Lock Out Tag Out Procedures
Lock Out Tag Out Procedures
OF
HAZARDOUS ENERGY CONTROL
PROGRAM (LOCK OUT & TAG OUT)
CONTENT
CONTENT........................................................................................................................................2
GENERAL SCOPE.........................................................................................................................1
1.0 OBJECTIVE...............................................................................................................................1
2.0 SCOPE AND APPLICATION...................................................................................................2
2.1 SCOPE............................................................................................................................2
2.2 APPLICATION..............................................................................................................2
erecting......................................................................................................................3
installing....................................................................................................................3
constructing...............................................................................................................3
repairing....................................................................................................................3
adjusting....................................................................................................................3
inspecting..................................................................................................................3
un-jamming...............................................................................................................3
setting up...................................................................................................................3
troubleshooting ........................................................................................................3
testing........................................................................................................................3
cleaning.....................................................................................................................3
dismantling................................................................................................................3
servicing....................................................................................................................3
maintaining...............................................................................................................3
lubricating.................................................................................................................3
3.0 RESPONSIBILITIES.................................................................................................................3
3.1 SITE/OPERATION........................................................................................................3
3.2 AUTHORIZED INDIVIDUALS....................................................................................3
3.3 AFFECTED INDIVIDUALS.........................................................................................4
3.4 OTHERS ........................................................................................................................4
4.0 Top Ten Safety Activities for LOTO.........................................................................................4
5.0 DESIGN.......................................................................................................................................6
TECHNICAL PROCEDURE FOR................................................................................................7
HAZARDOUS ENERGY CONTROL PROGRAM.....................................................................7
1.0 LOTO PROGRAM.....................................................................................................................7
1.1 Key Elements of the LOTO Program.............................................................................8
1.2 General Requirements for LOTO...................................................................................8
1.3 LOTO Placard ................................................................................................................9
GENERAL SCOPE
1.0
OBJECTIVE
The purpose of this program is to establish comprehensive Saint-Gobain China
Delegation Lockout and Tag out (LOTO) expectations and requirements. It establishes
Saint-Gobains expectations regarding safe methods of controlling energy during
servicing and/or maintenance of machines and equipment and during reenergizing of the
machine and equipment at the end of the servicing and/or maintenance. This program
was designed to prevent injuries caused by unexpected activation of hazardous energies.
Unexpected release of hazardous energy can include any unintended motion,
energization, start-up or release of stored energy, deliberate or otherwise, from the
perspective of the person(s) at risk.
The Saint-Gobain China Delegation LOTO program will help the facility or
operation/organization comply with country-specific regulatory requirements and the
company EHS policy.
This program constitutes the minimum Saint-Gobain China Company LOTO
expectations. The most important element of the program is that Saint-Gobain China
personnel and contractors shall not perform activities, as defined in Paragraph 2.2
Application, with equipment energized. In special situations, a risk assessment process
may be used to document the necessity to work on energized equipment (e.g., it is not
possible to perform the task while using LOTO). In these situations, alternative energy
control procedures providing equivalent protection to employees are required.
This program provides Saint-Gobain Chinas expectations regarding:
Management review of the total hazardous energy control process to ensure its
functioning effectiveness.
2.0
2.1
2.2
APPLICATION
This program applies to Saint-Gobain China operation/sites that belong to Industry.
Distribution entities are invited to follow strictly Saint-Gobain Group LOTO Standard
that has been designed in order to meet Distribution needs.
For operation/sites that already have a LOTO procedure, they have to check if their
procedure complies with the LOTO validation criteria and submit it to their respective
Sector for approval. If the operation/site does not have any LOTO procedure in place,
this program will be adopted after submission to their Sector. In addition, each
operation/site should complement this program with more detailed document to make it
closer to production reality.
This standard applies to, but is not limited to, activities that are performed on a machine,
a piece of equipment, a process or circuit. Primary, secondary, stored and single source
energy sources require a lockout when performing servicing and/or maintenance
activities. Primary energy sources are the main energy sources, such as electricity, gas,
fluids, etc., provided to machines, equipment, processes and circuits.
