0% found this document useful (0 votes)
220 views24 pages

The CoCoMo 2.0 Software Cost Estimation Model

This document provides an overview of the baseline COCOMO 2.0 software cost estimation model. It describes the model's objectives of being open, parsimonious, and continuous with previous COCOMO models. The document outlines the model's approach to estimating effort and schedule for three process models: Application Composition, Early Design, and Post-Architecture. It also discusses development of output ranges and next steps to further refine the model through additional data collection and analysis.

Uploaded by

deepsea_br
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
220 views24 pages

The CoCoMo 2.0 Software Cost Estimation Model

This document provides an overview of the baseline COCOMO 2.0 software cost estimation model. It describes the model's objectives of being open, parsimonious, and continuous with previous COCOMO models. The document outlines the model's approach to estimating effort and schedule for three process models: Application Composition, Early Design, and Post-Architecture. It also discusses development of output ranges and next steps to further refine the model through additional data collection and analysis.

Uploaded by

deepsea_br
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 24

Kemerer, C.

(1987), An Empirical Validation of Software Cost Estimation Models, Communi-


cations of the ACM, May 1987, pp. 416-429.
Kominski, R. (1991), Computer Use in the United States: 1989, Current Population Reports, Series
P-23, No. 171, U.S. Bureau of the Census, Washington, D.C., February 1991.
Kunkler, J. (1983), A Cooperative Industry Study on Software Development/Maintenance Pro-
ductivity, Xerox Corporation, Xerox Square --- XRX2 52A, Rochester, NY 14644, Third
Report, March 1985.
Miyazaki, Y., and K. Mori (1985), COCOMO Evaluation and Tailoring, Proceedings, ICSE 8,
IEEE-ACM-BCS, London, August 1985, pp. 292-299.
Parikh, G., and N. Zvegintzov (1983). The World of Software Maintenance, Tutorial on Soft-
ware Maintenance, IEEE Computer Society Press, pp. 1-3.
Park R. (1992), Software Size Measurement: A Framework for Counting Source Statements.
CMU/SEI-92-TR-20, Software Engineering Institute, Pittsburgh, PA.
Park R, W. Goethert, J. Webb (1994), Software Cost and Schedule Estimating: A Process Im-
provement Initiative, CMU/SEI-94-SR-03, Software Engineering Institute, Pittsburgh,
PA.
Paulk, M., B. Curtis, M. Chrissis, and C. Weber (1993), Capability Maturity Model for Software,
Version 1.1, CMU-SEI-93-TR-24, Software Engineering Institute, Pittsburgh PA 15213.
Pfleeger, S. (1991), Model of Software Effort and Productivity, Information and Software Tech-
nology 33 (3), April 1991, pp. 224-231.
Royce, W. (1990), TRWs Ada Process Model for Incremental Development of Large Software
Systems, Proceedings, ICSE 12, Nice, France, March 1990.
Ruhl, M., and M. Gunn (1991), Software Reengineering: A Case Study and Lessons Learned,
NIST Special Publication 500-193, Washington, DC, September 1991.
Selby, R. (1988), Empirically Analyzing Software Reuse in a Production Environment, In Soft-
ware Reuse: Emerging Technology, W. Tracz (Ed.), IEEE Computer Society Press, 1988.,
pp. 176-189.
Selby, R., A. Porter, D. Schmidt and J. Berney (1991), Metric-Driven Analysis and Feedback Sys-
tems for Enabling Empirically Guided Software Development, Proceedings of the Thir-
teenth International Conference on Software Engineering (ICSE 13), Austin, TX, May 13-
16, 1991, pp. 288-298.
Silvestri, G. and J. Lukasieicz (1991), Occupational Employment Projections, Monthly Labor
Review 114(11), November 1991, pp. 64-94.
SPR (1993), Checkpoint Users Guide for the Evaluator, Software Productivity Research, Inc.,
Burlington, MA., 1993.
Banker, R., H. Chang and C. Kemerer (1994a), Evidence on Economies of Scale in Software De-
velopment, Information and Software Technology (to appear, 1994).
Behrens, C. (1983), Measuring the Productivity of Computer Systems Development Activities
with Function Points, IEEE Transactions on Software Engineering, November 1983.
Boehm, B. (1981), Software Engineering Economics, Prentice Hall.
Boehm, B. (1983), The Hardware/Software Cost Ratio: Is It a Myth? Computer 16(3), March
1983, pp. 78-80.
Boehm, B. (1985), COCOMO: Answering the Most Frequent Questions, In Proceedings, First
COCOMO Users Group Meeting, Wang Institute, Tyngsboro, MA, May 1985.
Boehm, B. (1989), Software Risk Management, IEEE Computer Society Press, Los Alamitos, CA.
Boehm, B., T. Gray, and T. Seewaldt (1984), Prototyping vs. Specifying: A Multi-Project Exper-
iment, IEEE Transactions on Software Engineering, May 1984, pp. 133-145.
Boehm, B., and W. Royce (1989), Ada COCOMO and the Ada Process Model, Proceedings,
Fifth COCOMO Users Group Meeting, Software Engineering Institute, Pittsburgh, PA,
November 1989.
Boehm, B., B. Clark, E. Horowitz, C. Westland, R. Madachy, R. Selby (1995), Cost Models for
Future Software Life Cycle Processes: COCOMO 2.0, to appear in Annals of Software
Engineering Special Volume on Software Process and Product Measurement, J.D. Arthur
and S.M. Henry, Eds., J.C. Baltzer AG, Science Publishers, Amsterdam, The Netherlands.
Available from the Center for Software Engineering, University of Southern California.
Chidamber, S. and C. Kemerer (1994), A Metrics Suite for Object Oriented Design, IEEE Trans-
actions on Software Engineering, (to appear 1994).
Computer Science and Telecommunications Board (CSTB) National Research Council (1993),
Computing Professionals: Changing Needs for the 1990s, National Academy Press,
Washington DC, 1993.
Devenny, T. (1976). An Exploratory Study of Software Cost Estimating at the Electronic Systems
Division, Thesis No. GSM/SM/765-4, Air Force Institute of Technology, Dayton, OH.
Gerlich, R., and U. Denskat (1994), A Cost Estimation Model for Maintenance and High Reuse,
Proceedings, ESCOM 1994, Ivrea, Italy.
Goethert, W., E. Bailey, M. Busby (1992), Software Effort and Schedule Measurement: A Frame-
work for Counting Staff Hours and Reporting Schedule Information. CMU/SEI-92-TR-
21, Software Engineering Institute, Pittsburgh, PA.
Goudy, R. (1987), COCOMO-Based Personnel Requirements Model, Proceedings, Third CO-
COMO Users Group Meeting, Software Engineering Institute, Pittsburgh, PA, November
1987.
IFPUG (1994), IFPUG Function Point Counting Practices: Manual Release 4.0, International
Function Point Users Group, Westerville, OH.
Kauffman, R., and R. Kumar (1993), Modeling Estimation Expertise in Object Based ICASE En-
vironments, Stern School of Business Report, New York University, January 1993.
lows:
The effort range values can be used in the schedule equation, EQ 6., to determine schedule
range values.
7. CONCLUSIONS
Software development trends towards reuse, reengineering, commercial off-the shelf
(COTS) packages, object orientation, applications composition capabilities, non-sequential pro-
cess models, rapid development approaches, and distributed middleware capabilities require new
approaches to software cost estimation.
The wide variety of current and future software processes, and the variability of informa-
tion available to support software cost estimation, require a family of models to achieve effective
cost estimates.
The baseline COCOMO 2.0 family of software cost estimation models presented here pro-
vides a tailorable cost estimation capability well matched to the major current and likely future
software process trends.
The baseline COCOMO 2.0 model effectively addresses its objectives of openness, parsi-
mony, and continuity from previous COCOMO models. It is currently serving as the framework
for an extensive data collection and analysis effort to further refine and calibrate its estimation ca-
pabilities.
8. ACKNOWLEDGMENTS
This work has been supported both financially and technically by the COCOMO 2.0 Pro-
gram Affiliates: Aerospace, AT&T Bell Labs, Bellcore, DISA, EDS, E-Systems, Hewlett-Packard,
Hughes, IDA, IDE, JPL, Litton Data Systems, Lockheed, Loral, MDAC, Motorola, Northrop, Ra-
tional, Rockwell, SAIC, SEI, SPC, Sun, TASC, Teledyne, TI, TRW, USAF Rome Lab, US Army
Research Lab, Xerox.
9. REFERENCES
Amadeus (1994), Amadeus Measurement System Users Guide, Version 2.3a, Amadeus Software
Research, Inc., Irvine, California, July 1994.
Banker, R., R. Kauffman and R. Kumar (1994), An Empirical Test of Object-Based Output Mea-
surement Metrics in a Computer Aided Software Engineering (CASE) Environment,
Journal of Management Information Systems (to appear, 1994).
Model Optimistic Estimate Pessimistic Estimate
Application Composition 0.50 E 2.0 E
Early Design 0.67 E 1.5 E
Post-Architecture 0.80 E 1.25 E
than the 17 Post-Architecture cost drivers. However, their larger productivity ranges (up to 5.45
for PERS and 5.21 for RCPX) stimulate more variability in their resulting estimates. This situation
is addressed by assigning a higher standard deviation to Early Design (versus Post-Architecture)
estimates; see Section 7.3.
6.2 Development Schedule Estimates
The original COCOMO used the waterfall-oriented Software Requirements Review and
Software Acceptance Test as its development cost and schedule estimation endpoints. With non-
waterfall process models the back endpoint is still basically appropriate (at least for the initial de-
livery of an evolving system), but the front endpoint needs to be rethought, particularly for sched-
ule estimation. Our current proposed approach is as follows:
For Applications Composition, the front endpoint is a milestone marking stakeholder
concurrence on the systems basic functionality, concept of operation, and technical ap-
proach.
For other approaches, schedules will be estimated separately for the Early Design and
Post-Architecture stages. The Early Design stage has the same beginning milestone as
has Applications Composition. Its ending milestone, and the beginning milestone of the
Post-Architecture stage, is an Architecture Readiness Review marking stakeholder con-
currence on the life-cycle appropriateness and acceptable risk-freedom of the proposed
architecture. A Software Acceptance Test is the back endpoint of the Post-Architecture
stage. For the Post-Architecture stage, the Ada COCOMO incremental development
model can be used for incremental development cost and schedule estimation.
For the Post-Architecture stage, the previously proposed schedule estimation model
will be used, with the 3.0 coefficient replaced by 2.5. Schedule estimation models for
the other two stages are under development. These will use size; personnel experience
(precedentedness) and capability ratings; team cohesion; and multisite development as
primary schedule drivers.
(4)
The quantity PM differs from PM in that it eliminates the effect of the SCED effort multi-
plier. This clears up an anomaly in the original COCOMO, in which a 75% schedule com-
pression setting would not achieve 75% of the nominal schedule because of the effect of
the SCED multiplier on the PM estimate.
6.3 Output Ranges
A number of COCOMO users have expressed a preference for estimate ranges rather than point
estimates as COCOMO outputs. The three-models of COCOMO 2.0 enable the estimation of likely
ranges of output estimates, using the costing and sizing accuracy relationships in Section 3.2, Fig-
ure 2. Once the most likely effort estimate E is calculated from the chosen model (Application
Composition, Early Design, or Post-Architecture), a set of optimistic and pessimistic estimates,
representing roughly one standard deviation around the most likely estimate, are calculated as fol-
TDEV 2.5 PM ( )
0.33 0.2 B 1.01 ( ) + ( )

