1. The document appears to be an estimate for the construction of a ground floor block at a pharmaceutical college including item-wise quantities, rates and costs.
2. It provides details of excavation and piling works, concreting works including pile caps and foundations, brick masonry for superstructure and basement, finishing works like flooring, plastering, painting etc.
3. The estimate also includes reinforcement, doors, windows, electrical works and provides an abstract of total estimated cost.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100%(1)100% found this document useful (1 vote)
744 views32 pages
Estimate of Building
1. The document appears to be an estimate for the construction of a ground floor block at a pharmaceutical college including item-wise quantities, rates and costs.
2. It provides details of excavation and piling works, concreting works including pile caps and foundations, brick masonry for superstructure and basement, finishing works like flooring, plastering, painting etc.
3. The estimate also includes reinforcement, doors, windows, electrical works and provides an abstract of total estimated cost.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 32
S.
No Description No Length Breadth Deapth Quantity
1 A. 500 MM dia and 5.00 m depth (DUR) 28 28 nos B. 450 MM dia and 5.00 m depth (SUR) 34 34 nos B. 300 MM dia and 3.66 m depth (SUR) 6 6 nos 2 7 2.80 2.80 0.60 32.93 17 2.80 0.80 0.60 22.85 55.78 cum 3 7 2.80 2.80 0.10 5.49 17 2.80 0.80 0.10 3.81 9.30 cum 4 7 2.80 2.80 0.10 5.49 17 2.80 0.80 0.10 3.81 9.30 cum 5 7 2.80 2.80 0.75 41.16 17 2.80 0.80 0.75 28.56 69.72 cum 6 21 4.21 0.45 0.45 17.90 3 4.21 0.23 0.45 1.31 19.21 cum 7 16 3.75 0.23 0.35 4.83 6 7.75 0.23 0.35 3.74 3 3.26 0.23 0.35 0.79 9.36 cum Earth work excavation and depositing on bank with initial and lift in loamy and clayey soils like black cotton soil, red earth and ordinary gravel for piles caps. Filling godavari sand in foundation in layers of 150 mm thick including watering and ramming, campacting with the standard specifications complete for finished item of work under pile caps. Plain cement concrete (1:4:8) mix using 40 mm granite metal from approved quarry, including cost and conveyance of all materials, labour charges, machine mixing, vibrating finishing curing etc., complete for levelling course under pile caps. DETAILED ESTIMATE Proposed G.F construction of Block 4 at Sir CRR Pharmaceutical College, Eluru W.G.Dist,A.P (Rates are as per -----------------------------------------------------) Providing RCC Under reamed piles including boring under reaming to 2.5 times the dia of the bore, tying grills, placing in position and concreting in M20 grade mix using 20 mm size hard blasted granite machine crushed chips, including cost and conveyance of all materials labour charges, machine mixing, laying, compacting, finishing, curing complete but excluding cost of steel and its fabrication charges for piles of various diameters. VRCC M20 Grade mix using 20 mm size blasted granite crusher chips including cost and conveyance of all materials and all operational incidental and labour charges such as centering, machine mixing, laying, vibrating, finishing, curing but excluding cost of steel and its fabrication charges for plinth beams. Ground floor: VRCC M20 grade using 20mm HBG metal including cost and coveyance of all materials and labour charges machine mixing placing concrete in position, vibrating, finishing, curing but excluding cost steel and its fabrication charges for pile caps. VRCC M20 grade mix using 20 mm size blasted granite crusher chips including cost and conveyance of all materials and all operational incidental and labour charges such as centering, machine mixing, laying, vibrating, finishing, curing but excluding cost of steel and its fabrication charges for columns. 8 3 20.45 0.45 0.30 9.10 4 16.85 0.45 0.30 11.60 3 28.65 0.45 0.20 7.74 1 9.75 0.45 0.20 0.88 29.32 cum 9 1 28.65 16.85 482.75 2 11.02 1.80 39.67 Roof Slab 150 mm thick 522.42 sqm 10 16 3.75 0.23 0.85 11.73 6 7.75 0.23 0.85 9.09 3 3.26 0.23 0.85 1.91 22.73cum 11 16 3.75 0.23 3.46 47.75 6 7.75 0.23 3.46 37.00 3 3.26 0.23 3.46 7.78 1 79.34 0.12 1.20 10.95 Deductions Doors D1 1 2.40 2.40 0.23 1.32 D2 2 1.00 2.10 0.23 0.48 D3 2 0.75 2.10 0.23 0.72 Windows 12 1.50 1.50 0.23 6.21 94.75cum 12 32 3.75 3.46 415.20 12 7.75 3.46 321.78 6 3.26 3.46 67.68 2 79.34 1.20 190.42 Deductions Doors D1 1 2.40 2.40 5.76 D2 2 1.00 2.10 4.20 D3 2 0.75 2.10 3.15 Windows 12 1.50 1.50 27.00 954.96sqm 13 Ceiling 1 28.65 16.85 482.75 2 11.02 1.80 39.67 Beams 3 20.45 0.90 55.22 4 16.85 0.90 60.66 3 28.65 0.90 77.36 1 9.75 0.90 8.78 Columns 21 4.21 1.80 159.14 3 4.21 1.36 17.18 900.74sqm Plastering 12mm thick in CM (1:6) including cost conveyance of all materials charges, scaffolding, finishing, curing complete. Beam, Column and ceiling plastering 20mm thick in CM (1:4) including cost conveyance of all materials charges, scaffolding, finishing, curing complete.