This document provides guidelines for major developers regarding Dubai Electricity and Water Authority's (DEWA) power supply requirements. It outlines technical requirements that must be submitted to DEWA for planning 400/132kV and 132/22-11kV substations, designing 22-11kV distribution networks, and allocating necessary cables. Requirements include total connected load, substation locations and sizes, cable corridors, load characteristics, and time frames for DEWA to build substations. Submitting the required documents and plans on time is necessary for DEWA to ensure power supply for projects.
This document provides guidelines for major developers regarding Dubai Electricity and Water Authority's (DEWA) power supply requirements. It outlines technical requirements that must be submitted to DEWA for planning 400/132kV and 132/22-11kV substations, designing 22-11kV distribution networks, and allocating necessary cables. Requirements include total connected load, substation locations and sizes, cable corridors, load characteristics, and time frames for DEWA to build substations. Submitting the required documents and plans on time is necessary for DEWA to ensure power supply for projects.
This document provides guidelines for major developers regarding Dubai Electricity and Water Authority's (DEWA) power supply requirements. It outlines technical requirements that must be submitted to DEWA for planning 400/132kV and 132/22-11kV substations, designing 22-11kV distribution networks, and allocating necessary cables. Requirements include total connected load, substation locations and sizes, cable corridors, load characteristics, and time frames for DEWA to build substations. Submitting the required documents and plans on time is necessary for DEWA to ensure power supply for projects.
This document provides guidelines for major developers regarding Dubai Electricity and Water Authority's (DEWA) power supply requirements. It outlines technical requirements that must be submitted to DEWA for planning 400/132kV and 132/22-11kV substations, designing 22-11kV distribution networks, and allocating necessary cables. Requirements include total connected load, substation locations and sizes, cable corridors, load characteristics, and time frames for DEWA to build substations. Submitting the required documents and plans on time is necessary for DEWA to ensure power supply for projects.
Power Supply Guidelines for Major Projects i April 2008 Cont ents 1. Introduction 2. Requirements
2.1 Technical Requirement . 2 2.1.1 Location and layout of the project 2 2.1.2 Nature of the project .. 2 2.1.3 TCL of the project . 2 2.1.4 Power factor . 3 2.1.5 Load Characteristics . 3 2.1.6 Supply Voltage 3 2.1.7 Substation plot sizes .. 4 2.1.8 Location of substation plot 4 2.1.9 Site plan for 132kV substation 5 2.1.10 Corridors . 5 2.1.11 Time frame required for DEWA to build the substation 6 2.1.12 Requirement for 22-11kV Network/Design approval .. 6 2.2 General Requirements . 8
3. Annexures
3.1 List of documents to be submitted ... 10 3.2 Distribution network design requirements and guidelines for 11/ 0.4kV supply .. 11
Dubai Electricity & Water Authority
1 Introduction
Power Supply Guidelines for Major Projects 1 of 12 April 2008 1 Int roduct i on To ensure the availability of power, it is essential that the load projections, the time of power requirements and other factors from all the potential developers are available with DEWA well in advance.
The purpose of this document is as follows: To provide guidelines to all the major developers and the consultants in regard to the DEWAs power supply requirements. To assist the developers and the consultants in understanding the requirements for submissions of project Master Plan documents and to facilitate the project power supply on time.
Dubai Electricity & Water Authority
2 Requirements
Power Supply Guidelines for Major Projects 2 of 12 April 2008 2 Requi rements In order to avail the power supply for any project on time, it is necessary to submit and get approve the technical pre-requisites on time as DEWA require lead-time as indicated in Item No. 11.
2.1 Technical Requirements The technical requirements that are necessary to be submitted to DEWA for planning any 400/132kV and 132/22-11kV DEWA substations, designing the 22-11kV Distribution Network and allocating necessary 22-11kV cables from the 132/22-11kV substations are listed below: 2.1.1 Location and layout of the project Location and project layout shall be shown on Dubai Map.