SCEDPercentage
100
---------------------------------------------- =
5.3.4 PROJECT FACTORS
SITE - Multisite Development
Given the increasing frequency of multisite developments, and indications that multisite
development effects are significant, the SITE cost driver has been added in COCOMO 2.0. Deter-
mining its cost driver rating involves the assessment and averaging of two factors: site collocation
(from fully collocated to international distribution) and communication support (from surface mail
and some phone access to full interactive multimedia).
6. Additional COCOMO 2.0 Capabilities
This section covers the remainder of the initial COCOMO 2.0 capabilities: Early Design and
Post-Architecture estimation models using Function Points; schedule estimation, and output esti-
mate ranges. Further COCOMO 2.0 capabilities, such as the effects of reuse and applications com-
position on phase and activity distribution of effort and schedule, will be covered in future papers.
6.1 Early Design and Post-Architecture Function Point Estimation
Once one has estimated a products Unadjusted Function Points, using the procedure in Section
4.2.2 and Figure 5, one needs to account for the products level of implementation language (as-
sembly, higher order language, fourth-generation language, etc.) in order to assess the relative con-
ciseness of implementation per function point. COCOMO 2.0 does this for both Early Design and
Post-Architecture models by using tables such as those generated by Software Productivity Re-
search [SPR 1993] to translate Unadjusted Function Points into equivalent SLOC.
For Post-Architecture, the calculations then proceed in the same way as with SLOC. In fact,
one can implement COCOMO 2.0 to enable some components to be sized using function points,
and others (which function points may not describe well, such as real-time or scientific computa-
tions) in SLOC.
For Early Design function point estimation, conversion to equivalent SLOC and application of
the scaling factors in Section 5 are handled in the same way as for Post-Architecture. In Early De-
sign, however, a reduced set of effort multiplier cost drivers is used. These are obtained by com-
bining the Post-Architecture cost drivers as shown in Table 9.
The resulting seven cost drivers are easier to estimate in early stages of software development
Table 5: Early Design and Post-Architecture Cost Drivers
Early Design Cost Driver
Counterpart Combined
Post-Arch. Cost Driver
RCPX RELY, DATA, CPLX, DOCU
RUSE RUSE
PDIF TIME, STOR, PVOL
PERS ACAP, PCAP, PCON
PREX AEXP, PEXP, LTEX
FCIL TOOL, SITE
SCED SCED
DOCU - Documentation match to life-cycle needs
Several software cost models have a cost driver for the level of required documentation. In
COCOMO 2.0, the rating scale for the DOCU cost driver is evaluated in terms of the suitability of
the projects documentation to its life-cycle needs. The rating scale goes from Very Low (many
life-cycle needs uncovered) to Very High (very excessive for life-cycle needs).
5.3.2 PLATFORM FACTORS
The platform refers to the target-machine complex of hardware and infrastructure software
(previously called the virtual machine). The factors have been revised to reflect this as described
in this section. Some additional platform factors were considered, such as distribution, parallelism,
embeddedness, and real-time operation, but these considerations have been accommodated by the
expansion of the Module Complexity ratings in Table 5.
PVOL - Platform Volatility
Platform is used here to mean the complex of hardware and software (OS, DBMS, etc.)
the software product calls on to perform its tasks. If the software to be developed is an operating
system then the platform is the computer hardware. If a database management system is to be de-
veloped then the platform is the hardware and the operating system. If a network text browser is to
be developed then the platform is the network, computer hardware, the operating system, and the
distributed information repositories. The platform includes any compilers or assemblers support-
ing the development of the software system. This rating ranges from low, where there is a major
change every 12 months, to very high, where there is a major change every two weeks.
5.3.3 PERSONNEL FACTORS
PEXP - Platform Experience
COCOMO 2.0 broadens the productivity influence of PEXP, recognizing the importance
of understanding the use of more powerful platforms, including more graphic user interface, data-
base, networking, and distributed middleware capabilities;
LTEX - Language and Tool Experience
This is a measure of the level of programming language and software tool experience of the
project team developing the software system or subsystem. Software development includes the use
of tools that perform requirements and design representation and analysis, configuration manage-
ment, document extraction, library management, program style and formatting, consistency check-
ing, etc. In addition to experience in programming with a specific language the supporting tool set
also effects development time. A low rating given for experience of less than 2 months. A very high
rating is given for experience of 6 or more years.
PCON - Personnel Continuity
The rating scale for PCON is in terms of the projects annual personnel turnover: from 3%,
very high, to 48%, very low.
Table 4: Effort Multipliers Cost Driver Ratings for the Post-Architecture Model
Very Low Low Nominal High Very High Extra High
RELY slight inconve-
nience
low, easily
recoverable
losses
moderate, eas-
ily recoverable
losses
high nancial
loss
risk to human
life
DATA DB bytes/Pgm
SLOC < 10
10 D/P < 100 100 D/P <
1000
D/P 1000
CPLX see Table 5
RUSE none across project across program across product
line
across multi-
ple product
lines
DOCU Many life-
cycle needs
uncovered
Some life-
cycle needs
uncovered.
Right-sized to
life-cycle
needs
Excessive for
life-cycle
needs
Very excessive
for life-cycle
needs
TIME 50% use of
available exe-
cution time
70% 85% 95%
STOR 50% use of
available stor-
age
70% 85% 95%
PVOL major change
every 12 mo.;
minor change
every 1 mo.
major: 6 mo.;
minor: 2 wk.
major: 2 mo.;
minor: 1 wk.
major: 2 wk.;
minor: 2 days
ACAP 15th percentile 35th percentile 55th percentile 75th percentile 90th percentile
PCAP 15th percentile 35th percentile 55th percentile 75th percentile 90th percentile
PCON 48% / year 24% / year 12% / year 6% / year 3% / year
AEXP 2 months 6 months 1 year 3 years 6 years
PEXP 2 months 6 months 1 year 3 years 6 year
LTEX 2 months 6 months 1 year 3 years 6 year
TOOL edit, code,
debug
simple, fron-
tend, backend
CASE, little
integration
basic lifecycle
tools, moder-
ately integrated
strong, mature
lifecycle tools,
moderately
integrated
strong,
mature, proac-
tive lifecycle
tools, well inte-
grated with
processes,
methods, reuse
SITE:
Collocation
International Multi-city and
Multi-com-
pany
Multi-city or
Multi-com-
pany
Same city or
metro. area
Same building
or complex
Fully collo-
cated
SITE:
Communications
Some phone,
mail
Individual
phone, FAX
Narrowband
email
Wideband
electronic
communica-
tion.
Wideband
elect. comm,
occasional
video conf.
Interactive
multimedia
SCED 75% of nomi-
nal
85% 100% 130% 160%
If B = 1.0, the economies and diseconomies of scale are in balance. This linear model is
often used for cost estimation of small projects. It is used for the COCOMO 2.0 Applications Com-
position model.
If B > 1.0, the project exhibits diseconomies of scale. This is generally due to two main
factors: growth of interpersonal communications overhead and growth of large-system integration
overhead. Larger projects will have more personnel, and thus more interpersonal communications
paths consuming overhead. Integrating a small product as part of a larger product requires not only
the effort to develop the small product, but also the additional overhead effort to design, maintain,
integrate, and test its interfaces with the remainder of the product.
See [Banker et al 1994a] for a further discussion of software economies and diseconomies
of scale.
Process Maturity as a COCOMO 2.0 Cost Driver
The Process Maturity scale factor is organized around the 18 Key Process Areas (KPAs) in
the SEI Capability Maturity Model. The rating is determined by a projects compliance with the 18
KPAs using one of two schemes:
Percentage compliance for the overall KPA based on existing KPA goal or Key Practice
compliance assessment data;
Levels of compliance to the KPAs goals (typically 2 to 4 per KPA) rated on a 5-level
scale.
Given these inputs, a process maturity index is computed for the project. Putting the con-
tribution in the exponent means that process maturity effects will be larger on large-scale projects
than on small ones. Using a 0-to-5 scale rather than a 1-to-5 scale as in the CMM reflects our judge-
ment that rework effort will be reduced more by getting to Level 3 than by going from Level
3 to Level 5, where more of the contribution may be due to other factors than rework reduction
which are already accounted for in COCOMO 2.0 (e.g., reuse).
5.3 MULTIPLICATIVE COST DRIVERS
There are 17 cost drivers used in the COCOMO 2.0 Post-Architecture model to adjust the
model to reflect the software product under development. They are grouped into four categories:
product, platform, personnel, and project. Table 3 lists all of the cost drivers with their rating cri-
terion. This section discusses only the new cost drivers added to this model. See Table 1 for the
differences between the original COCOMO and this version of the model. The counterpart 7 cost
drivers for the Early Design Model are defined in [Boehm et al. 1995].
5.3.1 PRODUCT FACTORS
RUSE - Required Reusability
This cost driver accounts for the additional effort needed to construct components intended
for reuse on the current or future projects. This effort is consumed with creating more generic de-
sign of software, more elaborate documentation, and more extensive testing to ensure components
are ready for use in other applications.
1.0. The exponential cost drivers, called Scale Factors and represented by the B exponent, account
for the relative economies or diseconomies of scale encountered as a software project increases its
size. This set is described in the next section. A constant, A, is used to capture the linear effects on
effort with projects of increasing size. The estimated effort for a given size project is expressed in
person months (PM), see (2) The following sections discuss the new COCOMO 2.0 cost drivers.
(2)
5.2 EXPONENT SCALE FACTORS
Table 3 provides the rating levels for the COCOMO 2.0 exponent scale factors. A project's
numerical ratings W
i
are summed across all of the factors, and used to determine a scale exponent
B via the following formula:
(3)
Thus, a 100 KSLOC project with Extra High (0) ratings for all factors will have W
i
= 0, B
= 1.01, and a relative effort E = 100
1.01
= 105 PM. A project with Very Low (5) ratings for all fac-
tors will have W
i
= 25, B = 1.26, and a relative effort E = 331 PM. This represents a large variation,
but the increase involved in a one-unit change in one of the factors is only about 4.7%. Thus, this
approach avoids the 40% swings involved in choosing a development mode for a 100 KSLOC
product in the original COCOMO.
If B < 1.0, the project exhibits economies of scale. If the product's size is doubled, the
project effort is less than doubled. The project's productivity increases as the product size is in-
creased. Some project economies of scale can be achieved via project-specific tools (e.g., simula-
tions, testbeds), but in general these are difficult to achieve. For small projects, fixed startup costs
such as tailoring and setup of standards and administrative reports are a source of economies of
scale.
* % significant module interfaces specified,% significant risks eliminated.
Table 3: Rating Scheme for the COCOMO 2.0 Scale Factors
Scale Factors
(W
i
)
Very Low
(5)
Low
(4)
Nominal
(3)
High
(2)
Very High
(1)
Extra High
(0)
Precedentedness thoroughly
unprecedented
largely
unprecedented
somewhat
unprecedented
generally
familiar
largely famil-
iar
throughly
familiar
Development
Flexibility
rigorous occasional
relaxation
some
relaxation
general
conformity
some
conformity
general goals
Architecture /
risk resolution
*
little (20%) some (40%) often (60%) generally
(75%)
mostly (90%)
full
(
100%
)
Team cohesion very difcult
interactions
some difcult
interactions
basically
cooperative
interactions
largely
cooperative
highly
cooperative
seamless
interactions
Process maturity See discussion in this paper.
PM
estimated
EM
i
i