(over out side brick work) VRCC M20 Grade mix using 20 mm size blasted granite crusher chips including cost and conveyance of all materials and all operational incidental and labour charges such as centering, machine mixing, laying vibrating, finishing, curing but excluding cost of steel and its fabrication charges for roof beams. VRCC M20 Grade mix using 20 mm size blasted granite crusher chips including cost and conveyance of all materials and all operational incidental and labour charges such as centering, machine mixing, laying vibrating, finishing, curing but excluding cost of steel and its fabrication charges Roof slabs. Brick masonary in CM (1:6) using second class bricks including cost and conveyance of all materials from approved quarry and all labour charges, finishing and curing complete for foundation and basement. Brick masonary in CM (1:6) using second class bricks including cost and conveyance of all materials from approved quarry and all labour charges, finishing and curing complete for super structure. 14 1 28.65 16.85 1.10 531.03 2 11.02 1.80 1.10 43.64 574.67 cum 15 Doors D1 1 2.40 2.40 5.76 D2 2 1.00 2.10 4.20 D3 2 0.75 2.10 3.15 13.11 sqm 16 Windows 12 1.50 1.50 27.00 27 sqm 17 1 28.65 16.85 0.10 48.28 2 11.02 1.80 0.10 3.97 52.24 sqm 18 1 28.65 16.85 482.75 2 11.02 1.80 39.67 522.42sqm 19 Doors D1 1 2.25 2.40 2.40 12.96 D2 2 2.25 1.00 2.10 9.45 D3 2 2.25 0.75 2.10 7.09 Windows 12 1.50 1.50 1.50 40.50 70.00sqm 20 1855.70sqm 21 25000kg 22 1 28.65 16.85 482.75 482.75 sqm 954.96+900.74 Flooring with ceramic tiles 1st quality of all shades (Johnson or equivalent) set in CM (1:4) over existing bed concrete including all materials and labour charges. Filling gravel in basement in layers of 150mm thick including watering and ramming, compacting with standard specifications complete for finishing item of work. Supplying and fixing 1st class teak wood fully paneled doors including, all furniture and fittings complete. Supplying and fixing 1st class teak wood fully paneled windows including all furniture and fittings complete and excluding M.S. safety grill. Water Proof Plastering with C.M (1:4) 20 mm thick over Roof Slab. Supplying and fabriation of Tor steel reinforcement including cost and conveyance, cutting rods, tying grills placing in position, including cost of binding wire coplete. Plain Cement concrete (1:4:8) mix using 40mm granite metal form approved quarry, including cost and conveyance of all materials, labour charges machine mixing, vibrating furnishing, curring etc., complete for concrete bed under flooring. Painting doors and windows with two coats of best synthetic enamel paint to approved brand (Berger or equivalent) over a primary coat including cost and conveyance of all materials, all operational and labour charges such as scaffolding, cost brushes etc., complete. White cement 2 coats for walls and ceiling using best quality white cement (Birla or equivalent) including cost and conveyance of all materials, all operational and labour charges such as scaffolding, cost brushes etc., complete. S.No Description Qty Unit Rate Per Amount 1 A. 500 MM dia and 5.00 m depth (DUR) 28.00 nos 16834.92 1No 471378 B. 450 MM dia and 5.00 m depth (SUR) 34.00 nos 11870.58 1No 403600 B. 300 MM dia and 3.66 m depth (SUR) 6.00 nos 4310.21 1No 25861 2 55.78 cum 170.32 1cum 9500 3 9.30 cum 1363.21 1cum 12678 4 9.30 cum 4575.77 1cum 42555 5 69.72 cum 8098.04 1cum 564595 6 19.21 cum 9447.65 1cum 181489 7 9.36 cum 9928.88 1cum 92934 Providing RCC Under reamed piles including boring under reaming to 2.5 times the dia of the bore, tying grills, placing in position and concreting in M20 grade mix using 20 mm size hard blasted granite machine crushed chips, including cost and conveyance of all materials labour charges, machine mixing, laying, compacting, finishing, curing complete but excluding cost of steel and its fabrication charges for piles of various diameters. Earth work excavation and depositing on bank with initial and lift in loamy and clayey soils like black cotton soil, red earth and ordinary gravel for piles caps. Filling godavari sand in foundation