TABLE OF CONTENTS
GENERAL 2
PROJECT ORGANIZATION 3
LANGUAGE 3
CORRESPONDENCE 3
COORDINATION MEETING 9
NUMBERING SYSTEM 12
ENGINEERING 15
PROCUREMENT COORDINATION 17
CONSTRUCTION COORDINATION 17
PROJECT REPORTING AND RECORDING 17
ATTACHMENTS 21
Attachment 1; Fax Form 21
Attachment 2; Transmittal Form 22
Attachment 3; MOM Form 23
KLM Technology
Group
Project Engineering Standard
PROJECT COORDINATION
PROCEDURE
(PROJECT STANDARDS AND
SPECIFICATIONS)
Page 2 of 23
Rev: 01
Feb 2012
GENERAL
Introduction
This coordination procedure has been prepared in order for CLIENT, CONTRACTOR
Project Team and Lead Engineers / 3rd Party or whoever is involved in the execution
of the project to understand and follow the practices to be used between CLIENT or
OWNER and CONTRACTOR.
The procedures hereunder neither affect nor modify the provisions of the CONTRACT.
This procedure may be modified by changes in mutual agreement between CLIENT
and CONTRACTOR as job progresses, if necessary.
Parties and Project Managers
Related parties
1. CLIENT
2. CONTRACTOR who will provide detailed engineering, procurement and
construction, commissioning and start-up required for the successful
completion of PROJECT.
In order to enable the smooth project execution and communication, each party has
appointed the following project managers and all official contact shall be through the
following project managers:
1. CLIENT Project Manager :
2. CONTRACTOR Project Manager :
The person being assigned as Project Manager shall be responsible for the
coordination between the parties hereto pertaining to all matters under the Contract.
All written communications and document transmittals between the parties will be
transmitted to each Project Manager. In addition to that, each Project Engineers and
Relevant Managers will communicate (Queries and Responses) with the related
disciplines and distribute the details, as appropriate, within their respective
organizations.
KLM Technology
Group
Project Engineering Standard
PROJECT COORDINATION
PROCEDURE
(PROJECT STANDARDS AND
SPECIFICATIONS)
Page 3 of 23
Rev: 01
Feb 2012
Project Name and Job Number
Project name and job numbers are as follows;
Project Name :
CONTRACTORs Job Number :
PROJECT ORGANIZATION
The project organization and assigned personnel of CLIENT and CONTRACTOR are
shown in Project Execution Plan.
LANGUAGE
The language of the CONTRACT shall be in English. It shall be used in contract
communications, reports, correspondences, technical drawings, specifications,
invoices, etc. All Contractor, Vendor and Subcontractor drawings and other
documents shall be in English language.
CORRESPONDENCE
General
This section outlines the general procedure for the exchange of communications and
interface relationships as related to the work associated with the PROJECT. All
correspondences related to services under the CONTRACT shall be carried out
between the Project Managers. All correspondences shall be identified by stipulated
numbering system.
Letters
All letters shall contain the following information.
1. Name and title of addressee and addresser
2. Project name
KLM Technology
Group
Project Engineering Standard
PROJECT COORDINATION
PROCEDURE
(PROJECT STANDARDS AND
SPECIFICATIONS)
Page 4 of 23
Rev: 01
Feb 2012
3. Subject
4. Date (ex. February 06, 2010)
5. Reference number of correspondence, which will be in accordance with Project
Numbering Procedure.
The letter shall be used for project general and contractual correspondence only. Each
letter shall be limited to one (1) subject whenever applicable, and all letters shall be
mailed by the fastest method. All formal technical matters shall be sent under
Transmittals.
Minutes of Meeting
The minutes of meeting shall be used for a record of a meeting held between CLIENT
and CONTRACTOR. The minutes of a meeting shall be limited to one (1) meeting.
However, a meeting extending several days on the same subject may be recorded in
one set of minutes, and other pertinent information are shown.
