0% found this document useful (0 votes)
82 views8 pages

Managing Supply Chain Risk

Download as pdf or txt
Download as pdf or txt
Download as pdf or txt
You are on page 1/ 8

Managing Supply Chain Risk

Mark L. Spearman
Factory Physics Inc.
A Risky World
In recent years, companies have begun to realize the severity of the risk facing the entire corporation
by not addressing supply chain risk. Indeed, more than two-thirds of the companies surveyed by
Accenture said they had experienced a supply chain disruption from which they took more than one
week to recover (Manufacturing Business Technology 2006). Furthermore, the study revealed that 73
percent of the executives surveyed had a major disruption in the past five years. Of these, 36
percent took more than one month to recover. Why does it take companies so long to recover?
Why are so many companies susceptible to disruption? Do the new Advanced Planning and
Optimization systems offer any help? I plan to address these and other issues in this article.
There are at least two reasons why modern supply chains are so susceptible to such disruption: (1)
supply chains are not designed with risk in mind and (2) modern planning and scheduling systems
and practices are not robust enough to operate under conditions significantly different from those
for which they are planned.
Last Century Supply Chain Planning
Although MRP, MRP II and even ERP are now so last century, to use my daughters favorite
phrase, it is useful to see what works and what doesnt. The goal of these systems has always been
to reduce inventory, improve customer service, and to reduce cost by increasing the utilization of
expensive equipment and labor. Unfortunately, these systems do not explicitly consider risk and
have ignored key facts regarding the processes they try to control.
The first attempts in this area date back to the 1960s beginning with Material Requirements Planning
(MRP) that provided material plans with no consideration of capacity. This evolved into
Manufacturing Resources Planning (MRP II) which provided some capacity checking modules
around the basic MRP functionality. Interestingly, virtually all ERP systems today (including the
high end offerings of SAP and Oracle) continue to have the same basic MRP calculations as the core
of their production planning offering. Not surprisingly, a recent survey (Burns 2006) showed that
users gave low marks to these high end, typically expensive, ERP/SCM systems for performance in
distribution and manufacturing (averaging 2.5 and 2.6, respectively, out of 4.0). In a survey
performed by Microsoft of mid-sized companies (median revenue of $21 million, average around
$100 million) 27 percent of 229 companies found their ERP/SCM system to be ineffective and 46
percent found it to be only somewhat effective. Only three percent found the system used to be
very effective.
There are two basic problems with these systems: (1) lot sizing is done without consideration of
capacity and (2) planning lead times are assumed to be attributes of the part. The first issue results
in conservative (i.e., large) lot sizes which increase inventory and reduce responsiveness. The second
www.factoryphysics.com Page 2 of 8

