Uat Plan & Status at Sti Dewas: Uat No. Uat Case Scenarios Uat Dates
Uat Plan & Status at Sti Dewas: Uat No. Uat Case Scenarios Uat Dates
Uat Plan & Status at Sti Dewas: Uat No. Uat Case Scenarios Uat Dates
2008
UAT PLAN & STATUS AT STI DEWAS
3 Normal Goods receipt inspection / RM Inspction (01 Inspection type) QM 28.07.2008 DONE MODULE COMP%
4 Goods receipt inspection (Rejection Vendor Return delivery) (01 Inspection type) QM 29.07.2008 DONE SD 86
5 Goods receipt inspection (AWD) (01 Inspection type) QM 30.07.2008 DONE MM 100
10 Rejection at Inprocess and Final Inspection (04 Inspection type) QM 02.08.2008 DONE CO 100
17 Calibration QM 09.08.2008
26 Production order confirmation and Transfer of goods to FG/DS stores PP 06.08.2008 DONE
33 Sales to Existing Customer: Against Open PO ( Using scheduling Agreement ) SD 23 & 24 Jul 2008 DONE
48 Purchase of Materail other than Raw materail - Reorder Level MM 01.08.2008 DONE
52 STO from One plant to other(NRGP not used for SBU's) MM 06.08.2008 DONE
106 Maintain Attendance - Daily Time In - Out upload & Record Maintenance HR ?
107 Training & Event Management HR 04.08.2008 DONE
101 OF 109 93
Shekhar