All agreements involving changes or exceptions to specifications, cost, or other
important subjects made verbally between CLIENT and CONTRACTOR at a meeting
shall be recorded and issued by CONTRACTOR as minutes of meeting within two (2)
calendar days after a meeting. Otherwise, CONTRACTOR has to advise the
concerned parties of the anticipated date when the minutes of meeting is available.
Minutes of meeting shall be authorized by signed by the representatives of each
concerned parties prior to distribution.
The minutes of meeting also shall clearly indicate the following;
1. The date of the meeting
2. The participants
3. All decisions made
4. Other important subjects discussed
5. A note of any action to be taken
6. The person or party responsible for that action
7. The date for completion of such action
KLM Technology
Group
Project Engineering Standard
PROJECT COORDINATION
PROCEDURE
(PROJECT STANDARDS AND
SPECIFICATIONS)
Page 5 of 23
Rev: 01
Feb 2012
8. Reference number of minutes of meeting, which will be in accordance with
Project Numbering Procedure.
Faxes (Telefaxes)
Each Fax (Telefax) shall contain the same information of letters above and one
subject in principle. All Faxes shall be assigned a number in accordance with Project
Numbering Procedure.
Document Transmittals
Document transmittals shall accompany drawings, requisitions, purchase orders and
other self-explanatory documents. Receivers of routine transmittals shall confirm their
receipt. All Transmittals shall be assigned a number in accordance with Project
Numbering Procedure.
Document Transmittals to the OWNER from CONTRACTOR
Transmission of documentation, other than correspondence, from CONTRACTOR to
the OWNER shall be under a transmittal form. All transmittals shall be addressed to
the OWNERs Authorized Representative signed by the CONTRACTORs Project
Manager or his duly Authorized Representative.
Dispatch of documents to OWNER shall be by hand carry, courier service, fax
machine or E-mail, where applicable, for saving time. The addressee will return a copy
of transmittal with date of receipt and signature.
The transmittal shall include, beside the identification numbers, also the number of
copies, title and revision number of the documents which are being transmitted
together with the purpose for which the document is transmitted.
The documents transmitted for review", for information", for construction" and as
built/for record" shall be submitted with separate transmittals. Drawings and
documents of each discipline shall be sent under cover of different transmittal.
KLM Technology
Group
Project Engineering Standard
PROJECT COORDINATION
PROCEDURE
(PROJECT STANDARDS AND
SPECIFICATIONS)
Page 6 of 23
Rev: 01
Feb 2012
Document Transmittals to the CONTRACTOR from OWNER
Transmission of documentation, other than correspondence, from OWNER
(Authorized) Representative only to the CONTRACTOR shall be under the transmittal
form. That transmittal shall be addressed to the CONTRACTORs Authorized
Representative only.
Dispatch of documents to OWNER shall be by hand carry, courier service, fax
machine or E-mail, where applicable, for saving time. The addressee will return a copy
of transmittal with date of receipt and signature.
The transmittal shall include, beside the identification numbers, also the number of
copies, title and revision number of the documents which are being transmitted
together with the purpose for which the document is transmitted.
1. All transmittal covers shall be signed and a copy of it shall be returned back to
sender.
2. Contractor shall have copies of related 3rd party transmittals
E-Mails
E-mail is considered as an effective correspondence. This is normally used for
seeking discipline-to-discipline level clarifications. However if any e-mail contains a
decision and instruction which can affect the cost and the schedule of the project, then
it shall be confirmed formally in writing by Letters or Faxes or Transmittals which shall
be sent within five(5) days of e-mail correspondence.
Telephonic Discussions
Telephonic or personal discussions can be actively done for successive project
execution and/or clarification. If these are to be considered official, then should be
confirmed in same way as e-mail through letters/faxes/transmittal as well.
Numbering of Correspondences
All correspondences, transmittals and Conference Notes (Minutes of Meetings)
between the parties shall be numbered as defined in Project Numbering Procedure. It