0% found this document useful (0 votes)
51 views6 pages

06 13 2014 WMS Weekly Report

its complete work pattern

Uploaded by

Harshit Verma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
51 views6 pages

06 13 2014 WMS Weekly Report

its complete work pattern

Uploaded by

Harshit Verma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

Oracle EBS WMS Implementation

Date: 18 August 2014 Page 1



Document Control Week Off: 9-June-2014

Project Name Oracle R12 WMS Implementation
Document Status Active
Reported Date 13/June/2014
Prepared By Zensar
Version 1.0
Reviewed By Philip Bench/Krishna G/Jacob C

High Level Status

Track Status Comments
Overall On Track
Resources On Track
Issues / Risks On Track, Risk Reservation issue in WMSCRP instance

On Track On Track, Risk Off Track, Significant Risk
Milestone Start Date End Date Status Comment
Project Definition 27-Jan-2014 31-Jan-2014 100 % Completed usage matrix .
Setup & Configuration 03-Feb-2014 21-Feb-2014 100 % Validate onhand receipt transactions interface (81477 rec)
ARFC Design 24-Feb-2014 04-Apr-2014 60 % Functional Design & Setup in progress
ARFC CRP 14-Apr-2014 02-May-2015 100 %
CRP testing completed on WMSTST instance
From 10-Apr-14 to 08-May-14
ARFC Development & IT Testing 17-Mar-2014 11-Jul-2014 60 % Technical development status attached
ARFC SIT 19-May-2014 30-May-2014 05 % Instance available. Transaction being cleared
Retrogression SIT 2-Jun-2014 13-Jun-2014
ARFC Training 09-Jun-2014 11-Jul-2014
ARFC UAT 14-Jul-2014 25-Jul-2014
ARFC Data migration 28-Jul-2014 01-Aug-2014
Modification & Issue Resolution 21-Jul-2014 01-Aug-2014
Cutover 04-Aug-2014 08-Aug-2014
ARFC Go Live 11-Aug-2014 --
Post go live support 11-Aug-2014 5-Sep-2014







Oracle EBS WMS Implementation

Date: 18 August 2014 Page 2


Progress

Current Week
Activities:
Bhaskar Wanjari
1. Development T59A: Shipping : Pre-pack doc (Packing instructions, Battery
labels) for ARFC ( W105).

Harshit Verma
1. MWA development T67: Carton details required for Ship confirm
i.e. value > 0 (Dims) ( W109) .

Praveen Yandagoudar
1. Code Migration to SIT instance .

Tejas Pawar
1. Support to SR 3-9046929981 : Uncosted Material transaction stuck with Error
- Cleared all the pending ,stuck transaction for all organization.
- Closed the SR
.2. Support to SR 3-9056964921 ,PO Receiving Issue
- Worked with Oracle , Investigated the available patches.
- Finalized a patch to resolve this issue,Followup with oracle on call and
received the password to download the patch

3 Analyze the oracle functionality for issue W99 T167: Capture Shipping label and
Packing slip details during LPN Pack & trigger the same reports during the
transaction .



Next Week
Activities:
1. WMS Setup & configuration (WMSTST)
2. WMS Setup (WMSSIT)
3. CRP issue resolution & testing
4. Discuss on conversion plan activities
5. Technical Development activities









Task List :

Smart sheet count: Requirements and issues logged in CRP testing


Category Count Closed
Conversion 4
Setup 7 1
Oracle EBS WMS Implementation

Date: 18 August 2014 Page 3

SR 4 2
Development 9
Testing 6 1
Followup 3
Oracle EBS WMS Implementation

Date: 18 August 2014 Page 4

Technical Development Status:

# Gap # Deliverables MD 050 MD 070 Code
Unit
Testing
Remark
1 W97
To capture serial number during packing i.e. before ship
confirm. To customize the pack page.
100% 100% 100% 90% Waiting for feedback
2 W108
Capture additional serial number at pack for serial controlled
items
100% 100% 90% 90%
MWA Work in Progress for
At Receipt Items
3 W16
Ability to enter weight, dims into system at box level.
Outbound dimensions/weight per outbound box incl type
(pallet/box)
100% 100% 100% 100% Waiting for feedback
4 W57 Ability to prepare Export docs during Pack (last step in Pack) 100% 100% 100% 100% Waiting for feedback
5 W99
Capture Shipping label and Packing slip details during LPN
Pack & trigger the same reports during the transaction
100% 100% 100% 100% Waiting for feedback
6 W72
Capability to prevent Over issue and Under issue of
components
On hold

7 W83 Prevent WIP move if all components are not issues for the job On hold

8 W96
Serial number check before completing job. To scan part serial
number & box serial number, validate then pack
100% 100% 100% 100% Waiting for feedback
9 W103 Receiving : Customization to request labels (Quantity) On hold
10 W105 Shipping : Pre-pack doc (Packing instructions, Battery labels) On hold
11 W95 Marc GT integration On hold
12 Data Migration :- On hand Conversion 100% 100% 100% 100% Done for CRP
13 W109
T67: Carton details required for Ship confirm i.e. value > 0
(Dims). To be profile driven (e.g. by site or by orders like drop
ship)

14 W70
WIP Move Assembly - Provide the capability to default first
operation and Last operation in Mobile handheld

Oracle EBS WMS Implementation

Date: 18 August 2014 Page 5

# Gap # Deliverables MD 050 MD 070 Code
Unit
Testing
Remark
15 W112
T147: MCS, Guad, CTO need to be able to ship by Delivery
(Quick Ship) on serialized (SO issue) product)
25% 75% 90% 50%
1. Modified the code
2. Initial Testing In Progress
16 W110
T135: Move Any LPN page - Receipt Putaway, provide LOV for
suggested drop To Locator where onhand quantity exist

17 W111
T137: Receipt page - Modify sub-I and locator field as
mandatory

18 W113 T138: Misc transaction MWA form need to add reference field
19 W114 T139: Sub-i transfer MWA form need to add reference field
20
T149: Script to update PO receipt routing from Direct to
Standard for DAYTON DC, Trimble Corvallis, Trimble Mexico,
EERSEL &
25% 25% 10% Development In Progress
21
T152: Script update all open Work Orders (sub-inventory
supply, completion) for Dayton DC, Gaud.
25% 25% 10% Development In Progress
22
T153: Script to update locator pick / drop seq for Dayton DC,
MCS, GUAD, CTO & ERFC
25% 75% 50% Development In Progress







Oracle EBS WMS Implementation

Date: 18 August 2014 Page 6


Key Issues

# Key Issues Responsible Date Status
1 474 On hand issue transactions failed. Fixed
124, pending 350
All issue transactions fixed
Jacob Chacko
Bhaskar V
2-21-2014

2-27-2014
Open

Closed
2 WMSCRP inbound Outbound issues
Applied patch to resolve issue
Jacob Chacko 3-25-2014
3-31-2014
Open
Closed
3
WMSCRP instance 185 records stuck due to
cannot relieve reservation. SR # 3-8819256311
Script provided by Oracle. Cleared 35 records
from ARFC. 150 ERFC records stuck, have to
decide if required to clear.
Dinesh Andhare 3-30-2014

4-30-2014
Open

Closed
4 System not generating xml for receipt label
SR # 3-8875341531
Generating XML
Dinesh Andhare 4-18-2014

4-17-2014
Open

Closed


Key Risks

# Key Risks Responsible Date Status
1 Test onhand issue/receipt code in new
instance WMSCRP to mitigate failure risk.
Bhaskar V
Jacob C
28-Feb-2014

Open