4 2006 Dec Q
4 2006 Dec Q
4 2006 Dec Q
Accounting for
Costs
INTERMEDIATE LEVEL
QUESTION PAPER
3 Which of the following is a feature of cost accounting but not of financial accounting?
A Control accounts
B Cost classification
C Cost units
D Periodic stocktaking
4 Which of the following factors may affect the choice of computer output medium?
(i) Whether a hard copy of the output is required
(ii) Whether the output requires further computer processing
(iii) Whether a large volume of output is to be used for reference purposes
A (i) and (ii) only
B (i) and (iii) only
C (ii) and (iii) only
D All three factors
5 Production units and total costs relating to the last three periods have been:
Period 1 Period 2 Period 3
Production (units) 129,440 117,620 126,310
Total costs (£) 198,968 187,739 195,376
Using the high-low method, what is the estimated variable cost per unit of production?
A £0·87
B £0·95
C £1·05
D £1·15
2
6 What is the first-in first-out (FIFO) method used for?
A Calculating normal/abnormal losses
B Estimating equivalent units
C Valuing raw material issues from stock
D Valuing raw material receipts into stock
8 In the context of stock control what is the maximum stock control level?
A The level below which stock should not fall if usage is at the maximum expected
B The level below which stock should not fall if average usage occurs
C The level that stock should not exceed if usage is at the minimum expected
D The level that stock should not exceed if average usage occurs
3 [P.T.O.
11 The overheads of two service departments (SCC1 and SCC2) in a factory require re-apportionment to the two
production departments (PCC1 and PCC2):
Total overhead % to PCC1 % to PCC2
SCC1 £32,170 35 65
SCC2 £24,850 65 35
12 A company with a single product manufactured 10,200 units in a period in which 10,300 units were sold. Consider
the following statements:
(i) The profit for the period would be higher using absorption costing (compared with marginal costing)
(ii) Stock values would be higher using absorption costing (compared with marginal costing)
4
15 Costs incurred in a process totalled £61,600 for a period. 22,000 units of finished product were manufactured, of
which 440 units were rejected. This is the normal level of rejects for the process. Rejected units are sold for £1·80
per unit.
What was the cost per unit of good output (to the nearest penny)?
A £2·76
B £2·80
C £2·82
D £2·86
16 A process requires the input of a single raw material at the start of the process. There are no process losses. 10,000
units of the material were input to the process in a period. At the end of the period, processing was only 75% complete
on 800 units of the material. There was no work-in-progress at the beginning of the period.
17 Products X and Y are joint products. The joint process costs for a period, during which 10,000 units of X and 15,000
units of Y were manufactured, were £87,500.
The sales value method is used to apportion the joint process costs. Selling prices are £6·00 per unit for Product X
and £8·00 per unit for Product Y.
18 A hotel has 60 available rooms. Room occupancy was 80% during a 90 day period during which total costs incurred
were £104,976.
What was the cost per occupied room per night in the period?
A £12·44
B £15·55
C £19·44
D £24·30
5 [P.T.O.
19 A company has fixed costs per period as follows:
Manufacturing £56,000
Non-manufacturing £38,000
Variable costs of the company's single product are £4·20 per unit and the selling price is £7·00 per unit.
What sales revenue (to the nearest £000) is required in a period to make a profit of £6,000?
A £163,000
B £167,000
C £241,000
D £250,000
20 A capital investment project requires a cash outflow of £81,000 at the start of the project. Annual cash inflows are
forecast to be constant for four years (Years 1 to 4).
The net present value (NPV) of the project at a discount rate of 12% per annum is £8,683 (positive). The internal
rate of return of the project is 17%. Annuity factors (Years 1 to 4) at 12% and 17% are 3·037 and 2·743 respectively.
(40 marks)
6
Section B – ALL FOUR questions are compulsory and MUST be attempted
(b) Distinguish between cost centres, profit centres and investment centres. (4 marks)
(10 marks)
2 A company manufactures a single product. Currently, the company employs a team of six direct operatives who
produce a total of 2,500 units of the product in a 40-hour week. The hourly rate of pay for all operatives is £8·00.
