This document provides a method statement for cable testing and health monitoring at RAS Gas. It outlines the purpose, scope, site planning, test instruments, and work methodology to be used. The methodology includes performing insulation resistance measurements, tan delta measurements on power cables using very low frequency, and time domain reflectometry to locate any cable faults. The testing will assess the overall health of existing low voltage power cables at the site.

Uploaded by

Rakesh Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
349 views13 pages

REV - 3 MS Cable Testing - RG

This document provides a method statement for cable testing and health monitoring at RAS Gas. It outlines the purpose, scope, site planning, test instruments, and work methodology to be used. The methodology includes performing insulation resistance measurements, tan delta measurements on power cables using very low frequency, and time domain reflectometry to locate any cable faults. The testing will assess the overall health of existing low voltage power cables at the site.

Uploaded by

Rakesh Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 13

AYT INTERNATIONAL WLL

[2014]
[Cable Testing And Health
Monitoring]
[PROJECT: RGCP-385-Upgrading Ve!"i#$ Appr!a"%
&$'#e( in )er#%-*+
Building No. 9, Opposite Embassy of Federal Republic of Germany, Bin Omran,
P.O. Box 10161, Doha, Qatar Tel: +974 44660758 Fax: +974 44989886Web: www.aytme.com

Ra' Ga' C!(pan$ Li(i#ed
PROJECT TITLE: RGCP-385 - UPGRADING VELOCITY APPROACH SYSTEM IN BERTH-2

,!" - N!-: AYT./&.012200 AYT In#erna#i!na WLL Re3i'i!n: 23

Page 4 *

METHOD OF STATEMENT FOR CABLE TESTING AND
HEALTH MONITORING AT RAS GAS
BY

AYT INTERNATIONAL WLL
IN
AUGUST 2014


* RE-I&&UE, 5OR TE&TING 01-A6g-01 A!7 Ra7e'% A78er
0 RE-I&&UE, 5OR TE&TING 0*-A6g-01 A!7 Ra7e'% A78er
2 I&&UE, 5OR TE&TING 29-A6g-01 A!7 Ra7e'% A78er
5 I&&UE, 5OR APPROVAL 29-A6g-01 A!7 Ra7e'% A78er
/AR: ,E&CRIPTION ,ATE )Y C;:, APV,
APV, 8$
C%i$!da
A(ana
APV, 8$
RA&GA&
REVISIONS
CLIENT : Ra'Ga' C!(pan$ Li(i#ed
PROJECT: RGCP-385 - UPGRA,ING VELOCITY APPROAC; &Y&TE/ IN )ERT;-*
JO) NO- : RGCP-385
,OC NO-: AYT./&.012200



Ra' Ga' C!(pan$ Li(i#ed
PROJECT TITLE: RGCP-385 - UPGRADING VELOCITY APPROACH SYSTEM IN BERTH-2

,!" - N!-: AYT./&.012200 AYT In#erna#i!na WLL Re3i'i!n: 23

Page 4 3

METHOD OF STATEMENT FOR CABLE TESTING AND
HEALTH MONITORING


Sr. No. Contents Page No.
1.0 Purpose 04
2.0 Scope 04
3.0 Site Planning and Preparations 04
4.0 Test Instruments 05
5.0 Work et!odolog" 0#

5.1 Insulation $esistance easurement 0#
5.2 Tan %elta easurement &' Po(er Ca)le 0*
5.3 Ca)le +ault &ocali,ation-T%$. 10
#.0 Work /0ecution Plan at $as 1as &N1 2ert! 2 11
*.0 Sa3et" 13





Ra' Ga' C!(pan$ Li(i#ed
PROJECT TITLE: RGCP-385 - UPGRADING VELOCITY APPROACH SYSTEM IN BERTH-2

,!" - N!-: AYT./&.012200 AYT In#erna#i!na WLL Re3i'i!n: 23

Page 4 1

1.0 Purpose

The Objective is to carry out Non-Destructive Testing such as the Insulation
Resistance, TDR and Tan Delta Measurement as Diagnostic Test to assess overall
health of existing Low Voltage Power Cables. The insulation of the power cable over a
period of time deteriorates due to external and internal factors. This reduces the
reliability of the cable.

This document describes the method of above mentioned Measurement and the way to
interpret the results and give recommendations.

