PHEONWJ-G-SPE-0101 0 - Structural and Piping Fabrication Quality Control
PHEONWJ-G-SPE-0101 0 - Structural and Piping Fabrication Quality Control
PHEONWJ-G-SPE-0101 0 - Structural and Piping Fabrication Quality Control
Document Number
PHEONWJ GSPE01 01
Document Title
Revision
Page
Date
Revision
PHE ONWJ
Reviewer
PHEONWJGSPE01 01 Rev.0
Page 2 of 1 0
Table of Contents
Table of Contents...........................................................................................................................3
1.
Scope......................................................................................................................................4
2.
References
.............................................................................................................................4
3.
Definition
4.
Abbreviations..........................................................................................................................4
5.
Responsibility
6.
Drawing
7.
Definitions
8.
Control
9.
Inspection
of Terms.................................................................................................................4
.........................................................................................................................4
..................................................................................................................................5
..............................................................................................................................5
System.......................................................................................................................5
11.
PHEONWJGSPE01 01 Rev.0
Page 3 of 1 0
1. Scope
This procedure outlines the actions to be taken by CONTRACTOR and COMPANY in the
inspection of structural, piping and mechanical work. The actual tolerance requirements such
as coating thickness are listed in the project specifications and standards. This procedure is
not meant to supersede the specifications but to provide a framework that will allow timely
2. References
2.1 .
2.2.
Company
Specification
PHEONWJ -G-SPE-0254
PHEONWJ-I-PRC-001 1
Quality Manual
PHEONWJ-S-PRC-0005
PHEONWJ -S-SPE-01 02
PHEONWJ -X-SPE-0001
PHEONWJ -X-SPE-0004
PHEONWJ-X-SPE-0005
International
AISC
AISI
API
ASME
ASTM
AWS
3. Definition of Terms
COMPANY
CONTRACTOR
The party that carries out all or part of the design, engineering,
the CONTRACTOR.
SUPPLIER/VENDOR
4. Abbreviations
AFC
DCS
IHP
NDT
5. Responsibility
Both of CONTRACTOR and COMPANY has the same responsibility for quality control,
inspection at the various hold points does not relieve CONTRACTOR of his obligation under
Page 4 of 1 0
the contract to perform quality control procedures to assure proper performance of the
WORK. Any additional defects discovered after the hold point inspections must be repaired
inspections per the fabrication codes and the terms of the contract.
6. Drawing
The basic documents for carrying out this procedure will be CONTRACTORs shop drawings,
for preparing shop drawings in strict compliance with the contract drawings and good
engineering practice.
Deviations from the contract drawings must be specifically authorized in writing by the
7. Definitions
7.1 .
Item:
7.2.
7.3.
7.4.
Stage 0 Assembly: This is an item that has been either fabricated from stock
materials by cutting or purchased for inclusion in the structure or piping system such
Stage 1 Assembly: This is an item that has been fabricated by connecting together
more than one stage 0 assemblies normally by welding, for example a brace or a
pipe spool.
Stage 2 Assembly: This is an item that has been fabricated by connecting together
more than one assembly at least one of which is stage 1 or stage 2, for example
8. Control System
8.1 .
Stage
CONTRACTOR for each stage 1 assembly. Generally this will be one DCS for each
shop drawing. If more than one stage 1 assembly is fabricated from one shop
etc, of the Parts Used section of the DCS. The remainder of the form is for
8.2.
Stage
assembly. The DCS is essentially the same as for the stage 1 assemblies except
that each item that is a stage 1 or stage 2 assembly must be verified to have a
9.1 .
fabrication.
PHEONWJGSPE01 01 Rev.0
Page 5 of 1 0
Engineer before 04.00 pm each work day of the IHPs that will be reached on the
following work day. The COMPANYs QA/QC Engineer shall assign inspectors to be
Fabrication may not proceed to the next step until the COMPANY Inspector has given
9.2.
Inspection
9.2.1 .
Hold Points
Stage 0 Assemblies
dimensions
of
each
item
per
9.2.1 .1
Inspector shall verify
CONTRACTORs cutting instructions, assembly drawings, or
9.2.1 .2
Inspector shall approve the surface preparation of all items that
2 assembly.
9.2.1 .3
Inspector shall approve the prime coat application of all items that
stage 2 assembly.
9.2.1 .4
Inspector shall approve the top coat application of all items that
stage 2 assembly.
9.2.1 .5
Inspector shall witness and approve the hydrotest of all items
stage 2 assembly.
9.2.2.
9.2.3.
Inspector shall verify that there has been final approval of the DCS of each
stage 1 and stage 2 assembly that will be included as items on the next
stage 2 assembly.
Inspections
9.2.3 .1
Inspector shall approve any surface preparation of the final
9.2.3 .2
Inspector shall approve any prime coat of the final assembly that
assembly.
9.2.3 .3
Inspector shall approve any top coat of the final assembly that is
required after all items have been incorporated into the assembly.
