Site Work First Stage (Precast & Conatiner Areas)

0%

0%

A6320

(200)mm Backfilling by excavated materials, compaction.

04-Feb-14

06-Feb-14

0%

0%

A6330

Anti-termite Works

05-Feb-14

06-Feb-14

0%

0%

A6440

(200)mm Backfilling by roadbase, compaction & polythene sheet

06-Feb-14

10-Feb-14

0%

0%

A6530

Waterproofing for for isolated, strip footings and pedestals

04-Feb-14

04-Feb-14

0%

0%

03-Feb-14

05-Feb-14

A6450

Backfilling by excavated materials & compaction

04-Feb-14

04-Feb-14

0%

0%

A6540

Waterproofing for isolated footings and pedestal

03-Feb-14

03-Feb-14

0%

0%

A6580

Anti-termite Works

04-Feb-14

05-Feb-14

0%

0%

55

06-Jan-14

11-Mar-14

21-Jan-14

0%

25

06-Jan-14

23-Jan-14

21-Jan-14

0%

10

06-Jan-14

18-Jan-14

21-Jan-14

0%

Site Work Second Stage (Canopy Area)

Subrstructure Works
Footing Works
Footings First Stage (Precast & Conatiner Areas)

0%

A6100

PCC for Isolated footing

06-Jan-14

07-Jan-14

22-Jan-14

A6210

Steel work for Isolated & Strip footings

08-Jan-14

14-Jan-14

23-Jan-14

A6220

Formwork for Isolated & Strip footings

11-Jan-14

16-Jan-14

23-Jan-14

A6230

Casting Concrete for Isolated & Strip footings

18-Jan-14

18-Jan-14

A6550

Waterproofing for PCC

07-Jan-14

08-Jan-14

21-Jan-14

18

18-Jan-14

23-Jan-14

22-Jan-14

Footing Seond Stage (Canopy Area)

22-Jan-14

100%

100%

80%

100%

26-Jan-14

100%

100%

0%

100%

21-Jan-14

100%

100%
0%

A6240

PCC for Isolated Footings

19-Jan-14

19-Jan-14

22-Jan-14

A6250

Steel work for Isolated Footings

20-Jan-14

21-Jan-14

23-Jan-14

A6260

Formwork for Isolated Footings

21-Jan-14

22-Jan-14

23-Jan-14

A6270

Casting Concrete for Isolated Footings

22-Jan-14

23-Jan-14

A6310

Approval of Canopy Super Structure Drawings

18-Jan-14

A6570

Waterproofing for PCC

20-Jan-14

20-Jan-14

16

19-Jan-14

03-Feb-14

0%

15

19-Jan-14

03-Feb-14

0%

Pedestal Works
Pedestal First Stage (Precast & Conatiner Areas)

23-Jan-14

22-Jan-14

100%

100%

80%

100%

26-Jan-14

100%

100%

0%

100%

0%

100%

100%

100%

23-Jan-14

A6600

(75)mm Mass concrete for isolated footing

03-Feb-14

03-Feb-14

0%

0%

A6280

Steel work for Pedestal

19-Jan-14

21-Jan-14

0%

100%

A6290

Formwork for Pedestal

20-Jan-14

23-Jan-14

0%

100%

A6300

Casting Concrete for Pedestal

21-Jan-14

22-Jan-14

0%

100%

23-Jan-14

25-Jan-14

Pedestal Second Stage (Canopy Area)

0%

A6410

Steel work for Pedestal

23-Jan-14

23-Jan-14

0%

100%

A6420

Formwork for Pedestal

25-Jan-14

25-Jan-14

0%

100%

A6430

Casting Concrete for Pedestal

0%

100%

Ground Slab (Precast & Conatiner Areas)

25-Jan-14

25-Jan-14

25

10-Feb-14

11-Mar-14

0%

A6340

PCC for Ground Beams and Ground Slab

10-Feb-14

11-Feb-14

0%

0%

A6350

Steel work for Ground Beams, Embedded Plate and (Ground Slab...

