Progress Update For Pre Fabrication Works

This document provides a progress update for pre-fabrication and site erection works. It includes 36 systems with details on pipe diameter, man hours, weightage and percentage completion of drawing preparation, material cutting, fitting, welding, testing and other pre-fabrication activities. It also provides updates on the number of lines, weightage, and percentage completion of delivery, field welds, supports, testing and other site erection activities for the 36 systems. The overall completion percentage for pre-fabrication works is 77.44% and for site erection works is 59.10%.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
232 views4 pages

Progress Update For Pre Fabrication Works

This document provides a progress update for pre-fabrication and site erection works. It includes 36 systems with details on pipe diameter, man hours, weightage and percentage completion of drawing preparation, material cutting, fitting, welding, testing and other pre-fabrication activities. It also provides updates on the number of lines, weightage, and percentage completion of delivery, field welds, supports, testing and other site erection activities for the 36 systems. The overall completion percentage for pre-fabrication works is 77.44% and for site erection works is 59.10%.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

PROGRESS UPDATE FOR PRE FABRICATION WORKS

Report No
Report Date

S.No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36

Service
A-01
A-02
A-03
A-04
A-05
A-06
A-07
A-08
A-09
A-10
A-11
A-12
A-13
A-14
A-15
A-16
A-17
A-18
A-19
A-20
A-21
A-22
A-23
A-24
A-25
A-26
A-27
A-28
A-29
A-30
A-31
A-32
A-33
A-34
A-35
A-36

Prepared by

Description
System - 01
System - 02
System - 03
System - 04
System - 05
System - 06
System - 07
System - 08
System - 09
System - 10
System - 11
System - 12
System - 13
System - 14
System - 15
System - 16
System - 17
System - 18
System - 19
System - 20
System - 21
System - 22
System - 23
System - 24
System - 25
System - 26
System - 27
System - 28
System - 29
System - 30
System - 31
System - 32
System - 33
System - 34
System - 35
System - 36

Test Pack

Dia Inch
726
896
487
12
182
336
367
542
547
440
883
381
849
384
10
954
841
725
561
617
636
117
652
247
839
311
997
586
747
50
704
382
491
187
812
241
18739

Weld Map Material


Pipe
Blasting &
Final
Deliver to
Drawing
from
Fit up Welding NDT
Cutting
Painting Inspection
Site
Man Hour Weightage
Preparation Stores
25
30
17
1
7
12
13
19
19
15
30
13
29
13
1
32
29
25
19
21
22
4
22
9
28
11
34
20
25
2
24
13
17
7
28
9
645

3.87%
4.78%
2.60%
0.06%
0.97%
1.79%
1.96%
2.89%
2.92%
2.35%
4.71%
2.03%
4.53%
2.05%
0.05%
5.09%
4.49%
3.87%
2.99%
3.29%
3.39%
0.62%
3.48%
1.32%
4.48%
1.66%
5.32%
3.13%
3.99%
0.27%
3.76%
2.04%
2.62%
1.00%
4.33%
1.29%
100%

5%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

5%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

15%
100%
100%

25%
100%
100%

20%
100%
100%

6%
100%
100%

12%
100%
100%

6%
100%

6%
100%

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%
100%

100%
100%
100%
100%

100%
100%
100%
100%

100%
100%
100%
100%

100%
100%
100%
100%

100%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%
100%

100%
100%
100%
100%
100%

100%
100%
100%
100%
100%

100%
100%
100%
100%
100%

100%
100%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

100%
100%

100%
100%

100%
100%

100%
100%

100%
100%

100%
100%

100%
100%
100%
100%

100%
100%
100%
100%

100%
100%
100%

100%

100%

100%

100%

100%

100%
100%

100%
100%

100%
100%
100%

100%
100%
100%

100%
100%

100%
100%

Individual
Progress
100.00%
88.00%
10.00%
100.00%
100.00%
100.00%
100.00%
76.00%
94.00%
94.00%
94.00%
94.00%
25.00%
88.00%
88.00%
88.00%
100.00%
88.00%
88.00%
100.00%
100.00%
88.00%
22.00%
88.00%
88.00%
100.00%
100.00%
100.00%
5.00%
100.00%
100.00%
5.00%
88.00%
50.00%
50.00%
25.00%