In an effort to improve productivity, and thus to increase output in the normal 40-hour week, an incentive scheme
has been suggested. The scheme, which the six operatives have agreed to trial over a 4-week period, provides for
differential piecework payments in addition to a reduced basic rate per hour. Details of the scheme are:
Basic hourly rate £4·00 per hour
Differential piecework rates:
First 2,500 units of output in a week £0·375 per unit
Output 2,501 to 3,000 units in a week £0·45 per unit on additional units over 2,500
Output over 3,000 units in a week £0·60 per unit on additional units over 3,000
In the first week of the trial, total output was 3,080 units in the 40 hours worked.
Required:
(a) For the existing time rate payment system, calculate:
(i) the labour cost per unit, based on the current weekly output of 2,500 units; (2 marks)
(ii) the % change in the labour cost per unit if weekly output in the 40 hours worked could be increased to
2,750 units. (2 marks)
(15 marks)
7 [P.T.O.
3 A company has three production departments (X, Y and Z) in its factory. After completion of all overhead allocation
and apportionment, the production department budgets for Year 6 included the following:
Department
X Y Z
Overhead costs £51,240 £87,120 £66,816
Direct labour hours – – 11,520
Machine hours 4,200 5,280 –
A predetermined overhead absorption rate is established for each production department each year.
Actual data for Month 1 of Year 6 included:
Department
X Y Z
Overhead costs £4,410 £7,190 £5,610
Direct labour hours – – 985
Machine hours 340 426 –
Required:
(a) Calculate, from the data provided, an appropriate predetermined overhead absorption rate for each
production department for Year 6. (4 marks)
(b) Calculate the amount of the over/under absorption of overhead in Month 1 in each production department
and in total for the factory. (9 marks)
(16 marks)
8
4 A company currently has spare labour hours in Department X and spare machine capacity in Department Z, and is
considering each of the following independent opportunities:
1. Whether to quote for Contract W which would be completed in the near future.
2. Whether to take on sub-contract work for a period of three years.
1. Contract W:
The contract would be carried out without the need for any additional direct operatives in Department X where
two existing operatives, each paid at a rate of £7·50 per hour for a guaranteed 37-hour week, would work on
the contract for a total of 220 hours. In another department, Department Y, additional labour would have to be
taken on at a cost of £2,400.
Total material costs for the contract are estimated at £5,740, based on replacement prices. Included in materials
is Component M, a quantity of which is in stock. Component M is no longer used in the company’s business.
Details of Component M are:
Stockholding 80 units
Required for Contract W 120 units
Purchase price of existing stock £6·10 per unit
Disposal proceeds of existing stock if sold £4·60 per unit
Replacement price £6·50 per unit
Overheads would be absorbed on the contract on the following basis:
Production overheads – 120% of direct labour cost (only 20% of the overheads
absorbed would be an incremental cost)
Non-production overheads – 40% of total production cost (none of the overheads
absorbed would be an incremental cost)
2. Sub-contract work:
The sub-contract work would be carried out in Department Z, utilising existing machinery. The machinery is now
surplus to requirements and would otherwise be sold. The net book value of the machinery is £140,000 but the
current disposal value is only £120,000. If used for three years on the sub-contract work the disposal value
would be expected to reduce to £10,000. The remaining net book value of the machinery would be depreciated
on a straight-line basis over the three years.
Net cash inflows from the sub-contract work, occurring at the end of each year, are forecast to be:
Year 1 £40,000
Year 2 £55,000
Year 3 £60,000
Required:
(a) Calculate the minimum price that could be quoted for Contract W in order to recover incremental costs only.
(Show workings clearly.) (10 marks)
(b) Calculate the net present value (NPV) for the sub-contract work at a cost of capital of 10% per annum.
Discount factors at 10%:
Year 1 0·909
Year 2 0·826
Year 3 0·751 (9 marks)
(19 marks)