9.2.3 .4
Inspector shall approve the dimensions of the assembly after all
PHEONWJGSPE01 01 Rev.0
Page 6 of 1 0
9.2.4.
Weld Details
9.2.4.1
Inspector shall approve the fit-up of all welds.
9.2.4.2
Inspector shall visually inspect all welds.
9.2.4.3
Inspector shall approve all NDT reports.
9.2.4.4
Inspector shall approve all welding repairs. No repairs will be
the DCS.
9.2.5.
Bolt-up Details
9.2.5.1
Inspector shall approve the fit-up between piping components
prior to the insertion of any flange bolts or tack welding for field
welds.
9.2.5.2
Inspector shall verify that pipe section and weld connection can
deformation indication.
9.2.5.3
Inspector shall verify that each flanged and threaded connection
did not leak during leak testing. This includes instruments and
other connections that were not verified for the hydrotest plus
The DCS
1 0.2. The following documentation will be required to be included with the DCS for it to be
considered completed.
1 0.2.1
The DCS sheet will be typewritten in a format similar to that shown in
Section 1 2
1 0.2.2
CONTRACTORs shop drawing of the assembly covered by the DCS. All
included items in the assembly must be shown in this drawing. All weld
1 0.2.3
Cutting plans or VENDOR drawings for all stage O assemblies.
Where
1 0.2.4
The Mill Certificates for all pipe, plate and structural shapes.
Inspector cannot verify that the particular item actually is covered by the mill
materials, also.
1 0.2.5
The complete and approved DCS package for all stage 1 and stage 2
1 0.2.6
The NDT reports for all welds and weld repairs.
PHEONWJGSPE01 01 Rev.0
Page 7 of 1 0
1 0.3. The COMPANY QA/QC Engineer must sign each DCS prior to its being considered
1 0.3 .1
Every item included in the assembly is listed in the DCS.
1 0.3 .2
No item had undocumented fabrication work such as cutting, welding,
1 0.3 .3
Every applicable hold point inspection has been approved.
1 0.3 .4
All stage 1 or stage 2 assemblies included on the DCS as items have
1 0.3 .5
The welder identified on every weld is properly qualified.
1 0.3 .6
The welding procedure used is applicable to the type of weld.
1 0.3 .7
All outstanding welding repairs are complete and properly corrected.
1 0.3 .8
All the documents listed in 1 0.2 above are included in the package.
1 1 . Documentation Requirement
1 1 .1 .1
1 1 .1 .2
1 1 .1 .3
1 1 .1 .4
1 1 .1 .5
Fabrication Procedures
Assembly Procedure
Records
1 1 .1 .6
Individual Welder Identification Symbol
1 1 .1 .7
All Welder Qualification Certificates inclusive of back-up data
1 1 .1 .8
Weld Identification and Marking Scheme
1 1 .1 .9
All Non Destructive Test Procedures
1 1 .1 .1 0
All Non Destructive Testing Operators Qualification Certificates
1 1 .1 .1 1
Production Weld Test Reports inclusive of NDT Reports
1 1 .1 .1 2
Dimensional Survey Report
1 1 .1 .1 3
Pressure Test/Leak Test Report
1 1 .1 .1 4
Complete set of Document Control Sheet and back-up documents
1 1 .1 .1 5
A complete set of dimensional as built drawings
PHEONWJGSPE01 01 Rev.0
Page 8 of 1 0
1 1 .1 .1 6
Load out procedures and sea fastening arrangement
1 1 .2.
Document
Approval
Approval Timing
Material Control
Procedures
Fabrication Drawings
Fabrication Procedures
Assembly Procedures
Welding Procedures
Specifications together
application
Welding Procedure
Qualification Test
Records
Welding Consumables
Control Procedures
Individual Welder
Identification Symbol
NDT Personnel
Qualification
Certificates
24 hours before
commencing work
work
Welder Qualification
Certificates
24 hours before
commencing work
Document Control
Sheets
Test certificates
for material
for Construction
Weld identification
and Marking Scheme
Painting Procedures
Three copies of each of the above listed documents, shall be submitted to COMPANY
PHEONWJGSPE01 01 Rev.0
Page 9 of 1 0
1 2.
Sample Document Control Sheet
PE
Dcs#:
Item or
Dra wing
Hea t NBR or
Dimension
Surfa ce Prep.
Ta
g
#
or
Qty
Or
Desc
Mech
Test
NBR
Inspection
Inspection
I
Stag e " 0" Assembles
II
Stag e " 1 " & " 2" Assembles
Dcs Nbr
Appl Da te
Surfa ce Prep
Inspection
Prime C oat
Top Coa t
Dimension
F it - up
Weld Nbr.
Weld ed Nbr.
Procedure Nbr.
Visua l Inspection
Inspection
Fit - up
Hydrotest
Lea k- Test
Inspection
App rova l
Inspector :
Chief
Da te:
Proj ect Engineer:
Prime Coa t
Top Coa t
Hydrotest
Inspection
Inspection
Inspection
Repa ir Required
Yes or No
Da te:
Page 1 0 of 1 0