Secondary energy sources are downstream from the primary (or main) energy source.
For example, electricity, fluids, etc., secondary energy lockout points are used to isolate
a specific component of a system without the necessity of locking out the entire system.
Stored energy must also be taken into consideration. Stored energy, such as motion,
pressure, gravity, capacitance or temperature, is a potential hazard that still exists after a
primary energy source has been locked out. For example, a pump motor for a hydraulic
system may be locked out, effectively stopping fluid flow, but energy in the form of
pressure may still exist in an accumulator. This pressure in the accumulator should be
bled off before work proceeds. All stored energy must be controlled to ensure complete
machine safety.
Single source machines are machines, equipment, processes and circuits that can be
completely deactivated through the isolation and locking out of a single energy source.
Below is a listing of typical activities in which energy control procedures apply:
erecting
inspecting
cleaning
installing
un-jamming
dismantling
constructing
setting up
servicing
repairing
troubleshooting
maintaining
adjusting
testing
lubricating
LOTO applies to all sources of energy, including, but not limited to, those energy
sources: Primary, Secondary Energy Source & Strored Energy Source.
3.0
3.1
RESPONSIBILITIES
SITE/OPERATION
The site/operation shall be responsible for complying with the applicable provisions of
this program by establishing an effective program for the protection of individuals from
hazardous energy during activities listed in Paragraph 2.2 Application.
The site/operation shall fully implement the provisions of this program within six (6)
months from the date this document enter into force. New site/operations or
acquisitions shall fully implement this program within six (6) months of initial
operations as SAINT-GOBAIN CHINA.
When Saint-Gobain China is retained as a service provider at a customer site, SaintGobain China personnel will adhere to this program, although special circumstances
may require utilization of alternative actions. Upon request of the customer and approval
by a qualified Saint-Gobain China authorized employee, Saint-Gobain China personnel
may follow the customers LOTO program, provided the program ensures equal or
greater protection to authorized individuals and affected individuals.
3.2
AUTHORIZED INDIVIDUALS
Authorized individuals shall be identified by site/operation and be responsible for
performing hazardous energy control in compliance with the site-specific program,
procedures and detailed training provided to them by the Saint-Gobain China business
and/or site/operation (e.g. LOTO Champion).
3.3
AFFECTED INDIVIDUALS
Affected individuals consist of all personnel who are not authorized individuals and who
must receive LOTO awareness training, which will include the importance of not
attempting to start up a locked out machine, equipment, process or circuit. Affected
individuals need to recognize and understand LOTO procedures.
3.4
OTHERS
LOTO Champion
Facility engineer
Maintenance Manager
Area manager
EHS Coordinator
Supervisor
Area Safety
Representatives
Maintenance
technicians
4.0
The top ten core requirements for using LOTO to prevent injuries are:
1.
One Lock, One Key, And One Person: The basis of LOTO is that any individual
has total control of the lockout of the machine, equipment, process or circuit
that is being serviced and/or maintained. This concept assures the individual sole
lockout responsibilities.
2.
3.
4.
Authorized/Affected Individuals:
Authorized individuals must be
knowledgeable and able to perform all aspects of the LOTO process. Affected
individuals must understand and respect the LOTO and not attempt to modify or
remove LOTO done by others.
5.
The Proper Tools: LOTO is conducted with a specific set of tools. These tools
include keys, locks, multiple lockout devices and red tags. Proper use and
application of these tools is learned through this program and effective training.
6.
7.
8.
9.
10. Risk Assessment: Risk assessment can help to find the best condition for
individual work. It establishes safety action to reduce the risk when normal LOTO
program is impossible to implement.
5.0
DESIGN
GENERAL ELECTRIC EQUIPMENT
All machines, equipment, processes and circuits that are to be delivered to Saint-Gobain
China shall be designed, manufactured, supplied and installed so that the site/operation
can comply with the energy control guidelines explained in this program. It is SaintGobain Chinas responsibility to review the suppliers product to ensure that safety
issues are addressed. The paragraphs in this section define what is expected of suppliers.