in layers of 150 mm thick including watering and ramming, campacting with the standard specifications complete for finished item of work under pile caps. Plain cement concrete (1:4:8) mix using 40 mm granite metal from approved quarry, including cost and conveyance of all materials, labour charges, machine mixing, vibrating finishing curing etc., complete for levelling course under pile caps. ABSTRACT ESTIMATE Proposed G.F construction of Block 4 at Sir CRR Pharmaceutical College, Eluru W.G.Dist,A.P (Rates are as per -----------------------------------------------------) Ground floor: VRCC M20 grade using 20mm HBG metal including cost and coveyance of all materials and labour charges machine mixing placing concrete in position, vibrating, finishing, curing but excluding cost steel and its fabrication charges for pile caps. VRCC M20 grade mix using 20 mm size blasted granite crusher chips including cost and conveyance of all materials and all operational incidental and labour charges such as centering, machine mixing, laying, vibrating, finishing, curing but excluding cost of steel and its fabrication charges for columns. VRCC M20 Grade mix using 20 mm size blasted granite crusher chips including cost and conveyance of all materials and all operational incidental and labour charges such as centering, machine mixing, laying, vibrating, finishing, curing but excluding cost of steel and its fabrication charges for plinth beams. 8 29.32 cum 9075.67 1cum 266099 9 522.42 sqm 1137.89 1sqm 594457 Roof Slab 150 mm thick 10 22.73 cum 4206.09 1cum 95604 11 94.75 cum 4126.74 1cum 391009 12 954.96 sqm 120.53 1sqm 115101 13 900.74 sqm 139.58 1sqm 125725 14 574.67 cum 424.49 1cum 243942 15 13.11 sqm 9051.72 1sqm 118668 16 27.00 sqm 10618.03 1sqm 286687 17 52.24 sqm 4575.77 1sqm 239038 18 522.42 sqm 965.88 1sqm 504595 Supplying and fixing 1st class teak wood fully paneled doors including, all furniture and fittings complete. Brick masonary in CM (1:6) using second class bricks including cost and conveyance of all materials from approved quarry and all labour charges, finishing and curing complete for foundation and basement. Brick masonary in CM (1:8) using second class bricks including cost and conveyance of all materials from approved quarry and all labour charges, finishing and curing complete for super structure. Plastering 12mm thick in CM (1:5) including cost conveyance of all materials charges, scaffolding, finishing, curing complete. Filling gravel in basement in layers of 150mm thick including watering and ramming, compacting with standard specifications complete for finishing item of work. Supplying and fixing 1st class teak wood fully paneled windows including all furniture and fittings complete and excluding M.S. safety grill. Plain Cement concrete (1:4:8) mix using 40mm granite metal form approved quarry, including cost and conveyance of all materials, labour charges machine mixing, vibrating furnishing, curring etc., complete for concrete bed under flooring. VRCC M20 Grade mix using 20 mm size blasted granite crusher chips including cost and conveyance of all materials and all operational incidental and labour charges such as centering, machine mixing, laying vibrating, finishing, curing but excluding cost of steel and its fabrication charges for roof beams. VRCC M20 Grade mix using 20 mm size blasted granite crusher chips including cost and conveyance of all materials and all operational incidental and labour charges such as centering, machine mixing, laying vibrating, finishing, curing but excluding cost of steel and its fabrication charges Roof slabs. Flooring with ceramic tiles 1st quality of all shades (Johnson or equivalent) set in CM (1:8) over existing bed concrete including all materials and labour charges. Beam, Column and ceiling plastering 12mm thick in CM (1:3) including cost conveyance of all materials charges, scaffolding, finishing, curing complete.