Dis trib utio n s ub s tatio n - 20/04kV MCs e t me tal-c lad s witc hg e ar (Sc hne id e r Ele c tric )
Electrical testing and commissioning of Metal-Clad switchgear is essential to the saf e start f or the f irst time, regardless of its size, type or industry. T his article cover testing and start-up / commisioning procedures f or all the components of medium voltage switchgear like circuit breaker, busbars, instrument transf ormers (current/voltage), disconnect and grounding switches etc.
1.1. Objective
To verif y the physical condition and proper connections of bus bar.
Insulation test (Megger) Micro ohmmeter High voltage tester Torque wrench
T he test shall be done with CBs inserted and closed. Measure the contact dc resistance between panels by injecting 100A DC . T his will include busbar joint, CB contact resistance, CB cluster resistance, and CT primary resistance (if applicable).
Limit s:
T he obtained results should be similar f or all phases f or each set of measurement. Other inf luencing f actors to be considered, like length of the measured path, rating of the busbar, rating of CB, rating of CT and temperature.