Modifications affecting energy isolation shall comply with or exceed these standard
requirements. Machine, equipment, process and circuit design should incorporate
employee safety as a priority. A risk assessment shall be performed during the
engineering design stage of development. The risk assessment performs two functions;
first, it determines the need for energy control devices and systems; second, it
determines the appropriate type of energy control that is required.
LOTO PROGRAM
The site/operation/service organization shall establish a written program for hazardous
energy control that details the requirements of the LOTO program. The written program
shall be based on this LOTO program and the Saint-Gobain LOTO Standard. The
purpose of this program is to ensure that risk of exposure to hazards will be eliminated
or minimized before any authorized individual performs any activity where the
unexpected energizing, start-up or release of stored energy could occur and cause injury
(see Figure 1).
Task requiring access to
machine, equipment or process.
NO
Exposed to hazard?
YES
Report your manager and
LOTO work team
Guards removed?
Interlocks bypassed?
YES
Perform
Lockout
Procedure
YES
Perform
Task
Perform Risk
Assessment
Improve the
LOTO device
7
YES
1.1
1.2
a means to achieve lockout without the need to dismantle, rebuild or replace the
energy-isolating device, or permanently alter its energy control capability.
1.3
LOTO Placard
A LOTO Placard is a laminated sheet or sheets that contain detailed LOTO information
for the specified machine system, workstation or a single machine. LOTO Placards are
usually posted on the main electrical panel. Based on an identification of the primary
energies (energies required to run (energize) the machine/s), it lists:
the main disconnects (lockout points used to isolate all energies to the machine
or machine system), and
secondary disconnects (lockout points that can be used to isolate energy to a
single workstation or a single machine),
the locations for energy dissipation or blocking and
other safety hazards in and near the machine.
For each of these, there is a description of lockout/control locations, lockout/control
procedures, and verification procedures. Most LOTO Placards will also include a plan
layout of the machine on which the lockout/control points and other LOTO-related
hazards are marked. Matching the symbols on the LOTO Placard, energy labels
attached at or near lockout/control disconnects on the machinery.
2.0
LOTO METHODS
2.1
FLOWCHART
STEP 1
STEP 2
STEP 3
ID Energy Sources
Notify Others
Shutdown Equipment
STEP 4
STEP 5
STEP 6
Isolate Equipment
LOTO Equipment
STEP 7
STEP 8
STEP 9
Verify Isolation
The selected method of hazardous energy control depends on whether the task can be
performed with or without energized conditions. In all cases, the primary method of
control shall be LOTO as specified in Paragraph APPENDIX D.
2.2
Lock Type
Purpose
Duration of
Use
Lock Color
Key
Tags
Group Lock
Not assigned to an
individual employee
and used to lock out
individual energyisolating devices or
energy sources when
group LOTO is used.
One shift or
the end of the
task,
whichever is
shorter.
Specific lock
color is not
required but lock
must be unique
and used for
LOTO only.
required
Single shift
use only.
Specific lock
color is not
required but red
is typically used.
Red tags
required.
2.3
2.4
10
performed, and the removal should be documented through the Risk Assessment and
Risk Reduction program outlined in . The site/operation-specific procedure shall
incorporate the requirements in Paragraph APPENDIX D, Step 9 in addition to the
following elements:
2.5
ensuring that the authorized individual has been informed before he/she resumes
work at that facility that his/her lockout or tag out device has been removed.
Group LOTO
Machine, equipment, process and circuit may require servicing and/or maintenance by
more than one authorized individual. Each authorized individual performing service
and/or maintenance must apply his/her Individual LOTO Lock. Every authorized
individual who applies an Individual LOTO Lock shall verify that the machine,
equipment, process or circuit has attained a zero energy state or observe the verification
process. Multiple lock application can be accomplished with the following:
The use of Group Lock and Lock Box. For example, if a machine with multiple
energy sources is going to be serviced by multiple personnel, it may be useful to
use General LOTO Locks at the energy sources. Keys for the General LOTO
Locks are held in lock box to which employees attach their Individual LOTO
Locks.