issue is similar. Because the planning lead time does not depend on current work in process (WIP)
levels and because being late (resulting in poor customer service) is worse than being early (resulting
in extra inventory), most systems employ pessimistic (i.e., long) lead times. The result, again, is more
inventory and less responsiveness and is especially aggravated when the bill of material is deep.
Efforts to address these problems have gone on for many years. Almost twenty years ago Kanet
(1988) described problems with contemporary planning systems that remain today. Consequently,
most companies do not run their plants using the output of their ERP/SCM systems but, instead,
massage the output using ad hoc spreadsheets.
21
st
Century Supply Chain Planning Problems
Obviously, with this kind of work around there exists an opportunity to sell more sophisticated
software and for some time now there have been numerous offerings. These applications are
typically deterministic simulations of the process that assume the demand, inventory, work in
process, run rates, setup times, etc. are all known and then seek to generate a schedule that is
optimal under some specified criteria. One of the earliest of these that was moderately successful
is the Factory Planner software that has been offered by i2 under various names (e.g., Rhythm)
since 1988. Interestingly, the new offerings by Oracle and SAP appear to be different only in style
and, perhaps, in the level of integration with other data.
Nonetheless, there are at least three problems that prevent the approach of using deterministic
simulation from being effective in managing supply chain risk:
1. The supply chain and plant have inherent randomness that does not allow for the
complete specification of a time for each job with a given labor component at each process center.
Such detailed schedules often quickly become out of date because of the intrinsic variability in the
system. Moreover detailed schedules do not manage risk which involves random events which may
or may not happen. In the past, the disconnect between detailed schedules and the inherent
randomness in all processes has been addressed using ever more detailed models requiring ever
more computer power. This misses the point. Variability and risk are facts of life and are the result
of not only process variation (something that one attempts to control) but also unforeseen events
and variability in demand (things that cannot be controlled). At any rate, the result is the same
regardless of the variability source. Detailed scheduling can only provide a very short term solution
and, in practice, the solution often becomes invalid between the time it is generated and the time
that the schedule is distributed and reviewed as part of production planning meetings.
2. The detailed scheduling system must be re-run often because of the short term nature
of the solution. This becomes cumbersome and time consuming. Moreover, without a method for
determining whether a significant change has occurred, oftentimes the schedule is regenerated in
response to random noise (e.g., a temporary lull in demand) which is then fed back into the system.
Unfortunately, feeding back random noise results in an increase in the variability in the system being
controlled (Sterman 2000). Because of these problems, many companies have turned off their
Advanced Planning and Scheduling systems after spending a great deal of money to install them.
One of our own clients, a biopharmaceutical company, shut down its advanced planning and
optimization module after trying to manage the massive data collection efforts for keeping it fed.
3. It is impossible to find an optimal schedule. The scheduling problems addressed are
mathematically characterized as NP-Hard which means that no algorithm exists that works in
polynomial time to provide an optimal scheduling solution. The practical result is that for realistic
problems faced in modern factories and in the supply chain, there has not been enough time since
the beginning of the universe to find an optimal schedule regardless of the speed of the computer.
Consequently, heuristics must be applied to generate a, hopefully, near optimal schedule. The
effectiveness of these heuristics is typically unknown for a broad range of applications.
The result is that a great deal of computer power is used to create a detailed schedule for a single
instance that will never happen (i.e., the random sample path will never be what is predicted a
priori) and the schedule becomes obsolete as soon as something unanticipated occurs. Effectively,
detailed schedules never reflect current conditions.
The most advanced systems today offer two methods of planning for manufacturing supply chains:
(1) what-if analysis using a deterministic simulation of the supply chain and (2) optimization of
a set of penalties (again, using a deterministic simulation) associated with inventory, on-time
delivery, setups, and wasted capacity.
In addition to the fundamental problems listed above there are two practical problems with this
approach: (1) what-if analysis is tedious and (2) optimizing a penalty function is not intuitive.
The tediousness of what-if analysis comes from all the detail that must be considered. Figure 1
shows the output of a typical APO application. The graph shows the scheduled production on six
machines in one factory along with projected inventory plot of one of the items produced. The
planner can move jobs in the schedule and drill down on other items to view inventory projections.
While this level of integration is impressive, it is not particularly useful especially when there are
hundreds of machines (not to mention labor) to consider along with thousands of individual items,
each with their own demand.
Likewise, the use of penalties to determine an optimal schedule is not intuitive. What should
the penalty be for carrying additional inventory? What is the cost of a late order? What are the
savings generated by reducing the number of setups, particularly if there is no reduction in head
count? What is the cost of having idle machines? Penalties such as these are, at best, an estimate and
the source of endless internal wrangling between production and accounting.
Thus, there is currently a huge gap between what is needed and what is offered. Described below is
the means to combine existing technology with new technology that can address all of these issues
without the tediousness or the complexity of modern APO systems.

Figure 1: Output of APO application showing a production schedule and inventory
www.factoryphysics.com Page 3 of 8