A Size ( )
B
=
B 1.01 0.01W
i
+ =
this in its allocation of estimated effort for modifying reusable software.
The reuse equation for equivalent new software (ESLOC) to be developed is:
(1)
This involves estimating the amount of software to be adapted, ASLOC, and three degree-
of-modification parameters: the percentage of design modification (DM); the percentage of code
modification (CM), and the percentage of the original integration effort required for integrating the
reused software (IM). The Software Understanding increment (SU) is rated very high on structure,
applications clarity, and self-descriptiveness. For this rating the software understanding and inter-
face checking penalty is only 10%. If the software is rated very low on these factors, the penalty is
50%.
The other nonlinear reuse increment deals with the degree of Assessment and Assimilation
(AA) needed to determine whether even a fully-reused software module is appropriate to the ap-
plication, and to integrate its description into the overall product description.
5. COCOMO 2.0 COST MODELING
5.1 MODELING EFFORT
This software cost estimation model uses sets of multiplicative and exponential cost drivers
to adjust for project, target platform, personnel, and product characteristics. The set of multiplica-
tive cost drivers are called Effort Multipliers (EM). The nominal weight assigned to each EM is
1.0. If a rating level has a detrimental effect on effort, then its corresponding multiplier is above
1.0. Conversely, if the rating level reduces the effort then the corresponding multiplier is less than
Figure 5. Nonlinear Reuse Effects
0.5
0.25
0.75
1.0
0.046
0.25 0.5 0.75 1.0
Usual Linear Assumption
Data on 2954
NASA modules
[Selby, 1988]
Relative
Cost
Amount Modified
0.55
0.70
1.00
ESLOC ASLOC
AA SU + 0.4 DM 0.3 CM 0.3 IM + + + ( )
100
------------------------------------------------------------------------------------------------------------------- =
maintenance involves understanding the software to be modified. Thus, as soon as one goes from
unmodified (black-box) reuse to modified-software (white-box) reuse, one encounters this soft-
ware understanding penalty. Also, [Gerlich and Denskat 1994] shows that, if one modifies k out of
m software modules, the number N of module interface checks required is N = k * (m-k) + k * (k-
1)/2.
The size of both the software understanding penalty and the module interface checking pen-
alty can be reduced by good software stucturing. Modular, hierarchical structuring can reduce the
number of interfaces which need checking [Gerlich and Denskat 1994], and software which is well
structured, explained, and related to its mission will be easier to understand. COCOMO 2.0 reflects
Step 1: Determine function counts by type. The unadjusted function counts should be counted
by a lead technical person based on information in the software requirements and de-
sign documents. The number of each of the five user function types should be counted
(Internal Logical File
*
(ILF), External Interface File (EIF), External Input (EI), Exter-
nal Output (EO), and External Inquiry (EQ)).
Step 2: Determine complexity-level function counts. Classify each function count into Low,
Average and High complexity levels depending on the number of data element types
contained and the number of file types referenced. Use the following scheme:
Step 3: Apply complexity weights. Weight the number in each cell using the following scheme.
The weights reflect the relative value of the function to the user.
Step 4: Compute Unadjusted Function Points. Add all the weighted functions counts to get one
number, the Unadjusted Function Points.
*
Note: The word le refers to a logically related group of data and not the physical implementation of those
groups of data
For ILF and EIF For EO and EQ For EI
Record
Elements
Data Elements
File
Types
Data Elements
File
Types
Data Elements
1 - 19 20 - 50 51+ 1 - 5 6 - 19 20+ 1 - 4 5 - 15 16+
1 Low Low Avg 0 or 1 Low Low Avg 0 or 1 Low Low Avg
2 - 5 Low Avg High 2 - 3 Low Avg High 2 - 3 Low Avg High
6+ Avg High High 4+ Avg High High 3+ Avg High High
Function Type
Complexity-Weight
Low Average High
Internal Logical Files 7 10 15
External Interfaces Files 5 7 10
External Inputs 3 4 6
External Outputs 4 5 7
External Inquiries 3 4 6
Figure 4. Function Count Procedure
ity, thus have a maximum of 5% contribution to estimated effort. This is inconsistent with COCO-
MO experience; thus COCOMO 2.0 uses Unadjusted Function Points for sizing, and applies its
reuse factors, cost driver effort multipliers, and exponent scale factors to this sizing quantity. The
COCOMO 2.0 procedure for determining Unadjusted Function Points is shown in Figure 4.
4.3 ADJUSTING SOFTWARE DEVELOPMENT SIZE
4.3.1 BREAKAGE
COCOMO 2.0 replaces the COCOMO Requirements Volatility effort multiplier and the
Ada COCOMO Requirements Volatility exponent driver by a breakage percentage, BRAK, used
to adjust the effective size of the product. Consider a project which delivers 100,000 instructions
but discards the equivalent of an additional 20,000 instructions. This project would have a BRAK
value of 20, which would be used to adjust its effective size to 120,000 instructions for COCOMO
2.0 estimation. The BRAK factor is not used in the Applications Composition model, where a cer-
tain degree of product iteration is expected, and included in the data calibration.
4.3.2 EFFECTS FROM REUSE
The COCOMO 2.0 model uses a nonlinear estimation model for estimating size in reusing
software products. Analysis in [Selby 1988] of reuse costs across nearly 3000 reused modules in
the NASA Software Engineering Laboratory indicates that the reuse cost function is nonlinear in
two significant ways (see Figure 5):
It does not go through the origin. There is generally a cost of about 5% for assessing,
selecting, and assimilating the reusable component.
Small modifications generate disproportionately large costs. This is primarily due to
two factors: the cost of understanding the software to be modified, and the relative cost
of interface checking.
[Parikh and Zvegintzov 1983] contains data indicating that 47% of the effort in software
Table 2: User Function Types
External Input (Inputs) Count each unique user data or user control input type that (i) enters
the external boundary of the software system being measured and
(ii) adds or changes data in a logical internal le.
External Output (Outputs) Count each unique user data or control output type that leaves the
external boundary of the software system being measured.
Internal Logical File (Files) Count each major logical group of user data or control information
in the software system as a logical internal le type. Include each
logical le (e.g., each logical group of data) that is generated, used,
or maintained by the software system.
External Interface Files (Interfaces) Files passed or shared between software systems should be counted
as external interface le types within each system.
External Inquiry (Queries) Count each unique input-output combination, where an input causes
and generates an immediate output, as an external inquiry type.
cutable statements and data declarations in different languages. The goal is to measure the amount
of intellectual work put into program development, but difficulties arise when trying to define con-
sistent measures across different languages. To minimize these problems, the Software Engineer-
ing Institute (SEI) definition checklist for a logical source statement is used in defining the line of
code measure. The Software Engineering Institute (SEI) has developed this checklist as part of a
system of definition checklists, report forms and supplemental forms to support measurement def-
initions [Park 1992, Goethert et al. 1992].
Some changes were made to the line-of-code definition that depart from the default definition
provided in [Park 1992]. These changes eliminate categories of software which are generally small
sources of project effort. Not included in the definition are commercial-off-the-shelf software
(COTS), government furnished software (GFS), other products, language support libraries and op-
erating systems, or other commercial libraries. Code generated with source code generators is not
included though measurements will be taken with and without generated code to support analysis.
The COCOMO 2.0 line-of-code definition is calculated directly by the Amadeus automated
metrics collection tool [Amadeus 1994] [Selby et al. 1991], which is being used to ensure uniform-