Lock box when an energy-isolating device can accommodate only one key. This
key is placed inside the lock box and all authorized individuals servicing and/or
maintaining the machine, equipment, process and circuit secure and attach their
Individual LOTO Locks.
11
2.6
IMMEDIATE
HAND-OFF
Shift
A
Shift
B
Communication is an important part of the shift or personnel change process. LOTO and
servicing and/or maintenance information must be exchanged between authorized red
tags, which have remark areas to provide additional information.
During the shift or personnel change process, every authorized individual who applies
an Individual LOTO Lock shall verify (or observe verification) that the machine,
equipment, process or circuit has attained a zero energy state.
NOTE
Field Service personnel must coordinate LOTO procedures at
the customers sites with their customer representative.
Generally, energy isolation devices cannot be secured without
12
2.7
2.8
Electric power transmission and distribution systems and gas transmission and
distribution systems, including underground gas storage systems, gas wells and
compressor stations.
13
2.8.1
Hazard Notification.
Program Coordination.
All outside service organization or contractor programs shall be coordinated with SaintGobain Chinas hazardous energy control program when there is integration of job
tasks. Protection for all individuals within the facility who may be affected shall be
mutually understood, communicated and agreed upon between the parties.
2.8.3
Communications.
Saint-Gobain China personnel and outside services or contractors shall keep each other
informed of any activities or conditions that may adversely affect the application of
hazardous energy control or impact the normal operation of machines, equipment, or
processes and circuits. The Saint-Gobain China representative should supply the service
or contractor with a copy of the operation/site-specific LOTO program. The SaintGobain China representative should review with outside services and contractors all
expectations, rules and hardware involved in the LOTO process. All written copies of
the contractors LOTO program and all project safety information shall be kept on file
with the Saint-Gobain China representative for the life of the project.
NOTE
Examples of activities or conditions that warrant communication
between the parties include interruption of energy supply,
disabling a fire protection/security system, emergency alarm
systems, hazardous area ventilation and special equipment that
are needed for energy isolation.
2.8.4
14
contractors will be given locks by the LOTO Supervisor and shown where to place them
to assure their individual control of the energy source(s) while working. Any authorized
individual who is asked to serve in a LOTO Supervisor role must acknowledge that they
are accepting responsibility for the safety of all personnel to be protected by the LOTO.
Per the requirements listed below, a site/operation may implement a LOTO Supervisor
system when:
A risk assessment has been completed that documents the greater hazard that would be
controlled by using the LOTO Supervisor method, and the specific alternative
procedures to be implemented.
The Central EHS Manager or site EHS Manager has reviewed the risk assessment and
provided documented approval of the need for the use of the LOTO Supervisor
approach and the specific alternative procedures to be used. Such approvals may be in
the form of a blanket approval or procedure for LOTO Supervisor applications that are
expected to be repeated periodically.
All contractors to be protected by LOTO receive training on the procedures the
LOTO Supervisor follows. The employees have the right to either perform LOTO
verification or observe the LOTO Supervisor perform verification.
The LOTO Supervisor must be present on the facility at all times that the LOTO is
in place, and must be in possession of a list of all employees protected by the
LOTO.
Lockouts under the LOTO Supervisor method are limited to the length of the task
or the end of the shift, whichever is shorter.
Placement of a LOTO under the LOTO Supervisor method involves the following steps:
Place the LOTO following the procedures in APPENDIX D, and LOTO Placard
for the equipment or process being locked out.
Inform the contractors to be protected by the LOTO of their right to perform the
verification step, or observe the LOTO Supervisor perform verification, and
provide the contractors with the opportunity to exercise this right.
2.8.5
15
3.0
3.1
3.2
Training Overview
Authorized individuals shall be trained and pass the examination prior to performing any
type of LOTO activity. The examination should include written text and on-site
demonstration. Affected individuals shall also be trained per this program. In
APPENDIX E, Table 1 is a summary of the training requirements. Table 2 summarizes
the training frequency requirements.
