Installation and Commissioning Forms - Eclipse Node

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 10

Harris Stratex Networks

Eclipse Node Installation and Commissioning Forms


Rev 3 June 07
Introduction

Purpose is to provide:
A prompt for preparing data for new installations.
A datapack for installers.
A data entry form to capture additional as-built data.
An as-built record with sign-off.

Associated forms included in this file are:
Installation Inspection Form
Customer Acceptance Form
Remedial Action Form

Navigation:
The Master Site Data column lists entries required. Click on a
+ tab at the far left of the screen to open up required links and
modules for the Node. Click tab to close.
The Build / As-Built Data column is for data entry. Build data
is data to be entered at the planning (datapack prep) stage. As-
built data is data to be entered at site, mostly from Portal.
The Portal column highlights the data to be entered into Portal
and data to be entered from Portal.
The Comments column is to capture any additional data.

See the Example Form for additional guidance.

Forms can be printed.

Important! Please provide feedback on the use of these forms.
Feedback is needed to provide guidance on what improvements should
be made to assist the application and usability of these forms. Please
send feedback to:
Director Installation Practices
Director of Services, Americas
Global Technical Support Manager
Eclipse Node Forms: V1.3 June06 Commercial-In-Confidence 1
Harris Stratex Networks
Eclipse Node Installation and Configuration Form For Site:
Installer: INU
Installer Contact Details:
Scheduled Start Date:
Scheduled Completion Date:
New or Existing Site: INUe
Electrical Supply OK yes/no:
Site Grounding OK yes/no:
Antenna Mounts OK yes/no:
Site Security OK yes/no:
Site Plans Included yes/no:
Master Site Data Build / As-Built Data Portal
Entry To
Comments
Node
Node Type INU or INUe To
Node Name To
Site Name To
Site Grid Reference To
Tech Services contact details To
NOC contact details
Site location
Site access See attached map
Rack number/name
INU location in rack
Chassis serial number (All serial numbers begin with three letters)
NCC serial number
FAN serial number(s)
License serial number (Enter from NCC FlashCard label)
Licensed capacity
License capacity checked From
-48Vdc power supply connection
Networking
Terminal IP Address To
Subnet Mask To
Static or dynamic routing To
Static routing data
DHCP yes/no; address range To
Trap destinations To
Link 1
Link 2
Link 3
Link 4
DAC 16x
DAC 16x
DAC 4x
DAC 155o / 2x155o
DAC 2x155e
DAC ES
DAC GE
DAC 155oM
DAC 3xE3/DS3
DAC 3xE3/DS3M
Traffic Circuits
Bus configuration To
Circuit connections To
General Instructions:
Slot Allocations
1=
2=
3=
4=
5=
6=
7=
8=
9=
10=
To = Enter into Portal
From = Enter from Portal
Eclipse I+C Form: V1.3 June06 Commercial-In-Confidence 2
Harris Stratex Networks
Circuit naming To (Each circuit in a network should have a unique name,
and that name should be entered at all Nodes that carry
that circuit. Trib names should also relate to its circuit
name to permit easy association of trib with circuit when
setting a DAC BER test using the circuit loopback
feature.)
AUX
NPC
Date/Time
(Specify Date/Time setting) To
BER Circuit Checks
Trib-trib BER check
(Specify the tri/cct[s] and period)
From
Alarms exit check
Active alarms yes/no From
Ground checks
Single point bldg ground y/n
Master Ground Bar resistance
Rack to MGB resistance
-48V PSU to MGB resistance
Tower ground resistance(s)
Other resistance readings
Meter used
Site Inspection Report
completed yes/no
Hardware Installation completed
Name:
Signature:
Date:
Node Installation & Tests
completed
Name:
Signature:
Date:
Completion Comments
Eclipse I+C Form: V1.3 June06 Commercial-In-Confidence 3
Harris Stratex Networks
Eclipse Node Installation and Configuration Form For Site: Lakeside
Installer: Joeseph Brown INU
Installer Contact Details: 021 362 700
Scheduled Start Date: 10-Sep-05
Scheduled Completion Date: 14-Sep-05
New or Existing Site: Existing INUe
Electrical Supply OK yes/no: Yes
Site Grounding OK yes/no: Yes
Antenna Mounts OK yes/no: Yes
Site Security OK yes/no: Yes
Site Plans Included yes/no: Yes
Master Site Data Build / As-Built Data Portal
Entry To
Comments
Node
Node Type INU or INUe INU To
Terminal Name E101 To