Approved By

Overall
Percentage
3.87%
4.21%
0.26%
0.06%
0.97%
1.79%
1.96%
2.20%
2.74%
2.21%
4.43%
1.91%
1.13%
1.80%
0.05%
4.48%
4.49%
3.40%
2.63%
3.29%
3.39%
0.55%
0.77%
1.16%
3.94%
1.66%
5.32%
3.13%
0.20%
0.27%
3.76%
0.10%
2.31%
0.50%
2.17%
0.32%
77.44%

Approved By

PROGRESS UPDATE FOR SITE ERECTION WORKS

Report No

S.No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36

Service
A-01
A-02
A-03
A-04
A-05
A-06
A-07
A-08
A-09
A-10
A-11
A-12
A-13
A-14
A-15
A-16
A-17
A-18
A-19
A-20
A-21
A-22
A-23
A-24
A-25
A-26
A-27
A-28
A-29
A-30
A-31
A-32
A-33
A-34
A-35
A-36

Prepared by

Description
System - 01
System - 02
System - 03
System - 04
System - 05
System - 06
System - 07
System - 08
System - 09
System - 10
System - 11
System - 12
System - 13
System - 14
System - 15
System - 16
System - 17
System - 18
System - 19
System - 20
System - 21
System - 22
System - 23
System - 24
System - 25
System - 26
System - 27
System - 28
System - 29
System - 30
System - 31
System - 32

Test Pack

No of
Lines
42
27
25
39
18
24
79
78
29
13
42
87
82
14
67
85
73
69
76
25
67
38
79
17
21
81
18
65
71
15
75
16
87
73
72
74
1863

Weightage

Report Date

2.25%
1.45%
1.34%
2.09%
0.97%
1.29%
4.24%
4.19%
1.56%
0.70%
2.25%
4.67%
4.40%
0.75%
3.60%
4.56%
3.92%
3.70%
4.08%
1.34%
3.60%
2.04%
4.24%
0.91%
1.13%
4.35%
0.97%
3.49%
3.81%
0.81%
4.03%
0.86%
4.67%
3.92%
3.86%
3.97%
100%

Delivery to
Field
Pipe
Fit up
Valves NDT Punch List Hydrotest
Site
Welds Supports
4%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

Flushing
Final
&
Insulation
Individual
Acceptance
Cleaning
Progress

30%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

12%
100%
100%

6%
100%
100%

8%
5%
100% 100%
100% 100%

4%
100%
100%

8%
100%
100%

6%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%

100%
100%

100%

100%
100%
100%
50%
100%
100%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%
100%

100%
100%

100%
100%

100%
100%
100%

100%
100%

100%
100%
100%
100%
100%

100%
100%
100%
100%
100%

100%
100%
100%
100%
100%

100%
100%
100%
100%
100%

100%
100%
100%
100%
100%

100%
100%

100%
100%

100%
100%

100% 100%
100% 100%

100%
100%

100%
100%
100%
100%

100%
100%
100%
100%

100%
100%
100%

100% 100%
100%

100%

12%

5%
83.00%
83.00%
34.00%
83.00%
77.00%
69.00%
69.00%
69.00%
69.00%
69.00%
69.00%
46.00%
46.00%
69.00%
69.00%
60.00%
57.00%
60.00%
60.00%
69.00%
69.00%
65.00%
34.00%
69.00%
69.00%
69.00%
69.00%
69.00%
4.00%
69.00%
69.00%
4.00%
52.00%
69.00%
60.00%
46.00%

Approved By

Overall
Percentage
1.87%
1.20%
0.46%
1.74%
0.74%
0.89%
2.93%
2.89%
1.07%
0.48%
1.56%
2.15%
2.02%
0.52%
2.48%
2.74%
2.23%
2.22%
2.45%
0.93%
2.48%
1.33%
1.44%
0.63%
0.78%
3.00%
0.67%
2.41%
0.15%
0.56%
2.78%
0.03%
2.43%
2.70%
2.32%
1.83%
59.10%