Scope Management Plan
Scope Management Plan
Scope Management Plan
2014
Table of Contents
1.0 INTRODUCTION .............................................................................................................................. 1 2.0 SCOPE MANAGEMENT APPROACH ..................................................................................................... 1 3.0 ROLES AND RESPONSIBILITIES ............................................................................................................ 1 4.0 SCOPE DEFINITION.......................................................................................................................... 3 5.0 PROJECT SCOPE STATEMENT ............................................................................................................. 3 6.0 WORK BREAKDOWN STRUCTURE ....................................................................................................... 4 7.0 SCOPE VERIFICATION..................................................................................................................... 17 8.0 SCOPE CONTROL .......................................................................................................................... 17
1.0 INTRODUCTION
The Scope Management Plan provides the scope structure for Keadue wastewater treatment plant. The scope management method is roles and responsibilities as they relate to project scope, scope definition, verification and control measures; scope change control and the projects work breakdown structure.
Responsibilities - Responsible for collecting requirements for the Project - All design elements of the project - Reporting to the PM as required by the Communications Management Plan - DE may not approve any project expenses nor allocate any resources without PM approval - Managed by the PM.
Ken Geelan
Responsible for collecting requirements for the Project All design elements of the project Reporting to the PM as required by the Communications Management Plan DE may not approve any project expenses nor allocate any resources without PM approval Managed by the PM. Measure and prove project scope Make possible scope change requests Facilitate impact assessments of scope change requirements Organize and facilitate scheduled change control meetings Communicate outcomes of scope change requests Responsible for acquiring human resources for the project through coordination with Functional Managers Update project documents upon approval of all scope changes. Monitoring and controlling the outcome of the project Development of Software package which will provide for any delays or issues with the construction of the overall project IM will report status to the PM IMs performance will be evaluated by the PM
Functional managers, are responsible providing resources for the project in accordance with the project operating plan Working with the PM to determine skill sets required Responsible for conducting performance appraisals of assigned resources based
Feasibility Study
Assigned to:
Cathal
Status:
In Progress Assigned to: Identify Two Most Attractive Options Status: Yet to Begin Farah Source Detailed Information on Chosen Options Assigned to: Farah
Assigned to:
Cathal
Status:
Yet to Begin Assigned to: Apply Selection Critera Farah Identify Most Attractive Option Status: Yet to Begin Status: Yet to Begin Assigned to: Farah
Status:
Assigned to:
Farah
Status:
In Progress
Status:
Yet to Begin
Background Study
Farah
Completed
Assigned to:
Farah
Status:
Completed
Assigned to:
Farah
Status:
Completed
Schedule
Source Construction Info. For Chosen WWTP Option Source Generic Info. On WWTP Construction Assigned to: Ken Generate Generic Schedule from Sourced Data Assigned to: Ken Incorporate Monitoring System into Generic Schedule Assigned to: Mouhanad
Assigned to:
Status:
Completed
Status:
In Progress
Status:
Yet to Begin
Status:
Yet to Begin
Design Pipe Network & Size Units for Chosen WWTP Option
Assigned to:
Assigned to:
Status:
Completed
Status:
Completed
Monitoring System
Status:
In Progress
Status:
Yet to Begin
To be more clearly defining the work necessary for project completion the WBS Dictionary is used and it includes WBS Dictionary for each WBS element. The WBS Dictionary includes a detailed description of work for each element and the deliverables and resource needs for that element. The project team will use the WBS Dictionary as a statement of work for each WBS element. Feasibility Study - WBS Dictionary
Level
WBS Code 1
Definition of Work Feasibility Study is to decided on various WWTP The work to initiate the project. Gather information on WWTPs from printed material, internet and other various resources Carry out a desk top study on all information obtained on WWTPs from various sources Set up an excel sheet to analyse the chosen WWTPs with respect to P.E., overall size and cost in order to choose the most suitable system
Resources
1.1
Initiation
1.1.1
List of Potential WWTP Options. List of desk top study of WWTP for the project.
Cathal
Cathal
1.1.2
1.1.3
Farah
1.2
Planning
1.2.1
The work for the planning process for the project. Gather information about the current Keadue WWTP capacity and established a method to determine future capacities Source information from Roscommon Co. Co. for developments in the Keadue area and other relevant information necessary Search standards for information in relation to effluent requirements Determine if any design work is required for the chosen WWTP Determine if WWTPs perform to EPA standards
Farah
1.2.2
1.2.3
1.2.4
Farah
Cathal
1.2.5
1.3
Execution
1.3.1
Preliminary Design
1.3.2
Develop WWTP Develop checklist of Option options to compare Checklist WWTPs Eliminate most non suitable WWTPs based on checklist to determine the most attractive option
1.3.3
List of Farah Preliminary design work of WWTP. List of WWTPs Cathal options to compare to other WWTPs. List of most Farah attractive Options.
1.3.4
Source Detailed Gather required Information on information on Chosen Options chosen WWTPs Compare and contrast various technological requirements between the chosen packages The work involved for the control process of the project. Source information in relation to required standards and carry out any checks/calculations in relation to sludge disposal etc.
1.3.5
List of information of chosen WWTPs. Comprising of various technical requirements of chosen packages.
Cathal
Farah
1.4
Control
1.4.1
Farah
1.4.2
Source information in relation to construction cost and labour for the chosen systems.