ly collected data in the COCOMO 2.0 data collection and analysis project. We have developed a
set of Amadeus measurement templates that support the COCOMO 2.0 data definitions for use by
the organizations collecting data, in order to facilitate standard definitions and consistent data
across participating sites.
To support further data analysis, Amadeus will automatically collect additional measures in-
cluding total source lines, comments, executable statements, declarations, structure, component in-
terfaces, nesting, and others. The tool will provide various size measures, including some of the
object sizing metrics in [Chidamber and Kemerer 1994], and the COCOMO sizing formulation
will adapt as further data is collected and analyzed.
4.2.2 Function Point Counting Rules
The function point cost estimation approach is based on the amount of functionality in a soft-
ware project and a set of individual project factors [Behrens 1983] [Kunkler 1985] [IFPUG 1994].
Function points are useful estimators since they are based on information that is available early in
the project life cycle. A brief summary of function points and their calculation in support of CO-
COMO 2.0 is as follows.
Function Point Introduction
Function points measure a software project by quantifying the information processing func-
tionality associated with major external data or control input, output, or file types. Five user func-
tion types should be identified, as defined in Table 2.
Each instance of these function types is then classified by complexity level. The complexity
levels determine a set of weights, which are applied to their corresponding function counts to de-
termine the Unadjusted Function Points quantity. This is the Function Point sizing metric used by
COCOMO 2.0. The usual Function Point procedure involves assessing the degree of influence (DI)
of fourteen application characteristics on the software project determined according to a rating
scale of 0.0 to 0.05 for each characteristic. The 14 ratings are added together, and added to a base
level of 0.65 to produce a general characteristics adjustment factor that ranges from 0.65 to 1.35.
Each of these fourteen characteristics, such as distributed functions, performance, and reusabil-
Figure 3. Baseline Object Point Estimation Procedure
Step 1: Assess Object-Counts: estimate the number of screens, reports, and 3GL components
that will comprise this application. Assume the standard definitions of these objects in
your ICASE environment.
Step 2: Classify each object instance into simple, medium and difficult complexity levels de-
pending on values of characteristic dimensions. Use the following scheme:
Step 3: Weigh the number in each cell using the following scheme. The weights reflect the rel-
ative effort required to implement an instance of that complexity level.:
Step 4: Determine Object-Points: add all the weighted object instances to get one number, the
Object-Point count.
Step 5: Estimate percentage of reuse you expect to be achieved in this project. Compute the
New Object Points to be developed,
Step 6: Determine a productivity rate, PROD = NOP / person-month, from the following
scheme
Step 7: Compute the estimated person-months: PM = NOP / PROD.
For Screens For Reports
Number of
Views
contained
# and source of data tables
Number of
Sections
contained
# and source of data tables
Total < 4
(< 2 srvr
< 3 clnt)
Total < 8
(2/3 srvr
3-5 clnt)
Total 8+
(> 3 srvr
> 5 clnt)
Total < 4
(< 2 srvr
< 3 clnt)
Total < 8
(2/3 srvr
3-5 clnt)
Total 8+
(> 3 srvr
> 5 clnt)
< 3 simple simple medium 0 or 1 simple simple medium
3 - 7 simple medium difcult 2 or 3 simple medium difcult
> 8 medium difcult difcult 4 + medium difcult difcult
Object Type
Complexity-Weight
Simple Medium Difcult
Screen 1 2 3
Report 2 5 8
3GL Component 10
Developers experience and capability Very Low Low Nominal High Very High
ICASE maturity and capability Very Low Low Nominal High Very High
PROD 4 7 13 25 50
NOP Object Points ( )
100 %reuse ( )
100
--------------------------------------- =
4.1.1 COCOMO 2.0 Object Point Estimation Procedure
Figure 3 presents the baseline COCOMO 2.0 Object Point procedure for estimating the effort
involved in Applications Composition and prototyping projects. It is a synthesis of the procedure
in Appendix B.3 of [Kauffman and Kumar 1993] and the productivity data from the 19 project data
points in [Banker et al. 1994].
Definitions of terms in Figure 3 are as follows:
NOP: New Object Points (Object Point count adjusted for reuse)
srvr: number of server (mainframe or equivalent) data tables used in conjunction with
the SCREEN or REPORT.
clnt: number of client (personal workstation) data tables used in conjunction with the
SCREEN or REPORT.
%reuse: the percentage of screens, reports, and 3GL modules reused from previous ap-
plications, pro-rated by degree of reuse.
The productivity rates in Figure 3 are based on an analysis of the year-1 and year-2 project data
in [Banker et al. 1994]. In year-1, the CASE tool was itself under construction and the developers
were new to its use. The average productivity of 7 NOP/person-month in the twelve year-1 projects
is associated with the Low levels of developer and ICASE maturity and capability in Figure 3. In
the seven year-2 projects, both the CASE tool and the developers capabilities were considerably
more mature. The average productivity was 25 NOP/person-month, corresponding with the High
levels of developer and ICASE maturity in Figure 3.
As another definitional point, note that the use of the term object in Object Points defines
screens, reports, and 3GL modules as objects. This may or may not have any relationship to other
definitions of objects, such as those possessing features such as class affiliation, inheritance, en-
capsulation, message passing, and so forth. Counting rules for objects of that nature, when used
in languages such as C++, will be discussed under source lines of code in the next section.
4.2 Applications Development
As described in Section 3.2, the COCOMO 2.0 model uses function points and/or source lines
of code as the basis for measuring size for the Early Design and Post-Architecture estimation mod-
els. For comparable size measurement across COCOMO 2.0 participants and users, standard
counting rules are necessary. A consistent definition for size within projects is a prerequisite for
project planning and control, and a consistent definition across projects is a prerequisite for process
improvement [Park 1992].
The COCOMO 2.0 model has adopted counting rules that have been formulated by wide com-
munity participation or standardization efforts. The source lines of code metrics are based on the
Software Engineering Institute source statement definition checklist [Park 1992]. The function
point metrics are based on the International Function Point User Group (IFPUG) Guidelines and
applications of function point calculation [IFPUG 1994] [Behrens 1983] [Kunkler 1985].
4.2.1 Lines of Code Counting Rules
In COCOMO 2.0, the logical source statement has been chosen as the standard line of code.
Defining a line of code is difficult due to conceptual differences involved in accounting for exe-
* Different multipliers.
Different rating scale
Table 1: Comparison of COCOMO, Ada COCOMO, and COCOMO 2.0
COCOMO Ada COCOMO
COCOMO 2.0:
Stage 1
COCOMO 2.0:
Stage 2
COCOMO 2.0:
Stage 3
Size Delivered Source Instructions (DSI)
or Source Lines Of Code (SLOC)
DSI or SLOC Object Points Function Points (FP) and
Language
FP and Language or
SLOC
Reuse Equivalent SLOC =
Linear f(DM, CM, IM)
Equivalent SLOC =
Linear f(DM, CM, IM)
Implicit in model % unmodied reuse: SR
% modied reuse:
nonlinear
f(AA,SU,DM,CM,IM)
Equivalent SLOC =
nonlinear
f(AA,SU,DM,CM,IM)
Breakage Requirements Volatility
rating: (RVOL)
RVOL rating Implicit in model Breakage %: BRAK BRAK
Maintenance Annual Change Trafc (ACT) =
%added + %modied
ACT Object Point
Reuse Model
Reuse model Reuse model
Scale (b) in
MM
NOM
= a(Size)
b
Organic: 1.05
Semidetached: 1.12
Embedded: 1.20
Embedded: 1.04 - 1.24
depending on degree of:
early risk elimination
solid architecture
stable requirements
Ada process maturity
1.0
1.01 - 1.26 depending on
the degree of:
precedentedness
conformity
early architecture,
risk resolution
team cohesion
process maturity (SEI)
1.01 - 1.26 depending on
the degree of:
precedentedness
conformity
early architecture,
risk resolution
team cohesion
process maturity (SEI)
Product Cost Drivers RELY, DATA, CPLX
RELY
*
, DATA,
CPLX
*
, RUSE
None
RCPX
*
, RUSE
*
RELY, DATA, DOCU
*
CPLX