16
4.0
PROGRAM REVIEW
The site/operation shall annually assess the condition and effectiveness of each of the
elements of the hazardous energy control program as described in Saint-Gobain
China Health and Safety Annual Review system. At a minimum, the assessment
shall include:
4.1
LOTO hardware;
energy-isolating devices;
4.2
Performance Feedback
The site/operation shall establish a documented system that inspects performance by
authorized individuals and also provides both positive and negative feedback to
appropriate individuals and supervisors regarding the hazardous energy control program.
Where deficiencies are found, corrective action shall be taken and appropriate
individuals informed of the required improvements.
Appropriate disciplinary actions shall be implemented when defects are identified
during the audit or when this Saint-Gobain China program is not being followed by
affected or authorized employees. When necessary, employee violations of this program
17
shall be documented and appropriate disciplinary action taken. The enforcement of this
program, and all safety regulations, can result in disciplinary procedures up to and
including termination.
18
RISK ASSESSMENT
Risk assessment is an analytical tool consisting of a number of discrete steps intended to
ensure that hazards are properly identified, that associated risks are evaluated and that
appropriate measures are taken to reduce those risks to an acceptable level. Elements of a risk
assessment process include the following steps:
1.
Identify all tasks: All tasks and activities should be considered. Examples of activities
for which tasks should be identified include set up, installation, removal, maintenance,
operating, adjusting, cleaning, troubleshooting and programming.
2.
Identify hazards: Hazards associated with each task, such as mechanical, electrical,
thermal, pneumatic, hydraulic, radiation, residual or stored energy, motion, fuels and
human factors should be considered. Associated hazards for a particular task not related
to hazardous energy release may also need to be reviewed. Consideration should
include human error, management system deficiencies and foreseeable improper use of
equipment.
3.
Assess the severity of harm: Severity of harm addresses the degree of injury or illness
that could occur. The degrees are based on extent of injury or illness (from death to no
injury), and extent of treatment involved. The following is an example of severity
levels:
Catastrophic - death or permanently disabling injury or illness (unable to return to
work)
Serious - severe debilitating injury or illness (able to return to work at some point)
Moderate - significant injury or illness requiring more than first aid (able to return
to same job)
Minor - no injury or slight injury requiring no more than first aid (little or no lost
work time)
(Note: When determining risk, the worst credible severity of harm is to be
selected.)
4.
Evaluate the risk: Based on the results of Steps 3 and 4 above, the level of risk is
estimated by applying the level of severity of harm and the probability of occurrence of
that harm to Table A-.
Table A-. Risk Estimation Matrix
Severity of Harm
Probability of
Occurrence of Harm
Catastrophic
Serious
Moderate
Minor
Very Likely
High
High
High
Medium
Likely
High
High
Medium
Low
Unlikely
Medium
Medium
Low
Negligible
Remote
Low
Low
Negligible
Negligible
An example: a serious severity of harm and a likely probability of occurrence of that harm yield a high level
of risk.
A.2
training.
20
Often, for any particular machine, equipment, process and circuit, the solution may include
aspects of each of these elements. The risk reduction process should involve the affected
personnel, should be documented.
The following questions should be asked to determine the adequacy of the risk reduction
process:
Is the safety level adequate? Can the task be performed without causing injury or
damage to health?
Have appropriate safety measures been taken for all tasks or activities? Are the
measures taken compatible with each other?
21
A.3
on a periodic basis.
22
23
Adjacent Equipment/
Process:
Affected Individual:
Alarm:
Associated
Equipment/Process:
Authorized Individual:
Control Header or
Circuit:
24
Control Reliability:
Control System:
De-energized:
Dissipate:
Energized:
Energy-Isolating Device:
Energy Source:
Exclusive Personal
Control:
25
Guard:
Hardwired:
Hazardous Energy:
Integrator:
Interlock:
Lockout Device:
LOTO (lockout/tagout):
The placement of a lock and red tag on the energyisolating device in accordance with an established
procedure, indicating that the energy isolating device shall
not be operated until removal of the lock and red tag, in
accordance with an established procedure.