18-Feb-14

24-Feb-14

0%

0%

A6360

Formwork for Ground Beams and (Ground Slab-1st layer)

20-Feb-14

26-Feb-14

0%

0%

A6370

Casting Concrete for Ground Beams and (Ground Slab-1st layer)

26-Feb-14

26-Feb-14

0%

0%

A6380

BRC Mesh for the Ground Slab- 2nd layer and embeded plates

02-Mar-14

05-Mar-14

0%

0%

A6390

Concrete casting for Ground Slab-2nd layer

10-Mar-14

11-Mar-14

0%

0%

A6400

(50)mm Rigid Floor Insulation

27-Feb-14

01-Mar-14

0%

0%

A6560

Waterproofing for PCC for Ground Beams and ground slab

11-Feb-14

13-Feb-14

0%

0%

A6590

Formwork for Ground Slab-2nd layer

06-Mar-14

10-Mar-14

0%

0%

97

13-Jan-14

29-Apr-14

0%

72

13-Jan-14

03-Apr-14

0%

Superstructure Works
Steel Structure Works
A6740

Steel structure - Steel Columns works

30-Jan-14

03-Feb-14

0%

0%

A6750

Steel structure -Steel Tie Beams Works

11-Mar-14

12-Mar-14

0%

0%

A6760

Steel Sheet @ Roof & Shade

30-Mar-14

03-Apr-14

0%

0%

A6960

Steel Staircase Fixing

30-Mar-14

02-Apr-14

0%

0%

A6970

Approval of Steel Staircase Drawings

13-Jan-14

0%

100%

11

11-Mar-14

22-Mar-14

A6620

Precast Colunm & Panels Fixing

11-Mar-14

17-Mar-14

0%

0%

A6770

Hollow Core Slab @ level 5.186 m & 5.95 m

17-Mar-14

19-Mar-14

0%

0%

A6910

Hollow Core Slab @ level 7.9 m

19-Mar-14

20-Mar-14

0%

0%

A6990

Hollow Core Slab @ level 9.2 m

20-Mar-14

22-Mar-14

0%

0%

Precast Works

0%

20

26-Jan-14

10-Feb-14

A6610

Canopy Shade Structure balance work

05-Feb-14

10-Feb-14

0%

0%

A6500

Canopy Shade Structure Colunms

26-Jan-14

28-Jan-14

0%

100%

23

02-Mar-14

25-Mar-14

02-Mar-14

05-Mar-14

Canopy Shade Works

Container Works
A6710

11/16

OD

Placing of the containers for the ground level

Date
24-Oct-13
10-Jul-14

0%

0%
0%

Revision
Project Start Date
Project Finish Date

Checked

0%

Approved

Al Wasl Box Park


Activity ID

Activity Name

BL1 Start

BL1 Finish

Actual Start

Actual Finish

Activity %
Complete

Schedule %
Complete

A6720

Placing of the containers for the first and roof level

12-Mar-14

15-Mar-14

0%

0%

A6730

Hardly cladding & Block Works

22-Mar-14

25-Mar-14

0%

0%

12

16-Mar-14

27-Mar-14

0%

16-Mar-14

22-Mar-14

0%

Concrete Works
Concrete Works @ Container Roof Level
A6780

Steel work for the roof slab

18-Mar-14

19-Mar-14

0%

0%

A6790

Formwork for the roof slab

16-Mar-14

17-Mar-14

0%

0%

A6800

Casting concrete for the roof slab

20-Mar-14

22-Mar-14

0%

0%

17-Mar-14

19-Mar-14

17-Mar-14

19-Mar-14

Concrete Works for Staircase


A6980

RCC for Staircase

0%
0%

0%

19-Mar-14

25-Mar-14

A6680

Steel work for the roof slab

20-Mar-14

23-Mar-14

0%

0%

A6690

Formwork for the roof slab

19-Mar-14

19-Mar-14

0%

0%

A6700

Casting concrete for the roof slab

24-Mar-14

25-Mar-14

0%

0%

20-Mar-14

26-Mar-14

Concrete Works @ Precast Roof Level 5.186 & 5.95

Concrete Works @ Precast Roof Level 7.9

0%

0%

A6920

Steel work for the roof slab

23-Mar-14

25-Mar-14

0%

0%

A6930

Formwork for the roof slab

20-Mar-14

22-Mar-14

0%

0%

A6940

Casting concrete for the roof slab

26-Mar-14

26-Mar-14

0%

0%

22-Mar-14

27-Mar-14

Concrete Works @ Precast Roof Level 9.2

0%

A7010

Steel work for the roof slab

24-Mar-14

26-Mar-14

0%

0%

A7000

Formwork for the roof slab

22-Mar-14

23-Mar-14

0%

0%

A7020

Casting concrete for the roof slab

27-Mar-14

27-Mar-14

0%

0%

22-Mar-14

26-Mar-14

22-Mar-14

26-Mar-14

21

15-Mar-14

05-Apr-14

0%

27-Mar-14

03-Apr-14

0%

Thermal & Insulation Works


A6110

Thermal insulations

Roofing Works
Roofing Works (Precast Roof Area Level 5.186 & 5.95)