, RUSE
*
Platform Cost Drivers TIME, STOR, VIRT,TURN TIME, STOR, VMVH,
VMVT, TURN
None Platform difculty:
PDIF
*
TIME, STOR,
PVOL(=VIRT)
Personnel Cost Drivers ACAP, AEXP, PCAP,
VEXP, LEXP
ACAP
*
, AEXP, PCAP
*
,
VEXP, LEXP
*
None Personnel capability and
experience:
PERS
*
, PREX
*
ACAP
*
, AEXP

, PCAP
*
,
PEXP
*
, LTEX
*
,
PCON
*
Project Cost Drivers MODP, TOOL, SCED
MODP
*
, TOOL
*
,
SCED, SECU
None
SCED, FCIL
*
TOOL
*
, SCED, SITE
*
ysis should also enable the further calibration of the relationships between object points, function
points, and source lines of code for various languages and composition systems, enabling flexibil-
ity in the choice of sizing parameters.
3.3 Other Major Differences Between COCOMO and COCOMO 2.0
The tailorable mix of models and variable-granularity cost model inputs and outputs are not the
only differences between the original COCOMO and COCOMO 2.0. The other major differences
involve size-related effects involving reuse and re-engineering, changes in scaling effects, and
changes in cost drivers. These are summarized in Table 1. Explanations of the acronyms and ab-
breviations in Table 1 are provided at the end of this paper.
4. Cost Factors: Sizing
This Section provides the definitions and rationale for the three sizing quantities used in CO-
COMO 2.0: Object Points, Unadjusted Function Points, and Source Lines of Code. It then discuss-
es the COCOMO 2.0 size-related parameters used in dealing with software reuse, re-engineering,
conversion, and maintenance.
4.1 Applications Composition: Object Points
Object Point estimation is a relatively new software sizing approach, but it is well-matched to
the practices in the Applications Composition sector. It is also a good match to associated proto-
typing efforts, based on the use of a rapid-composition Integrated Computer Aided Software En-
vironment (ICASE) providing graphic user interface builders, software development tools, and
large, composable infrastructure and applications components. In these areas, it has compared well
to Function Point estimation on a nontrivial (but still limited) set of applications.
The [Banker et al. 1994] comparative study of Object Point vs. Function Point estimation ana-
lyzed a sample of 19 investment banking software projects from a single organization, developed
using ICASE applications composition capabilities, and ranging from 4.7 to 71.9 person-months
of effort. The study found that the Object Points approach explained 73% of the variance (R
2
) in
person-months adjusted for reuse, as compared to 76% for Function Points.
A subsequent statistically-designed experiment [Kaufman and Kumar 1993] involved four ex-
perienced project managers using Object Points and Function Points to estimate the effort required
on two completed projects (3.5 and 6 actual person-months), based on project descriptions of the
type available at the beginning of such projects. The experiment found that Object Points and
Function Points produced comparably accurate results (slightly more accurate with Object Points,
but not statistically significant). From a usage standpoint, the average time to produce an Object
Point estimate was about 47% of the corresponding average time for Function Point estimates. Al-
so, the managers considered the Object Point method easier to use (both of these results were sta-
tistically significant).
Thus, although these results are not yet broadly-based, their match to Applications Composi-
tion software development appears promising enough to justify selecting Object Points as the start-
ing point for the COCOMO 2.0 Applications Composition estimation model.
With respect to process strategy, Application Generator, System Integration, and Infrastructure
software projects will involve a mix of three major process models. The appropriate sequencing of
these models will depend on the projects marketplace drivers and degree of product understand-
ing.
The Application Composition model involves prototyping efforts to resolve potential high-risk
issues such as user interfaces, software/system interaction, performance, or technology maturity.
The costs of this type of effort are best estimated by the Applications Composition model.
The Early Design model involves exploration of alternative software/system architectures and
concepts of operation. At this stage, not enough is generally known to support fine-grain cost esti-
mation. The corresponding COCOMO 2.0 capability involves the use of function points and a
small number of additional cost drivers.
The Post-Architecture model involves the actual development and maintenance of a software
product. This model proceeds most cost-effectively if a software life-cycle architecture has been
developed; validated with respect to the system's mission, concept of operation, and risk; and es-
tablished as the framework for the product. The corresponding COCOMO 2.0 model has about the
same granularity as the previous COCOMO and Ada COCOMO models. It uses source instruc-
tions and / or function points for sizing, with modifiers for reuse and software breakage; a set of
17 multiplicative cost drivers; and a set of 5 factors determining the project's scaling exponent.
These factors replace the development modes (Organic, Semidetached, or Embedded) in the orig-
inal COCOMO model, and refine the four exponent-scaling factors in Ada COCOMO.
To summarize, COCOMO 2.0 provides the following three-model series for estimation of Ap-
plication Generator, System Integration, and Infrastructure software projects:
1. The earliest phases or spiral cycles will generally involve prototyping, using Applica-
tion Composition capabilities. The COCOMO 2.0 Application Composition model
supports these phases, and any other prototyping activities occurring later in the life cy-
cle.
2. The next phases or spiral cycles will generally involve exploration of architectural al-
ternatives or incremental development strategies. To support these activities, COCO-
MO 2.0 provides an early estimation model. This uses function points for sizing, and a
coarse-grained set of 5 cost drivers (e.g., two cost drivers for Personnel Capability and
Personnel Experience in place of the 6 current Post-Architecture model cost drivers
covering various aspects of personnel capability, continuity and experience). Again,
this level of detail is consistent with the general level of information available and the
general level of estimation accuracy needed at this stage.
3. Once the project is ready to develop and sustain a fielded system, it should have a life-
cycle architecture, which provides more accurate information on cost driver inputs, and
enables more accurate cost estimates. To support this stage of development, COCOMO
2.0 provides a model whose granularity is roughly equivalent to the current COCOMO
and Ada COCOMO models. It can use either source lines of code or function points for
a sizing parameter, a refinement of the COCOMO development modes as a scaling fac-
tor, and 17 multiplicative cost drivers.
The above should be considered as current working hypotheses about the most effective forms
for COCOMO 2.0. They will be subject to revision based on subsequent data analysis. Data anal-
for an example of such tailoring guidelines).
Second, the granularity of the software cost estimation model used needs to be consistent with
the granularity of the information available to support software cost estimation. In the early stages
of a software project, very little may be known about the size of the product to be developed, the
nature of the target platform, the nature of the personnel to be involved in the project, or the de-
tailed specifics of the process to be used.
Figure 2, extended from [Boehm 1981, p. 311], indicates the effect of project uncertainties on
the accuracy of software size and cost estimates. In the very early stages, one may not know the
specific nature of the product to be developed to better than a factor of 4. As the life cycle proceeds,
and product decisions are made, the nature of the products and its consequent size are better known,
and the nature of the process and its consequent cost drivers are better known. The earlier com-
pleted programs size and effort data points in Figure 2 are the actual sizes and efforts of seven
software products built to an imprecisely-defined specification [Boehm et al. 1984]