Manufacturer:
Modifier:
26
Remanufacturer:
Risk Assessment:
Safety Signs:
Servicing and/or
Maintenance:
Site/Operation:
redesign
or
27
28
ENERGY TYPE
AND
MAGNITUDE:
LOCKOUT
LOCATION:
ISOLATES
....
BLOCKS .
..
DISSIPATES
.
LOCKOUT /
CONTROL
PROCEDURES:
VERIFICATION
PROCEDURES:
29
C.1.3 Troubleshooting
C.2
C.3
30
C.5
31
C.6
For existing machines, the area maintenance manager signs and thereby authorizes the
Placard.
For new machines, the production engineer responsible for the project signs and thereby
authorizes the Placard. Where the design work for a new machine is done by a
contractor, it is permissible to get the supplier to make the Placard, but it must still be
signed by the production engineer responsible for the project before it is put into service.
C.7
The maker of the LOTO Placard is qualified (i.e. completed the full LOTO
training and LOTO Placard training)
The safety specialist and the safety representative were involved (their role
is to check the logic and format of the Placard when the final Placard is ready to be
verified)
Labels installed (this means LOTO Labels AND switch identification labels)
C.8
1
Steps
Assemble qualified
Summary
Consider the need for electrical, hydraulic, pneumatic, mechanical or other
32
Prepare Draft Of
Placard
6
7
C.9
33
34
2.
Notify others: All personnel associated with the equipment on which the work will
be done shall be notified prior to the application and after the removal of lockout
devices and tag out devices (Personnel may include operators, technicians,
engineers or area managers).
3.
Shutdown Equipment: Turn off all energy switches and/or buttons to the
equipment.
4.
5.
Lockout or tag out device application: The authorized individuals shall attach and
secure lockout or tag out devices. Use the following guidelines:
Individual LOTO Lock and red tag shall be attached and secured to the
machine, equipment, process or circuit energy-isolating device (disconnect,
valves, etc.). When an energy isolating location is not designed to accept a
lock, use of a lockout device such as a clamshell, ball valve, circuit breaker,
wall switch or gate valve is required. Note that 1 lock, 1 key, 1 person is the
rule that must be followed.
35
NOTE
Group lockout with lock box may also be used in complex, multi-person
applications.
Verify that the energy-isolating devices remain locked out and in a safe
or off position.
Where a red tag cannot be attached and secured directly to the energy
isolating device, the red tag shall be located as close as safely possible to the
device, in a position that will be immediately obvious to anyone attempting to
operate the machine, equipment, process or circuit. In addition, a tag shall be
placed at the operators control position to alert personnel that the machine,
equipment, process and circuit are de-energized. For example, where an
electrical bus with integral isolating switches is located overhead, the tag would
be placed conspicuously on the operator panel warning not to use the
equipment.
6.
Release stored energy: The authorized individual shall ensure that all potentially
hazardous energy (stored, residual, chemical or potential) is relieved, dissipated,
restrained, drained or otherwise controlled. Additional measures may be necessary
to prevent re-accumulation of energy to protect individuals. Examples of stored
energy systems include accumulators, capacitors, gravity, surge tanks, chemical
lines and springs.
7.
Verification of isolation: The authorized individual shall verify that isolation and
de-energization have been accomplished using the procedures in the equipmentspecific LOTO procedure prior to starting servicing and/or maintenance on
machines, equipment, processes and circuits that have been locked out or tagged
out. Verification must confirm that the machine, equipment, process or circuit has
achieved a zero energy state such as 0 electricity, 0 pneumatic, 0 fluid or gas
pressures, etc. (Verification of a zero energy state can be accomplished by test
equipment, circuit activation attempts, gages, visual inspection, etc.)
8.
Keep LOTO enforced while performing intervention: Avoid open any energy and
doing anything that could potentially reactivate the equipment. If you want to
restate the equipment, please follow the step 9.
9.
Return to service: The authorized individual shall perform the following before
returning the equipment to service:
Inspect the work area to ensure that non-essential items have been removed,
guards are in place, the machine, equipment, process or circuit is operationally
intact, and all personnel are in a safe location.