0%
0%

0%

A6810

Light weight screed

27-Mar-14

29-Mar-14

0%

0%

A6820

Gravel

03-Apr-14

03-Apr-14

0%

0%

A6830

Waterproof memebrane

02-Apr-14

02-Apr-14

0%

0%

A6840

Glass Foam Insulation

31-Mar-14

02-Apr-14

0%

0%

A6850

Bitumen waterproofing

30-Mar-14

31-Mar-14

0%

0%

22-Mar-14

30-Mar-14

Roofing Works (Roof Conatiner Areas)

0%

A6630

Light weight screed with BRC Mesh

22-Mar-14

24-Mar-14

0%

0%

A6640

Gravel

29-Mar-14

30-Mar-14

0%

0%

A6650

Waterproof memebrane

27-Mar-14

29-Mar-14

0%

0%

A6660

Glass Foam Insulation

26-Mar-14

27-Mar-14

0%

0%

A6670

Bitumen waterproofing

25-Mar-14

26-Mar-14

0%

0%

27-Mar-14

03-Apr-14

Roofing Works (Precast Roof Area Level 7.9)

0%

A6860

Light weight screed with BRC Mesh

27-Mar-14

29-Mar-14

0%

0%

A6870

Gravel

03-Apr-14

03-Apr-14

0%

0%

A6880

Waterproof memebrane

02-Apr-14

02-Apr-14

0%

0%

A6890

Glass Foam Insulation

31-Mar-14

02-Apr-14

0%

0%

A6900

Bitumen waterproofing

30-Mar-14

31-Mar-14

0%

0%

27-Mar-14

05-Apr-14

A7030

Light weight screed with BRC Mesh

27-Mar-14

30-Mar-14

0%

0%

A7070

Gravel

03-Apr-14

05-Apr-14

0%

0%

A7060

Waterproof memebrane

03-Apr-14

03-Apr-14

0%

0%

A7050

Glass Foam Insulation

01-Apr-14

02-Apr-14

0%

0%

A7040

Bitumen waterproofing

31-Mar-14

01-Apr-14

0%

0%

15-Mar-14

22-Mar-14

Roofing Works (Precast Roof Area Level 9.2)

Roofing Works (Upper Roof Container)

0%

0%

A6460

WBP plywood backing

15-Mar-14

16-Mar-14

0%

0%

A6470

Roof Finishes

20-Mar-14

22-Mar-14

0%

0%

A6480

Waterproof membrane

19-Mar-14

19-Mar-14

0%

0%

A6490

Insulation

17-Mar-14

19-Mar-14

0%

0%

32

27-Mar-14

29-Apr-14

Facade Works

0%

A6120

Fixing C channel on the containers level 1 and 2

27-Mar-14

30-Mar-14

0%

0%

A6130

Aluminium Louver Panel , Signages, Dry Walls& Container Paint F...

30-Mar-14

07-Apr-14

0%

0%

A6150

Glazing works

10-Apr-14

16-Apr-14

0%

0%

A6510

Bitumen, Aluminium, Steel cladding, Pergola, Laminated Glass, C...