2.1.2 Nature of the project Residential, Industrial, Commercial, etc to be mentioned.
2.1.3 Total Connected Load of the project & Expected Maximum Demand Total connected load and expected peak demand. Realistic power requirement date. Split up details of the load like, Residential, Commercial, Industrial, Cooling, etc. Detailed plot-wise loads and phasing of the project reflecting respective zones of 132/22-11kV substations. 2.1 Technical Requirements
Dubai Electricity & Water Authority
2 Requirements
Power Supply Guidelines for Major Projects 3 of 12 April 2008 In case ultimate load details are not available, the load requirement up to next 5 years should be submitted. Details of the District Cooling load (size, location and the expected phasing of its commissioning).
2.1.4 Power Factor Power Factor is to be maintained at not less than 0.95 and any capacitor bank installation required at customer end shall be by the customer at his own cost.
2.1.5 Load Characteristics (quality of voltage, harmonics, flickering, dents, etc.) Load at the consumer end should follow generally the European Standard EN 50160. Installation of special equipment and devices if required to maintain the same as per the standards shall be by the consumer at own cost. Voltage drop calculation, harmonic study, fault level calculation, etc., to be submitted by the consumer for any dirty load/ private switchgear.
2.1.6 Supply Voltage 132/22-11kV substation is required for new consumers requesting 20MVA peak or more at the 132kV voltage level. Large loads might require 400/132kV source at a voltage level of 400kV. The project should allocate plots for the required number of substations and associated corridors for necessary overhead lines/cable circuits. 2.1 Technical Requirements
Dubai Electricity & Water Authority
2 Requirements
Power Supply Guidelines for Major Projects 4 of 12 April 2008 11kV shall be the general distribution voltage and additionally 22kV can be considered on selected cases for which prior approval is necessary.
2.1.7 Substation Plot Sizes 400/132kV substation - 200 x 200m. 132/22-11kV substation - 80 x 60m (single storey), 60 x 50m (double storey). 22-11/0.4kV substation - Refer to Distribution Substation Guideline.
2.1.8 Location of Substation Plot 400/132kV Substation location o The 400/132kV substation plot should have access to heavy vehicles. o Enough space/corridors for taking 400kV overhead lines IN/OUT. o Enough space/corridors for taking 132kV cables OUT.
132/22-11kV Substation location o The 132/22-11kV substation plot shall have access from two major roads or one major road and Sikka. o Enough space/corridors for taking 132kV cables IN. o Enough space/corridor for taking out 60 numbers of 11kV outgoing cables or 30 numbers of 22kV cables with proper duct arrangement with maximum 150mm space between the cables. 2.1 Technical Requirements
Dubai Electricity & Water Authority
2 Requirements
Power Supply Guidelines for Major Projects 5 of 12 April 2008 o Location of 132/22-11kV substations should be provided at the load centre and close to district cooling plants if available. o When a project requires more than one 132/22-11kV substation, the feeding zone of each substation shall be specified.
2.1.9 Site Plan for 132/22-11kV Substation Approved site plan /affection plan of the substation plot is required from the competent authority. The developer shall confirm, whether the building permit for the substation building will be issued by Dubai Municipality or some other authority.
2.1.10 Corridors 400 kV overhead lines o 80m wide corridor (double circuit tower line). 132 kV overhead lines o 32m wide corridor (double circuit tower line). 132 kV underground cables o 2.5m for each circuit. 22-11 kV under ground cable o Exclusive 22-11kV corridor of 2.5 3.0 m width to be provided on both sides of the road around the 132/11kV substations. o Cross-section to be provided for each road section, dedicated 22-11kV corridors should be available on both sides of road. 2.1 Technical Requirements
Dubai Electricity & Water Authority
2 Requirements
Power Supply Guidelines for Major Projects 6 of 12 April 2008 o Duct arrangement for each road crossings is to be provided. o In case of 132/11kV substation is away from the road RightofWay (ROW), the party shall provide sufficient corridor from the substation boundary to the road.