36
Remove locks, tags and lockout devices from each energy-isolating device
by the authorized individual who applied the device.
Notify affected personnel that energy is about to be restored to the machine,
equipment, process and circuit.
Visually inspect and/or cycle test the equipment for servicing and/or
maintenance task completion. If the task is completed the machine, equipment,
process and circuit may be returned to service. If the task is not completed,
repeat the necessary LOTO steps.
Follow the proper sequential startup steps for the equipment, process or
circuit.
37
Authorized Individuals
Applications
Yes
Yes
Definitions
Yes
Yes
Elements
Yes
Yes
Requirements
Yes
Yes
No
Yes
Step-by-Step Methods
No
Yes
Yes
Initial training
Initial demonstration
Affected Individuals
Authorized Individuals
Required
Required
Not applicable
Required
(must be observed and verified by another
authorized employee, i.e. "hands on")
Annual refresher
training
Recommended
Required
Annual demonstration
Not applicable
Required
(must be observed and verified by another
authorized employee every third year, i.e. "hands
on" and in the other years may be accomplished
by use of computer simulated demonstrations)
E.1
38
Field Service personnel shall receive training on electrical safety and the SaintGobain China LOTO programs. Specific information regarding hazardous
energy in the field locations shall be discussed during pre-job safety meetings
with customer representatives.
Each authorized individual shall receive training in the type of energy that
might be encountered during servicing and/or maintenance and methods or
means to control and isolate that energy.
The site/operation shall document that all initial and additional training has been
conducted. The documentation shall contain each individuals name, dates of
training, the training topic and the assessment result.
initial training, and must be repeated no less often than every three years
thereafter. It must be performed on real equipment under the observation of an
authorized individual.)
The site/operation should avoid exclusive use of generic training programs to ensure that
authorized individuals adequately understand the site/operation-specific program.
Documentation of the information covered during training shall be maintained.
Training methods may include, but are not limited to, formal instruction (direct
instructor contact), computer-based or interactive training.
Annual refresher training should be conducted to maintain an appropriate level of
awareness.
E.3
Additional Training
Retraining shall be provided for all authorized individuals whenever there is a change in
their job assignments, a change in machine, equipment, process or circuit that presents a
new hazard, or when there is a change in the energy control procedures.
Additional retraining shall also be conducted immediately whenever an audit reveals, or
whenever the site/operation has other reason to believe, that the authorized individuals
knowledge or use of the energy control procedures is inadequate or inconsistent with the
requirements.
E.4
Demonstration of Training
The site/operation shall conduct an annual demonstration of the effectiveness of the
training that is conducted for each authorized individual. This "hands on" demonstration
is observed and verified by another authorized employee. The demonstration shall be
done in such a way as to ensure that authorized individuals demonstrate the following:
40
APPENDIX F DESIGN
F.1
Exposure Minimization
Verify that Saint-Gobain China machines, equipment, processes and circuits employ
available safeguards that are reliable, work to minimize hazard exposure and minimize
any adverse effect on the process. The machines, equipment, processes and circuits
should be designed or modified so that personnel are not exposed to hazardous energy
during routine and repetitive servicing and maintenance activities.
NOTE
This can be accomplished by positioning controls outside
hazardous areas, adding controls at appropriate locations,
providing external lubrication points or providing guarding.
F.2
Partial Energization
For those functions when partial energization is necessary, Saint-Gobain China
authorized individuals shall perform a risk assessment similar to that outlined in to
determine the safest method of machine, equipment, process and circuit access. When it
is necessary for machines, equipments, processes and circuits to remain partially
energized (e.g., in order to hold parts, save information, retain heat or provide local
lighting); alternative control methodologies shall be provided for personnel safety.
