This letter from the Florida Department of Environmental Protection warns the U.S. Army Corps of Engineers of possible violations of its environmental permit for the Miami Harbor Phase III Channel Expansion Project. During a site inspection, the DEP observed unpermitted impacts to hardbottom areas and coral reefs beyond the project scope. The letter cites specific permit conditions that the Corps appears to be violating or not complying with, including failing to adequately monitor and report coral stress levels and sediment accumulation, notify the agencies of sediment stress within 24 hours, and conduct a required pre-construction survey of mitigation sites. The DEP requests the Corps take corrective actions to come into compliance with the permit.
This letter from the Florida Department of Environmental Protection warns the U.S. Army Corps of Engineers of possible violations of its environmental permit for the Miami Harbor Phase III Channel Expansion Project. During a site inspection, the DEP observed unpermitted impacts to hardbottom areas and coral reefs beyond the project scope. The letter cites specific permit conditions that the Corps appears to be violating or not complying with, including failing to adequately monitor and report coral stress levels and sediment accumulation, notify the agencies of sediment stress within 24 hours, and conduct a required pre-construction survey of mitigation sites. The DEP requests the Corps take corrective actions to come into compliance with the permit.
This letter from the Florida Department of Environmental Protection warns the U.S. Army Corps of Engineers of possible violations of its environmental permit for the Miami Harbor Phase III Channel Expansion Project. During a site inspection, the DEP observed unpermitted impacts to hardbottom areas and coral reefs beyond the project scope. The letter cites specific permit conditions that the Corps appears to be violating or not complying with, including failing to adequately monitor and report coral stress levels and sediment accumulation, notify the agencies of sediment stress within 24 hours, and conduct a required pre-construction survey of mitigation sites. The DEP requests the Corps take corrective actions to come into compliance with the permit.
This letter from the Florida Department of Environmental Protection warns the U.S. Army Corps of Engineers of possible violations of its environmental permit for the Miami Harbor Phase III Channel Expansion Project. During a site inspection, the DEP observed unpermitted impacts to hardbottom areas and coral reefs beyond the project scope. The letter cites specific permit conditions that the Corps appears to be violating or not complying with, including failing to adequately monitor and report coral stress levels and sediment accumulation, notify the agencies of sediment stress within 24 hours, and conduct a required pre-construction survey of mitigation sites. The DEP requests the Corps take corrective actions to come into compliance with the permit.
Environmental Branch U.S. Army USACE of Engineers J acksonville District 701 San Marco Boulevard J acksonville, FL 32207
RE: WARNING LETTER OF POSSIBLE VIOLATIONS AND NON-COMPLIANCE
Miami Harbor Phase III Federal Channel Expansion Permit No. 0305721-001-BI County: Miami-Dade
Dear Mr. Summa:
The purpose of this Warning Letter is to advise the U.S. Army Corps of Engineers (USACE) of possible violations and non-compliance issues related to Department of Environmental Protection (the Department) Environmental Resource Permit Number 0305721-001-BI (Permit), for the Miami Harbor Phase III Federal Channel Expansion Project (Project).
On J uly 22-23, 2014, Department staff conducted a site inspection of the Project. Please see the Departments Site Inspection Report attached. During this diving inspection, significant impacts to hardbottom beyond those that were permitted were observed. These additional impacts indicate possible violations of Chapter 373 and Chapter 403, Florida Statutes (Fla. Stat.).
Section 373.430(1)(b), Fla. Stat., states that: It shall be a violation of this part, and it shall be prohibited for any person: to fail to obtain any permit required by this part or by rule or regulation adopted thereto, or to violate or fail to comply with any rule, regulation, order, or permit adopted or issued by a water management district, the department, or local government pursuant to their lawful authority under this part.
Section 373.430(2), Fla. Stat., states that: Whoever commits a violation specified in subsection (1) is liable for damage caused and for civil penalties as provided in s. 373.129.
In addition, Section 403.161(1)(b), Fla. Stat., states that: It shall be a violation of this chapter, and it shall be prohibited for any person: to fail to obtain any permit required by this chapter or by rule or regulation, or to violate or fail to comply with any rule, regulation, order, permit, or certification adopted or issued by the department pursuant to its lawful authority.
