Building Information Modeling (BIM) : Now and Beyond
Building Information Modeling (BIM) : Now and Beyond
Beyond
Salman Azhar, (Auburn University, USA)
Malik Khalfan and Tayyab Maqsood, (RMIT University, Australia)
Abstract
Building Information Modeling (BIM), also called n-D Modeling or Virtual Prototyping
Technology, is a revolutionary development that is quickly reshaping the Architecture-
Engineering-Construction (AEC) industry. BIM is both a technology and a process. The
technology component of BIM helps project stakeholders to visualize what is to be built in a
simulated environment to identify any potential design, construction or operational issues.
The process component enables close collaboration and encourages integration of the roles
of all stakeholders on a project. The paper presents an overview of BIM with focus on its
core concepts, applications in the project life cycle and benefits for project stakeholders with
the help of case studies. The paper also elaborates risks and barriers to BIM implementation
and future trends.
Keywords: Building Information Modeling (BIM), n-D Modeling, Collaboration, Integrated Project
Delivery (IPD), Information Technology, Project Management
Introduction
Building Information Modeling (BIM) is a revolutionary technology and process that has
quickly transformed the way buildings are conceived, designed, constructed and operated
(Hardin, 2009). Although the roots of BIM can be traced back to the parametric modeling
research conducted in USA and Europe in late 1970s and early 1980s, the Architecture-
Engineering-Construction (AEC) industry practically started to implement it in projects from
the mid-2000s. During the last seven years, the term BIM has gone from being a buzzword
to the centerpiece of AEC technology (Khemlani, in Eastman et al., 2011).
The National Building Information Modeling Standards (NBIMS) committee of USA defines
BIM as follows: BIM is a digital representation of physical and functional characteristics of a
facility. A BIM is a shared knowledge resource for information about a facility forming a
reliable basis for decisions during its life cycle; defined as existing from earliest conception to
demolition. A basic premise of BIM is collaboration by different stakeholders at different
phases of the life cycle of a facility to insert, extract, update or modify information in the BIM
to support and reflect the roles of that stakeholder (NBIMS, 2010).
The Associated General Contractors of America (AGC) perceived BIM as: Building
Information Modeling is the development and use of a computer software model to simulate
the construction and operation of a facility. The resulting model, a Building Information
Model, is a data-rich, object-oriented, intelligent and parametric digital representation of the
facility, from which views and data appropriate to various users needs can be extracted and
analyzed to generate information that can be used to make decisions and improve the
process of delivering the facility (AGC, 2005).
As is clear from the above two definitions that BIM is not just software; it is a process and
software. BIM means not only using three-dimensional intelligent models but also making
significant changes in the workflow and project delivery processes (Hardin, 2009). BIM
represents a new paradigm within AEC, one that encourages integration of the roles of all
stakeholders on a project. It has the potential to promote greater efficiency and harmony
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) Building information modeling (BIM): now and beyond, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28
16
among players who, in the past, saw themselves as adversaries (Azhar et al., 2008a). BIM
also supports the concept of Integrated Project Delivery (IPD) which is a novel project
delivery approach to integrate people, systems, business structures and practices into a
collaborative process to reduce waste and optimize efficiency through all phases of the
project life cycle (Glick and Guggemos, 2009).
The purpose of this paper is to provide an overview of BIM concept, applications, benefits,
risks and associated challenges to the AEC industry. In the following section, the BIM
concept is discussed from technology and process standpoints. After that, the BIM
applications in the project life cycle programming, design, preconstruction, construction
and post-construction are discussed. This is followed by discussion on BIM benefits for
project stakeholders namely owners, designers, constructors and facility managers. After
that, BIM risks and barriers to implementation in the AEC industry are elaborated. At the
end, the future of BIM is examined and conclusions are drawn.
Understanding BIM
BIM as a Technology
From technology perspective, a building information model is a project simulation consisting
of the 3D models of the project components with links to all the required information
connected with the project planning, design, construction or operation as depicted in Figure
1 (Kymmell, 2008). The BIM technology hailed from the object-oriented parametric modeling
technique (Azhar et al., 2008b). The term parametric describes a process by which an
element is modified and an adjacent element or assembly (e.g. a door attached to a wall) is
automatically adjusted to maintain a previously established relationship (Stine, 2011).
Figure 1 A Visual Representation of BIM Concept
The principal difference between BIM technology and conventional 3D CAD is that the latter
describes a building by independent 3D views such as plans, sections and elevations.