1.4.3
Analyse Information
Analyse further information gathered previously in relation to construction and costs. Carry out various checks/calculations in relation to costs, eco footprint etc. of chosen WWTPs Decide which WWTPs is most suitable based on selection criteria The work to closeout the project.
List of Information on construction cost and labour for the chosen Systems. Analyse information in relation to construction and cost.
Cathal
Farah
1.4.4
Cathal
1.4.5
Farah
1.5
1.5.1
1.5.2
Suitable WWTP is chosen for project Official handover of Give chosen system to Information of scheduling team to chosen option allow for the to Scheduling commencement of a team site specific schedule The most suitable WWTP is chosen
Cathal
Cathal
Scheduling - WBS Dictionary Level WBS Code Element Name Definition of Work All work to develop the schedule for the upgrade works at Keadue WWTP. The work to initiate the project. Source general information on the construction of WWTPS. This information is not to be site specific. By using the general information sourced, develop a generic schedule for the construction of a typical WWTP plant. List of information on the construction of WWTPS. Ken Deliverables A schedule of works required for the project. Resources
Scheduling
4.1
Initiation
4.1.1
4.1.2
Ken
10
4.1.3
4.2
Planning
4.2.1
4.2.2
Incorporate the generic monitoring system into the generic schedule once the system has been handed over by the relevant development team. The work for the planning process for the project. Observe site and identify any works required prior to construction (Fencing, widening of access route, traffic management etc.) Identify if any site clearance works are required on site.
Mouhanad
Ken
Ken
11
4.2.3
4.2.4
Study plans of existing site with the aim of identifying any sections which may be kept/upgraded in the planned development. Identify existing services and determine if current provisions are sufficient for planned development. Work involved executing the project. Once chosen WWTP details have been handed over to the scheduling team any and all available information relating to said WWTP is to be sourced and filed.
Information on site requiring demolition/ upgrading into the planned development. Information on existing services and if any required services.
Ken
Ken
4.3
Execution
4.3.1
Ken
12
4.3.2
4.3.3
4.3.4
4.4
Control
4.4.1
Conduct any design work required. (Pipe sizing, plant design, pumps sump design etc.) Revisit generic schedule and update accordingly to suit chosen WWTP option. Develop H&S plan for planned development. The work involved for the control process of the project. Examine allocated timeframes and contents and verify them against similar projects schedules.
Ken
Ken
Ken
Ken
13
4.4.2
Test monitoring systems ability to provide for common issues and site, once again verifying the contingencies against similar projects. The work to close-out the project. Compile all documentation relating to similar and conclude on overall performance. Handover final schedule to relevant development team to allow the system to be included in overall package.
4.5
Closeout
4.5.1
Ken
Ken
4.5.2
14
Monitoring and Controlling - WBS Dictionary WBS Code Definition of Work All work to develop the Monitoring and controlling schedule for the upgrade works at Keadue WWTP. The work to initiate the project. Gather information on Monitoring Systems from printed material, internet and other various resources Gather information on Monitoring Systems from the public works contract for civil engineering works The work for the planning process for the project. Gather information on potential sources of delay for the project Deliverables List of monitoring and controlling schedule for the upgrade work. Resources
Level
Element Name
4.1
Initiation
4.1.1
Mouhanad
4.1.2
Ken
4.2
Planning
4.2.1
Mouhanad
15
4.2.2
Source data required allowed for delay Develop Monitoring System for Generic WWTP Project Execution Identify potential causes of delay in WWTP site Develop Delay Costs relating WWTP site Develop automated system to allow for delays
4.2.3
4.3
Search for information in relation to allowed days for delay Set up an excel sheet to analyse sources of delay with respect to delay of project Work involved executing the project. Gather required information for causes of delay in WWTPs Carry out calculation in relation to delay costs of WWTP Develop options to allow for delays in WWTP
Allowed the amount of days for delay. Excel sheet for analyse sources of delay for project.
Ken
Mouhanad
4.3.1
Information of causes of delay in WWTP. Results for the amount of delay costs. Options to allow for delays in WWTP
Mouhanad
Mouhanad
4.3.2
Mouhanad
4.4
Control Monitoring system test for verified delays to analyse results Mouhanad
4.4.1
Run monitoring Test monitoring systems for system in verified delays WWTP and then analyse results
16
4.4.2
4.5
Closeout
4.5.1
After running monitoring systems for verified delays, compare to similar project The work to close-out the project. Officially handover of the construction schedule to the schedule developer
Mouhanad
essential, the process for recommending changes to the scope of the project must be carried out. Any project team member can request changes to the project scope in Keadue wastewater treatment plant. All change requirements must be submitted to the Project Manager in the form of a project change request document. The Project Manager will then reconsider the optional change to the scope of the project in Keadue wastewater treatment plant. The Project Manager will then either deny the change request, because it might not apply to the aim of the project or set up a change control meeting between the project team to reconsider the change request additional and carry out an impact consideration of the change. The project manager will give initial agreement to the change request. The Project Manager will then formally submit the change request to the Change Control Board. If the Change Control Board approves the scope change the Project Manager will then officially accept the change by signing the project change control document. When getting the approval of the scope change by the Change Control Board and the Project Manager will update all project documents and communicate the scope change to all project team members stakeholders for the Keadue wastewater treatment plant.
18
SPONSOR ACCEPTANCE
Date: ___________________
19