Section 403.141(1), Fla. Stat., states that: Whoever commits a violation specified in s. 403.161(1) is liable to the state for any damage caused to the air, waters, or property,
Florida Department of Environmental Protection Bob Martinez Center, Room 608 2600 Blair Stone Road, MS 3566 Tallahassee, Florida 32399-2400
RICK SCOTT GOVERNOR
CARLOS LOPEZ-CANTERA LT. GOVERNOR
HERSCHEL T. VINYARD, J R. SECRETARY Eric Summa August 18, 2014 Page 2 of 5
including animal, plant, or aquatic life, of the state and for reasonable costs and expenses of the state in tracing the source of the discharge, in controlling and abating the source and the pollutants, and in restoring the air, waters, and property, including animal, plant, and aquatic life, of the state to their former condition, and furthermore is subject to the judicial imposition of a civil penalty for each offense in an amount of not more than $10,000 per offense. However, the court may receive evidence in mitigation. Each day during any portion of which such violation occurs constitutes a separate offense. Nothing herein shall give the department the right to bring an action on behalf of any private party.
On April 18, 2014, a written Compliance Assistance Offer was issued to the USACE regarding other possible Permit non-compliance issues, as part of an agency investigation preliminary to agency action in accordance with Section 120.57(5), Fla. Stat.
While the Department has been in dialogue with the USACE regarding matters addressed in the Departments Compliance Assistance Offer, a Department review has concluded that possible non-compliance issues are still on-going with this Project.
The USACE appears to remain out of compliance with the following Specific Conditions of the Permit:
Specific Condition 32 a.ii.d, of the Permit provides, in part, that stress expressed above normal by corals and/or octocorals within transects will require an additional survey to outline the area(s) of impact. Impacted areas shall continue to be monitored monthly during the construction, one month post-construction, and two times during next year in order to document results of the impact. Final monitoring results shall document permanent impacts, if any, to be used for estimates of additional mitigation using UMAM.
A Department staff review of the weekly Coral Stress and Sediment Block Monitoring reports submitted through August 7, 2014, and the site inspection conducted by Department staff on J uly 22 and 23, 2014, shows that coral stress at the channel-side compliance sites was significantly greater than coral stress at the reference sites. According to SC 32 a. ii. d., stress expressed above normal by corals and/or octocorals within transects will require an additional survey to outline the area(s) of impact.
The methodology proposed by Great Lakes Dredge and Dock (GLDD) on J uly 31, 2014, to outline the impacted areas is insufficient and does not meet the intent of the Permit. Specifically, GLDD recommended that surveys be "basic in nature, covering a minimal area with just a visual interpretation of impact" along 40-meter transects.
During the recent site inspection by Department staff, impacts to hardbottom resources were observed; these impacts were visually conspicuous through the entire length of the surveyed area (200 meters from the channel edge and continuous beyond that limit). In order to document the full extent of impacts and outline the impacted areas as required by the Permit, transects should extend until impacts can no longer be visually detected, or when sediment Eric Summa August 18, 2014 Page 3 of 5
depths (i.e., recently-accumulated fine sediments) diminish to levels comparable to other areas outside of the influence of the project (i.e., control sites). These transects will likely be significantly longer than 200 meters, as recently observed by Department staff during the site visit. The Department recommends that GLDD use Dr. J ennifer Petersons J uly 9, 2014, guidance for outlining and monitoring the impacted areas, or a similar methodology that is equally prescriptive.
In addition, Specific Condition 32 a. iii. a. 2, of the Permit provides that Measured net sediment accumulation levels at project area sites where corals show decline potentially associated with dredging shall be used to adjust or ground truth the sedimentation average rate of 1.5 mm per day above the reference site accumulation currently proposed as the maximum for the project. Evidence of 1) coral decline (per SC 32.a.ii.d), or 2) sedimentation rate of 1.5 mm per day above the reference site that results in stress as defined in SC 32.a.ii.c defines a significant event; In the case of a significant event, the dredging operation must move to a new location until: 1) effected organisms have recovered (signs of stress are no longer visible) as approved by a biologist, or 2) a determination is made that it is potentially a secondary impact and the protocols in SC 32.a.ii.d for monitoring and additional mitigation , if any, shall be followed.