Editing one of these views requires that all other views must be checked and updated, an
error-prone process that is one of the major causes of poor documentation. In addition, data
in these 3D drawings are graphical entities only, such as lines, arcs and circles, in contrast
to the intelligent contextual semantic of BIM models, where objects are defined in terms of
building elements and systems such as spaces, walls, beams and columns. A building
B
u
i
l
d
i
n
g
B
Residential
Commercial
Healthcare
Institutional
Sports
Entertainment
I
n
f
o
r
m
a
t
i
o
n
I
Spatial
Elements
Systems
Quantities
Schedule
Operations
M
o
d
e
l
i
n
g
M
Site
Architectural
Structural
MEP Systems
Sustainability
Management
Program-
ming
Design
Pre
construction
Construction Operations Demolition
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) Building information modeling (BIM): now and beyond, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28
17
information model carries all information related to the building, including its physical and
functional characteristics and project life cycle information, in a series of smart objects. For
example, an air conditioning unit within a BIM would also contain data about its supplier,
operation and maintenance procedures, flow rates and clearance requirements (Azhar and
Richter, 2009; CRC Construction Innovation, 2007).
Eastman et al. (2011) indicated that the following types of digital models do not fall under the
category of BIM: (1) models that contain 3D data only and no object attributes (i.e. missing
i of BIM) ; (2) models with no support of behavior; (3) models that are composed of multiple
2D CAD reference files that must be combined to define the building; and (4) models that
allow changes to dimensions in one view that are not automatically reflected in other views.
BIM as a Process
BIM can be viewed as a virtual process that encompasses all aspects, disciplines, and
systems of a facility within a single, virtual model, allowing all team members (owners,
architects, engineers, contractors, subcontractors and suppliers) to collaborate more
accurately and efficiently than traditional processes. As the model is being created, team
members are constantly refining and adjusting their portions according to project
specifications and design changes to ensure the model is as accurate as possible before the
project physically breaks ground (Carmona and Irwin, 2007). The foundations of BIM are laid
on two pillars, communication and collaboration. The successful implementation of BIM
requires early involvement of all project stakeholders. It means that the traditional project
delivery systems (e.g. design-bid-build) have very limited role in BIM-based projects.
Recently the Integrated Project Delivery (IPD) concept emerges as a natural companion to
BIM. IPD brings key construction management, trades, fabrication, supplier and product
manufacturer expertise together with design professionals and the owner earlier in the
process to produce a design that is optimized for quality, aesthetics, constructability,
affordability, timeliness and seamless flow into lifecycle management. In the United States,
the IPD has become a preferred project delivery system for all major projects involving BIM
(McGraw-Hill Construction, 2008). Figure 2 illustrates the difference between traditional
and BIM process.
Figure 2 A Comparison between Traditional and BIM Process
(Courtesy of: Holder Construction, Atlanta, Georgia, USA)
BIM Applications in the Project Life Cycle
BIM applications spans over the entire life cycle of a facility. This section presents a brief
overview of important BIM applications in the project programming, design, preconstruction,
construction, and post-construction (operations and maintenance) phases.
BIM and Project Programming
The use of BIM in the project programming phase allows project team to analyze space and
understand the complexity of space standards and land regulations, which saves time and
provide the team with opportunity of doing more value-added activities (CICRP, 2009).
Traditional Process
A
C
S
M
E
Concept & Design Documents & Drawings Construction & Operation
x
x
x
BIM Process
A
C
S
M
E
P
Cost
FP
Prog
FM
Data
Relational Database
(Design, Documents, Data)
Construction
& Operation
Active Access,
Sharing & Data Use
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) Building information modeling (BIM): now and beyond, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28
18
Recently, some researchers have investigated the integration of BIM with GIS (Geographical
Information Systems) which can aid project planners in selecting appropriate site and
conducting project feasibility and marketing studies (Berlo and Laat, 2011; Isikdag et al.,
2008). Following are some of the benefits of GIS-BIM based site analysis (CICRP, 2009):
Aid in determining if potential sites meet the required criteria according to project
requirements, technical and financial factors, etc.
Decrease costs of utility demand and demolition.
Minimize risk of hazardous materials.
The advances and economy of 3D laser scanning equipment has allowed practitioners to
accurately scan existing utilities and integrate them in the BIM model as show in Figure 3. In
addition, 3D laser scanning can be used to scan and accurately (within industry tolerances)
develop BIM models of existing facilities which can be later used for renovation and adaptive
re-use of existing buildings.
Figure 3 Utilization of BIM Model for Underground Utilities Coordination
(Courtesy of: Holder Construction, Atlanta, Georgia, USA)
BIM and Project Design
The architects and engineers can take advantage of BIM applications at different stages of
project design namely schematic design (SD), detailed design (DD) and construction
detailing (CD). Table 1 illustrates specific BIM applications in each stage of project design.