10

17-Apr-14

27-Apr-14

0%

0%

A6520

Aluminium Staircase Handrail & LED Screen

27-Apr-14

29-Apr-14

0%

0%

A6950

Aluminium, Steel Doors and Wooden Doors

10-Apr-14

16-Apr-14

0%

0%

05-Apr-14

09-Apr-14

0%

05-Apr-14

09-Apr-14

0%

05-Apr-14

09-Apr-14

67

20-Feb-14

28-Apr-14

67

20-Feb-14

28-Apr-14

Finishes
Internal Finishes
A6140

Screed Floor finishes for the ground level

MEP Works
A6160

12/16

OD

MEP Works and External Lighting

Date
24-Oct-13
10-Jul-14

0%

0%
0%

Revision
Project Start Date
Project Finish Date

0%

Checked

0%

Approved

Al Wasl Box Park


Activity ID

Activity Name

Facility Finish Date

OD

BL1 Start

BL1 Finish

29-Apr-14

05-May-14

A6170

Facility finish date

A7260

Testing and Commissioning Works

A7270

Handingover to Tenant

Plot M10

29-Apr-14

Actual Start

Actual Finish

Activity %
Complete

Schedule %
Complete
0%

05-May-14

0%

0%

05-May-14

0%

0%

05-May-14

0%

0%

174

23-Dec-13

31-May-14

23-Dec-13

09-Jan-14

23-Dec-13

0%

32

23-Dec-13

c2620

FC-01 Received Design Drawings from Consultant

09-Jan-14

15-Jan-14

100%

100%

c2630

FC-02 Received Design Drawings from Consultant

23-Dec-13

23-Dec-13

100%

100%

c2640

FC-03 Received Design Drawings from Consultant

09-Jan-14

15-Jan-14

100%

100%

c2650

FC-04 Received Design Drawings from Consultant

09-Jan-14

15-Jan-14

100%

100%

160

30-Dec-13

31-May-14

31-Dec-13

0%

160

30-Dec-13

31-May-14

31-Dec-13

0%

75

30-Dec-13

09-Mar-14

31-Dec-13

0%

31-Dec-13

45

30-Dec-13

09-Mar-14
06-Jan-14

Design

Building Works
FC-02
Facility Start Date
B0520

Facility start date

Shop Drawings Schedule

31-Dec-13

0%

100%

100%
0%

30-Dec-13

3680

Shop Drawings Submission

30-Dec-13

0%

100%

3690

Shop Drawings Approval

06-Jan-14

0%

100%

23-Jan-14

Construction Shop Drawings

Steel Structure Works

0%

30-Jan-14

0%

3390

Shop Drawings Approval

30-Jan-14

0%

0%

3380

Shop Drawings Submission

23-Jan-14

0%

100%

23-Jan-14

Precast Building Element Works

28-Jan-14

0%

3400

Shop Drawings Submission

23-Jan-14

0%

100%

3670

Shop Drawings Approval

28-Jan-14

0%

100%

23-Jan-14

3410

Shop Drawings Submission

23-Jan-14

0%

100%

3660

Shop Drawings Approval

28-Jan-14

0%

100%

11-Feb-14

Precast Boundary Wall Works

MEP Works
3420

Shop Drawings Submission

11-Feb-14

3430

Shop Drawings Approval

18-Feb-14

16-Feb-14

Hardscape Works

28-Jan-14

0%

18-Feb-14

0%
0%

0%

0%

0%

23-Feb-14

0%

3460

Shop Drawings Submission

16-Feb-14

0%

0%

3470

Shop Drawings Approval

23-Feb-14

0%

0%

29-Jan-14

3490

Shop Drawings Approval

03-Feb-14

0%

0%

3480

Shop Drawings Submission

29-Jan-14

0%

100%

13-Feb-14

Aluminium and Glazing Works

Container Works
3500

Shop Drawings Submission

13-Feb-14

3510

Shop Drawings Approval

18-Feb-14

05-Mar-14

Aircell Insulation

03-Feb-14

0%

18-Feb-14

0%
0%

0%

0%

0%

09-Mar-14

0%

3520

Shop Drawings Submission

05-Mar-14

0%

0%

3530

Shop Drawings Approval

09-Mar-14

0%

0%

30-Jan-14

3640

Shop Drawings Submission

30-Jan-14

0%

0%

3650

Shop Drawings Approval

02-Feb-14

0%

0%

16-Feb-14

Roof Waterproofing Works

Stone Cladding Works


3540

Shop Drawings Submission

16-Feb-14

3550

Shop Drawings Approval

23-Feb-14

29-Jan-14

EIFS System Works