F.3
41
F.3.2 Identification
Verify that all energy-isolating devices shall be adequately labeled or marked unless
they are located and arranged so their purpose is clearly evident. The identification
should be of consistent format within each facility or operation and shall include the
following:
F.3.3 Capability
Verify that energy-isolating devices shall be capable of either being locked or otherwise
secured in an effective isolating position. Examples of effective isolating devices may
include, but are not limited to the following:
locking covers that only work when the switch is in the safe position;
42
F.4
F.5
F.6
COMPONENT ISOLATION
Verify that the machine, equipment, process or circuit installation shall provide for the
local isolation of component parts or component systems if they are to be serviced or
maintained separately. The number and location of energy-isolating devices shall be
determined by the configuration of the machine, equipment, process or circuit and the
intended application. Warning labels should be affixed to the machine, equipment,
process and circuit when remote or separate sources of hazardous energy must be
controlled.
F.7
DOCUMENTATION REQUIREMENTS
Each site shall require that written manual(s) (documentation) be provided by the
manufacturers, systems integrators, modifiers and remanufacturers. The written manual
(documentation) must detail:
the specific location and procedures for use of the provided energy-isolating
devices;
43
F.8
F.9
If control systems such as those listed above are not available, then LOTO procedures
must be applied.
F.10
PHYSICAL SAFEGUARDS
Verify that physical safeguards (e.g., pins, blanks, blocks, restraints, chains or blinds)
shall be designed, with the appropriate safety factor, to withstand all forces to which
they will be subjected. Physical safeguards vary for different stored energy sources.
Fabrication of special safeguard devices may be required when risk assessment of
machines, equipment, processes and circuits is completed. Physical safeguards must be
designed to minimize hazardous exposure.
44
Radiation
Magnetic
Water
45
6.
7.
8.
9.
46
All authorize and affected person should receive comprehensive LOTO training
and refreshing training on a regular basis and not exceeding 12 months time.
Managers are responsible to check if his/her team members are trained effectively.
The Maintenance Manager and/or Supervisor or equivalent must be trained in the
LOTO procedure. He is responsible to check if his/her team is applying it
correctly and must perform regular audits.
Each complex piece of machinery or equipment must have an LOTO Placard and
all energy sources labeled on the machine and identified on the Placard.
The maximum permitted duration for a LOTO is one shift or the end of the task,
whichever is shorter. If the duration of the task exceeds one shift, please follow
shift or personnel change requirements.
Shift or personnel change: The immediate hand-off of LOTO in progress.
Authorized individuals of the outgoing shift remove their individual LOTO locks
and red tags. Authorized individuals of the next shift simultaneously apply and
secure their individual LOTO locks and red tags at the same energy-isolating
device and verify that a zero energy state exists in the system via the "tryout"
process. If the job is not completed by the end of a shift workers are not to
REMOVE their LOCK & TAG until their relief person has attached their own
lock & tag.
Red Tag Danger Do Not Operate: Red tags (must be red in color) are used with
every Personal LOTO Lock to indicate that the energy source is locked out and an
authorized employee is actively working on the machine, equipment, process or
circuit.
One Lock, One Key, and One Person: When require servicing and/or maintenance
by more than one authorized individual. Each authorized individual performing
service and/or maintenance must apply his/her Individual LOTO Lock.
After an employee completes their work, they are to only to remove THEIR OWN
lock & tag. Only the person to whom the lock is assigned is to have a key to that
lock or is to remove the lock & tag.
Only specific dedicated LOTO device can be used as LOTO device, it is usually in
red color. Each Lock and Tag should be nominative.
Emergency stops are not considered as energy-isolating device.
Master keys are not allowed unless the site Sector EHS approves it due to very
special conditions.
When the authorized individual who applied the lockout or tag out device is not
available to remove it, the authorized manager, together with at least three
individuals knowledgeable of the work being performed, may remove the device
47
only after verification that the employee is not at the facility, all reasonable efforts
to inform the authorized individual that the device has been removed have been
made, and ensuring that the authorized individual has been informed before he/she
resumes work at that facility that his/her lockout or tag out device has been
removed.
Specific procedures and training for such removal have been developed,
documented and incorporated into the energy control program.
When Saint-Gobain employees are performing work in another company (our
customer) as a contractor, we should use our own LOTO procedure unless our
customer LOTO procedure is safer than ours.
The LOTO procedure should be reviewed each year and improved if needed.
48