2.1.11 Time Frame required for DEWA to build the Substation 400/132kV substation o 40 months 132/22-11kV substation o 30 months o Above time frame is after finalization of load requirements, substation locations, cable corridors and receiving the affection plan of the plot for the substation in the ownership of DEWA. o If the 132/22-11kV substation is required earlier than 30 months by any developer, the construction of the 132/22-11kV substation has to be arranged by developer through a DEWA approved consultant and contractor. The design of the substation shall be as per DEWA standard.
2.1.12 Requirement for 22-11kV Network/Design Approval Latest planning of the development (with both hard & soft copy). Approved 22-11kV Substation location. (Refer to Distribution Substation Guideline for approval of 11kV substations). 2.1 Technical Requirements
Dubai Electricity & Water Authority
2 Requirements
Power Supply Guidelines for Major Projects 7 of 12 April 2008 Total connected load, maximum demand and capacity for individual 22-11kV substation. Realistic power requirement date. Zone-wise/phase-wise load details with respective 132/22- 11kV substations to be provided if the number of 132/22- 11kV substations is two or more. In case of number of 132/22-11kV substations are more, project loads should be allocated to respective 132/22- 11kV substations for effective network design (Phase wise). Also the 132/22-11kV substations need to be planned for commissioning to match the power requirement date of projects. District cooling loads (if any) should be located adjacent to the related 132/22-11kV substation. No source metering is allowed (metering equipment to be arranged in the 22-11kV switchgear room). 22-11kV corridors details for all the roads within the project boundary. No 22-11kV corridors will be accepted under carriageway. Approved cross section of all the roads (with 22-11kV corridor indicated) to be submitted at the time of 22-11kV network design request. Generally, in case of private switchgear, approval for single line diagram should be obtained prior to purchase. All the distribution network requirements and guidelines for 11/0.4kV supply mentioned in Annexure - 1 shall be strictly followed.
2.1 Technical Requirements
Dubai Electricity & Water Authority
2 Requirements
Power Supply Guidelines for Major Projects 8 of 12 April 2008
2.2 General Requirements 1. The developers or their consultants shall submit the documents as listed in Annexure 1 for DEWA review to System Planning Department:
Addressed to: Dr. Awad Ibrahim Senior Manager- System Planning Dubai Electricity and Water Authority P O Box 564, Dubai Fax: 04 - 3249206 2. The listed document shall be submitted in three sets of hard copies and 1 set of soft copy. 3. The details as mentioned above shall be submitted well in advance to DEWA and got approved to avoid any delay in starting the project. 4. Once approved, DEWA expects that the developer will adhere to the plan and any minor changes in the project plan, changes in phasing, etc. shall be informed to DEWA in time and got approved. Changes on works during the execution stage shall not be entertained. 5. Any power supply requirement for the project shall be from the 132/22-11kV substation built for the project. The developer shall phase the developments and accordingly the power requirements matching the commissioning schedule of the 132/22-11kV substation built for the project. 6. During the progress of the Project, bi-annual updated information shall be submitted by the party which shall include: i. Energized load details till date. 2.2 General Requirements
Dubai Electricity & Water Authority
2 Requirements
Power Supply Guidelines for Major Projects 9 of 12 April 2008 ii. 22-11kV substation approvals under process (not energized). iii. HV Building NOC load applied (not yet submitted for 22-11kV substations approval) less than or more than 5MW. iv. The developer shall issue confirmation on the individual partys loads (who had applied for HV Building NOC) as a part of their Master Plan in terms of magnitude and time. Load under design/approval but not approved for HV building NOC including the load of project shall be as per the agreement already signed between party and developer. v. The update information shall be submitted by the party in area maps indicating plot numbers, power requirement dates and comparison with the original information received as per the approved Master Plan. 7. DEWA will not be responsible for any delay in commissioning due to any change/ revision of loads, which might result in re-design of 22- 11kV cable circuits. 8. For processing the HV NOC applications for more than 5MW for any major project, the developer shall confirm the load figures indicated in NOC application same as that in the approved project Master Plan.