. The later
USAF/ESD proposals data points are from five proposals submitted to the U.S. Air Force Elec-
tronic Systems Division in response to a fairly thorough specification [Devenny 1976].
Third, given the situation in premises 1 and 2, COCOMO 2.0 enables projects to furnish
coarse-grained cost driver information in the early project stages, and increasingly fine-grained in-
formation in later stages. Consequently, COCOMO 2.0 does not produce point estimates of soft-
ware cost and effort, but rather range estimates tied to the degree of definition of the estimation
inputs. The uncertainty ranges in Figure 2 are used as starting points for these estimation ranges.

These seven projects implemented the same algorithmic version of the Intermediate COCOMO cost model,
but with the use of different interpretations of the other product specications: produce a friendly user inter-
face with a single-user le system.
Figure 2. Software Costing and Sizing Accuracy vs. Phase
L
I

G
G
G
G
G
G
G
G
G
G
G
Relative
Size
Range
Phases and Milestones
4x
2x
1.5x
1.25x
x
0.5x
0.25x
L L L L L
Feasibility Plans
Concept of
Operation
Rqts.
Spec.
Product
Design
Product
Design
Spec.
and
Rqts.
Devel.
and
Test
Accepted
Software
Detail
Design
Spec.
Detail
Design
I

Size (SLOC)
Cost ($)

