This document discusses how to determine the probability that a project will be completed by a specified date using the critical path method (CPM). It explains that the probability for each path is calculated using the path's expected duration and standard deviation. The probabilities of all paths finishing on time are then multiplied to determine the probability the whole project will finish on schedule. An example is provided to illustrate how to calculate path probabilities and determine the probability of a project completing within 15 or 17 weeks.
This document discusses how to determine the probability that a project will be completed by a specified date using the critical path method (CPM). It explains that the probability for each path is calculated using the path's expected duration and standard deviation. The probabilities of all paths finishing on time are then multiplied to determine the probability the whole project will finish on schedule. An example is provided to illustrate how to calculate path probabilities and determine the probability of a project completing within 15 or 17 weeks.
This document discusses how to determine the probability that a project will be completed by a specified date using the critical path method (CPM). It explains that the probability for each path is calculated using the path's expected duration and standard deviation. The probabilities of all paths finishing on time are then multiplied to determine the probability the whole project will finish on schedule. An example is provided to illustrate how to calculate path probabilities and determine the probability of a project completing within 15 or 17 weeks.
This document discusses how to determine the probability that a project will be completed by a specified date using the critical path method (CPM). It explains that the probability for each path is calculated using the path's expected duration and standard deviation. The probabilities of all paths finishing on time are then multiplied to determine the probability the whole project will finish on schedule. An example is provided to illustrate how to calculate path probabilities and determine the probability of a project completing within 15 or 17 weeks.
Operations Management eBook 11/e Content Chapter Opener Introduction Project Life Cycle Behavioral Aspects of ... Work Breakdown Structure Planning and Schedulin... PERT and CPM Deterministic Time Est... A Computing Algorithm Probabilistic Time Est... Determining Path Pr... Simulation Budget Control TimeCost Trade-Offs: ... Advantages of Using PE... Critical Chain Project... Other Topics in Projec... Project Management Sof... Operations Strategy Risk Management Summary Key Points Key Terms Solved Problems Discussion and Review ... Taking Stock Critical Thinking Exer... Problems Case: The Case of the ... Case: Time, Please The probability that a given path will be completed in a specified length of time can be determined using the following formula: The resulting value of z indicates how many standard deviations of the path distribution the specified time is beyond the expected path duration. The more positive the value, the better. (A negative value of z indicates that the specified time is earlier than the expected path duration.) Once the value of z has been determined, it can be used to obtain the probability that the path will be completed by the specified time from Appendix B, Table B. Note that the probability is equal to the area under the normal curve to the left of z, as illustrated in Figure 17.10. If the value of z is +3.00 or more, the path probability is close to 100 percent (for z = +3.00, it is .9987). Hence, it is very likely the activities that make up the path will be completed by the specified time. For that reason, a useful rule of thumb is to treat the path probability as being equal to 100 percent if the value of z is +3.00 or more. A project is not completed until all of its activities have been completed, not only those on the critical path. It sometimes happens that another path ends up taking more time to complete than the critical path, in which case the project runs longer than expected. Hence, it can be risky to focus exclusively on the critical path. Instead, one must consider the possibility that at least one other path will delay timely project completion. This requires determining the probability that all paths will finish by a specified time. To do that, find the probability that each path will finish by the specified time, and then multiply those probabilities. The result is the probability that the project will be completed by the specified time. It is important to note the assumption of i ndependenc e. It is assumed that path duration times are independent of each other. In essence, this requires two things: Activity times are independent of each other, and each activity is only on one path. For activity times to be independent, the time for one must not be a function of the time of another; if two activities were always early or late together, they would not be considered independent. The assumption of independent paths is usually considered to be met if only a few activities in a large project are on multiple paths. Even then, common sense should govern the decision of whether the independence assumption is justified. EXAMPLE 6 www.mhhe.com/stevenson11e p. 764 Search eBook... p. 765 Determining Path Probabilities file:///D:/DATA/gerges/ay7 kalamk/STUFF/BUE/2014/OR/Operations ... 1 of 4 5/19/2014 3:44 PM Selected Bibliography ...
Using the information from Example 5, answer the following questions: a. Can the paths be considered independent? Why? b. What is the probability that the project can be completed within 17 weeks of its start? c. What is the probability that the project will be completed within 15 weeks of its start? d. What is the probability that the project will not be completed within 15 weeks of its start? FIGURE 17.10 The path probability is the area under a normal curve to the left of z SOLUTION
a. Yes, the paths can be considered independent, since no activity is on more than one path and you have no information suggesting that any activity times are interrelated. b. To answer questions of this nature, you must take into account the degree to which the path distributions overlap the specified completion time. This overlap concept is illustrated in the accompanying figure, which shows the three path distributions, each centered on that path's expected duration, and the specified completion time of 17 weeks. The shaded portion of each distribution corresponds to the probability that the part will be completed within the specified time. Observe that paths a-b-c and g-h-i are well enough to the left of the specified time, so that it is highly likely that both will be finished by week 17, but the critical path overlaps the specified completion time. In such cases, you need consider only the distribution of path d-e-f in assessing the probability of completion by week 17. To find the probability for a path you must first compute the value of z using Formula 17-8 for the path. For example, for path d-e-f, we have Determining Path Probabilities file:///D:/DATA/gerges/ay7 kalamk/STUFF/BUE/2014/OR/Operations ... 2 of 4 5/19/2014 3:44 PM Turning to Appendix B, Table B, with z = +1.00, you will find that the area under the curve to the left of z is .8413. The computations are summarized in the following table. Note: If the value of z exceeds +3.00, treat the probability of completion as being equal to 1.000. c. For a specified time of 15 weeks, the z values are Paths d-e-f and g-h-i have z values that are less than +3.00. From Appendix B, Table B, the area to the left of z = 1.00 is Determining Path Probabilities file:///D:/DATA/gerges/ay7 kalamk/STUFF/BUE/2014/OR/Operations ... 3 of 4 5/19/2014 3:44 PM .1587, and the area to the left of z = +1.40 is .9192. The path distributions are illustrated in the figure. The joint probability of all finishing before week 15 is the product of their probabilities: 1.00(.1587)(.9192) = .1459. d. The probability of not finishing before week 15 is the complement of the probability obtained in part c: 1 .1459 = .8541. Go Go Search eBook... Determining Path Probabilities file:///D:/DATA/gerges/ay7 kalamk/STUFF/BUE/2014/OR/Operations ... 4 of 4 5/19/2014 3:44 PM
Power Transmission Design Project EGMN 300-001-32729 Mechanical Systems Design Fall 2016 Engineering Building West Classroom 0101 0800-0915, Tuesday & Thursday