2.0 Scope

The scope of this document is to define the procedures for Insulation Resistance, TDR
and Tan Delta Measurement
Sr. No. AYT SCOPE OF WORK
CHIYODA SCOPE OF
WORK
1
Complete electrical Testing (IR, TAN
DELTA, AND CABLE FAULT
LOCATION) & Final Report
Submission
Disconnection of cable ends and
tapping of naked ends (Under
RG Maintenance).

3.0 Site Planning and Preparations

The following activities are required on site before performing the Cable Integrity Test;
Arranging the gate pass of required Personnel and Testing Equipments supported by
Chiyoda Almana..
Arranging Safety Induction training, supported by Chiyoda Almana and Ras Gas .
Arranging the PTW, supported by Chiyoda Almana.
Opening of MCC, Panel, JBs and Isolation of existing Power Supply from both
ends, supported by Ras Gas.

Ra' Ga' C!(pan$ Li(i#ed
PROJECT TITLE: RGCP-385 - UPGRADING VELOCITY APPROACH SYSTEM IN BERTH-2

,!" - N!-: AYT./&.012200 AYT In#erna#i!na WLL Re3i'i!n: 23

Page 4 5
Grounding and Termination of existing cable if required, supported by AYT.
Existing Cable Test Report and Results if required, provided by Ras Gas
Securing the area during Testing by Chiyoda Almana/AYT.
Power Supply: 1 Phase, 250V, 5Amp AC to our equipments, supported by
Chiyoda Almana and Ras Gas.
Storage Area for our equipments (area required 1 x 1 m
2
) if the work goes for more
than one day.
Semi-Skilled Technician to be provided to help our engineer to carry out the tests.

4.0 Test Instruments

The following Instruments are needed to conduct the Insulation Resistance, TDR and
Tan Delta Measurement at site:
Sr. No. EQUIPMENTS MAKE SERIAL NO
1 Insulation Tester (MIT 520/2) MEGGER 110111/2845
2 Tan Delta Kit with VLF (HVA28TD) HVDSA G;2*0*-0*)20*
3 Cable Fault Locator (T 905A) KEHUI 2011124699
4 Laptop (2000-2d06SE) HP 5CG3475GM8
5 Multimeter FLUKE 96500117

NOTE: We are going to use Laptop at site. So we need approval from RASGAS regarding this.
Calibration Certificates of Test Equipments to be provided by AYT.









Ra' Ga' C!(pan$ Li(i#ed
PROJECT TITLE: RGCP-385 - UPGRADING VELOCITY APPROACH SYSTEM IN BERTH-2

,!" - N!-: AYT./&.012200 AYT In#erna#i!na WLL Re3i'i!n: 23

Page 4 <
5.0 Work Methodology

5.1 Insulation Resistance Measurement
Prior and after the high voltage withstand test or Tan Delta Measurement; the
cable shall be tested for Insulation Resistance (IR).
For insulation testing, we need to disconnect Cables from panel or equipment
and keep them isolated from power supply.
The cable screen/armour should be earthed during the above measurement.
Cables shall be tested for insulation resistance with an insulation tester (i.e.
Megger) at 500 Volts for 1 minute.
The minimum insulation resistance to earth or between phases shall be 100
meg-ohms.



IR Value Measurement
Applied Voltage Before Tan Delta After Tan Delta
R YBE in G
500 V

Y RBE in G
B RYE in G
RY BE in G
YB RE in G
BR YE in G

Ra' Ga' C!(pan$ Li(i#ed
PROJECT TITLE: RGCP-385 - UPGRADING VELOCITY APPROACH SYSTEM IN BERTH-2

,!" - N!-: AYT./&.012200 AYT In#erna#i!na WLL Re3i'i!n: 23

Page 4 9
5.2 Tan Delta Meas!e"ent #$ LV %#&e! Ca'le

Tan Delta value of the insulation of the cable is a very good indicator of the
health conditions of the cable. The test is a non destructive diagnostic test
using voltage levels up to 1.5 times the conductor to ground voltage". This is
because of the fact that there would less numbers of voltage cycles per time unit.
Normally as per the maintenance practice and recommendations, 1.5 times of Uo
value is to be applied between Phase and Ground.



The Tan measurement has to be made by using Very Low Frequency source at
0.1Hz. Using a VLF AC Hipot, the test voltage is applied to the cable (Phase to
Earth) while the tan delta controller takes measurements. Typically, the applied
test voltage is raised in steps, if the Tan numbers indicate good cable insulation;
the test voltage is raised up to 0.5 to 1.5Uo.