I
I
I
I
I
I
I
I
I
I
I
USAF/ESD
Proposals
Completed
Programs
3. COCOMO 2.0 STRATEGY AND RATIONALE
The four main elements of the COCOMO 2.0 strategy are:
Preserve the openness of the original COCOMO;
Key the structure of COCOMO 2.0 to the future software marketplace sectors described
above;
Key the inputs and outputs of the COCOMO 2.0 submodels to the level of information
available;
Enable the COCOMO 2.0 submodels to be tailored to a project's particular process
strategy.
COCOMO 2.0 follows the openness principles used in the original COCOMO. Thus, all of its
relationships and algorithms will be publicly available. Also, all of its interfaces are designed to be
public, well-defined, and parametrized, so that complementary preprocessors (analogy, case-
based, or other size estimation models), post-processors (project planning and control tools, project
dynamics models, risk analyzers), and higher level packages (project management packages, prod-
uct negotiation aids), can be combined straightforwardly with COCOMO 2.0.
To support the software marketplace sectors above, COCOMO 2.0 provides a family of in-
creasingly detailed software cost estimation models, each tuned to the sectors' needs and type of
information available to support software cost estimation.
3.1 COCOMO 2.0 Models for the Software Marketplace Sectors
The User Programming sector does not need a COCOMO 2.0 model. Its applications are typi-
cally developed in hours to days, so a simple activity-based estimate will generally be sufficient.
The COCOMO 2.0 model for the Application Composition sector is based on Object Points.
Object Points are a count of the screens, reports and third-generation-language modules developed
in the application, each weighted by a three-level (simple, medium, difficult) complexity factor
[Banker et al. 1994, Kauffman and Kumar 1993]. This is commensurate with the level of informa-
tion generally known about an Application Composition product during its planning stages, and
the corresponding level of accuracy needed for its software cost estimates (such applications are
generally developed by a small team in a few weeks to months).
The COCOMO 2.0 capability for estimation of Application Generator, System Integration, or
Infrastructure developments is based on a tailorable mix of the Application Composition model
(for early prototyping efforts) and two increasingly detailed estimation models for subsequent por-
tions of the life cycle.
3.2 COCOMO 2.0 Model Rationale and Elaboration
The rationale for providing this tailorable mix of models rests on three primary premises.
First, unlike the initial COCOMO situation in the late 1970's, in which there was a single, pre-
ferred software life cycle model (the waterfall model), current and future software projects will be
tailoring their processes to their particular process drivers. These process drivers include COTS or
reusable software availability; degree of understanding of architectures and requirements; market
window or other schedule constraints; size; and required reliability (see [Boehm 1989, pp. 436-37]
tions, parameters, or simple rules. Every enterprise from Fortune 100 companies to small business-
es and the U.S. Department of Defense will be involved in this sector.
Typical Infrastructure sector products will be in the areas of operating systems, database
management systems, user interface management systems, and networking systems. Increasingly,
the Infrastructure sector will address middleware solutions for such generic problems as distrib-
uted processing and transaction processing. Representative firms in the Infrastructure sector are
Microsoft, NeXT, Oracle, SyBase, Novell, and the major computer vendors.
In contrast to end-user programmers, who will generally know a good deal about their ap-
plications domain and relatively little about computer science, the infrastructure developers will
generally know a good deal about computer science and relatively little about applications. Their
product lines will have many reusable components, but the pace of technology (new processor,
memory, communications, display, and multimedia technology) will require them to build many
components and capabilities from scratch.
Performers in the three middle sectors in Figure 1 will need to know a good deal about com-
puter science-intensive Infrastructure software and also one or more applications domains. Creat-
ing this talent pool is a major national challenge.
The Application Generators sector will create largely prepackaged capabilities for user
programming. Typical firms operating in this sector are Microsoft, Lotus, Novell, Borland, and
vendors of computer-aided planning, engineering, manufacturing, and financial analysis systems.
Their product lines will have many reusable components, but also will require a good deal of new-
capability development from scratch. Application Composition Aids will be developed both by the
firms above and by software product-line investments of firms in the Application Composition sec-
tor.
The Application Composition sector deals with applications which are too diversified to be
handled by prepackaged solutions, but which are sufficiently simple to be rapidly composable from
interoperable components. Typical components will be graphic user interface (GUI) builders, da-
tabase or object managers, middleware for distributed processing or transaction processing, hyper-
media handlers, smart data finders, and domain-specific components such as financial, medical, or
industrial process control packages.
Most large firms will have groups to compose such applications, but a great many special-
ized software firms will provide composed applications on contract. These range from large, ver-
satile firms such as Andersen Consulting and EDS, to small firms specializing in such specialty
areas as decision support or transaction processing, or in such applications domains as finance or
manufacturing.
The Systems Integration sector deals with large scale, highly embedded, or unprecedented
systems. Portions of these systems can be developed with Application Composition capabilities,
but their demands generally require a significant amount of up-front systems engineering and cus-
tom software development. Aerospace firms operate within this sector, as do major system inte-
gration firms such as EDS and Andersen Consulting, large firms developing software-intensive
products and services (telecommunications, automotive, financial, and electronic products firms),
and firms developing large-scale corporate information systems or manufacturing support systems.
MO 2.0s current state. Further details on the definition of COCOMO 2.0 are provided in [Boehm
et al. 1995]
2. FUTURE SOFTWARE PRACTICES MARKETPLACE
MODEL
Figure 1 summarizes the model of the future software practices marketplace that we are us-
ing to guide the development of COCOMO 2.0. It includes a large upper end-user programming
sector with roughly 55 million practitioners in the U.S. by the year 2005; a lower infrastructure
sector with roughly 0.75 million practitioners; and three intermediate sectors, involving the devel-
opment of applications generators and composition aids (0.6 million practitioners), the develop-
ment of systems by applications composition (0.7 million), and system integration of large-scale
and/or embedded software systems (0.7 million)
*
.
End-User Programming will be driven by increasing computer literacy and competitive
pressures for rapid, flexible, and user-driven information processing solutions. These trends will