Schematic design Detailed design Construction Detailing
Options Analysis (to
compare multiple design
options)
Photo Montage (to
integrate photo realistic
images of project with its
existing conditions)
3D exterior and interior models
Walk-through and fly-through
animations
Building performance analyses
(e.g. energy modeling)
Structural analysis and design
4D phasing and scheduling
Building systems analysis
(e.g. clash detections)
Shop or fabrication drawings
Table 1 BIM applications in project design phase
Case study 1 (Azhar, 2011)
This case study illustrates the use of BIM in the schematic design phase. The Options
Analysis was performed for selecting the most economical and workable building layout. The
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) Building information modeling (BIM): now and beyond, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28
19
project is a higher education facility at Savannah State University, Savannah, Georgia, USA.
For this project, the general contractor coordinated with the architect and the owner at the
schematic design phase to prepare building information models of three different design
options. For each option, the BIM-based cost estimates were also prepared using three
different cost scenarios (budgeted, midrange, and high range), as shown in Figure 3. The
owner was able to walk through all the virtual models to decide the best option that fit his
requirements. The entire process took 2 weeks, and the owner achieved roughly $1,995,000
cost savings at the schematic design stage by selecting the most economical design option.
Although it could be argued that the owner may have reached the same conclusion using
traditional drawings, the use of BIM technology helped him make a quick, definitive, and
well-informed decision.
Aspect Owners
Requirements
Option A Option B Option C
Front Elevation
Plan
Stories Not specified 2 2 3
Cost Scenarios
Budget: $147.74/sf $11,000,000 $12,897,111 $12,270,919 $10,910,894
Mid-Range: $175.00/sf $13,030,325 $15,276,800 $14,535,140 $12,924,100
High-Range: $200.00/sf $14,891,800 $17,459,200 $16,611,600 $14,770,400
Figure 3 Options Analysis for the Savannah State Academic Building
(Courtesy of: Holder Construction Company, Atlanta, GA)
BIM in the Preconstruction Phase
The applications of BIM in the preconstruction phase can be summarized as follows:
Estimating: From building information models, the contractors can perform fairly accurate
quantity survey and prepare detailed estimates. Based on the data of 32 major projects,
the Stanford Universitys Center for Integrated Facilities Engineering (CIFE) reported that
the accuracy of BIM-based estimates was within 3% with up to 80% time reduction in
generating these estimates (cited by CRC Construction Innovation, 2007).
Site coordination: Using 3D or 4D site coordination models, the contractors can plan for
site logistics, develop traffic layouts, and identify potential hazards at the jobsite which
can aid in preparing a more realistic site safety plan.
Constructability analysis: Using BIM models, the project team can perform detailed
constructability analysis to plan sequence of operations at the jobsite.
Case study 2
This case study illustrates the use of BIM for safety planning and management. The project
is Wellness Center Building at the campus of Auburn University, Auburn, Alabama which is
currently under construction and planned to complete by April 2013. The project team
developed the BIM model of the facility in the project design phase and uses it for site
coordination and constructability analysis. Through coordinated meetings involving project
managers, site superintendents, and subcontractors, all possible major and minor site
Option A
Option B
Option C
Option A
Option B
Option C
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) Building information modeling (BIM): now and beyond, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28
20
hazards are identified and appropriate mitigation plans are developed (see Figure 4). The
relevant 4D animations are also used in the tool box meetings to illustrate daily construction
activities to the workers. So far, no major or minor accident is reported at the site. The site
superintendents rated BIM as a great tool for educating workers in quick time about the
site hazards (Azhar et al., 2012).
(a) Fall protection railings (b) Fall protection plan for roof workers
Figure 4 A BIM-based site specific safety plan (Azhar et al., 2012)
BIM in the Construction Phase
In the construction phase, the project team can use BIM for the following activities: (1)
Project progress monitoring using 4D phasing plans; (2) For trade coordination meetings
(see Figure 5); and (3) Integrating RFIs, change orders and punch list information in the BIM
models. Throughout the construction period, the project team must continuously update the
BIM model so that it reflects the most up-to-date information which later on can be used by
the facility managers for building operations and maintenance.
The advances in smartphone and tablets technology have allowed contractors and
subcontractors to frequently use BIM models at the jobsite for information extraction and
coordination. Some of the notable BIM apps include BIMX
, Bentley Navigator
, Buzzsaw
,
etc. Recently the Autodesk
, which
allows users to share BIM models in a web environment and perform various tasks in the
field such as walk-throughs, clash detection and preparing digital RFIs (Rubenstone, 2012).