Site Name Lakeside To
Site Grid Reference Eastxxx Southxxx To
Tech Services contact details 021 362 701 To
NOC contact details 021 362 702
Site location 10km west of Ekatahuna
Site access Via Ridge road at first bridge See attached map
Rack number/name 2B
INU location in rack Directly under terminal E104
Chassis serial number LES00934567 (All serial numbers begin with three letters)
NCC serial number LEX00099997 From
FAN serial number(s) LER00094564
License serial number SNI35435 From
Licensed capacity 40xE1 for slot 1, 40xE1 for slot 2.
License capacity checked 40xE1 for slot 1, 40xE1 for slot 2.
10xE1 for slots 3 & 4.
From
-48Vdc power supply connection Provide and install 12A Cct Breaker on supply
panel at top of rack
Networking
Terminal IP Address 192.168.10.1 To
Subnet Mask 225.225.255.0. To
Static or dynamic routing RIP 2 To
Static routing data N/A
DHCP yes/no; address range Yes, 192.168.10.2 to 192.168.10.10 To
Trap destinations N/A To
Link 1
Link name/number Lakeside-Belmont To
Remote end site name Belmont To
Remote end node/terminal name E103 To
Local antenna type(s) VHLP2-180-EX
Local antenna diameter(s) 0.6M
Antenna serial number(s) AN35235
Height on tower / pole mount ID 21M `
Initial pointing (compass/map ref) 74 degrees
Polarization Vertical
Protected yes/no No To
Protection type N/A To
ODU(s) direct mounting, yes/no Yes
ODU type ODU 300hp
ODU serial number SNA7687988 From
ODU cable length(s) required 35m
Location of RAC in INU Slot 1 To
RAC type RAC 30
RAC serial number LEA00878770 From
Tx frequency 17.85 GHz To
Rx frequency 18.25 GHz To
General Instructions: 4-wheel drive access only. This time of the year the track will be wet and slippery. Please do a battery check and run the back-up diesel
generator for about 30 mins and check associated panel lights. Should all be green.
Slot Allocations
1= RAC 30
2= RAC 30
3= Aux
4= DAC 16x
5=
6=
7=
8=
9=
10=
To = Enter into Portal
From = Enter from Portal
Eclipse I+C Form V1.3 June06 Commercial-In-Confidence 4
Harris Stratex Networks
Master Site Data Build / As-Built Data Portal
Entry To
Comments
T/R spacing 400 MHz To
Tx power 17 dBm To
Detected forward power 17.1 dBm From
Capacity 32xE1 To
Modulation 16QAM To
ATPC yes/no No To
ATPC data
Expected RSL -51 dBm
Indicated RSL -50 dBm From
Expected RSSI 1.25
Indicated RSSI 1.27 From
Expected fade margin 35 dB
Measured fade margin 37 dB From
G.826 link check Zero errors over 14 hours From
Alarms check No active alarms from Link 1 From
Performance check All indications normal From
Link 1
Link 2
Link name/number Lakeside to Pine Hill To
Remote end site name Pine Hill To
Remote end node/terminal name E102 To
Local antenna type(s) VHLP2-180-EX
Local antenna diameter(s) 0.6M
Antenna serial number(s) SN12495
Height on tower / pole mount ID 21M
Initial pointing (compass/map ref) 178 degrees
Polarization Vertical
Protected yes/no No To
Protection type N/A To
ODU(s) direct mounting, yes/no Yes
ODU type ODU 300hp
ODU serial number SNBO93859 From
ODU cable length(s) required 38m
Location of RAC in INU Slot 2 To
RAC type RAC 30
RAC serial number LEN00243551 From
Tx frequency 17.95 GHz To
Rx frequency 18.35 GHz To
T/R spacing 400 MHz To
Tx power 22dBm To
Detected forward power 21.5 dBm From
Capacity 32xE1 To
Modulation 16QAM To
ATPC yes/no No To
ATPC data
Expected RSL -53 dBm
Measured RSL -52 dBm From
Expected RSSI 1.3v
Indicated RSSI 1.35v From
Expected fade margin 33 dB
Measured fade margin 32 dB From
G.826 link check Zero errors over 14 hours From
Alarms check No active alarms from Link 2 From
Performance check All indications normal From
Link 2
Link 3
Link 4
DAC 16x
DAC location in INU Slot 4 To
Serial number LEX00234567 From
E1 or DS-1 E1 To
Bal or Unbal Unbal To
DS1 encoding N/A To
DS1 line length N/A To
Port / trib names Lak 1 to 8 To
Connect to Rack BNC panel: ports 1 to 8
Eclipse I+C Form V1.3 June06 Commercial-In-Confidence 5
Harris Stratex Networks
Master Site Data Build / As-Built Data Portal
Entry To
Comments
DAC 16x
DAC 16x
DAC 4x
DAC 155o / 2x155o
DAC 2x155e
DAC ES
DAC GE
DAC 155oM
DAC 3xE3/DS3
DAC 3xE3/DS3M
Traffic Circuits
Bus configuration E1 To
Circuit connections Link 1 ports 1-8 to DAC 16x, slot 4, ports 1-8.
Link 1 ports 9 to 32 to Link 2, slot 2, ports 1 to
24.
To
Circuit naming Link 1 ports 1-8: Bel/Lak 1 to Bel/Lak 8.