For enhanced results to have a standard or previous test to compare for trending
purposes, Phase to Phase Comparisons or Comparison with Previous reports. The
very first test on a cable yields valuable information about the insulation. Also,
most Tan testing is performed on a comparative basis.

Ra' Ga' C!(pan$ Li(i#ed
PROJECT TITLE: RGCP-385 - UPGRADING VELOCITY APPROACH SYSTEM IN BERTH-2

,!" - N!-: AYT./&.012200 AYT In#erna#i!na WLL Re3i'i!n: 23

Page 4 8
In the absence of existing Ras Gas Cable Test Report /Results all values found
during Testing shall be compare to previous Test results performed by AYT with
same condition of existing Cables (Age of Cables, Cable Size, Manufacturer if
possible, etc).
More on that in the next section, if a cables insulation is perfect then the loss
factor (Tan) will not change as the applied voltage is increased. The capacitance
and loss will be similar with 0.5Uo to 1.5Uo applied to the cable.
If the cable has water tree, contamination, thus changing the capacitive/resistive
nature of the insulation, then the Tan numbers will be higher at higher voltages.
Rather than a flat curve for the loss number versus voltage, the curve will be non
linear. See the below graph,

Test Setup and Connection Diagram:
The below is the Test setup for VLF Tan Measurement with VLF. Follow the
instruction given in the manual of the equipments;


Ra' Ga' C!(pan$ Li(i#ed
PROJECT TITLE: RGCP-385 - UPGRADING VELOCITY APPROACH SYSTEM IN BERTH-2

,!" - N!-: AYT./&.012200 AYT In#erna#i!na WLL Re3i'i!n: 23

Page 4 =
Tan Delta Report Format

Our all equipments are full operated by soft and having inbuilt automatic test
format as like below which will be submitted at site,



Ra' Ga' C!(pan$ Li(i#ed
PROJECT TITLE: RGCP-385 - UPGRADING VELOCITY APPROACH SYSTEM IN BERTH-2

,!" - N!-: AYT./&.012200 AYT In#erna#i!na WLL Re3i'i!n: 23

Page 4 02
5.3 Time Domain Reflectometer
The TDR method is the most established and widely used measuring method for
determination of
The total length of a cable
The location of low resistive cable faults
The location of cable interruptions
The location of joints along the cable
The Time Domain Reflectometer sends a low voltage impulse into the cable
under test. The low voltage impulse (max. 160V) travels through the cable and is
reflected positively at the cable end or at any cable interruption (cable cut). At a
short circuit point this low voltage impulse is reflected negatively.



The Time Domain Reflectometer is measuring the time between release and
return of the low voltage impulse. A change of the impedance in the cable, e.g. a
joint, will be displayed as a laid S. The relevant distances are shown by automatic
cursor settings to the significant locations in the graph.







Ra' Ga' C!(pan$ Li(i#ed
PROJECT TITLE: RGCP-385 - UPGRADING VELOCITY APPROACH SYSTEM IN BERTH-2

,!" - N!-: AYT./&.012200 AYT In#erna#i!na WLL Re3i'i!n: 23

Page 4 00



6.0 Work Execution Plan at Ras Gas LNG Berth 2

Ca'le Deta(ls
Ite" N# Ca'le N# )t* Re"a!+s
1
%,-4,.1,/C00.A,TB
0 %,-4,.1,/C00.A
1 Set CA%STAN MOTOR 1MD2A2
2
%,-4,.1,/C00.B,TB
0 %,-4,.1,/C00.B
1 Set CA%STAN MOTOR 1MD2B2
-
%,-4,.1,/C00.C,TB
0 %,-4,.1,/C00.C
1 Set CA%STAN MOTOR 1MD2C2
4
%,-4,.1,/C00.D,TB
0 %,-4,.1,/C00.D
1 Set CA%STAN MOTOR 1MD2D2
3
%,-4,.1,/C00.E,TB
0 %,-4,.1,/C00.E
1 Set CA%STAN MOTOR 1MD2E2
4
%,-4,.1,/C00.F,TB
0 %,-4,.1,/C00.F
1 Set CA%STAN MOTOR 1BD2A2
.
%,-4,.1,/C00.G,TB
0 %,-4,.1,/C00.G
1 Set CA%STAN MOTOR 1BD2B2
5
%,-4,.1,/C00.H,TB
0 %,-4,.1,/C00.H
1 Set CA%STAN MOTOR 1BD2C2
6 %,-4,7,R-41,-,1 1 Set D(s8la* B#a!9 1.1,Y010,DIS%2