(over out side brick work) 19 70.00 sqm 136.73 1sqm 9571 20 1855.7 sqm 43.61 1sqm 80927 21 25000.00 kgs 59.75 1kg 1493685 22 482.75 sqm 371.63 1sqm 179404 6549102.00 White cement 2 coats for walls and ceiling using best quality white cement (Birla or equivalent) including cost and conveyance of all materials, all operational and labour charges such as scaffolding, cost brushes etc., complete. Supplying and fabriation of Tor steel reinforcement including cost and conveyance, cutting rods, tying grills placing in position, including cost of binding wire coplete. Water Proof Plastering with C.M (1:3) 20 mm thick over Roof Slab. Painting doors and windows with two coats of best synthetic enamel paint to approved brand (Berger or equivalent) over a primary coat including cost and conveyance of all materials, all operational and labour charges such as scaffolding, cost brushes etc., complete. Sl. No. Index-code Description Unit Quantity 1 2 3 4 5 1 RBR- Excavation for Structures FNDN-1 Ordinary soil Manual Means Upto 3 m depth Unit = cum Taking output = 10 cum a) Labour Mate day 0.00 Mazdoor (Unskilled) day 3.64 Add MA@25% b) Material Sienorage charges Add contractor's profit @14% Rate per 10cum = (a+b+c) Rate per cum = (a+b+c)/10 2 RBR-FNDN-2 Sand filling Unit = cum a) Labour Mate day 0.00 Mazdoor (Unskilled) day 0.31 Add MA@25% b) Material Sand cum 1.05 Sienorage charges for sand cum 1.05 Add contractor's profit @14% Rate per cum = a+b+c+d 3 BLD- Cement Mortar (1 : 3) CSTN-1-4 Unit : 1cum A. MATERIALS: Cement kg. 480.00 Sand (including 5% wastage) cum 1.05 Seigniorage charges for Fine Sand cum 1.05 B. MACHINERY - Nil - C. LABOUR: Man mazdoor for mixing mortar day 0.20 Add MA@25% Grand Total 4 BLD- Cement Mortar (1 : 5) CSTN-1-6 Unit : 1cum A. MATERIALS: Cement kg. 288.00 Sand (including 5% wastage) cum 1.05 DATA SHEET Name of the Work : Repairs and additional accomodation of sub division,QC Sub division&lab at Eluru Estimate Amount Rs. 30.00 Lakhs Earthwork in excavation for structures as per drawing and technical specifications Note : Classifications of Earth Work Specification are as per 302.2.1(a) of MORD and Filling in foundation trenches as per drawing and technical specification Clause 305.3.9 Seigniorage charges for Fine Sand cum 1.05 B. MACHINERY - Nil - C. LABOUR: Man mazdoor for mixing mortar day 0.20 Add MA@25% Grand Total 5 BLD- Cement Mortar (1 : 6) CSTN-1-7 Unit : 1cum A. MATERIALS: Cement kg. 240.00 Sand (including 5% wastage) cum 1.05 Seigniorage charges for Coarse Sand cum 1.05 B. MACHINERY - Nil - C. LABOUR: Man mazdoor for mixing mortar day 0.20 Add MA@25% Grand Total 6 BLD- Cement Mortar (1 : 8) CSTN-1-8 Unit : 1cum A. MATERIALS: Cement kg. 180.00 Sand (including 5% wastage) cum 1.05 Seigniorage charges for Coarse Sand cum 1.05 B. MACHINERY - Nil - C. LABOUR: Man mazdoor for mixing mortar day 0.20 Add MA@25% Grand Total 7 BLD-CSTN-2-5 Unit = 1cum A. MATERIALS: Cement kg 162.00 Coarse aggregate 40 mm cum 0.90 Fine aggregate (Sand) cum 0.45 Seigniorage charges for C.A cum 0.90 Seigniorage charges for F.A cum 0.45 B. MACHINERY Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00 C. LABOUR: Mason 1 st class day 0.10 Mazdoor (unskilled) day 1.39 Water Charges 1% of Labour Add MA@25% Add contractor's profit @14% Rate per cum 8 BLD- R.C.C. M-20 Nominal Mix CSTN-2-13 FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth) Plain Cement concrete (1:4:8) using 40 mm metal with Concrete mixture. All work upto plinth level. RCC M- 20 Nominal mix (Cement:fine aggregate: coarse aggregate) corresponding to A. MATERIALS: 20mm HBG graded metal cum 0.900 Sand cum 0.450 Seigniorage charges for C.A cum 0.90 Seigniorage charges for F.A cum 0.45 Cement Kgs 400.00 B. LABOUR: 1st Class Mason day 0.133 2nd Class Mason day 0.267 Mazdoor (Both Men and Women) day 3.600 Add MA@25% B. MACHINERY Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.000 BASIC COST per 1 cum 9 FOOTINGS BASIC COST per 1 cum cum 1.00 Centering charges cum 1.00 Add contractor's profit @14% Total 10 PEDASTALS BASIC COST per 1 cum cum 1.00 Centering charges cum 1.00 Add contractor's profit @14% Total 11 PLINTH BEAMS BASIC COST per 1 cum cum 1.00 Centering charges cum 1.00 Add contractor's profit @14% Total 12 Augoring and boring of holes in site for Bored cast-in-situ R.C.C. Piles for building foundations in loamy, clayey soils like Black cotton soils and ordinary soils as per IS 2911 - 1980 as per approved designs including all operations, incidental, labour charges, hire charges of machinery, augur bore drill and shell equipment, etc, complete including for all depths and for finished item of work for piles of 500 mm dia for a depth of 5.0m including under-reaming of two bulbs A. MATERIALS : Nil B. LABOUR Mazdoor day 4.733 C) Labour Allowance Add contractor's profit @14% 13 Augoring and boring of holes in site for Bored cast-in-situ R.C.C. Piles for building foundations in loamy, clayey soils like Black cotton soils and ordinary soils as per IS 2911 - 1980 as per approved designs including all operations, incidental, labour charges, hire charges of machinery, augur bore drill and shell equipment, etc, complete including for all depths and for