Link 1 ports 9-24: Bel/Pin 1 to Bel/Pin 16.
Link 1 ports 25-32: Bel/Wel 1 to Bel/Wel 8.
To
AUX
AUX location in INU Slot 3 To
Serial number LEA05090295 From
Auxiliary ports
Port 1: function, type, port settings,
name
Data, sync, P1, default, Aux Bel/Lak To
Port 2: function, type, port settings,
name
To
Port 3: function, type, port settings,
name
To
Auxiliary ports
Auxiliary circuits
Port 1: to/circuit name Port 1 to Link 1 port 1, Bel/Lak To
Port 1: to/circuit name To
Port 1: to/circuit name To
Auxiliary circuits To
Alarm I/O
Port layout 4xin, 2xout To
Port 1, type, active condition Digital input, active high To Wire to intruder alarm: alarm is active when circuit is
broken.
Port 2, type, active condition To
Port 3, type, active condition To
Port 4, type, active condition To
Port 5, type, active condition To
Port 6, type, active condition To
Alarm I/O
Alarm actions
Destination IP address, slot, and
output. Trigger(s).
192.168.2.1, slot 4, output 1.
AUX alarm input 1.
To At commissioning check that the destination output (bell)
at Belmont activates when the intruder alarm is activated.
Also check that the alarm event is raised at the NOC.
Destination IP address, slot, and
output. Trigger(s).
To
Destination IP address, slot, and
output. Trigger(s).
To
Destination IP address, slot, and
output. Trigger(s).
To
Destination IP address, slot, and
output. Trigger(s).
To
Alarm actions
Eclipse I+C Form V1.3 June06 Commercial-In-Confidence 6
Harris Stratex Networks
Master Site Data Build / As-Built Data Portal
Entry To
Comments
AUX
NPC
Date/Time
(Specify Date/Time setting) Sync to Portal PC Date/Time To
BER Circuit Checks
Trib-trib BER check
(Specify the trib/cct[s] and period)
BER check completed on trib 1 Lakeside to
Belmont.
From Tribs from Belmont through to Pine Hill will be checked
during Pine Hill commissioning.
Alarms exit check
Active alarms yes/no No active alarms From
Ground checks
Single point bldg ground y/n Yes
Master Ground Bar resistance 0.62 ohms
Rack to MGB resistance 0.15 ohms
-48V PSU to MGB resistance 0.27 ohms
Tower ground resistance(s) Not possible to measure. Cannot get meter jaws around
the ground straps.
Other resistance readings
Meter used Prova clamp-on, model DX Serial number 00458
Site Inspection Report
completed yes/no
Yes. Attached.
Hardware Installation completed
Name: Joe Brown
Signature:
Date: 14 September 2005
Node Installation & Tests
completed
Name: Joesphine Brown
Signature:
Date: 14 September 2005
Completion Comments The second farm gate is almost off its hinges.
One of the two tower-top warning lights is out.
Diesel generator checked out OK
Eclipse I+C Form V1.3 June06 Commercial-In-Confidence 7
Harris Stratex Networks
Eclipse Node Installation Inspection Report For Site:
Check for correct and complete installation of:
Item Pass Fail Comments
Antenna Mounting
Antenna side support (if used)
ODU fastening
ODU grounding
ODU connector weatherproofing
ODU cable fastening
ODU cable grounding
Lightning surge suppressor(s)
RAC to surge suppressor jumper cable
INU location in rack
INU is labelled (if required)
INU grounding
INU power supply wiring
INU cards are correctly secured
Unused slots have blank plates fitted
Trib cables are correctly and neatly installed
Trib cables are numbered (if required)
Alarms all-clear
Site left clean and tidy
Site photos taken (if required)
Site ground measurements (if required)
Checked by:
Name:
Signature:
Date:
Additional Comments:
Inst. Insp. Report: V1.2 Mar04 Commercial-In-Confidence 8
Harris Stratex Networks
Eclipse Node Customer Acceptance Form
Site Name:
Eclipse Node Name:
Related documents Received Yes/No
Eclipse Installation and Commissioning Form:
Eclipse Installation Inspection Report:
Acceptance Category* Category
Accepted / Conditionally Accepted / Not Accepted:
*If conditionally accepted or not accepted, the action required to
achieve acceptance must be detailed in a Remedial Action Form
Signed By:
Customer
Name:
Signature:
Title:
Date:
Harris Stratex Networks
Name:
Signature:
Title:
Date:
Acceptance Form V.1.2 Mar04 Commercial-In-Confidence 9
Harris Stratex Networks
Eclipse Node Remedial Action Form
Site Name:
Eclipse Node Name:
Item No. Responsibility
Signed As Completed
Customer
Name:
Signature:
Title:
Date:
Harris Stratex Networks
Name:
Signature:
Title:
Date:
Description of Remedial Action Required