www.factoryphysics.com Page 4 of 8

Factory Physics

Principles and Advanced Supply Chain Solutions


Hopefully, we have begun to realize that the solution to business problems is not always more
information technology! Instead of faster computers and more integration, we need to make a
fundamental change in the way we manage manufacturing supply chains.
Before that, one must understand how manufacturing supply chains work and there is no better way
to do this than to review of some basic Factory Physics principles. These principles describe how
all manufacturing supply chains work beginning with the fact that all manufacturing supply chains
consist of only two essential elements: Demand and Transformation. Without Demand, there
would be no market for our goods. If there was no need for Transformation, those demanding the
goods could find them laying about (e.g. people have demand for air everyday but there is no
business providing that air).
Likewise, in any manufacturing supply chain there are two primitive components: Stocks and
Flows. The Flows represent both the Transformation element (an out flow) and the Demand
element (an in flow). The Stocks provide a means to separate and coordinate these two Flows.
In a perfect world, Transformation would exactly meet Demand. This means that there would be
perfect processes (producing exactly what is needed) and perfect customers (purchasing exactly what
is produced when it is produced). But, because there is variability, this perfect world cannot exist.
Therefore, a Factory Physics Law states that in order to link Transformation and Demand, one or
more buffers are required and the more variability there is the more of a buffer will be needed.
While a Stock is one way to match Demand to Transformation, there are two others: (1) extra time
and (2) extra capacity. Thus, another Factory Physics Law is that there are three and only three
possible buffers to interface between Demand and Transformation: inventory, time, and
capacity. In other words, the Transformation can satisfy Demand in several ways: (1) immediately
from Stock, (2) by making the Demand wait for the product, or (3) by maintaining extra capacity in
order to provide timely production upon demand. Thus, effective risk management is, essentially, a
matter of effective buffer deployment. Determining an optimal portfolio of buffers means determining
how much risk to take on and, given that risk, determining how best to buffer it whether it is extra
inventory, extra time to satisfy the customer, or extra capacity to have available to cover disruptions.
Unfortunately, there is no one answer to this problem. The optimal configuration of risk and
buffers will be very different for different business situations. The aspirin operations of Bayer
Corporation and the computer factory of Dell Corporation have very different configurations.
Bayer is likely to have a considerable amount of inventory with little excess capacity (to keep costs
down). Conversely, Dell has no finished goods inventory and a significant amount of extra installed
capacity. How else could Dell build custom computers in a timely way when there are peaks in
demand at Christmas and at the beginning of the school year? Neither of these situations uses a
significant time buffer but the Moog Corporation, a supplier of custom servo-valves to high-tech and
aerospace customers, requires a time buffer to create a customized product.
It is also important to note that a flexible buffer is less costly than a permanent one. This is why
postponement, the ability to delay committing a common component into the final product until the
last possible moment, is effective in reducing both the inventory and the time buffers. Likewise,
having a flexible capacity buffer such as the make-up shift used by Toyota or temporary workers
that can be called upon when demand is higher than normal, is less costly than employing all the
workers all the time. Furthermore, quoting due dates with variable lead times is more effective than
stating a constant lead time.
www.factoryphysics.com Page 5 of 8

So how do we use this understanding to create a system that can (1) accommodate risk (2) provide a
method for effective planning and control, and (3) does not lose the forest for the trees (while
retaining the ability to see a particular tree if the need arises)? Key to creating such a system is to
replace our thinking of points in time when particular jobs finish at particular stations with a way to
think about the flow of jobs through the system. Smooth and continuous flow has been the essence
of the Toyota production systemthough we are not advocating everyone try and be like Toyota.
Achieving flow does not require that one duplicate what Toyota has done in automotive assembly.
If we can achieve flow, then planning and controlling production become easy. Then, instead of
attempting to schedule hundreds of individual jobs on a Gantt chart or trying to specify artificial
penalties in an APO, a planner would use a few basic measures and controls to manage the flow.
Figure 2 shows a supply chain segment and indicates all three buffers: time (customer lead time
or backorder time), inventory (between transformation and demand), and capacity (anything greater
than demand). The flow in figure 2 is a simple linear flow but it could contain several levels and
many routings. The stock contains either jobs that complete before their due date in the case of
make-to-order or of finished goods inventory in the case of make-to-stock. Coming from the left
are two arrows indicating make-to-order demand and raw materials. These materials would be
supplied by a previous supply chain segment. From the right comes an arrow showing make-to-
stock demand.
We can take this simple framework and create a new and more effective way to manage
manufacturing supply chains. The key to this is to reduce the number of values that must be
monitored as well as control variables in the problem. This means that instead of providing a
detailed schedule indicating where each job is scheduled on a machine during a given time
slice, we determine a set of control variables that will dynamically and automatically
determine the schedule as the system evolves. We call this approach, Dynamic Risk-based
Planning and Scheduling or DRPS. Under DRPS we need only monitor projected inventory and
projected service levels and then control a few key parametersreorder points and/or lead times,
production quantities (lot sizes), installed capacity, make-up capacity, WIP level and the virtual
queue.
A brief reflection on the design of the system will show that if we have optimized the planning
parameters listed above, the entire system will run well so long as projected service and inventory
levels stay within acceptable ranges. Lot sizes have been established that minimize WIP and finished
goods subject to the available capacity. Lead times (and/or re-order points) are set by considering
the tradeoffs between service and inventory levels. Thus, jobs can move through the flow in a first
in system first out (FISFO) order without the need for a detailed schedule. Safety stocks are set
considering the time in the virtual queue plus the time through the flow and with regard to the error
in our forecast. Thus, once these parameters are set (reviewed periodically perhaps once per
month), the planner need only monitor the projected inventory and service levels. The only time
action is required is when these levels exceed set trigger points.

Figure 2: A Make-to-order CONWIP line.
These trigger points take two forms: (1) indicating insufficient capacity and (2) indicating more
capacity than is needed. If the virtual queue grows beyond what is planned for in the lead times,
there is insufficient capacity and so the extra capacity (e.g., overtime, make-up shift, etc.) is
applied. If the virtual queue becomes too low, one can either reduce capacity or pull in some jobs
early. The result is not only a much simpler supply chain to manage but one that can automatically
respond to random changes in demand and supply without the need to reschedule. This ability to
automatically adjust is a tremendous improvement and makes DRPS more effective than the more
complex APO. Table 1 compares Dynamic Risk-based Planning and Scheduling with APO in this
regard.