finished item of work for piles of 450 mm dia for a depth of 4.5m including under-reaming of two bulbs A. MATERIALS : Nil B. LABOUR Mazdoor day 4.418 C) Labour Allowance Add contractor's profit @14% 14 Augoring and boring of holes in site for Bored cast-in-situ R.C.C. Piles for building foundations in loamy, clayey soils like Black cotton soils and ordinary soils as per IS 2911 - 1980 as per approved designs including all operations, incidental, labour charges, hire charges of machinery, augur bore drill and shell equipment, etc, complete including for all depths and for finished item of work for piles of 300 mm dia for a depth of 3.5m including under-reaming of two bulbs A. MATERIALS : Nil B. LABOUR Mazdoor day 2.961 C) Labour Allowance Add contractor's profit @14% 15 Supply and placing of the M20 nominal Mix Concrete corresponding to IS 456 with 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site and including seigniorage charges, sales & other taxes on all materials including all operational, incidental and labour charges such as machine mixing, pouring concrete , curing etc., complete but excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402)with minimum cement content as per IS code from standard suppliers approved by the department including tremmy pumping, laying concrete, curing etc. complete but excluding cost of steel and its fabrication charges for finished item of work for BORED CAST-IN-SITU UNDER REAMED PILES including Bore pile stem and under ream bulbs Unit=Cum A. MATERIALS: 20mm HBG graded metal cum 0.900 Sand cum 0.450 Cement Kgs 400.00 B. LABOUR: 1st Class Mason day 0.100 2nd Class Mason day 0.200 Mazdoor (Both Men and Women) day 3.450 Add MA@25% B. MACHINERY Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.000 Water (including for curing) kl 1.200 BASIC COST per 1 cum 16 DUR PILES---500mm dia BASIC COST per 1 No---5.00m depth cum 2.011 Add contractor's profit @14% Total 17 DUR PILES---450mm dia BASIC COST per 1 No---4.50m depth cum 1.360 Add contractor's profit @14% Total 18 DUR PILES---375mm dia BASIC COST per 1 No---3.75m depth cum 0.787 Add contractor's profit @14% Total 19 DUR PILES---300mm dia BASIC COST per 1 No---3.5m depth cum 0.438 Add contractor's profit @14% Total 20 BLD-CSTN-2-13 COLUMNS, LINTELS, WATER TANKS, RCC WALLS IN BUILDINGS A. MATERIALS: 20mm HBG graded metal cum 0.900 Sand cum 0.450 Cement Kgs 400.000 Seigniorage charges for C.A cum 0.90 Seigniorage charges for F.A cum 0.45 B. LABOUR: 1st Class Mason day 0.167 2nd Class Mason day 0.167 Mazdoor (Both Men and Women) day 4.700 Add MA@25% B. MACHINERY Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.000 BASIC COST per 1 cum 21 COLUMNS BASIC COST per 1 cum cum 1.00 Centering charges cum 1.00 Add contractor's profit @14% Total 22 LINTELS IN BUILDINGS BASIC COST per 1 cum cum 1.00 Centering charges cum 1.00 Add contractor's profit @14% Total 23 RCC SLABS, BEAMS A. MATERIALS: 20mm HBG graded metal cum 0.900 Sand cum 0.450 Seigniorage charges for C.A cum 0.90 Seigniorage charges for F.A cum 0.45 Cement Kgs 400.000 B. LABOUR: 1st Class Mason day 0.067 2nd Class Mason day 0.133 Mazdoor (Both Men and Women) day 2.500 Add MA@25% B. MACHINERY Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 0.267 BASIC COST per 1 cum 24 BEAMS BASIC COST per 1 cum cum 1.00 Centering charges cum 1.00 Add contractor's profit @14% Total 25 RCC SLABS 150mm thick BASIC COST per 1 sqm cum 0.130 Centering charges sqm 1.00 Add contractor's profit @14% Total 26 SUNSHADES BASIC COST per 1 rm cum 0.0375 Centering charges 1 rm sqm 0.60 Add contractor's profit @14% Total 27 BLD-CSTN-2-18 Unit = t (a) Material HYSD bars including 5 per cent for overlaps and wastage t 1.05 Binding wire kg 6.00 (b) Labour for cutting, bending, shifting to site, tying and placing in position Blacksmith / Bar bender day 2.00 Mazdoor (Unskilled) day 6.40 Add MA@25% Sundries on Material Add contractor's profit @14% Rate per t = a+b 28 BLD-CSTN-3-1 Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per Brick Masonry in CM (1:8) with Bricks traditional size 23 x 11 x 7 cms 2nd Class for super structure Unit = 1cum A. MATERIALS: Cement kg 36.00 Bricks traditional size 23 x 11 x 7 cms 2nd class Nos 512.00 Fine aggregate (Sand) cum 0.20 Seigniorage charges for F.A cum 0.20 B. LABOUR: Mason 1 st class day 0.24 Mason 2 nd class day 0.56 Mazdoor (unskilled) day 1.89 Add MA@25% Add contractor's profit @14% Total 29 BLD-CSTN-3-1 Unit = 1cum A. MATERIALS: Cement kg 48.00 Bricks traditional size 23 x 11 x 7 cms 2nd class Nos 512.00 Fine aggregate (Sand) cum 0.20 Seigniorage charges for F.A cum 0.20 B. LABOUR: Mason 1 st class day 0.24 Mason 2 nd class day 0.56 Mazdoor (unskilled) day 1.89 Add MA@25% C. SCAFOLDING Access Scafolding charges per sqm (1cum/0.23m thick = 4.35sqm) sqm 4.35 Add contractor's profit @14% Total Labour charges for country wood wrought and put up in large scantling of over 3 metres in length (Schedule Item No 288) Unit = 1 cum Labour : Carpenter day 17.700 Man Mazdoor day 8.800 Sundries including nails, screws etc., LS Add MA@25% Cost per cum 30 BLD-CSTN-11-5 Fully Panelled doors - Internal/External - Moulded panels (Schedule Item No 290) Single Shutter(Internal) 800 x 2000 mm Teak wood cum 0.083 Labour, wrought and putup in position frame&shutter cum 0.083 Add MA@25% Top Tower bolts 150mm long(Aluminium) Nos 1 Bottom Tower bolts 150mm long(Aluminium) Nos 2 Butt hings with screws 100mm long (Aluminium) Nos 4 Brick Masonry in CM (1:6) with Bricks traditional size 23 x 11 x 7 cms 2nd Class for Basement Door handle 125mm long(Aluminium) Nos 1 Door stopper Nos 1 Sundries for hold fasts etc. Add contractor's profit @14% Total for each door Rate per 1 sqm of door area 31 BLD-CSTN-11-21 Windows Panelled (Schedule Item No. 306) 900 x 1200 mm(Double Shutter) Teak wood cum 0.056 Labour, wrought and putup in position frame & shutters cum 0.056 Add MA@25% Top Tower bolts 100mm long(Aluminium) Nos 2 Bottom Tower bolts 100mm long(Aluminium) Nos 2 Butt hings with screws 75mm long (Aluminium) Nos 6 Door handle 75mm long(Aluminium) Nos 2 16mm dia MS bars Kgs 14.50 Deluxe window stay Aluminium Nos 3 Sundries for hold fasts etc. Add contractor's profit @14% Total for each window Rate per 1 sqm of door area 32 BLD-CSTN-7-6 Flooring with Edge-cut rectified ceramic tiles 7.3mm thick Ist quality, set over base coat of cement mortar (1:8), 12 mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste to full depth mixed with pigment of matching shade, including cost of all materials like cement, sand water and tiles etc., complete, including seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of all materials. Unit = 10 sqm A. MATERIALS: Ceramic tiles(Edge cut recified) sqm 10.10 Cement for CM (1:8) for base coat kg. 21.60 Cement for slurry kg. 33.00 White cement kg. 2.00 Sand for CM (1:8) cum 0.12 Seigniorage charges of sand cum 0.12 B. LABOUR Mason 1 st class day 0.96 Mason 2 nd class day 2.24 Mazdoor (unskiled) day 3.30 Add MA@25% Add water charges 1% 1.00% Add contractor's profit @14% Rate for 10 Sqm Basic Rate for 1 Sqm 33 BLD-CSTN-6-1 Unit = 10 sqm A. MATERIALS: Ornamental Plastering with CM (1:3), 12 mm thick including cost and conveyance of all materials and all labour charges etc.complete Cement Mortor (1:3) cum 0.150 B. LABOUR: Mason 1 st class day 0.60 Mazdoor (unskilled) day 0.96 Add MA@25% C. SCAFOLDING Access Scafolding charges sqm 10.00 Add contractor's profit @14% Total per 10 sqm Total per 1 sqm 34 BLD-CSTN-6-3 Plastering with CM (1:5), 12 mm thick including cost and conveyance of all materials and all labour charges etc.complete Unit = 10 sqm A. MATERIALS: Cement Mortor (1:5) cum 0.150 B. LABOUR: Mason 1 st class day 0.60 Mazdoor (unskilled) day 0.96 Add MA@25% C. SCAFOLDING Access Scafolding charges sqm 10.00 Add contractor's profit @14% Grand Total Total per 1 sqm 35 BLD-CSTN-6-3 Plastering with CM (1:5), 20 mm thick including cost and conveyance of all materials and all labour charges etc.complete Unit = 10 sqm A. MATERIALS: Cement Mortor (1:5) cum 0.21 B. LABOUR: Mason 2 nd class day 0.940 Mazdoor (unskiled) day 1.60 Add MA@25% C. SCAFOLDING Access Scafolding charges sqm 10.00 Add contractor's profit @14% Grand Total Total per 1 sqm 36 BLD-CSTN-8-25 Unit = 10 sqm A. MATERIALS: Cement Mortar 1:3 cum 0.21 Water proof compound Lit 2.00 B. LABOUR Mason 1 st class day 0.660 Mason 2 nd class day 1.540 Mazdoor (unskiled) day 3.70 Add MA@25% Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm thick with 1kg of water proof compound per bag of cement laid over roof when it is green including cost of all materials, seigniorage charges, excluding conveyance charges of materials and including all operational, incidental and labour charges for mixing mortar, laying, rendering smooth and thread lining, curing, rounding off junctions of wall and slab etc,, complete for finished item of work Add contractor's profit @14% Total per 10 sqm Total per 1 sqm 37 BLD-CSTN-9-5 Unit: 10 sqm A. MATERIALS : Water based cement primer Gr-I cum / kg 1.20 Paint grade white lime for wash cum / kg 0.80 Gum, conjee water, or prickly pear