Figure 5 Trade coordination meeting using BIM in a job trailer
(Courtesy of: Holder Construction Company, Atlanta, GA)
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) Building information modeling (BIM): now and beyond, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28
21
BIM in the Post construction Phase
A building information model contains complete information about a facility as it evolves
through planning, design and construction. This information can be leveraged for
downstream use by facility managers thereby making operations and maintenance of a
facility more efficient. Research suggests that 85% of the lifecycle cost of a facility occurs
after construction is completed and approximately $10 billion are annually lost in the U.S.
alone due to inadequate information access and interoperability issues during operations
and maintenance phases (Newton, 2004). The use of BIM for facility management (FM) can
significantly help to prevent these loses.
The fundamental benefit of a BIM model is that it provides information about a building and
its spaces, systems and components. The overall goal is to transfer these data into facility
management operations. In this manner information about building systems and equipment
can be accessed by simply clicking on an object in a BIM model. For example, the
information that is extracted for a piece of equipment such as a VAV box are location, name,
model number, product type, operation and maintenance manuals, commissioning
information and performance data. This makes it very simple for a maintenance worker to
access the required information vital to different systems in the building as shown in Figure 6
(Philips and Azhar, 2011).
(a) A HVAC Model (b) Data of HVAC Equipment
Figure 6 Illustration of use of BIM in facility operations
Following are some additional applications of BIM for facility operations and management:
(1) Maintenance work order management; (2) Emergency service request management; (3)
Space planning and management; (4) Inventory management and inspections; (5) Move
management; and (6) Real estate portfolio management.
BIM Benefits for Project Stakeholders
Before discussing benefits of BIM for project owners, designers, constructors and facility
managers, it is useful to summarize BIM applications for these stakeholders. Table 2
provides this summary. The individual benefits of BIM for each stakeholder are discussed in
the following sections.
Project Owners
Owners can achieve significant benefits on projects where BIM technology and processes
are applied. Eastman et al. (2011) and Reddy (2011) summarized the following benefits of
BIM for project owners: (1) Early design assessment to ensure project requirements are met;
(2) Operations simulation to evaluate building performance and maintainability; (3) Low
financial risk because of reliable cost estimates and reduced number of change orders; (4)
Better marketing of project by making effective use of 3D renderings and walk-though
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) Building information modeling (BIM): now and beyond, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28
22
animations; and (5) Complete information about building and its systems in a single file. Due
to these and other tangible and intangible benefits of BIM, large project owners in the USA
(such as the General Services Administration (GSA), the U.S. Army Corp of Engineers
(USACE), etc.) are increasingly requiring designers and contractors to utilize BIM in all
projects (Ku and Taiebat, 2011).
BIM Application Owners Designers Constructors
Facility
Managers
Visualization x x x x
Options analysis x x x
Sustainability analyses x x
Quantity Survey x x
Cost Estimation x x x
Site Logistics x x
Phasing and 4D scheduling x x
Constructability analysis x x
Building performance analysis x x x x
Building management x x
Table 2 BIM applications for project stakeholders
Project Designers
The project architects and engineers can take advantage of BIM in schematic and detailed
design; and construction detailing phases as summarized in Table 1. Following are some of
the main benefits of BIM for project designers: (1) Better design by rigorously analyzing
digital models and visual simulations and receiving more valuable input from project owners;
(2) Early incorporation of sustainability features in building design to predicts its
environmental performance; (3) Better code compliance via visual and analytical checks; (4)
Early forensic analysis to graphically assess potential failures, leaks, evacuation plans and
so forth; and (5) Quick production of shop or fabrication drawings (Kymel, 2008).
The early design and preconstruction stages of a building are the most critical phases to
make decisions on its sustainability features (Azhar et al., 2009). Traditional Computer-Aided
Design (CAD) planning environments typically lack the capability to perform sustainability
analyses in the early stages of design development. Building performance analyses are
typically performed after the architectural design and construction documents have been
produced. This failure to analyze sustainability continually during the design process results
in an inefficient process of retroactive modification to the design to achieve a set of
performance criteria (Schueter and Thessling, 2008). To assess building performance in the
early design and preconstruction phases realistically, access to a comprehensive set of data
regarding a buildings form, materials, context and systems is required. Since BIM allows for
multi-disciplinary information to be superimposed within one model, it creates an opportunity
for sustainability measures to be incorporated throughout the design process (Autodesk,
2008). Azhar et al. (2011) found that information for up to 17 LEED
(Leadership in Energy
and Environmental Design, a green building rating system used in the USA) credits can be
obtained in the design phase by performing BIM-based sustainability analyses. It means a
building information model can be used as a by-product for LEED
and iPAD
) and Augmented
Reality (AR) has made it possible to obtain complete information about a building component
by just pointing the device towards it. Joyce (2012) reported an AR-based system,
InfoSPOT