Situation ERP APO DRPS
Capacity greater than expected. Cannot work ahead of
generated schedule.
Can work ahead up to defined
earliest release dates.
Capacity less than expected. Schedule becomes increasingly
infeasible, orders become late
unless high safety lead time.
Shortfall trigger indicates
need for additional capacity. Do
not need high safety lead time.
Demand greater than expected Shortages unless very high
safety stock
Shortfall trigger indicates need
for additional capacity; no
shortages, minimal safety stock.
Demand less than expected Unneeded orders released;
inventory rises
No unneeded orders released;
inventory stays in planned
range
Table 1: Situational comparison of APO and DRPS
www.factoryphysics.com Page 6 of 8

Once these parameters (reorder points and/or lead times, production quantities (lot sizes), installed
capacity, make-up capacity, WIP level and the virtual queue.) are known, we are ready to implement
the system. Fortunately, we can do this relatively easily using the existing MRP system and a
generalized pull system known as CONWIP.
CONWIP
The CONWIP pull protocol is a method for achieving pull production in a wide range of
production environments (see Spearman, et al., (1990) and Hopp and Spearman (2000)) and is key to
flow management. This mechanism maintains a nearly constant level of WIP that is needed to keep
bottleneck processes busy by starting a new job only when the WIP level has fallen below a given
maximum level. The relation between throughput (output), WIP, and cycle time is seen in figure 3.
The result is predictable cycle times, smoother flow, and higher throughput than would be seen in
an equivalent push (e.g., MRP) system. The CONWIP mechanism also isolates the variability
inherent in demand from disturbing the flow. This is accomplished using the virtual queue. If
demand goes up, WIP does not but the virtual queue does and the projected service levels begin to
fall. Likewise if demand begins to fall, the virtual queue falls but WIP stays constant and projected
inventory levels begin to rise.

Figure 3: WIP, Demand, Throughput, and Cycle Time shown on Factory Physics Inc.s Flow
Optimizer
Using MRP with Pull
First, it is important to note that the plans generated by good old-fashioned MRP can be quite good
if several conditions hold:
1. Average demand does not exceed capacity.
2. Jobs are released using a pull system that prevents WIP explosions.
www.factoryphysics.com Page 7 of 8

www.factoryphysics.com Page 8 of 8

3. Cycle times are short enough to avoid expediting.
4. Safety stock (or safety lead time) are determined considering demand and capacity.
5. Batch sizes are determined considering demand and capacity to ensure minimal WIP and
low inventories.
6. Due dates are checked by considering the characteristics of the pull system and the sequence
of the jobs to be pulled.
If we have designed the system well, these conditions will hold. We use MRP in the usual way but
instead of starting jobs according to MRPs planned order release list, we pull them in using the
CONWIP protocol. The entire release list becomes the virtual queue. Then, knowing the cycle time
of the line and the rate at which jobs are being pulled into the line, we can accurately predict when
each job will complete.
Conclusions
We have seen that neither traditional systems such as MRP nor modern systems like APO
adequately address risk issues. It is also apparent that more IT is not the solution to the problem
without completely rethinking the problem. What we need is a system that is dynamic to avoid
rescheduling, risk-based to accommodate risk factors and randomness, and that links planning and
execution.
The steps to implement are:
1. Use appropriate, risk-based models to optimize MRP planning parameters: lot size, planned lead
times, and safety stock levels.
2. Use MRP to perform netting, BOM explosions, and generate a job release pool.
3. Quote lead times using the position in the virtual queue and cycle time in the CONWIP line.
4. Use a CONWIP system to pull from job release pool into shop.
5. Use FISFO (first-in-system-first-out) for prioritization in the line.
6. Monitor the virtual queue to indicate when extra capacity is needed.
Factory Physics Inc. is the leader in offering software and training to enable Dynamic Risk-Based
Planning and Scheduling. If you'd like to get a benchmark of your organization's performance,
improve on-time delivery and profitability or find out more about the power of Factory Physics
principles and software, email us today at [email protected].
If you would like to speak to someone directly, contact:
In the US and outside Europe:
Ed Pound
Factory Physics, Inc.
+1 (630) 870-1163
Email: [email protected]
In Europe:
Marc Colpaert
Factory Physics Europe
+32 (0)479-784634
Email: [email protected]
FACTORY PHYSICS is a registered trademark of Factory Physics, Inc. All rights reserved.
2007 Factory Physics, Inc. All rights reserved.

You might also like