juice including necessary fire wood B. LABOUR Brick Layers / Painter day 0.063 2nd class painter day 0.147 Mazdoor (unskilled) day 0.32 Sundries including brushes, ladders, etc., 1.00% Add MA@25% Add contractor's profit @14% Total cost for 10 sqm Total per 1 sqm 38 BLD-CSTN-10-6 Painting, Priming Coat on New Wood Work Unit: 10 sqm A. MATERIALS : Wood Primer L 0.700 B. LABOUR Painter--1st Class day 0.210 Painter--2nd Class day 0.490 Add MA@25% Sundries including brushes, soap, putty etc., 1.000% Total cost for 10 sqm 39 BLD-CSTN-10-12 Painting with Synthetic Enamel paints - Two Coats - for New Wood Work A. MATERIALS : Synthetic Enamel paint (at 20 sqm / litre as per British Paints (I) Ltd. Gr-I L 1.200 B. LABOUR Painter--1st Class day 0.360 Painter--2nd Class day 0.840 Add MA@25% Sundries including brushes, soap, putty etc., Total cost for 10 sqm 40 BLD-CSTN-10- 6&12 Painting with Synthetic enamil paint Gr-I two coats over a primary coat of wood primer for new wood work including cost and conveyance of all materlas and all labour charges etc.complete BLD-CSTN-10-6 BLD-CSTN-10-12 Add contractor's profit @14% Total cost for 10 sqm White washing two coats with whiting of approved quality to give an even shade after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials including cost of all materials, labour charges and incidental such as scaffolding, lift charges etc., complete for finished item of work, but excluding conveyance charges of materials 41 RBR-FNDN-2 Filling with gravel for formation of berms to cc road including all labour charges ete complete Gravel filling Unit = cum a) Labour Mate day - Mazdoor (Unskilled) day 0.31 Add MA @ 25% b) Material Gravel cum 1.000 Sienorage Charges cum 1.000 c&d) Overheads & Contractors Profit@ 14% Rate per cum = a+b+c+d Rate Rs. Amount Rs. 6 7 320.00 0.00 280.00 1019.20 254.80 220.00 209.16 1703.16 170.32 350.00 0.00 280.00 86.80 21.70 995.53 1045.30 40.00 42.00 167.41 1363.21 5.80 2784.00 1215.53 1276.30 40.00 42.00 280.00 56.00 14.00 4172.30 5.80 1670.40 1215.53 1276.30 DATA SHEET Name of the Work : Repairs and additional accomodation of sub division,QC Sub division&lab at Eluru Estimate Amount Rs. 30.00 Lakhs Earthwork in excavation for structures as per drawing and technical specifications Note : Classifications of Earth Work Specification are as per 302.2.1(a) of MORD and Filling in foundation trenches as per drawing and technical specification Clause 305.3.9 40.00 42.00 280.00 56.00 14.00 3058.70 5.80 1392.00 1215.53 1276.30 40.00 42.00 280.00 56.00 14.00 2780.30 5.80 1044.00 1215.53 1276.30 40.00 42.00 280.00 56.00 14.00 2432.30 5.80 939.60 1673.42 1506.08 1227.11 552.20 50.00 45.00 40.00 18.00 417.40 417.40 350.00 35.00 280.00 389.20 4.24 107.11 561.94 4575.77 Plain Cement concrete (1:4:8) using 40 mm metal with Concrete mixture. All work upto plinth level. RCC M- 20 Nominal mix (Cement:fine aggregate: coarse aggregate) corresponding to 2036.84 1833.16 1095.53 492.99 50.00 45.00 40.00 18.00 5.80 2320.00 350.00 46.55 320.00 85.44 280.00 1008.00 285.00 417.40 417.40 6551.54 6551.54 6551.54 552.00 552.00 994.50 8098.04 6551.54 6551.54 769.00 769.00 1024.88 8345.42 6551.54 6551.54 2158.00 2158.00 1219.34 9928.88 280.00 1325.24 331.31 231.92 1888.47 280.00 1236.90 309.23 216.46 1762.59 250.00 740.25 185.06 129.54 1054.85 2036.84 1833.16 1095.53 492.99 5.80 2320.00 350.00 35.00 320.00 64.00 280.00 966.00 266.25 417.40 417.40 104.00 124.80 6519.60 6519.60 13110.92 Central 0.306641 1835.53 14946.45 Tappers 1.067109 Pile portion 0.637813 6519.60 8866.66 2.011563 1241.33 10107.99 6519.60 5130.93 718.33 5849.26 6519.60 2855.58 399.78 3255.36 2036.84 1833.16 1095.53 492.99 5.80 2320.00 50.00 45.00 40.00 18.00 350.00 58.45 320.00 53.44 280.00 1316.00 356.97 417.40 417.40 6911.41 6911.41 6911.41 1376.00 1376.00 1160.24 9447.65 6911.41 6911.41 1514.00 1514.00 1179.56 9604.97 2036.84 1833.16 1095.53 492.99 50.00 45.00 40.00 18.00 5.80 2320.00 350.00 23.45 320.00 42.56 280.00 700.00 191.50 417.40 111.45 5778.11 5778.11 5778.11 2183.00 2183.00 1114.56 9075.67 5778.11 751.15 247.00 247.00 139.74 1137.89 5778.11 216.68 262.00 157.20 52.34 426.22 46500.00 48825.00 70.00 420.00 370.00 740.00 280.00 1792.00 633.00 0.00 7337.40 59747.40 Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per Brick Masonry in CM (1:8) with Bricks traditional size 23 x 11 x 7 cms 2nd Class for super structure 5.80 208.80 4237.39 2169.54 1215.53 243.11 40.00 8.00 350.00 84.00 320.00 179.20 280.00 529.20 198.10 506.79 4126.74 5.80 278.40 4237.39 2169.54 1215.53 243.11 40.00 8.00 