The weekly Offshore Coral Stress and Sediment Block Monitoring reports have shown the sediment traps and blocks to be ineffective for accurately measuring sediment accumulation at the channel-side monitoring stations. The Department has strongly recommended that sediment traps and blocks be replaced with a more reliable and simpler method to measure sediment accumulation on hardbottom. The methodology proposed by the USACE on August 8, 2014 is insufficient for adequately measuring the extent of sedimentation adjacent to the channel. The USACE proposed taking sediment depth measurements at five intervals along the center transect at each monitoring station, and measuring the sediment depth to the nearest cm. The Department strongly recommends that sediment depth measurements be taken every meter along each transect and the sediment depth measured to the nearest mm.
Specific Condition 32 a.i.d., 4, concerning notification of sediment stress states: Notification of sediment stress will be by phone, fax, or e- mail, and followed by a written report to be submitted within 24 hours to the agencies. Agencies will be notified immediately of the possibility of unacceptably high sediment levels on the reefs (or on the next work day if the indicators are noted on a weekend or holiday).
Staff observed evidence of project-related impacts to the Middle Reef (2 nd
reef) during the site inspection on J uly 23, 2014. Elevated coral stress at Middle and Outer Reef (2 nd and 3 rd reef) monitoring stations has been documented in weekly reports, but the Department was not notified of sediment stress within 24 hours, as required by specific condition 32 a.i.d., 4.
Specific Condition 33 of the Permit provides that A pre-construction survey shall be conducted at the northern mitigation reef site, and the location(s) of any benthic communities identified Eric Summa August 18, 2014 Page 4 of 5
in the survey shall be recorded by DGPS. During reef construction, no material shall be placed within 30 meters of the hardbottom communities. A copy of the survey shall be submitted to the Department prior to engaging in reef mitigation activities
A pre-construction survey identifying the locations of benthic communities was not provided to the Department. As documented by Department staff during the site inspection performed on J uly 22-23, 2014, material was placed within 30 meters, and in more than one location, directly on top of hardbottom communities. During the J uly 24, 2014 meeting with the USACE, the Department requested that the USACE provide a copy of the video survey methodology and the videos that were taken at the artificial reef site prior to construction. The Department has not received this information.
Damaged corals and octocorals should be transplanted as soon as possible to prevent mortality. The extent of the impacts to natural hardbottom in the area of mitigation reef should be surveyed, and the results of this survey should be provided to the Department. The results of this survey shall be evaluated by the Department to determine if additional mitigation is necessary. Department staff are available to provide assistance in the preparation of monitoring and transplantation protocols.
Please provide a response within 14 days of receipt of this Warning Letter. If you have any questions or comments, please contact J im Martinello, Environmental Administrator, in writing via e-mail at [email protected] or at the address provide above, referencing Mail Station 3566. When replying please also copy Charlotte Hand at [email protected] or at the same address above. When writing, please reference the project name and number provided above. If you would like additional information via telephone, please call Ms. Hand at (850) 245-7591.
This is part of an agency investigation, preliminary to agency action in accordance with Section 120.57(5), Fla. Stat. Your assistance in resolving these matters will be appreciated.
Sincerely,
Mark Thomasson, P.E. Director Division of Water Resource Management
Attachment: Site Inspection Report
cc: J im McAdams, USACE Laurel Reichold, USACE Matt Miller, USACE Terri J ordan-Sellers, USACE Russ Zimmerman, GLDD Danielle H. Irwin, DWRM Martin Seeling, DWRM Lainie Edwards, DWRM Eric Summa August 18, 2014 Page 5 of 5
J im Martinello, DWRM Roxane Dow, DWRM J ennifer Peterson, DWRM Kristina May, DWRM J CP Compliance Officer Vladimir Kosmynin, DWRM Brendan Biggs, DWRM J ill Creech, Director, SE District J ack Chisolm, OGC Gareth Leonard, OGC Lisa Gregg, FWC
A Practical Analysis of Sea Breeze Effects on Coastal Areas: (with Implications Associated with Renewable Energy Applications and Environmental Assessments)