Cost 6
Cost 6
A Tulip
194 0263-78631831040194-03 $03.00 0 1983 Butterworth & Co (Publishers) Ltd Project Management
If the manager is looking at classes of money e.g. OBSERVATIONS ON THE METHOD
wages and materials, then there are two options for
adjusting this factor. Either all of one type of money A result of using this approach in the early days of the
can be studied to the exclusion of all the others, or study is that a cost profile is produced as an output
some sort of weighting factor can be used in determin- rather than as an input item. Naturally, the cost
ing the cost of the job. For example, wage costs may be requirements will vary from period to period. The
considered doubled when compared to materials, using overall shape of the final cost curve will help the
the excuse that wages must be paid but outside manager in setting his own level of cost flow. He may,
suppliers can wait. for example, ignore a peak in one period knowing that
The easier of these options is the former. While the he can use the valley nearby. Normally, computer
most important type of money is being scheduled to the allocation algorithms need the maximum level to be
exclusion of all others, it does have implications for the supplied as a data item and also the rules to be
others as will be seen. It is also a system of ranking that observed when it tries to schedule over this limit.
a manager can be expected to do more easily than Although the smoothing algorithm has been com-
estimate the qualitative weighting between types. puterized in at least two computer programs, it is not
necessary for it to be done in this way. Used manually,
it accelerates the manager’s understanding of his
project by highlighting the sensitive portions. It also
Schedule this task allows him to try alternatives quickly. In one exercise,
The scan of all the tasks will select the best activity to the time required for determining a provisional budget
schedule. The obvious next step is to schedule it in the was cut from two weeks to two days. The benefits of
most favourable time slot. Three sets of data should be this are numerous, but the prime one must be that more
taken into account in this determination. real discussion can take place before a commitment is
made.
l the profile of the cost requirement of the tasks If the manager considers the categories of cost in turn
scheduled so far, using this method, it is only necessary to produce an
l the range between the earliest and latest times of ordered list. The sequence of cost types on this list will
this task, almost certainly not be the same as the sequence of
l the cost requirement of this task. these costs when looked at from the company view-
point. The most important cost should be the one that
When trying this method for the first time, most is necessary to keep the project progressing. It can be
students can intuitively locate the best position within tempting to pick a cost that occurs on one or two tasks
the given time range. This can be stated as the slot that only. In scheduling these tasks, the manager will then
gives the lowest overall profile at this time. A mathe- throw away much of the flexibility that he needs later in
matical statement of this is, however, a little longer. the process.
The earliest and latest times that constrain the Some managers are perturbed by the idea of needing
scheduling of the activity give a finite set of possible a late time for the tasks. The scheduling process uses
start times. The activity is scheduled at each of these that as a boundary but will not necessarily delay tasks
start times in turn. For each of these possibilities, the up to that date. However, the more flexibility is given
requirement for each time period is squared and then to the project by extending the late times, the lower will
summed. The position that gives the lowest sum of be the overall cost profile.
squares is then chosen as the best schedule time for this
activity.
This method of squaring forces the scheduling of new MULTIPROJECT ENVIRONMENT
jobs to avoid peaks of the previously committed cost.
In other words, it is always looking for the valleys in It is sometimes necessary to consider the proposed
order to fill them. project in the light of the currently committed load. For
example, during the sales campaign for a new contract,
it is no good quoting unrealistic dates and costs. An
Adjust times early date would commit the company to a cost rate
greater than it could handle and a late date would upset
Although there may not be a network in the true sense, the client.
there will often be a set of imprecise linkages. The In practice, starting with the costs committed to
activity that has just been scheduled may have implica- other projects, it was found that a very competitive and
tions on the activities yet to be done. For example, if it realistic estimate was supplied to clients by using the
was scheduled at its earliest time, then anything that smoothing process to the new project. The sales team
had to precede it may need its late time adjusting. This can normally supply all the information needed. Even
is not a major task to do quickly with a pencil and the late times are usually obtained early in the
rubber for the set of activities in question. discussions.
Should there be any further activities to schedule, To use the procedure, committed cost is taken as the
these four steps are repeated. If some types of cost starting profile and then the four steps outlined
were ignored and all jobs involving the important cost previously can be done for the proposed project. The
type have been scheduled, then the process can be exercise can be repeated using a number of variations
continued with the next category. In this case, all the on the proposal so that management can evaluate the
tasks that have already been scheduled will be con- best strategy to take in the negotiations. The sales team
sidered as critical in the initial stage of the process. will also have an indication of the implications to the
Internet 80s
*
- the supremely flexible
management system
specific requirements
DATA PROCESSING is specifically tailored to
meet the business and professional interests of
* machine independent - managers of computer installations and company
avoids conversion problems executives who procure computing equipment.
It contains news and features on industry
* integrated planning/financial developments, DP management issues, advances in
modeling capability technology, applications and new products and
services.
* interactive input - prompted
- menu driven
Further details and sample copy can be obtained from:
Christine Mullins
* advanced network plotting -
Butterworth Scientific Limited
interactive graphics - Journals Division,
PO Box 63, Westbury House,
CRD
Bury Street, Guildford, Surrey
GU2 SBH, UK.