350.00 84.00 320.00 179.20 280.00 529.20 198.10 0.00 0.00 516.54 4206.09 350.00 6195.00 280.00 2464.00 2164.75 10823.75 127134.50 10552.16 10823.75 898.37 224.59 92.00 92.00 92.00 184.00 106.00 424.00 Brick Masonry in CM (1:6) with Bricks traditional size 23 x 11 x 7 cms 2nd Class for Basement 101.00 101.00 50.00 50.00 178.05 1778.58 14482.75 9051.72 127134.50 7119.53 10823.75 606.13 151.53 76.00 152.00 76.00 152.00 89.00 534.00 60.00 120.00 48.00 696.00 116.00 348.00 180 1408.29 11467.48 10618.03 538.00 5433.80 5.80 125.28 5.80 191.40 30.00 60.00 1347.11 161.65 40.00 4.80 350.00 336.00 320.00 716.80 280.00 924.00 494.20 24.71 1186.17 9658.81 965.88 Ornamental Plastering with CM (1:3), 12 mm thick including cost and conveyance of all materials and all labour charges etc.complete 4172.30 625.85 0.00 350.00 210.00 280.00 268.80 119.70 0.00 0.00 171.41 1395.76 139.58 3058.70 458.81 350.00 210.00 280.00 268.80 119.70 0.00 0.00 148.02 1205.33 120.53 3058.70 642.33 350.00 329.00 280.00 448.00 194.25 0.00 0.00 225.90 1839.48 183.95 4172.30 876.18 92.00 184.00 350.00 231.00 320.00 492.80 280.00 1036.00 439.95 Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 20mm thick with 1kg of water proof compound per bag of cement laid over roof when it is green including cost of all materials, seigniorage charges, excluding conveyance charges of materials and including all operational, incidental and labour charges for mixing mortar, laying, rendering smooth and thread lining, curing, rounding off junctions of wall and slab etc,, complete for finished item of work 456.39 3716.32 371.63 134.00 160.80 20.60 16.48 1.55 400.00 25.20 320.00 47.04 280.00 89.60 1.14 40.75 53.56 436.12 43.61 135.00 94.50 400.00 84.00 320.00 156.80 60.20 3.96 399.46 230.00 276.00 400.00 144.00 320.00 268.80 103.20 7.92 799.92 399.46 799.92 167.91 1367.29 White washing two coats with whiting of approved quality to give an even shade after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials including cost of all materials, labour charges and incidental such as scaffolding, lift charges etc., complete for finished item of work, but excluding conveyance charges of materials 280.00 86.80 21.70 241.86 241.86 22.00 22.00 52.13 424.49 Sl. No. Description of Material Unit Name of the Quarry Lead in KM Conveya nce charges Initial Cost 1 2 3 4 5 6 7 1 Coarse Sand for Concrete 1.00 Cum Vadapalli 73.00 710.53 385.00 2 Coarse Sand for filling 1.00 Cum Vadapalli 73.00 710.53 285.00 3 Coarse Sand for Mortor 1.00 Cum Vadapalli 73.00 710.53 505.00 3 Aggregates 10mm nominal size 1.00 Cum I.Pangidi 76.00 736.84 656.00 4 Aggregates 20mm nominal size 1.00 Cum I.Pangidi 76.00 736.84 984.00 5 Aggregates 40mm nominal size 1.00 Cum I.Pangidi 76.00 736.84 588.00 6 Gravel 1.00 Cum Janampeta 12.00 143.86 98.00 7 Bricks 1000 Nos. Local 6.00 129.39 3707.00 8 Steel 1.00 MT 46500.00 9 Cement 1.00 MT 5800.00 1.Certified that the above leads are correct to the best of my knowledge 2.The above work spot lies within 12 Km from Muncipal Corporation Boundary LEAD STATEMENT Name of the Work : Repairs and additional accomodation of sub division,QC Sub division&lab at Eluru Estimate Amount Rs. 30.00 Lakhs Blasting charges Machine crushing charges Loading& Unloadin g charges Total Amount 8 9 12 0.00 0.00 0.00 1095.53 0.00 0.00 0.00 995.53 0.00 0.00 0.00 1215.53 70.00 164.00 0.00 1626.84 70.00 246.00 0.00 2036.84 70.00 147.00 0.00 1541.84 0.00 0.00 0.00 241.86 0.00 0.00 401.00 4237.39 0.00 0.00 0.00 46500.00 0.00 0.00 0.00 5800.00 LEAD STATEMENT Name of the Work : Repairs and additional accomodation of sub division,QC Sub division&lab at Eluru Estimate Amount Rs. 30.00 Lakhs PROPOSED ESTIMATE Er. GOKALE Proposed G.F construction of Block 4 at Sir CRR Pharmaceutical College, Eluru W.G.Dist,A.P S.No Description of Item 1 Civil works as per abstract estimate : 2 Provision for Electrification : 300000 3 Provision for water supply and sanitary : 200000 4 Provision for Over head tank,Staircase head room etc., : 200000 5 Provision for Strong room etc., : 500000 6 Provision for Earthfilling,outside paving erc., : 500000 7 Provision for railing,RCC Jollys, almarahs etc., : 100000 8 Provision for supervision charges : 200000 9 Provision for Unforeseen items : 200000 Total Estimated Cost Rs Proposed G.F construction of Block 4 at Sir CRR Pharmaceutical College, Amount (Rs) (Rupees -----------------------------------) GENERAL ABSRACT Eluru W.G.Dist,A.P (Rates are as per -----------------------------------------------------) Total Estimated Cost : Rs -------------------------