push the software marketplace toward having users develop most information processing applica-
tions themselves via application generators. Some example application generators are spread-
sheets, extended query systems, and simple, specialized planning or inventory systems. They
enable users to determine their desired information processing application via domain-familiar op-
*
These gures are judgement-based extensions of the Bureau of Labor Statistics moderate-growth labor distri-
bution scenario for the year 2005 [CSTB 1993; Silvestri and Lukasieicz 1991]. The 55 million End-User pro-
gramming gure was obtained by applying judgement based extrapolations of the 1989 Bureau of the Census
data on computer usage fractions by occupation [Kominski 1991] to generate end-user programming frac-
tions by occupation category. These were then applied to the 2005 occupation-category populations (e.g.,
10% of the 25M people in Service Occupations; 40% of the 17M people in Marketing and Sales Occupa-
tions). The 2005 total of 2.75 M software practitioners was obtained by applying a factor of 1.6 to the number
of people traditionally identied as Systems Analysts and Computer Scientists (0.829M in 2005) and
Computer Programmers (0.882M). The expansion factor of 1.6 to cover software personnel with other job
titles is based on the results of a 1983 survey on this topic [Boehm 1983].The 2005 distribution of the 2.75
M software developers is a judgement-based extrapolation of current trends.
Figure 1. Future Software Practices Marketplace Model
End-User Programming
(55M performers in US)
Infrastructure
(0.75M)
Application Generators
and Composition Aids
Application
Composition
System
Integration
(0.6M) (0.7M) (0.7M)
proaches; software process maturity initiativeslead to significant benefits in terms of improved
software quality and reduced software cost, risk, and cycle time.
However, although some of the existing software cost models have initiatives addressing
aspects of these issues, these new approaches have not been strongly matched to date by comple-
mentary new models for estimating software costs and schedules. This makes it difficult for orga-
nizations to conduct effective planning, analysis, and control of projects using the new approaches.
These concerns have led the authors to formulate a new version of the Constructive Cost
Model (COCOMO) for software effort, cost, and schedule estimation. The original COCOMO
[Boehm 1981] and its specialized Ada COCOMO successor [Boehm and Royce 1989] were rea-
sonably well-matched to the classes of software project that they modeled: largely custom, build-
to-specification software [Miyazaki and Mori 1985, Boehm 1985, Goudy 1987]. Although Ada
COCOMO added a capability for estimating the costs and schedules for incremental software de-
velopment, COCOMO encountered increasing difficulty in estimating the costs of business soft-
ware [Kemerer 1987, Ruhl and Gunn 1991], of object-oriented software [Pfleeger 1991], of
software created via spiral or evolutionary development models, or of software developed largely
via commercial-off-the-shelf (COTS) applications-composition capabilities.
1.2 COCOMO 2.0 OBJECTIVES
The initial definition of COCOMO 2.0 and its rationale are described in this paper. The def-
inition will be refined as additional data are collected and analyzed. The primary objectives of the
COCOMO 2.0 effort are:
To develop a software cost and schedule estimation model tuned to the life cycle prac-
tices of the 1990's and 2000's.
To develop software cost database and tool support capabilities for continuous model
improvement.
To provide a quantitative analytic framework, and set of tools and techniques for eval-
uating the effects of software technology improvements on software life cycle costs and
schedules.
These objectives support the primary needs expressed by software cost estimation users in
a recent Software Engineering Institute survey [Park et al. 1994]. In priority order, these needs
were for support of project planning and scheduling, project staffing, estimates-to-complete,
project preparation, replanning and rescheduling, project tracking, contract negotiation, proposal
evaluation, resource leveling, concept exploration, design evaluation, and bid/no-bid decisions.
1.3 TOPICS ADDRESSED
Section 2 describes the future software marketplace model being used to guide the devel-
opment of COCOMO 2.0. Section 3 presents the overall COCOMO 2.0 strategy and its rationale.
Section 4 summarizes a COCOMO 2.0 software sizing approach, involving a tailorable mix of Ob-
ject Points, Function Points, and Source Lines of Code (SLOC), with new adjustment models for
reuse and re-engineering. Section 5 discusses the new exponent-driver approach to modeling rela-
tive project diseconomies of scale and the new multiplicative cost drivers. Section 6 discusses
some additional model capabilities. Section 7 presents the resulting conclusions based on COCO-
THE COCOMO 2.0 SOFTWARE COST ESTIMATION
MODEL
Barry Boehm, Bradford Clark, Ellis Horowitz, Chris Westland
USC Center for Software Engineering
Ray Madachy
USC Center for Software Engineering and Litton Data Systems
Richard Selby
UC Irvine and Amadeus Software Research
Abstract
Current software cost estimation models, such as the 1981 Constructive Cost Model (CO-
COMO) for software cost estimation and its 1987 Ada COCOMO update, have been experiencing
increasing difficulties in estimating the costs of software developed to new life cycle processes and
capabilities. These include non-sequential and rapid-development process models; reuse-driven
approaches involving commercial off the shelf (COTS) packages, reengineering, applications
composition, and applications generation capabilities; object-oriented approaches supported by
distributed middleware; and software process maturity initiatives.
This paper provides an overview of the baseline COCOMO 2.0 model tailored to these new
forms of software development, including rationales for the model decisions. The major new mod-
eling capabilities of COCOMO 2.0 are a tailorable family of software sizing models, involving Ob-
ject Points, Function Points, and Source Lines of Code; nonlinear models for software reuse and
reengineering; an exponent-driver approach for modeling relative software diseconomies of scale;
and several additions, deletions, and updates to previous COCOMO effort-multiplier cost drivers.
This model is serving as a framework for an extensive current data collection and analysis effort
to further refine and calibrate the models estimation capabilities.
1. INTRODUCTION
1.1 MOTIVATION
Dramatic reductions in computer hardware platform costs, and the prevalence of commod-
ity software solutions have indirectly put downward pressure on systems development costs. This
makes cost-benefit calculations even more important in selecting the correct components for con-
struction and life cycle evolution of a system, and in convincing skeptical financial management
of the business case for software investments. It also highlights the need for concurrent product and
process determination, and for the ability to conduct trade-off analyses among software and system
life cycle costs, cycle times, functions, performance, and qualities.
Concurrently, a new generation of software processes and products is changing the way or-
ganizations develop software. These new approachesevolutionary, risk-driven, and collabora-
tive software processes; fourth generation languages and application generators; commercial off-
the-shelf (COTS) and reuse-driven software approaches; fast-track software development ap-