02-Feb-14

0%

23-Feb-14

0%
0%

0%

0%

0%

03-Feb-14

0%

3570

Shop Drawings Approval

03-Feb-14

0%

0%

3560

Shop Drawings Submission

29-Jan-14

0%

100%

05-Feb-14

Canopy and Louvers Works

10-Feb-14

0%

3580

Shop Drawings Submission

05-Feb-14

0%

0%

3590

Shop Drawings Approval

10-Feb-14

0%

0%

23-Feb-14

External Lighting Works


3600

Shop Drawings Submission

23-Feb-14

3610

Shop Drawings Approval

03-Mar-14

23-Feb-14

Sanitary Ware Works

03-Mar-14

0%
0%

0%

0%

0%

03-Mar-14

0%

3620

Shop Drawings Submission

23-Feb-14

0%

0%

3630

Shop Drawings Approval

03-Mar-14

0%

0%

56

31-Dec-13

09-Feb-14

31-Dec-13

Site Work/Preparations
B3550

Site Setting out

Site Work/ Under Foundation Level

13/16

15-Jan-14

0%

31-Dec-13

02-Jan-14

31-Dec-13

02-Jan-14

16

04-Jan-14

05-Jan-14

04-Jan-14

25-Jan-14

100%

100%
0%

B4300

Excavation up to level 1.45m & Compaction

04-Jan-14

04-Jan-14

04-Jan-14

23-Jan-14

100%

100%

B4310

Anti-termitte Works

04-Jan-14

04-Jan-14

25-Jan-14

25-Jan-14

100%

100%

Date
24-Oct-13
10-Jul-14

Revision
Project Start Date
Project Finish Date

Checked

Approved

Al Wasl Box Park


Activity ID

Activity Name

B4320

(200mm) Backfilling by roadbase , compaction & polythene sheet

Site Work First Stage (Under Steel Colunms)

BL1 Start

BL1 Finish

Actual Start

Actual Finish

05-Jan-14

05-Jan-14

25-Jan-14

25-Jan-14

05-Feb-14

09-Feb-14

Activity %
Complete

Schedule %
Complete

100%

100%
0%

B4440

(200)mm Backfilling by excavated materials, compaction.

06-Feb-14

08-Feb-14

0%

0%

B4450

Anti-termite Works

06-Feb-14

08-Feb-14

0%

0%

B4560

(200)mm Backfilling by roadbase, compaction & polythene sheet

08-Feb-14

09-Feb-14

0%

0%

B4730

Waterproofing for for isolated footings and pedestal

05-Feb-14

06-Feb-14

0%

0%

23-Jan-14

26-Jan-14

Site Work Second Stage (Under Canopy Shade))

0%

B4580

Backfilling by excavated materials & compaction

25-Jan-14

25-Jan-14

0%

100%

B4740

Waterproofing for isolated footings and pedestal

23-Jan-14

23-Jan-14

0%

100%

B4780

Anti-termite Works

0%

100%

Subrstructure Works
Footing Works
Footings First Stage (Under Steel Colunms)

26-Jan-14

26-Jan-14

67

06-Jan-14

22-Mar-14

25-Jan-14

0%

20

06-Jan-14

18-Jan-14

25-Jan-14

0%

20

06-Jan-14

13-Jan-14

25-Jan-14

0%

25-Jan-14

B3610

PCC for Isolated footing

06-Jan-14

06-Jan-14

B4330

Steel work for Isolated footing

07-Jan-14

B4340

Formwork for Isolated footing

09-Jan-14

B4350

Casting Concrete for Isolated footing

B4750

Waterproofing for PCC

Footing Seond Stage (Under Canopy Shade)

25-Jan-14

100%

100%

09-Jan-14

0%

100%

11-Jan-14

0%

100%

13-Jan-14

13-Jan-14

0%

100%

06-Jan-14

07-Jan-14

26-Jan-14

100%

100%

17

13-Jan-14

18-Jan-14

25-Jan-14
25-Jan-14

26-Jan-14

0%

B4360

PCC for Isolated Footings

13-Jan-14

14-Jan-14

100%

100%

B4370

Steel work for Isolated Footings

14-Jan-14

15-Jan-14

0%

100%

B4380

Formwork for Isolated Footings

16-Jan-14

16-Jan-14

0%

100%

B4390

Casting Concrete for Isolated Footings

18-Jan-14

18-Jan-14

0%

100%

B4430

Approval of Canopy Super Structure Drawings

13-Jan-14

0%

100%

B4770

Waterproofing for PCC

15-Jan-14

16-Jan-14

0%

100%

11

09-Jan-14

15-Jan-14

Footing Third Stage (Under Container)