Ra' Ga' C!(pan$ Li(i#ed
PROJECT TITLE: RGCP-385 - UPGRADING VELOCITY APPROACH SYSTEM IN BERTH-2

,!" - N!-: AYT./&.012200 AYT In#erna#i!na WLL Re3i'i!n: 23

Page 4 0*




FROM 413V MCC SWITCHBOARD 1SB,-431 TO TB2 : DATED;
Ite" N# Ca'le N# F!#" T# Ca'le Len<t= Ca'le S(>e
1 %,-4,.1,/C00.A,TB SB,-431 L3,4 .1,/C00.A,TB .10 -C,30
2 %,-4,.1,/C00.B,TB SB,-431 R3,- .1,/C00.B,TB 4.3 -C,30
- %,-4,.1,/C00.C,TB SB,-431 L4,4 .1,/C00.C,TB 4-0 -C,30
4 %,-4,.1,/C00.D,TB SB,-431 R4,- .1,/C00.D,TB 410 -C,30
3 %,-4,.1,/C00.E,TB SB,-431 L3,3 .1,/C00.E,TB 4.0 -C,30
4 %,-4,.1,/C00.F,TB SB,-431 R.,- .1,/C00.F,TB 353 -C,30
. %,-4,.1,/C00.G,TB SB,-431 R4,3 .1,/C00.G,TB 343 -C,30
5 %,-4,.1,/C00.H,TB SB,-431 R3,4 .1,/C00.H,TB 340 -C,30

FROM LOCAL RECE%TACLE %ANEL 1LR%,-412
1 %,-4,7,R-41,-,1
LR%,-41
CIRCUIT,-
7,R-41,-,1 1.3
2C,
141N#te22

FROM CA%STAN MOTOR TB 1.1,/C00.A,TB2 0 STARTER: DATED;

1 %,-4,.1,/C00.A .1,/C00.A,TB .1,/C00.A 10 -C,4 1N#te12
2 %,-4,.1,/C00.B .1,/C00.B,TB .1,/C00.B 10 -C,41N#te12
- %,-4,.1,/C00.C .1,/C00.C,TB .1,/C00.C 10 -C,41N#te12
4 %,-4,.1,/C00.D .1,/C00.D,TB .1,/C00.D 10 -C,41N#te12
3 %,-4,.1,/C00.E .1,/C00.E,TB .1,/C00.E 10 -C,41N#te12
4 %,-4,.1,/C00.F .1,/C00.F,TB .1,/C00.F 10 -C,41N#te12
. %,-4,.1,/C00.G .1,/C00.G,TB .1,/C00.G 10 -C,41N#te12
5 %,-4,.1,/C00.H .1,/C00.H,TB .1,/C00.H 10 -C,41N#te12

Ra' Ga' C!(pan$ Li(i#ed
PROJECT TITLE: RGCP-385 - UPGRADING VELOCITY APPROACH SYSTEM IN BERTH-2

,!" - N!-: AYT./&.012200 AYT In#erna#i!na WLL Re3i'i!n: 23

Page 4 03
Note:
1. Existing Cable Size to be verified at Site by Chiyoda.
2. Existing Cable from LRP-341, Circuit-3 shall be utilized with New Cable
Tag (P-34-J-R341-3-1) & New JB (J-R341-3-1) to be provided.

7.0 Safety
Adherence to the safety is must. Our engineers and Technicians will follow the safety
requirement of the client and also the instruction given in the equipment manual need
to be adhere!!!!!

We expect to have below arrangement on site,
7.1 There are area under test shall be barricaded by mentioning TEST under Process
7.2 Both end of test point shall be Isolated, Protected, Cleaned and proper Clearance
should be provided from the earth/body.
7.3 We need to have solid earth point
7.4 Single phase AC supply (220-250V) with multiple outputs (earth protection of
30mA).
7.5 Earthing Cable and Extension Cable will be arranged by AYT.

Note:-
1. Approval of laptop at the site.
2. Proper Earthing point near testing area.
3. In case of any emergency alarm, work completion period will be affected.
4. Material exit Pass preparation by Chiyoda Almana.