2.2 General Requirements
Dubai Electricity & Water Authority
3 Annexures
Power Supply Guidelines for Major Projects 10 of 12 April 2008 3 Annexures 3.1 Annexure 1 List of documents to be submitted
Sr. No. Documents Remarks
1
Key Plan showing the location and layout of the project in Dubai Map
2
Power requirements in terms of Total connected load and expected Peak Demand.
3
Phasing
4
Nature of Load
5
Details of District Cooling Loads (location / capacity, power requirement date etc)
6
Plot-wise loads and power requirement date
Excel sheet and marked in drawing
7
Locations of proposed 132/22-11kV substation
8
Locations of proposed 400/132kV substation
9
400kV corridors details within the project area
10
132kV corridors details with detailed road cross- sections
11
22-11kV corridors details with detailed road cross- sections
12
22-11kV ducts arrangements
The above documents shall be submitted in form of 3 sets of Hard Copies + 1 Digital Copy
3.1 Annexure 1
Dubai Electricity & Water Authority
3 Annexures
Power Supply Guidelines for Major Projects 11 of 12 April 2008 3.2 Annexure 2
Distribution Network Design requirements and Guidelines for 11/0.4kV Supply In line with the DEWAs power distribution network design, the following guidelines shall be followed strictly: 1. Ring Supply consisting of two feeders (two-feed ring) is mainly granted for power supply as normal feeding arrangement. Three feed ring arrangement may be accepted for cases where all the MV switchgears/RMU\s are installed in one location to ensure the specific supply reliability. 2. For reliable power supply, N-1 criterion is considered. Hence, in case of power failure in one of the feeders, the other feeder should be capable to meet the whole demand until the repair work is completed. 3. DEWAs standard 22-11kV cable size is 3C, 240sq.mm, XLPE Copper or Aluminium. 4. The maximum two feed ring summer capacity of 320A (for copper cables) normally should be divided equally between the feeders. For each copper feeder maximum sustained load should not exceed 160A under normal operating conditions. 5. The maximum two feed ring summer capacity of 280A (for Aluminium cables) normally should be divided equally between the feeders. For each aluminium feeder maximum sustained load should not exceed 140A under normal operating conditions. 6. For bulk loads such as furnace or district cooling loads requiring direct HV supply (private equipment), space for metering units at partys premises/substation to be considered. Necessary documents, drawings, single line diagram shall be submitted for DEWAs comments and approvals at design stage. 3.2 Annexure 2
Dubai Electricity & Water Authority
3 Annexures
Power Supply Guidelines for Major Projects 12 of 12 April 2008 7. Single unit load demand shall not exceed the maximum sustained current of DEWAs 22-11kV cable feeder, which is 160A. Hence the single unit load is limited to 160A (2.7MW). 8. Voltage drop shall not exceed 5% during normal operation at medium voltage level. For HV motors operating at 3.3 kV, 6.6 kV, 22 kV, 11 kV voltage level, voltage dip calculations during the motor starting must be prepared by the consumer along with motor specifications, starting characteristics, drawings, single line diagram etc for DEWAs comments and approval at the design stage. 9. For loads that may inject harmonics to DEWAs network, harmonic study shall be prepared by the party and approved by DEWA at the design stage. 10. Maximum allowable number of cables per trench for copper and aluminium cables is 16 and 12 respectively in maximum two layers (2.5 meter trench width close to 132/22-11kV substation and 2.0 meter elsewhere. 11. Horizontal spacing between cables is 150mm (edge to edge) and vertical spacing between cables is 100mm (edge to edge). 12. Separate corridor should be allocated for 22-11kV cable laying within partys premises along the road to ensure avoiding crossing between 132kV, 22kV and 11kV cables. 13. Special backfilling to be used for 22kV and 11kV cables with soil resistivity below 1.6 C-m/W. 14. Single Line Diagram shall be submitted for DEWAs comments and approval at the design stage.