25-Jan-14

0%

B4850

PCC for Isolated Footings

11-Jan-14

11-Jan-14

0%

100%

B4860

Steel work for Isolated Footings

12-Jan-14

12-Jan-14

0%

100%

B4880

Formwork for Isolated Footings

13-Jan-14

14-Jan-14

0%

100%

B4890

Casting Concrete for Isolated Footings

14-Jan-14

15-Jan-14

0%

100%

B4840

Approval of Container Super Structure Drawings

09-Jan-14

0%

100%

B4870

Waterproofing for PCC

13-Jan-14

13-Jan-14

0%

100%

12

13-Jan-14

05-Feb-14

0%

10

13-Jan-14

05-Feb-14

0%

Pedestal Works
Pedestal First Stage (Under Steel Colunms)
B4810

(75)mm Mass concrete

04-Feb-14

05-Feb-14

0%

0%

B4400

Steel work for Pedestal

13-Jan-14

15-Jan-14

0%

100%

B4410

Formwork for Pedestal

15-Jan-14

16-Jan-14

0%

100%

B4420

Casting Concrete for Pedestal

15-Jan-14

16-Jan-14

0%

100%

19-Jan-14

20-Jan-14

Pedestal Second Stage (Under Canopy Shade)

0%

B4530

Steel work for Pedestal

19-Jan-14

19-Jan-14

0%

100%

B4540

Formwork for Pedestal

20-Jan-14

20-Jan-14

0%

100%

B4550

Casting Concrete for Pedestal

20-Jan-14

20-Jan-14

0%

100%

15-Jan-14

16-Jan-14

B4900

Steel work for Pedestal

15-Jan-14

16-Jan-14

0%

100%

B4910

Formwork for Pedestal

16-Jan-14

16-Jan-14

0%

100%

B4920

Casting Concrete for Pedestal

16-Jan-14

16-Jan-14

0%

100%

Pedestal Third Stage (Under Container)

0%

34

09-Feb-14

22-Mar-14

B4460

PCC for Ground Beams (A-E) and Ground Slab

09-Feb-14

10-Feb-14

0%

0%

B4470

Steel work for Ground Beams (A-E), Embedded Plates and (Groun...

18-Feb-14

25-Feb-14

0%

0%

B4480

Formwork for Ground Beams (A-E) and (Ground Slab-1st layer)

25-Feb-14

04-Mar-14

0%

0%

B4490

Casting Concrete for Ground Beams (A-E) and (Ground Slab-1st l...

04-Mar-14

05-Mar-14

0%

0%

B4500

BRC Mesh for the Ground Slab- 2nd layer and embeded plates

06-Mar-14

13-Mar-14

0%

0%

B4510

Concrete casting for Ground Slab-2nd layer

20-Mar-14

22-Mar-14

0%

0%

B4520

(50)mm Rigid Floor Insulation

05-Mar-14

05-Mar-14

0%

0%

B4760

Waterproofing for PCC for Ground Beams (A-E) and ground slab

10-Feb-14

10-Feb-14

0%

0%

B4790

Formwork for Ground Slab-2nd layer

0%

0%

Ground Slab

Superstructure Works
Steel Structure Works

0%

13-Mar-14

20-Mar-14

107

20-Jan-14

20-May-14

0%

75

30-Jan-14

23-Apr-14

0%

B4210

Steel structure - Steel Columns works

30-Jan-14

04-Feb-14

0%

0%

B4570

Steel structure -Steel Tie Beams Works

22-Mar-14

23-Mar-14

0%

0%

B4800

Steel Sheet @ Roof

0%

0%

Canopy Shade Works

17-Apr-14

23-Apr-14

10

20-Jan-14

30-Jan-14

0%

B4820

Canopy Shade Structure balance work

27-Jan-14

30-Jan-14

0%

93.75%

B4700

Canopy Shade Structure Colunms

20-Jan-14

23-Jan-14

0%

100%

21

06-Mar-14

27-Mar-14

Container Works

14/16

OD

Date
24-Oct-13
10-Jul-14

0%

Revision
Project Start Date
Project Finish Date

Checked

Approved

Al Wasl Box Park


Activity ID

Activity Name

OD

BL1 Start

BL1 Finish

Actual Start

Actual Finish

Activity %
Complete

Schedule %
Complete

B4190

Placing of the containers for the ground level

06-Mar-14

11-Mar-14

0%

0%

B4200

Placing of the containers for the first and roof level

23-Mar-14

27-Mar-14

0%

0%

B4930

Hardly Cladding

23-Mar-14

27-Mar-14

0%

0%

29-Mar-14

06-Apr-14

0%

29-Mar-14

06-Apr-14

0%

Concrete Works
Concrete Works @ Container Roof Level
B4590

Steel work for the roof slab

01-Apr-14

03-Apr-14

0%

0%

B4600

Formwork for the roof slab

29-Mar-14

31-Mar-14

0%

0%

B4610

Casting concrete for the roof slab

05-Apr-14

06-Apr-14

0%

0%

06-Apr-14

09-Apr-14

Thermal & Insulation Works


B4220

Thermal insulations

Roofing Works
Roofing Works for Roof Container

0%

06-Apr-14

09-Apr-14

26

23-Mar-14

17-Apr-14

0%

0%
0%

09-Apr-14

17-Apr-14

0%

B4250

Light weight screed

09-Apr-14

10-Apr-14

0%

0%

B4620

Gravel

17-Apr-14

17-Apr-14

0%

0%

B4630

Waterproof memebrane

16-Apr-14

16-Apr-14

0%

0%

B4640

Glass Foam Insulation

14-Apr-14

16-Apr-14

0%

0%

B4650

Bitumen waterproofing

12-Apr-14

14-Apr-14

0%

0%

23-Mar-14

30-Mar-14

Roofing Works for Ground Container

0%

B4660

WBP plywood backing

23-Mar-14

24-Mar-14

0%

0%

B4670

Roof Finishes

27-Mar-14

30-Mar-14

0%

0%

B4680

Waterproof membrane

27-Mar-14

27-Mar-14

0%

0%

B4690

Insulation

25-Mar-14

26-Mar-14

0%

0%

52

30-Mar-14

20-May-14

Facade Works

0%

B4230

Fixing C channel on the containers level 1 and 2

09-Apr-14

13-Apr-14

0%

0%

B4240

Aluminium Louver Panel & Container Panel Facade Finish

17

13-Apr-14

30-Apr-14

0%

0%

B4270

Glazing works

16-Apr-14

23-Apr-14

0%

0%

B4710

Terracotta Panel Finish & Colunms Compressing Paint Finish

15

29-Apr-14

13-May-14

0%

0%

B4830

Alminium, Steel & Rolling Shutter Doors

24-Apr-14

29-Apr-14

0%

0%

B4720

Demontable Metal Screen Fixing

30-Mar-14

02-Apr-14

0%

0%

B4940

Bitumen, Aluminium & steel cladding, Pergola and Canopy

14-May-14

20-May-14

0%

0%

09-Apr-14

14-Apr-14

0%

09-Apr-14

14-Apr-14

0%

Finishes
Internal Finishes
B4260

Screed Floor finishes

MEP Works
B4280

MEP Works & External Lighting

Facility Finish Date

09-Apr-14

14-Apr-14

91

18-Feb-14

20-May-14

91

18-Feb-14

20-May-14

10

21-May-14

31-May-14

B4290

Facility finish date

B4960

Testing and Commissioning Works

B4970

Handingover to Tenant

21-May-14

0%

0%
0%

0%

0%
0%

29-May-14

0%

0%

29-May-14

0%

0%

31-May-14

0%

0%

137

09-Jan-14

26-May-14

09-Jan-14

137

09-Jan-14

26-May-14

09-Jan-14

135

09-Jan-14

24-May-14

135

09-Jan-14

24-May-14

131

09-Jan-14

20-May-14

19-Jan-14

131

09-Jan-14

20-May-14

19-Jan-14

Plot M2

158

25-Jan-14

01-Jul-14

0%

Design

25-Jan-14

25-Jan-14

0%

FC-01
A7560

FC-01 Building Works

FC-03
A7570

FC-03 Building Works

FC-04
A7580

FC-04 Building Works

0%
5%

15.33%
0%

0%

15.56%
0%

3%

16.03%

o1030

FC-01 Received Design Drawings from Consultant

25-Jan-14

0%

100%

o1040

FC-02 Received Design Drawings from Consultant

25-Jan-14

0%

100%

o1150

FC-03 Received Design Drawings from Consultant

25-Jan-14

0%

100%

158

25-Jan-14

01-Jul-14

Building Works

0%

o1190

FC-01 Building Works

158

25-Jan-14

01-Jul-14

0%

3.64%

o1200

FC-02 Building Works

154

25-Jan-14

26-Jun-14

0%

3.73%

o1210

FC-03 Building Works

148

25-Jan-14

21-Jun-14

0%

3.89%

Plot M3

126

01-Feb-14

05-Jun-14

20-Jan-14

Design

01-Feb-14

01-Feb-14

20-Jan-14

01-Feb-14

o1050

FC-01 Received Design Drawings from Consultant

o1060

FC-02 Received Design Drawings from Consultant

Building Works

0%
20-Jan-14

0%

20-Jan-14

100%

0%

20-Jan-14

100%

0%

01-Feb-14

126

01-Feb-14

05-Jun-14

26-Jan-14

0%

o1220

FC-01 Building Works

126

01-Feb-14

05-Jun-14

26-Jan-14

3%

0%

o1230

FC-02 Building Works

120

01-Feb-14

31-May-14

26-Jan-14

3%

0%

137

15-Feb-14

01-Jul-14
15-Feb-14

Plot M5

0%

15-Feb-14

o1070

FC-01 Received Design Drawings from Consultant

15-Feb-14

0%

0%

o1080

FC-02 Received Design Drawings from Consultant

15-Feb-14

0%

0%

Design

15/16

Date
24-Oct-13
10-Jul-14

0%

Revision
Project Start Date
Project Finish Date

Checked

Approved

Al Wasl Box Park


Activity ID
o1160

Activity Name
FC-03 Received Design Drawings from Consultant

Building Works

OD

BL1 Start

BL1 Finish

15-Feb-14

137

15-Feb-14

01-Jul-14

Actual Start

Actual Finish

Activity %
Complete

Schedule %
Complete

0%

0%
0%

o1250

FC-01 Building Works

137

15-Feb-14

01-Jul-14

0%

0%

o1260

FC-02 Building Works

124

15-Feb-14

18-Jun-14

0%

0%

o1270

FC-03 Building Works

131

15-Feb-14

25-Jun-14

0%

0%

Plot M6

129

25-Feb-14

03-Jul-14

0%

Design

25-Feb-14

25-Feb-14

0%

o1090

FC-01 Received Design Drawings from Consultant

25-Feb-14

0%

0%

o1100

FC-02 Received Design Drawings from Consultant

25-Feb-14

0%

0%

129

25-Feb-14

03-Jul-14

Building Works

0%

o1280

FC-01 Building Works

129

25-Feb-14

03-Jul-14

0%

0%

o1290

FC-02 Building Works

124

25-Feb-14

28-Jun-14

0%

0%

Plot M7

124

04-Mar-14

05-Jul-14

0%

Design

04-Mar-14

04-Mar-14

0%

o1110

FC-01 Received Design Drawings from Consultant

04-Mar-14

0%

0%

o1120

FC-02 Received Design Drawings from Consultant

04-Mar-14

0%

0%

124

04-Mar-14

05-Jul-14

o1310

FC-01 Building Works

124

04-Mar-14

05-Jul-14

0%

0%

o1320

FC-02 Building Works

121

04-Mar-14

02-Jul-14

0%

0%

Plot M8

126

08-Mar-14

10-Jul-14

0%

Design

08-Mar-14

08-Mar-14

0%

Building Works

0%

o1130

FC-01 Received Design Drawings from Consultant

08-Mar-14

0%

0%

o1140

FC-02 Received Design Drawings from Consultant

08-Mar-14

0%

0%

126

08-Mar-14

10-Jul-14

Building Works

0%

o1340

FC-01 Building Works

126

08-Mar-14

10-Jul-14

0%

0%

o1350

FC-02 Building Works

120

08-Mar-14

05-Jul-14

0%

0%

164

01-Feb-14

09-Jul-14

o1000

Precast Boundary Wall

90

18-Feb-14

19-May-14

0%

0%

o1010

Road Works

90

25-Mar-14

23-Jun-14

0%

0%

o1020

Landscape Works

90

12-Apr-14

09-Jul-14

0%

0%

o1170

Relocate / Protect Exist Services Works

75

01-Feb-14

16-Apr-14

0%

0%

o1180

Reinstall New Services

75

05-Mar-14

19-May-14

0%

0%

External Works

16/16

Date
24-Oct-13
10-Jul-14

0%

Revision
Project Start Date
Project Finish Date

Checked

Approved

You might also like